Update on FCPS Construction/Renovation Projects. June 2016

Similar documents
Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. August 2016

Update on FCPS Construction/Renovation Projects. December 2015

Update on FCPS Construction/Renovation Projects. November 2015

Update on FCPS Construction/Renovation Projects. August 2015

Update on FCPS Construction/Renovation Projects. September 2015

Building Excellence IV Capital Levy Projects Under Construction

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction

BOND CONSTRUCTION UPDATE

New Ringgold Middle School. Project Slideshow August 26, 2017

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

Seattle Public Schools Building Excellence IV Projects Under Construction

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

Chino Valley Unified School District Monthly Construction Update

DOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

Capital Projects Update

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

Oconomowoc Area School District Facility Construction Update July 27, 2018

NEW MIDDLE SCHOOL PROJECT

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012

4.1.3 Project Manual

SECTION ALTERNATES

Schedule of Values Cruise Terminal 2 Expansion

Darlington Area Schools - Building Evaluations

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

AGILITAS Property Development

PRESENTATION JANUARY 24, 2017

Heritage High School

APPLICATION AND CERTIFICATE FOR PAYMENT

CEFPI Monthly Meeting

Capital Projects Update

FACILITY COMPONENTS - MIDDLE SCHOOL

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data

Capital Projects Progress Report. January Presented by

NAAHB Workgroup Index General Ledger Account

NEW MIDDLE SCHOOL PROJECT

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

Project Status Update & Progress Report

Facilities Construction


NEW MIDDLE SCHOOL PROJECT

FACILITY COMPONENTS - ELEMENTARY SCHOOL

Board Work Session Feasibility Study. January 9, 2017

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

FACILITY COMPONENTS - ELEMENTARY SCHOOL

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

Building Systems and Design Elements included in SliDeRulE

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

PLUMMER ELEMENTARY SCHOOL

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

ADDENDUM 2 - JULY 14, 2015

TABLE OF CONTENTS. (Δ = Rev 06/08)

NEW MIDDLE SCHOOL PROJECT

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Drexel Hill Middle School

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

LLANO ISD SCHOOL BOARD MEETING. January 2016

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

Darlington Area Schools - Building Evaluations

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7

RAYMOND EDUCATION CAMPUS

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

Civic Center Renovation News

Minneapolis Community and Technical College T-Building Floor 2 Student Affairs Cost Estimating Form Templates - Exhibit C

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

Delco Activity Center Site Summary

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156

Owen County School District

City of Westerville Guide to Commercial Inspections

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT

Delta Gamma Sorority Renovation Budget Scope 3/7/2018

Oconomowoc Area School District Facility Construction Update June 29, 2018

TODAY S DATE: January 24th, 2019

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

Hunter s Point South Project

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)

Fleet Elementary School

RB Homes, Inc. 152 Witherspoon St. Princeton, NJ P: (609) / F: (609)

Appendix J - Custom Uniformat for EDU Migration

Lincoln Akerman School Hampton Falls, NH

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

SEATON ELEMENTARY SCHOOL

Transcription:

Update on FCPS Construction/Renovation Projects

Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (12): $162,424.12 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 88.4% Revised Completion Date per GC: No Change

Squires Elementary -- Renovation Rendering of Final Façade

Squires Elementary -- Renovation Work Completed to Date: Exterior block masonry completed (Phase 3). Roof system has been started and is 85% complete (Phase 3). Tile in the Lower Level restrooms is complete (Phase 3) Bar joists and decking completed at the kitchen addition (Phase 3). Acoustical spray in the Kitchen completed. (Phase 3) Current Work Effort (June): Brick to complete (Phase 3). Kitchen Hood, Walk-in Cooler/Freezers to install (Phase 3). Roof System to complete (Phase 3). Gym Equipment installation to start and complete (Phase 3). Start site demo (Phase 3).

Squires Elementary -- Renovation Kitchen Addition Roof System Interior CMU at Stage Gym Ramp Removal

Squires Elementary -- Renovation Stage Slab Poured Café Acoustical Spray Kitchen Quarry Tile Main Restroom

Garrett Morgan Elementary Architect: General Contractor: Moody-Nolan Architects Griggs Enterprises, Inc. GC Contract Sum: $14,980,350 Total Project Cost: $19,478,511 Change Orders to Date (11): $117,123.67 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 95.21% Revised Completion Date per GC: No Change

Garrett Morgan Elementary Rendering of Final Façade

Garrett Morgan Elementary Work Completed to Date: Complete Kitchen equipment hook-up. Complete interior storefronts and glass. Install blinds & shades. Install stage equipment. Install remaining asphalt. Current Work Effort (June): Complete with final grading. Install seed, sod, and plants. Complete pre-school fencing & dumpster. Complete asphalt. Complete punch list.

Garrett Morgan Elementary Media Center Café Entry Bench Entry Mural

Garrett Morgan Elementary Kitchen Art Room High Windows Media Ctr. Exterior Street View

Coventry Oak Elementary Architect: General Contractor: Clotfelter-Samokar Architects D.W. Wilburn, Inc. GC Contract Sum: $14,874,000 Total Project Cost: $19,848,291 Change Orders to Date (10): $49,466.44 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 92.0% Revised Completion Date per GC: No Change

Coventry Oak Elementary Rendering of Final Façade

Coventry Oak Elementary Work Completed to Date: Classroom and office casework installation completed. Steel canopies and interior detail work nearly completed. Interior soffit framing and drywall installation and painting continued. Interior finishes (painting, terrazzo marker boards / tack boards & ceilings) ongoing. Gym floor installed and painted and bleachers are installed. Mechanical, plumbing & electrical continues. Plumbing & light fixture installation ongoing. Current Work Effort (June): Mechanical, plumbing will complete, electrical will continue. Interior drywall, painting, VCT/rubber flooring, ceramic tile, gym wall pads and ceiling grid/pads, doors/hardware will complete. Final grading, asphalt, CMU and brick masonry, exterior doors and metal roof. Brick masonry will complete. Landscaping installation will complete.

Coventry Oak Elementary Car Loop Computer Lab Entrance Corridor

Coventry Oak Elementary Front Lobby Café Finishes Rear Lobby SE Elevation

New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost: $81,511,696 Change Orders to Date (9): $156,252.33 Scheduled Contract Completion Date: July 2017 % of Contract Completed: 44.91% Revised Completion Date per GC: No Change

New High at Winchester Road Schematic Rendering of Final Façade

New High at Winchester Road Work Completed to Date: Storm sewer, sanitary sewer and fire service continued. Grading at the parking lot on the west side and at the football field and tennis courts began. Brick was completed in Area B and began in Areas A, D, E1 & E2. Work on miscellaneous non-loadbearing walls continued throughout the building. Steel roof joists and deck were completed in Area E2 and steel columns and beams were set in the Main Lobby. Metal stud walls and parapets at the cafeteria were completed and metal stud framing in Area B continued. Drywall began in Area C. Roofing dry-ins were completed in Area A and Area E2, and began in Area E1. Air barrier application continued. Metal panels continued in Area C & E4. Type X storefront was installed. Electrical wall rough-ins continued in all areas. Overhead conduits, cable tray work, & panel tub mounting continued. Temporary power and lighting continued. Electrical work completed under west parking lot. Site lighting underground conduits began. Mechanical insulation, ductwork, plumbing and HVAC rough-ins will continue. Roof leaders and overflow in Main Gym were completed.

New High at Winchester Road Current Work Effort (June): Site utilities installation will continue. Grading will be near complete at the west and south parking lots, dense grade to begin. Foundations will be completed at the Bathrooms / Concessions. Concrete slab preparation will continue in the Auditorium and begin in the Cafeteria. Bearing walls will be completed in the Auditorium and Fieldhouse. Brick will continue in Area A. Steel joist/deck will be completed in Area E1. Roofing Dry-ins will move to Area D. Metal Panels will be completed in Area C & move to Area E4. Windows will begin installation in Area C. Air Barrier will continue as required. Electrical wall rough-ins will continue in all areas. Overhead conduits, & panel tub mounting will continue. Cable tray work in Area E1 will be completed. Temporary power and lighting will continue as required. Ductwork rough-ins will be completed on 2 nd floor of Area B and mechanical insulation will continue. Area A plumbing rough-ins will continue on the 2 nd floor. Plumbing, HVAC, mechanical room hydronic piping and mechanical insulation will continue in Areas E3 & E4. Main Gym duct installation will be completed.

New High at Winchester Road Area C Storefront Area C Gypsum Wallboard Area C Block Filler Auditorium Loadbearing CMU

New High at Winchester Road Areas E1 & D Roofs Areas E2 & E3 Brick West Parking Grading Field House & Football Bleachers