Title Anchor Head Itself Being Broken. Symposium on Backwards Problem in G.

Similar documents
Analysis for Failure Mechanism of Temporary Shoring Structure

A seismic reinforcement method for an existing pile foundation in soft ground and liquefiable ground

Skirted Spudcan Sheet Pile Wall Interaction during Jack- Up Rig Installation and Removal in a Harbour Area

PILE DESIGN METHOD FOR IMPROVED GROUND USING THE VACUUM CONSOLIDATION METHOD

EFFICIENCY OF MICROPILE FOR SEISMIC RETROFIT OF FOUNDATION SYSTEM

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY

Deformation monitoring and analysis of deep foundation pit of Xiaoshan rainbow Boulevard

Experimental Development of New Type Reinforced Soil Wall

Load Bearing Mechanism of Piled Raft Foundation during Earthquake

Development of the Combi-Gyro Method, a New Steel Wall Construction Method Combining Steel Sheet Piles and Pipe Piles

Issues on Design of Piled Raft Foundation

Damage states of cut-and-cover tunnels under seismic excitation

Full-Ring Experimental Study of the Lining Structure of Shanghai Changjiang Tunnel

Finite Element Analysis of Flexible Anchored Sheet Pile Walls: Effect of Mode of Construction and Dewatering Naveen Kumar 1, Arindam Dey 2*

Load Bearing Mechanism of Piled Raft Foundation during Earthquake

TABLE OF CONTENTS. 0 Structural calculations 0.1 General 0.2 Safety concept 0.3 Calculations for waterfront structures

Page 1 of 46 Exam 1. Exam 1 Past Exam Problems without Solutions NAME: Given Formulae: Law of Cosines: C. Law of Sines:

Verification of a multi-anchored wall

SEISMIC RESPONSE OF AN ISOLATION METHOD FOR CUT AND COVER TUNNEL USING POLYMER MATERIAL

Effect of Groundwater Depth on Differential Settlement of Wooden Houses during Soil Liquefaction

Sabah Shawkat Cabinet of Structural Engineering 2017

FULL-RING EXPERIMENTAL STUDY OF THE LINING STRUCTURE OF SHANGHAI CHANGJIANG TUNNEL

SPECIFICATION OF JACKED ANCHOR FOR RETAINING STRUCTURES

Effects of Wall Embedded Length Ratio and Wall Thickness Ratio on Undrained Stability of Cantilever Piled Walls

EFFECT OF DEEP EXCAVATION SUPPORTED BY CONCRETE SOLIDER PILE WITH STEEL SHEET PILE LAGGING WALL ON ADJACENT EXISTING BUILDINGS

Three-dimensional computer simulation of soil nailing support in deep foundation pit

PRESTRESSED CONCRETE STRUCTURES. Amlan K. Sengupta, PhD PE Department of Civil Engineering Indian Institute of Technology Madras

Atsushi NUMATA 1 and Nobuhiko KOTANI 2 1 Design Section Chief of the Renovation & Construction Department at Railway

Earth Retaining Walls CIVL455 CHAPTER I: INTRODUCTION

EXPERIMENTAL PROGRAMME

Effect of Seismic Reinforcement of Sheet Pile Quay Wall Using Ground Anchor

of New Hampshire, USA

Downloaded from Downloaded from /1

NPTEL Course. GROUND IMPROVEMENT Factors affecting the behaviour and performance of reinforced soil

To have a clear idea about what really happened and to prevent the

Seismic Design Guidelines to Mitigate Upheaval Buckling Of Small Diameter Pipes

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013

Better ZSOIL, Better Geotechnical Analysis

GROUP INSTALLATION OF PLASTIC BOARD DRAINS AT EMBANKMENT TOES FOR LIQUEFACTION AND LATERAL FLOW COUNTERMEASURES

Study on earth pressure acting upon shield tunnel lining in clayey and sandy grounds based on field monitoring

DAMAGE ANALYSIS AND SEISMIC DESIGN OF RAILWAY STRUCTURES FOR HYOGOKEN-NANBU (KOBE) EARTHQUAKE

Estimation of Lateral Earth Pressure on Cantilever Sheet Pile using Flat Dilatometer Test (DMT) Data: Numerical Study

International Journal of Engineering and Innovative Technology (IJEIT) Volume 2, Issue 6, December 2012

Static Response of Reinforced Soil Retaining Walls with Modular Block Facing

Geotechnical Analysis of Stepped Gravity Walls

Mechanical behavior and design method of weld-free steel structure with knee brace damper using square tube column

twenty seven concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

STUDY ON THE TUNNEL SECONDARY LINING CONCRETE CRACKING PERFORMANCE DURING SERVICE PERIOD OF WU- GUANG PASSENGER DEDICATED LINE

Effects of axial loads and soil density on pile group subjected to triangular soil movement

ASSIGNMENT 1 ANALYSIS OF PRESTRESS AND BENDING STRESS BFS 40303

IMPROVEMENT TECHNIQUE OF EARTHQUAKE RESISTANCE OF ROAD EMBANKMENT THROUGH NUMERICAL ANALYSES

Misan University - College of Engineering Civil Engineering Department

INFLUENCE OF PRSTRESS LEVEL ON SHEAR BEHAVIOR OF SEGMENTAL CONCRETE BEAMS WITH EXTERNAL TENDONS

DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE FOUNDATION ENGINEERING UNIT 1

DISPLACEMENT OF DIAPHRAGM WALL FOR VERY DEEP BASEMENT EXCAVATION IN SOFT BANGKOK CLAY

Modelling issues for numerical analysis of deep excavations

STATIC ALTERNATING CYCLIC HORIZONTAL LOAD TESTS ON DRIVEN

Single Piles and Pile Groups

ULTIMATE EARTHQUAKE RESISTANT CAPACITY OF CFT-FRAME

SHEAR BEHAVIOR OF RC BEAMS USING U-SHAPED UFC PERMANENT FORMWORK WITH SHEAR KEYS OR BOLTS

THE EXPERIMENTAL STUDY ON INNER SHIFT LINING STRUCTURE OF FREEZING SHAFT IN DEEP THICK AQUIFEROUS SOFT ROCK**

Rapid Axial Load Testing of Drilled Shafts

Performance of high capacity jack-in pile for high-rise building with preboring in weathered sedimentary rock formation

Research on Weight Reduction of PC Composite Members Using Ultra High Strength Fiber Reinforced Cementitious Composites (UFC)

Modelling of a pile row in a 2D plane strain FE-analysis

geopier Lateral resistance

METHOD FOR ASSESSING DAMAGE INDUCED IN UTILITIES DUE TO GROUND MOVEMENTS FROM MAJOR INFRASTRUCTURE PROJECTS

A Centrifugal Model Test on Seismic Reinforcement for Embankments on Peaty Ground

Settlement assessment of running tunnels a generic approach

Performance of Reinforced Earth Retaining Wall with Fly Ash under Static and Dynamic Loading

Numerical Analysis of a Novel Piling Framed Retaining Wall System

EARTHQUAKE DAMAGE INVESTIGATION OF GRAVITY-TYPE QUAY WALLS IN IBARAKI PORT

Sheeting Wall Analysis by the Method of Dependent Pressures

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

13.4 FOUNDATIONS FOR SINGLE-FAMILY HOUSES

Temporary Structures. Excavations and Excavation Supports

Extreme Loading for Structures Version 3.1

Two-dimensional finite element analysis of influence of plasticity on the seismic soil micropiles structure interaction

A THREE DIMENSIONAL STUDY OF THE EFFECT OF SOIL EROSION ON RIGID PIPES

GENERAL FRAME WORK OF RESARCH TOPICS UTILIZING THE 3-D FULL-SCALE EARTHQUAKE TESTING FACILITY

Geotechnical Engineering Software GEO5

Damage Evaluation of Railway Structures based on Train-induced Secondary AE Parameters

Design of Anchored-Strengthened Sheet Pile Wall: A Case Study

Failure of Heterogenous Composites due to Thermal Stresses in Presence of Pre-Cracks

Standard Specification for concrete structures-2002, Seismic Performance Verification

STUDY ON THE DAMAGES OF STEEL GIRDERS BY HYOGO-KEN NANBU EARTHQUAKE USING NONLINEAR SEISMIC RESPONSE ANALYSIS

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Seismic Design Guidelines To Mitigate Upheaval Buckling Of Small Diameter Pipes

Behavior of Lateral Resistance of Flexible Piles in Layered Soils

Evaluation of Tsunami Loading Based on Collapse Load of Structures

How to Design a Singly Reinforced Concrete Beam

DYNAMIC-RESPONSE CHARACTARISTICS OF STRUCTURES WITH MICROPILE FOUNDATION SYSTEM

Fire Resistance of Composite Beams Composed of Rolled Steel Profile Concreted Between Flanges

Transcription:

Title Failure Mechanism of Anchored Retai Anchor Head Itself Being Broken Author(s) Itoh, Kazuya; Kikkawa, Naotaka; Toy Naoaki; Katada, Toshiyuki Proceeding of TC3 Symposium Osaka Citation Symposium on Backwards Problem in G Engineering and Monitoring of Geo-C 1 Issue Date 11 URL http://hdl.handle.net/33/1735 Right Type Article Textversion publisher Kyoto University

Failure mechanism of anchored retaining wall due to the anchor head itself being broken Kazuya Itoh, Naotaka Kikkawa & Yasuo Toyosawa Construction Safety Research Group, National Institute of Occupational Safety and Health, Japan (JNIOSH), Tokyo, Japan Naoaki Suemasa & Toshiyuki Katada Department of Civil Engineering, Tokyo City University, Tokyo, Japan ABSTRACT: In this research, a case history of temporary earth support collapse is first illustrated briefly and the mechanisms of accident occurrences are introduced, with the results showing that the shallow penetration of piles mainly caused the sequences of collapse. In order to understand these failure characteristics and mechanisms, centrifuge model tests using an in-flight excavator were carried out. The failure mechanism of the retaining wall in this labour accident was firstly demonstrated using centrifuge model tests by Toyosawa et al. (199). In this paper, we added some viewpoints regarding the mechanism of the retaining wall and it was thus clarified that the active and passive earth pressures in the retaining wall increased during excavation and then the anchor head exceeded the capacity with respect to tensile stress. As a result, the retaining wall and ground behind the wall collapsed suddenly. 1 INTRODUCTON Accidents due to collapse frequently occur during ground excavation. The need to decrease these accidents is currently a major concern not only in Japan, but also in several other countries as well. Firstly, a case history has been described in which a temporary earth support collapsed and the ground behind the support failed. A total soil volume of m 3 with a maximum thickness of m slid into an excavation area and as a result five workers were killed and two others were injured. Secondly, in the laboratory, the model ground in front of the anchored retaining wall was excavated using an in-flight excavator in a centrifugal field. Based on the results of two centrifuge model tests, the deformation characteristics, the earth pressure and failure mechanisms are discussed in this paper. CASE HISTORY OF THE TEMPORARY EARTH SUPPORT COLLAPSE.1 Outline of the construction work This accident occurred at the building construction site which had an excavation area width of 17. m and length of 3.3 m as shown in Figure 1. Figure shows the results of a boring log geological survey. The main piles were used as a temporary earth support system with the lateral wooden sheeting method. The length and the interval of the main piles were 15 m and 1 m, respectively. The diameter of the ground anchors was 117 mm, the length 13

17. 1.5 Fig. 1 The ground plan and location for the boring investigation 11. 7.5 3.9 (a) The scene of the collapse accident (from south side) 3. (b) The scene of the collapse accident (from north side) Fig. Boring log of the construction site was.5 m (effective length 5. m), the angle was 5 degrees and the horizontal interval of the anchors was.5 m.. Situation relating to the accident occurrence In the morning that the accident occurred, at around 1: a. m., workers noticed that some H- steel piles on the east side had not penetrated below the excavation bottom. The engineer in charge felt there was a danger of a collapse, and he tried to reinforce the main piles with additional remedial piles and blind concrete. At around 1:15 p.m., with a loud noise, the central 15 m of the temporary earth support structure on the east side collapsed suddenly with the ground behind the support. The ground slid into the excavation area with a soil volume of approximately m 3 and a maximum thickness of approximately m. (c) Damaged H- steel for anchor head Fig. 3 The scene of the collapse accident Due to this collapse, eleven H- steel piles toppled. Four workers at the bottom of the excavation site were buried alive and three workers were struck by H- steel piles. As a result, five workers were killed and two others were injured. 1

H steel (H-3*3*1*15) Anchor head Anchor Excavation level of design Actual excavation level before failure Fig. Estimated mechanism of the collapse Fig. Cross section of profile of two layers Actual ground level Excavation shortage (3.3) Ground level for design Subgrade.3.3.3 3..3 5. Fig. 7 Model of sheet pile wall Fig. 5 The cause of a shortage of embedded depth of sheet pile walls.3 Estimation of the mechanism of the collapse The sequence of collapse is shown schematically in Fig.. The mechanism of collapse is summarized as follows; 1) Remedial work was being performed on the excavation bottom despite insufficient penetration of the main piles. It is assumed that, due to insufficient penetration, the earth pressure caused the displacement of the main piles. ) The main piles were supported by the ground anchors installed at an angle of 5 degrees from the horizontal plane. Downward force provided from the anchor's tensile force made the connection between the wale which supported the anchor heads and the anchor heads ineffective. 3) Finally, the unstable earth support structure led to a huge-volume soil collapse. The cause of insufficient penetration of the main piles was shortage of excavation at the upper site; due to an engineering error which disregarded the plane of design as shown in Figure 5.. Monitoring Instrumentation is usually required to monitor the performance of a sheet pile structure during construction. Measurements of movements and pressures furnish valuable information for use in verifying design assumptions. Most importantly, the data may forewarn of a potentially dangerous situation that could affect the stability of the structure. In this construction site, however, only visual inspection was used, such as checking for unusual surface signs. 3 CENTRIFUGE MODEL TESTS 3.1 JNIOSH NIIS Mark II Centrifuge Centrifuge model tests were conducted to examine the failure mechanism of this accident, such as the retaining wall supported to ground anchors. All the tests described here were conducted using the JNIOSH NIIS Mark II Centrifuge (Horii et al. ). 3. In-flight excavator The in-flight excavator developed by Toyosawa et al. (199) was used in this paper. In this test, for the excavation, this excavator can rake the soil horizontally by using a cutting blade. The movement of the in-flight excavator was controlled manually from the centrifuge operation room which is in the upstairs of the centrifuge. The model ground was excavated in steps up to the occurrence of collapse, where the excavated height of each step was about 5mm or mm. 15

7 Fig. Physical modelling of broken anchor head Fig. 1 Model setup Load (N) 1 B = mm 1 3 3.3 Model preparation (a) Pullout test apparatus B = 3. mm 1 3 Displacement (mm) B = 3 mm (b) Load displacement curves in pullout test Fig. 9 pullout test 1 3 From the boring log of the construction site shown in Figure, the excavation site consists mainly of Kanto loam (a kind of volcanic cohesive soil in Japan), sand and silt layers. In this paper, (1) a unit layer of sand, and () a strata of Kanto loam and sand layer were tested. 3.3.1 Sand layer Toyoura sand was poured uniformly into an alminium model box in which wall and anchors had been set. The relative density of sand was about 9 %. 3.3. Kanto loam and sand layer Toyoura sand was poured into the aluminium model box to a designated level. Then Kanto loam was placed and compressed on the sand layer. The profile of the model is illustrated in Fig.. An aluminium model box with internal dimensions of 1 mm (w), 5 mm (l) and 7 mm (h) was used. A Perspex window was installed in one side of the box in order to observe the model during the centrifuge test. The model sheet pile was inserted to the predetermined penetration depth. The model anchors, which were 1. mm diameter wire ropes through Teflon tubes, were installed at 5 degrees and the ends of wires were connected to the load cells. Figure 7 shows the model of sheet pile ( mm thick aluminium) with eight earth pressure sensors and six strain gages. 3. Modelling of broken anchor head Figure gives the experimental system for the broken anchor head used in this study. The mechanism of the broken anchor head is as follows. It is a problem of a simply supported beam of length B, and cross section, φ, carrying a tensile force. A series of pullout tests is carried out to clarify the brittleness of the anchor head model as shown in Fig. 9(a). Fig. 9(b) shows typical examples of how the beam of length B, would change the load - displacement curves for the case of wood (ramin) and cross section, φ, of 3mm. Comparing the data obtained from the beam of length B, it can be clearly seen that there is a decreasing maximum load as B increases. In this study, the model anchor head used was wood (ramin), B of mm, φ of 3mm from tensile force 9N at failure by Toyosawa (199). 3.5 Test procedure Figure 1 shows the model setup in the aluminium model box. The sensor s pressure value and bending moment on the model sheet pile were initialized prior to the model setup. Preloading for each anchor was adjusted to 9. N before testing. The centrifugal acceleration was then increased to 5g for each test. Once every sensor s value was stable, the excavation started. To simulate the real accident, the ground in front of the model sheet pile was excavated by the in-flight excavator to a depth of 9.5 m near the end of the sheet pile. 1

TEST RESULTS AND DISCUSSIONS.1 Sequence of failure Figure 11 shows the profile of each model after failure. Figure 11(a) shows the model with sand layer after failure. During the excavation process, the penetration depth of the wall decreased step by step as excavation proceeded. Failure occurred when the penetration depth of the wall reached about 35 mm and continuous failure with a small displacement emerged with each excavation step. Figure 1 shows the ground displacement field behind the model sheet pile at the final excavation step using PIV (Particle Image Velocimetory, Kikkawa et al. ). The failure line angle was about 5 degrees. The model consisting of Kanto loam and sand layers is shown after collapse in Fig. 11(b). The failure happened suddenly when the penetration depth reached about mm. The failure line s angle in the sand was about 5 degree.. Earth pressure and bending moment on sheet pile walls The measured earth pressure (total lateral stress) on the model sheet pile together with depth during increasing centrifugal acceleration and excavation processes are shown in Fig. 13. The active and passive earth pressures increased during excavation rather than with increasing centrifugal acceleration. For the sand layer model (Fig. 13(a)), both pressures rapidly increased at an excavation depth of 35mm. For the Kanto loam and sand layer (Fig. 13(b)), the active pressure exceeded kn/m and the passive pressure exceeded 1 kn/m at an excavation depth of mm. The variations of the bending moment with the depth of wall are shown in Fig. 1. The bending moment increased almost uniformly as the centrifugal acceleration increased. On the other hand, during excavation, the moment at the middle of the pile rapidly increased while the moment of the pile at the excavation surface decreased as the excavation depth increased. Therefore, the pile was bent significantly as the upper part of the pile stuck out while the pile at the excavation surface did not move much. This suggested that the anchor head suffered severe tensile force due to the bent pile..3 Tensile force acting on anchor Figure 15 shows the measured tensile force acting on the anchor with increasing centrifugal acceleration and excavation steps. The values in this figure were the average of the two anchors which were set in one model. The tensile force increased with increasing acceleration in each test. During the excavation process, tensile force increased gradually prior to the failure in both cases. It should be noted that those tensile forces were almost the same as the capacity of the anchor head as shown in Fig. 9, or had already exceeded the capacity. Therefore, it is believed that the active and passive earth pressures increased during excavation and then caused the anchor head to break. As a result the retaining wall and the ground behind the wall collapsed suddenly. 5 CONCLUSIONS (a) Sand layer (b) Kanto loam and sand layer Fig. 11 Profile of models after failure Fig. 1 PIV analysis in the case of the sand layer In this study, the case history of the labour accident involving the collapse of the anchored retaining wall was introduced. In order to understand the mechanism of the accident, we performed the centrifuge model tests in which model ground in front of the anchored retaining wall was excavated using an in-flight excavator. 17

1 Sheet pile wall Acceleration field 1G G 3G G 5G.5 m.5 m.75 m 1. m 1.5 m 1.5 m 1.75 m Initial level before excavation 1 Acceleration field 1G G 3G G 5G.3 m. m.9 m 1. m 1.5 m 1. m.1 m. m.7 m 3. m [Active side] [Passive side] - - - - 1 1 1 Lateral Pressure (kn/m ) (a) Lateral pressure on wall (Sand layer) - - - - 1 1 1 Lateral Pressure (kn/m ) (b) Lateral pressure on wall (Kanto loam and sand layer) Fig. 13 Lateral pressure on wall 1 Acceleration field 1G G 3G G 5G.5 m.5 m.75 m 1. m 1.5 m 1.5 m 1.75 m 1 3 Bending Moment (knm) (a) Bending moment at wall (Sand layer) Sheet pile wall 1 Acceleration field 1G G 3G G 5G.3 m. m.9 m 1. m 1.5 m 1. m.1 m. m.7 m 3. m Initial level before excavation Active side Passive side 1 3 Bending Moment (knm) (b) Bending moment at wall (Kanto loam and sand layer) Fig. 1 Bending moment at wall Based on the results of centrifuge model tests, it was revealed that the active and passive earth pressures in the retaining wall increased during excavation and the anchor head exceeded the capacity with respect to the tensile stress. As a result, the retaining wall and ground behind the wall collapsed suddenly. REFERENCES Toyosawa, Y., Horii, N., Tamate, S., Suemasa, N., and Katada, T. (199). Failure mechanism of anchored retaining wall. Proc., Int. Conf. Centrifuge 9, Tokyo, Rotterdam, Balkema, pp.7-7. Toyosawa, Y., Horii, N., Tamate, S. and Suemasa, N. (199). Failure characteristics of sheet pile wall in centrifuge tests. Proc., Geotechnical aspects of underground construction in soft ground, Balkema, pp.5-3. Horii, N., Itoh, K., Toyosawa, Y. and Tamate, S.. Development of the NIIS Mark-II geotechnical centrifuge, the th International Conference on Physical Modelling in Geotechnics, Ng, Zhang and Wang (eds.), Taylor & Francis, pp. 11-1. Tensile force acting on anchor (N) [Increasing acceleration] 1 1 1 3 5 Acceleration filed (g) [Excavation] Sand layer Kanto loam & Sand layers 1 3 5 (mm) Fig. 15 Tensile force with increasing centrifugal acceleration field and excavation steps Kikkawa, N., Nakata, Y., Hyodo, M., Murata, H., and Nishio, S.. Three-dimensional measurement of local strain using digital stereo photogrammetry in the triaxil test, Hyodo, Murata and Nakata (eds.), Taylor & Francis, pp. 1-7. 1