Update on FCPS Construction/Renovation Projects
Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (12): $162,424.12 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 88.4% Revised Completion Date per GC: No Change
Squires Elementary -- Renovation Rendering of Final Façade
Squires Elementary -- Renovation Work Completed to Date: Exterior block masonry completed (Phase 3). Roof system has been started and is 85% complete (Phase 3). Tile in the Lower Level restrooms is complete (Phase 3) Bar joists and decking completed at the kitchen addition (Phase 3). Acoustical spray in the Kitchen completed. (Phase 3) Current Work Effort (June): Brick to complete (Phase 3). Kitchen Hood, Walk-in Cooler/Freezers to install (Phase 3). Roof System to complete (Phase 3). Gym Equipment installation to start and complete (Phase 3). Start site demo (Phase 3).
Squires Elementary -- Renovation Kitchen Addition Roof System Interior CMU at Stage Gym Ramp Removal
Squires Elementary -- Renovation Stage Slab Poured Café Acoustical Spray Kitchen Quarry Tile Main Restroom
Garrett Morgan Elementary Architect: General Contractor: Moody-Nolan Architects Griggs Enterprises, Inc. GC Contract Sum: $14,980,350 Total Project Cost: $19,478,511 Change Orders to Date (11): $117,123.67 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 95.21% Revised Completion Date per GC: No Change
Garrett Morgan Elementary Rendering of Final Façade
Garrett Morgan Elementary Work Completed to Date: Complete Kitchen equipment hook-up. Complete interior storefronts and glass. Install blinds & shades. Install stage equipment. Install remaining asphalt. Current Work Effort (June): Complete with final grading. Install seed, sod, and plants. Complete pre-school fencing & dumpster. Complete asphalt. Complete punch list.
Garrett Morgan Elementary Media Center Café Entry Bench Entry Mural
Garrett Morgan Elementary Kitchen Art Room High Windows Media Ctr. Exterior Street View
Coventry Oak Elementary Architect: General Contractor: Clotfelter-Samokar Architects D.W. Wilburn, Inc. GC Contract Sum: $14,874,000 Total Project Cost: $19,848,291 Change Orders to Date (10): $49,466.44 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 92.0% Revised Completion Date per GC: No Change
Coventry Oak Elementary Rendering of Final Façade
Coventry Oak Elementary Work Completed to Date: Classroom and office casework installation completed. Steel canopies and interior detail work nearly completed. Interior soffit framing and drywall installation and painting continued. Interior finishes (painting, terrazzo marker boards / tack boards & ceilings) ongoing. Gym floor installed and painted and bleachers are installed. Mechanical, plumbing & electrical continues. Plumbing & light fixture installation ongoing. Current Work Effort (June): Mechanical, plumbing will complete, electrical will continue. Interior drywall, painting, VCT/rubber flooring, ceramic tile, gym wall pads and ceiling grid/pads, doors/hardware will complete. Final grading, asphalt, CMU and brick masonry, exterior doors and metal roof. Brick masonry will complete. Landscaping installation will complete.
Coventry Oak Elementary Car Loop Computer Lab Entrance Corridor
Coventry Oak Elementary Front Lobby Café Finishes Rear Lobby SE Elevation
New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost: $81,511,696 Change Orders to Date (9): $156,252.33 Scheduled Contract Completion Date: July 2017 % of Contract Completed: 44.91% Revised Completion Date per GC: No Change
New High at Winchester Road Schematic Rendering of Final Façade
New High at Winchester Road Work Completed to Date: Storm sewer, sanitary sewer and fire service continued. Grading at the parking lot on the west side and at the football field and tennis courts began. Brick was completed in Area B and began in Areas A, D, E1 & E2. Work on miscellaneous non-loadbearing walls continued throughout the building. Steel roof joists and deck were completed in Area E2 and steel columns and beams were set in the Main Lobby. Metal stud walls and parapets at the cafeteria were completed and metal stud framing in Area B continued. Drywall began in Area C. Roofing dry-ins were completed in Area A and Area E2, and began in Area E1. Air barrier application continued. Metal panels continued in Area C & E4. Type X storefront was installed. Electrical wall rough-ins continued in all areas. Overhead conduits, cable tray work, & panel tub mounting continued. Temporary power and lighting continued. Electrical work completed under west parking lot. Site lighting underground conduits began. Mechanical insulation, ductwork, plumbing and HVAC rough-ins will continue. Roof leaders and overflow in Main Gym were completed.
New High at Winchester Road Current Work Effort (June): Site utilities installation will continue. Grading will be near complete at the west and south parking lots, dense grade to begin. Foundations will be completed at the Bathrooms / Concessions. Concrete slab preparation will continue in the Auditorium and begin in the Cafeteria. Bearing walls will be completed in the Auditorium and Fieldhouse. Brick will continue in Area A. Steel joist/deck will be completed in Area E1. Roofing Dry-ins will move to Area D. Metal Panels will be completed in Area C & move to Area E4. Windows will begin installation in Area C. Air Barrier will continue as required. Electrical wall rough-ins will continue in all areas. Overhead conduits, & panel tub mounting will continue. Cable tray work in Area E1 will be completed. Temporary power and lighting will continue as required. Ductwork rough-ins will be completed on 2 nd floor of Area B and mechanical insulation will continue. Area A plumbing rough-ins will continue on the 2 nd floor. Plumbing, HVAC, mechanical room hydronic piping and mechanical insulation will continue in Areas E3 & E4. Main Gym duct installation will be completed.
New High at Winchester Road Area C Storefront Area C Gypsum Wallboard Area C Block Filler Auditorium Loadbearing CMU
New High at Winchester Road Areas E1 & D Roofs Areas E2 & E3 Brick West Parking Grading Field House & Football Bleachers