Increasing Hurricane Winds? Dockside Crane Retrofit Recommendations

Similar documents
Seismic Retrofit of Container Cranes

Seismic Response of Jumbo Container Cranes and Design Recommendations to Limit Damage and Prevent Collapse

The Effect of Ultra Large Container Vessels on Cranes and Infrastructure

Effect of ULCVs on Cranes and Infrastructure

Modifying Your Cranes to Serve Larger Ships

THE EFFECT OF ULTRA LARGE CONTAINER VESSELS ON CRANES AND INFRASTRUCTURE

Practical Observations for Rail Mounted Crane Interfaces

Offering a step-change in seismic technology

BERTHS 57, 58 AND 59 CONTAINER WHARF AT THE PORT OF OAKLAND

Reinforced Concrete Design. A Fundamental Approach - Fifth Edition

M 8.8 CHILE EARTHQUAKE PORT DAMAGE ASSESSMENT

Question 8 of 55. y 24' 45 kips. 30 kips. 39 kips. 15 kips x 14' 26 kips 14' 13 kips 14' 20' Practice Exam II 77

Lateral Design of Mid- Rise Wood Structures

Evaluating the Seismic Capacity of a Newly Designed Wharf at the Port of Oakland

Hurricane wind shelter retrofit room standards for existing houses

Bridge articulation No. 1.04

This guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866)

LIGHT-GAUGE PANELIZED WALL SYSTEMS. Michael Waggoner Mark Schroeder

SEISMIC BEHAVIOR AND DESIGN OF STEEL SHEAR CONNECTIONS WITH FLOOR SLABS

Inspection of Steel Girder Bridges

Learning Objectives. Topics. Moment Frames: Design and Detailing per AISC 341 and 358. Topics. Lateral Analysis/Choosing your Code

WALL CANTILEVER WORK STATION JIB CRANE

PRECAST CONCRETE CONNECTIONS - US PRACTICE

Structural Engineering, Mechanics, and Materials. Preliminary Exam - Structural Design

Machinery on Trolley Crane Design Port of Singapore

REPORT HOLDER: FASTENING SPECIALISTS, INC. 726 CENTRAL FLORIDA PARKWAY ORLANDO, FLORIDA EVALUATION SUBJECT:

STRUCTURAL FATIGUE HAPPENS: Maintain Your Cranes! By Patrick McCarthy

REPORT HOLDER: MITEK USA, INC. (FORMERLY USP STRUCTURAL CONNECTORS) SOUTHCROSS DRIVE, SUITE 200 BURNSVILLE, MINNESOTA EVALUATION SUBJECT:

Angle Cleat Base Connections

SHAKE TABLE TESTING OF CONTAINER CRANES

THE BRACE CONNECTION THE BOLTED OPTION FIGURE 1 MODEL SHOWING THE BOILER AND THE STRUCTURAL SUPPORT SYSTEM (BOILER BUILDING)

Overturning Forces. 12 times 300 lbs = 3,600 lbs of shear force along top of wall. Shear Wall

BUILDING RETROFITS: BREATHING NEW LIFE INTO EXISTING BUILDING STRUCTURES

This guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.

DRIVE-IN PALLET RACKING

Page 1 of 46 Exam 1. Exam 1 Past Exam Problems without Solutions NAME: Given Formulae: Law of Cosines: C. Law of Sines:

WHITE PAPER March 7, 2013

An Insider s Perspective

Drift Compatibility of Corner Joints. NEES Webinar #2 December 12, 2014

This guide can be used to prepare a specification for incorporating wall bracket jib cranes into a competitively bid construction project.

INFLUENCE OF DIFFERENT TYPES OF FULLY RESTRAINED CONNECTIONS ON THE RESPONSE OF SMRF STRUCTURES

SEISMIC RETROFITTING OF REINFORCED CONCRETE COLUMNS USING CARBON FIBER REINFORCED POLYMER (CFRP)

manualwise BRACED FOR BETTER SEISMIC DESIGN

ACHIEVING DUCTILE BEHAVIOR OF MOMENT CONNECTIONS PART II

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #3 November 21,

Installation of RMG Cranes at Intermodal Rail Yard ABSTRACT INTRODUCTION

A-Series Aluminum Gantry Crane

STEEL COLUMNS. Er. RAJINDER KUMAR (M.E. CIVIL) Sen. LECTURER G.P. COLLEGE, BATALA.

AXIAL LOAD FAILURE OF SHEAR CRITICAL COLUMNS SUBJECTED TO HIGH LEVELS OF AXIAL LOAD

Introduction to Cambering

70 & 74. CMAA is an affiliate of the Material Handling Industry of America division of Material Handing Industry. Prepared by

The content for this class has been provided by the following PB employees: With assistance from: Martine Klein, P.E. Narration by Greg Metzger, PB

Repair and Retrofit of a Coke Drum Skirt Attachment Weld

Structural Training - Part 1:

CVEN 483. Structural System Overview

Alternative Methods of Evaluating and Achieving Progressive Collapse Resistance

Basic quantities of earthquake engineering. Strength Stiffness - Ductility

High Capacity Weigh Modules

Investigation of Structural Steel Webs for Punching Shear

Structural Glossary. ARCH 631 Structural Glossary F2014abn

CHALLENGES AND CONSIDERATIONS IN SELECTION, ANCHORAGE DESIGN, AND INSTALLATION OF QUICK-RELEASE MOORING HOOKS ON EXISTING STRUCTURES by

Increasing Crane Girder Capacity Using the Strut-and-Tie Method. Michael A. Jordan*, Joe Oakley, Jr.**, Derrick Lind***, and Thomas Griswold****

OWNER S MANUAL SERIES MDS-96-BK, SM, DR

7 NON-STRUCTURAL ELEMENTS

John Jay College Expansion Project

Modelling of post-tensioned precast reinforced concrete frame structures with rocking beam-column connections

January 2011 Design Approach For Multiple Hazard Load Condition Hossein Ghara, P.E., M.B.A.

Seismic Considerations of Circuit Breakers

Trusted ICC ES TEK USA, Evaluation. report, or as to any. ICC-ES Evaluation

Cyclic Loading Tests Of Steel Dampers Utilizing Flexure-Analogy of Deformation

Inelastic Torsional Response of Steel Concentrically Braced Frames

FATIGUE FAILURES IN INDUSTRY CASE STUDIES

REPORT HOLDER: MITEK USA, INC. (FORMERLY USP STRUCTURAL CONNECTORS) SOUTHCROSS DRIVE, SUITE 200 BURNSVILLE, MINNESOTA EVALUATION SUBJECT:

Invention: Seismic Retrofitting by Exterior Steel Brace Structural Building Jacketing System

NON-LINEAR STRUCTURAL INTEGRITY ANALYSIS

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND

Facilitating innovative bridge design the bearings and expansion joints of the Golden Ears Bridge

Status of Design and Research & Development for ITER Sector Sub-assembly Tools

A Shim-less Slotted Bolt Energy Dissipating Connector

CE 479 CURTAIN WALL STRUCTURES. Guest Lecturer: Bruce Kaskel, SE, RA Principal Wiss, Janney, Elstner Associates, Inc.

PEMA 2014, Amsterdam Presented by Simo Hoite, Liftech Consultants Inc. February 6, 2014

BRACED FRAME USING ASYMMETRICAL FRICTION CONNECTIONS (AFC)

Full-scale Testing of the Cast Steel Yielding Brace System

KINETICS Pipe & Duct Seismic Application Manual

INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM)

TESTS AND MODELING OF T-STUB BOLTED I-BEAM TO SHS-COLUMN FRAME CONNECTIONS

Note on the assessment:

Tier 1 Assessment Linderman Gymnasium Polson, MT

Crucial Facts for Purchasing New or Replacement Conveyor Chain

Displacement-Based Seismic Analysis of A Mixed Structural System

SEISMIC PERFORMANCE AND RETROFIT OF BRIDGE FOOTINGS. David I. McLean 1

OWNER S MANUAL SERIES MDS-96-BK, SM, DR

(a) Pin-Pin P cr = (b) Fixed-Fixed P cr = (d) Fixed-Pin P cr =

HYBRID CONCRETE MASONRY CONSTRUCTION DETAILS. TEK 3-3B Construction (2009) Related TEK: 14-9A

Overview of Presentation. SCBFs are Conceptually Truss Structures

Types of Structures and Loads

Potential Solutions- Background: Current Designs. Potential Solutions. Goals for Design What are we concerned about?

ALISPLY. Scaffold Plank. Aligner. Plate Washer ½ x 6 x 6

BOAST. West Coast. Set to open this spring, the tallest building on the West Coast resists wind and seismic drifts with massive braces.

Transcription:

Increasing Hurricane Winds? Dockside Crane Retrofit Recommendations Patrick McCarthy, P.E. Associate Contributors: Hurricane Katrina. Source: www.nhc.noaa.gov Michael Jordan, S.E., Liftech Kenton Lee, S.E., Liftech Stu Werner, Seismic Systems & Engineering Consultants This is an image of Katrina, taken from the National Oceanic and Atmospheric Administration website. Cranes in New Orleans fared well, with only some local damage to operator s cabs. Try to remember this image later in this presentation; notice the size of the storm. 1

Topics Increasing winds? Traditional tie-down design Ductile link tie-down design 2of 27 We ll start by discussing hurricane winds. Are they increasing? 2

Global Warming Sea surface temperatures (SSTs) are increasing SST effect on hurricanes Correlated: Size and duration increase with SST Not correlated: Frequency and maximum wind speed Hurricane energy has doubled in 30 years 3of 27 SSTs are increasing. This affects hurricanes. Studies by Emanuel (Nature) and Hoyos (Science Express) indicate that hurricane intensity, size, and duration are increasing, and are correlated to increasing sea surface temperatures (SSTs). SSTs have increased approximately 0.5 C in the tropics. Storm duration has increased approximately 60%. Total North Atlantic plus Western North Pacific power dissipation index (PDI) (basically the total energy released) has approximately doubled over the last 30 years. There is no apparent correlation between the number of hurricanes formed each year and the SST. There is only a small correlation between increasing hurricane maximum wind speeds and SSTs. In effect, the theoretical maximum wind speed may not be increasing, but the winds are, and that effects cranes. 3

Effect on Cranes Crane design: ASCE-7 standard, 50 yr MRI ASCE-7 wind speeds are based on statistics Larger, more powerful storms result in greater likelihood of a crane at a given location being hit Wind force is proportional to wind speed squared Tie-down uplift force is sensitive to small changes in design wind speed 4of 27 Crane designs are typically based on the ASCE-7 standard, Minimum Design Loads for Buildings and Other Structures, with a 50-year mean recurrence interval (MRI), 3-second gust wind speed, at 10 m elevation. Certain-year MRI wind speeds are based on statistics. For instance, statistically, there is a 64% chance of exceeding a 50-year MRI wind speed in 50 years, or 1/50 in any given year. Remember the size of Katrina in the first slide? The area hit hard by that storm was tremendous. Also remember Emily, which traveled across Florida? Emily struck the west coast of Florida and went all the way through the state, and regained Category 2 status on the other side, damaging cranes on the east coast. Normally, we would expect Hurricanes to fizzle out before hitting land, or shortly after hitting land. If the likelihood of a hurricane hitting a location increases due to storms lasting longer (and being bigger), we would expect the ASCE-7 wind standard to gradually increase their statistical MRI wind speeds in hurricane regions. In other words, hurricanes are more likely to hit a certain location, so instead of hitting every 75 years with a certain storm, it might hit every 50 years. The same wind speed will occur more often, decreasing the recurrence interval for the same wind speed. A current 75-year wind may become a 50-year wind. Overturning moments are proportional to the wind speed squared. Note: Cranes here on the West Coast typically do not have tie-downs and are not likely to be affected by changing wind effects any time soon. 4

5of 27 Hurricanes cause damage. The risks are real. Typhoon Maemi struck Pusan, Korea in September of 2002. Two cranes are shown (see underside of crane boom). Initial failure of tie-down attachment to wharf. There can be consequential damage as well; six other cranes were also lost due to a single, initial tie-down failure and subsequent domino-effect collisions. 5

Topics Increasing winds? Traditional tie-down design Ductile link tie-down design 6of 27 Now we will present traditional tie-down design and some associated problems. 6

Crane Stowage Components 7of 27 Next slide Crane stowage components are shown here. Most failures are uplift-related, so we will focus on the tie-downs. Tie-downs take uplift (Y-dir) Stowage pins take gantry travel direction forces (Z-dir) Gantry wheels transmit trolley direction forces to rails (X-dir) 7

Gantry Stowage System Sill Beam Tie-downs Stowage Pin 8of 27 Tie-downs are most effective toward the end of the sill beam. 8

Traditional Tie-down Design 9of 27 Ideally, we would prefer only one tie-down per corner. For hurricane wind regions, uplift force is typically too large with today s jumbo cranes, to practically have only one tie-down per corner. The issues involved the inability to test turnbuckles, and the difficulty securing, due to size. 9

Uneven Force Distribution Wheel Shifting on Rail 10 of 27 Cranes are flexible and hurricane forces cause cranes to deflect and move. The forces in the tie-downs are not evenly distributed. Why? Crane structure deforms, translating and rotating. Gantry wheels can shift. Gap in stowage pin socket allows gantry wheels to roll (or slide) along the rail. Links are not perfectly straight. Wharf pins are not symmetric 10

Tie-down Load Distribution Tie-down corner distribution: Design: 60/40 (typical) Actual: 100/0 One tie-down may take up to 100% of the corner uplift load If one tie-down fails, other will also fail 11 of 27 For years, designers have used a 60/40 or 70/30 load distribution per corner. We thought this was conservative. Recent analyses indicate that the actual distribution may be as much as 100/0%. If a single tie-down was designed to 60% of the total uplift, the actual uplift would be 100/60 = 1.67 times the design uplift. The tie-down may survive due to factors of safety or it may not survive. Many older cranes have seen their design wind speed. Others have not. The tie-downs are typically not the weakest element 11

Wharf Hardware Wharf connection may fail due to improper design and/or fabrication 12 of 27 Usually, the wharf hardware to crane tie-down interface is the first to fail. Wharf connection design may not be consistent with crane design. The tie-down wharf hardware is often designed to a lower standard, compared to the tie-down design (ASD vs. LRFD). The unequal load distribution may cause the wharf hardware to give way. Upper image is a tie-down pullout failure with smooth anchor bolts. Lower image is a tie-down wharf bracket failure due to improper fabrication--4 mm (3/16 in) fillet weld between base plate and 60 mm (2.5 in.) lug. The fabricator also used a filler plate between the lug and base plate! Onsite inspection may have prevented this terrible workmanship. 12

How to Design? If possible, use one tie-down per corner Otherwise, two equalization approaches: Mechanical equalizer Ductile link 13 of 27 As mentioned, the best method is to use a single tie-down per corner, but this is often impractical. The mechanical equalizer beam system is not presented as it is heavy and difficult to implement. Another choice is to use a ductile link. 13

Topics Increasing winds? Traditional tie-down design Ductile link tie-down design 14 of 27 Now we ll present equalization through ductile yielding of a structural element. 14

Ductile Link Ductile link elongates Load is maintained as link stretches Original Shape Elongated Shape 15 of 27 If one link in the tie-down system is capable of deforming plastically without loss of strength until the other link engages, the tie-down loads will eventually equalize. Plastic elements acting as fuses have been used for decades to protect structures from severe damage during earthquakes. 15

How it Works: Idealized Design Uplift Load = 1,000 tons/corner Crane (deformed) Link A Link B Force 500 t Force 500 t Force 500 t 500 t 250 t 0 t Strain 50% Load Initial uneven distribution 16 of 27 Strain 75% Load Redistribution after yielding Strain 100% Load Force equalization How does it work? Initially the loads in multiple tie-downs are not equal. In some cases, the entire corner upload force is carried to one tie-down. In this example, with a 1,000 ton corner load, the initial distribution is uneven. The desired distribution at the design uplift load is 50/50. With the ductile link, the heavily loaded tie-down yields at half of the design uplift load, allowing load to transfer to the lightly loaded tie-down. As the uplift force increases, the ductile link stretches plastically. The load remains (relatively) constant in the heavily loaded tie-down and increases in the lightly loaded tiedown. Normally, the load might follow the dotted line shown in the middle graph. Eventually the load is shared equally, and the full strength of the multiple tie-downs is utilized, as intended. (Note that the force/strain graphs are idealized.) This protects the wharf hardware from overload. 16

Safety Links Protect against excessive stretch Provide redundancy in case the ductile link fails 17 of 27 Safety link (with slotted hole) Original Shape Elongated Shape What if both links are loaded to their failure deformation? Their strength is insufficient to continue carrying the load. How can we keep failure from occurring? It is likely that the elements in the rest of the system have some reserve strength. This strength can be utilized with the use of safety links connected in parallel with the ductile link. The ductile link has done its job and distributed the load. Now the failure should be controlled by the remaining weakest element. The safety link also provides some redundancy. 17

Ductile Link System Crane ear plate Link plate Safety link Ductile link Turnbuckle Wharf link Wharf ear plate 18 of 27 Notice how the ductile link fits in to a typical tie-down system. The ductile link-safety link system is typically larger than a traditional tie-down. There may be some interference with the gantry. 18

Ductile Links Implemented 19 of 27 Here is a ductile link system with four tie-downs per corner. (Implemented in New Jersey) 19

Components Ductile Link Safety Link 20 of 27 Important features: Controlled area and material properties of the ductile link Need material testing Grind stretching region smooth Slotted hole in safety link to allow for design stretch of ductile link (based on material testing) 20

Features Mild steel Easy to fabricate Smaller turnbuckles Can retrofit existing systems Improves reliability of the tie-down system 21 of 27 Ductile links improve reliability. This is the main feature Ductile links can be added to existing cranes, although it is not cheap, and sometimes it is difficult to fit. On new cranes with multiple tie-downs, using ductile links is relatively easy and should not increase the crane price. 21

Spare Parts Replace ductile links after significant elongation Must replace more frequently than the design storm wind MRI Expected replacement interval can be estimated Original Elongated 22 of 27 To ensure that adequate ductility exists and that the ductile link will equalize the loads in the next typhoon, the link should be replaced if significant stretch has occurred. This may be more frequently than design storm MRI because first link yields prior to developing full design corner uplift. We expect a typical replacement design interval to be a decade. Refer to the paper for a method of estimating the replacement interval. 22

Design Process 1. Forces and displacements 2. Tie-down force at each corner 3. Design ductile link breaking strength 4. Check other members 5. Design and test ductile link 6. Design the safety links 23 of 27 The design steps provided are only guidelines and only mention a few of the design issues. 1. Calculate forces and displacements due to factored dead and storm wind loads 2. Calculate the average tie-down force at each corner 3. Design the breaking strength for the calculated average tie-down uplift force 4. Verify that the strengths of the other tie-down and wharf hardware components exceed the link breaking strength 5. Design the ductile link dimensions based on material test samples of the link material. Verify that the link is ductile enough to accommodate the required plastic deformation 6. Design the safety links to develop ~120% of the strength of the weakest element 23

Example: Less Idealized Force, t 1200 1000 Design corner uplift 800 600 400 200 Design, other components 1 st Link 2 nd Link 0 0 25 50 75 100 125 150 175 200 225 250 275 300 Safety Link Engages Strain, 1/1000 Replace 1 st Link after yield 24 of 27 In reality, the link force at ultimate is greater than at yield, as shown. The design steps provided are only guidelines and only mention a few of the design issues. 1. 1 st link 2. 2 nd link 3. Safety link 4. Design uplift 5. Design other components in one link 6. Replacement 24

Costs and Risks Owners should weigh costs vs. risks Retrofits are costly Can use methods used for seismic risk reduction planning Condition of zero risk cannot be achieved 25 of 27 Retrofit cost is not cheap, but is not expensive compared to the crane costs. (Around $50-100 K as a really rough estimate.) See Stu Werner s Seismic Guidelines for Ports (TCLEE, ASCE, March 1998) for information regarding seismic risk reduction planning at major ports. Unacceptable crane damage risk must be weighed against costs of retrofit. Risk of economic, life safety, political, legal, and administrative losses must be considered. These are owner-specific. 25

Summary & Recommendations More dockside cranes will experience their design force (or greater) due to global warming Existing tie-down designs may be improperly designed for unequal corner load distribution Ductile link retrofit may be a solution Owners should weigh costs vs. risks 26 of 27 In closing, we recommend owners review their options. Ductile links may be an attractive solution for increasing crane stowage reliability in a changing environment. 26

Increasing Hurricane Winds? Dockside Crane Retrofit Recommendations Thank you This presentation is available for download www.liftech.net Patrick McCarthy, P.E. Associate Liftech Consultants Inc. Contributors: Michael Jordan, S.E., Liftech Kenton Lee, S.E., Liftech Stu Werner, Seismic Systems & Engineering Consultants See the paper for references and more information. 27

Copyright 2007 by Liftech Consultants Inc. All rights reserved. This material may not be duplicated without the written consent of Liftech Consultants Inc., except in the form of excerpts or quotations for the purposes of review. The information included in this presentation may not be altered, copied, or used for any other project without written authorization from Liftech Consultants Inc. Anyone making use of the information assumes all liability arising from such use.