Overview of the Southern African Power Pool (SAPP) energy programme for the Southern African Development Community (SADC) Fossil Fuel Foundation: IPP Conference 17 March 2016 Johannesburg
Objectives Overview of the overarching SAPP programme, including key single- and multi-country energy initiatives; and priority projects identified for planning, implementation and operation. Share the current opportunities and constraints to the roll-out of the programme Interventions being put in place to enable the effective delivery of a reliable electricity supply throughout the SADC region
Disclaimer Information presented is based on publicly available documentation and SRK s understanding via interaction with SAPP Not presented on behalf of SAPP or any it s the member utilities Acknowledge SAPP as primary source of information presented
What is SAPP Created with the primary aim of providing a reliable and economical electricity supply to the consumers of each of the 16 SAPP member utilities Consistent with the sustainable utilisation of natural resources and avoidance and minimisation of environmental and social impacts.
What is SAPP The SAPP is governed by four agreements: The Inter-Governmental Memorandum of Understanding The Inter-Utility Memorandum of Understanding Agreement Between Operating Members Operating Guidelines
SAPP Challenges Insufficient generation surplus capacity within SAPP became manifest in 2007/8 Due to inadequate investments in generation and transmission infrastructure over the last 30-years
Energy flows Average Unconstrained Price For Selected Day: USD/MWh: 41.36
SAPP Challenges The challenges being faced include, but not limited to: Generation and transmission projects identified for implementation are not properly prepared; Capacity constraints within SAPP utilities to prepare projects and bring them to bankability stage; and Project preparation funds have not been secured rapidly enough to prepare a sufficient number of projects.
SAPP Challenges In 2009 SAPP completed a revision of the Pool Plan Funded by the World Bank and the government of Norway Identified a number of priority projects to be prepared and implemented The status of project implementation was reviewed by the SAPP Executive Committee in 2011: Most of priority projects required further work to be bankable To achieve this, project preparatory funds were required
SAPP Challenges Responses received to assist with a number of priority projects: The government of Norway Swedish International Development Agency (Sida) Development Bank of Southern Africa Agence Française de Développement (AFD) Asian Development Bank (ADB)
SAPP Challenges In 2013, AfDB renewed its support to the Inga Hydro-power Project in the Democratic Republic of the Congo: $73 million technical assistance grant Support development phase of a new dam on the Congo River by contributing to the financing of the technical design, the development of an institutional structure to manage the investment and the negotiation of a public-private partnership. This preparatory work will lay the foundation for further investment operations which will install a new plant with a 4,800 MW capacity Expected to boost electricity access in DRC from 9% (2014) to >40% in 2022.
SAPP Challenges The World Bank has responded by assisting the SAPP to roll-out a Program for Accelerating Transformational Energy Projects An International Development Agency (IDA) grant up to $20M was provided for the establishment of a PAU within SAPP and provision of technical support
Program for Accelerating Transformational Energy Projects $20M from the World Bank: To help accelerate preparation of selected priority regional power generation and transmission projects in the operational region of the SAPP to value of Projects will be large-scale, complex regional energy projects Including technical, economic and financial feasibility studies, environmental assessments, legal documentation and financial transaction advisory work.
Program for Accelerating Transformational Energy Projects The project is comprised of three components: setting up the projects acceleration team: charged with moving ahead with preparation of regional projects identified as priorities; project preparation funds: including technical, economic and financial feasibility studies; and regional analytical support: support critical analytical work deemed important for advancing preparation of priority projects
Program for Accelerating Transformational Energy Projects Component A: Setting up the PAU under the SAPP (US$ 7 million which would fund the mobilization of a high caliber team Component B: Project Preparation Funds (US$10 million, initially). The funds in this component would be managed by the PAU. Key focus will be on environmental and social performance of projects Component C: Analytical support to SAPP (US$3 million). This component would support analytical work to update critical non-project specific information used by SAPP to support project preparation, including revision of the SAPP Pool Plan
Program for Accelerating Transformational Energy Projects The PAU will: Conduct regional analytical work Use the grant funding received by the SAPP-CC to screen, select, prepare and monitor the implementation of regional priority projects Play an advisory role to SADC governments Be accountable for the preparation and implementation of selected and agreed priority regional electricity projects in the Southern African Power Pool region
Program for Accelerating Transformational Energy Projects: Environmental & Social SAPP Member States operate in different legislative environments, with variability in national environmental and social safeguard requirements SAPP Environmental and Social Guidelines developed over a period of time to address some of these challenges Capacity building and training prioritized SRK assistance in 2014/15 Capacity constraints within many member utilities to comprehensively identify, assess, avoid or mitigate, and manage environmental and social risks and impacts remain
Program for Accelerating Transformational Energy Projects Environmental and Social Impact Assessment Guidelines For Transmission infrastructure for the SAPP Region SAPP Guidelines on the Use and Disposal of CFL Lamps SAPP Occupational Health & Safety Environmental Guideline Guidelines for Environmental Impact Assessment (EIA) for Thermal Power Plants SAPP Position on Climatic Change SAPP PCB Guidelines Jan 2008 SAPP Guidelines on the Management of Oil Spills Guidelines for the safe Control, Processing, Storing, Removing and Handling of Asbestos and Asbestos Containing Materials and Articles for SAPP Guidelines for the Management and Control of Electricity Utility Infrastructure with regard to Animal Interaction for SAPP. Guidelines for Environmental and Social Impact Assessments for Hydro Projects in SAPP Region
Program for Accelerating Transformational Energy Projects Component of Program includes development of an Environmental and Social Management Framework (ESMF) Purpose: provide technical guidance for environmental and social (impact and risk) assessment and management during preparation of the selected priority regional energy projects
Program for Accelerating Transformational Energy Projects Environmental and Social Management Framework (ESIA) Screening and guidance tool to assist in the high-level environmental and social screening of projects during preparation Strengthen the assessment and management of risks and impacts Particularly relevant where project loans from regional or international financial institutions are required Cater for projects of different categories based on the extent and significance of likely impacts and risks
SAPP Priority Projects For transmission projects, the following categories were agreed to: Outstanding transmission interconnectors whose aim is to interconnect nonoperating members of the SAPP Transmission interconnectors aimed at relieving congestion on the SAPP grid New transmission interconnectors aimed to evacuate power from generating stations to the load centers
SAPP Priority Projects Screening
SAPP Priority Projects Category A: Outstanding transmission interconnectors whose aim is to interconnect non-operating members of the SAPP: Mozambique-Malawi Zambia-Tanzania-Kenya Interconnection of Angola Category B: Transmission interconnectors aimed at relieving congestion on the SAPP grid: Central Transmission Connector (CNC - Zambia) Zimbabwe Zambia Botswana Namibia (ZIZABONA) Kafue-Livingstone Upgrade (Zambia)
SAPP Priority Projects Category C: Transmission Projects related to new Generation projects Mozambique Transmission Backbone CESUL Other Candidate Transmission Projects Second Mozambique Zimbabwe Interconnector Second Zimbabwe RSA Interconnector Second DRC Zambia Interconnector (Kolwezi Solwezi)
SAPP Priority Projects ZIZABONA (Zimbabwe Zambia Botswana Namibia) Facilitate power trade across Zimbabwe, Zambia, Botswana and Namibia Ease congestion on the existing north-south transmission corridor from South Africa to Zimbabwe Add a 400 kv western corridor to the Southern African Power Pool Support the transfer of 600 MW of electricity arising primarily from existing and future hydroelectric plants located in Zambia and Zimbabwe Updated Feasibility Study is still to be completed Estimated cost approx. R 223 million
SAPP Priority Projects Mozambique Transmission Backbone CESUL Transport electricity from new hydro power plants from Mphanda Nkuwa (1,500 MW) and Cahora Bassa (North Bank, 1,245 MW) to the markets. 400kV HVAC (High voltage alternative) line and 800 kv HVDC (High voltage direct) line Supply the major consumption zones within Mozambique and link with the South African market Feasibility Study complete Cost > $2 billion
Thank you Warrick Stewart Associate Partner & Principal Environmental Scientist SRK Consulting 011 441 1111 / 083 2991977 wstewart@srk.co.za www.srk.co.za
Project overview