Application for an Ontario Certificate of Authorization For Ontario based businesses CSA N285.0 Nuclear Components

Similar documents
Application for an Ontario Certificate of Authorization For businesses based Outside Ontario CSA N285.0 Nuclear Components

Conformity Assessment. Section III Nuclear Requirements Buenos Aires, Argentina May 2017

ACCREDITATION OF MANUFACTURERS OF BOILERS & PRESURE VESSELS

NOTICE ON NUCLEAR SCOPE STATEMENTS

ACCREDITATION OF PRESSURE RELIEF VALVE REPAIR ORGANIZATIONS

ACCREDITATION OF FITTING MANUFACTURERS

ACCREDITATION OF MANUFACTURERS AND INSTALLERS OF PRESSURE PIPING PARTS AND SYSTEMS

ACCREDITATION OF BOILER AND PRESSURE VESSEL REPAIR OR ALTERATION ORGANIZATIONS

2001 NBIC Interpretations

DESIGN REGISTRATION GUIDELINES FOR NUCLEAR PRESSURE RETAINING SYSTEMS AND COMPONENTS

GUIDE FOR ASME REVIEW TEAM LEADERS FOR REVIEW OF APPLICANTS FOR ASME CERTIFICATES OF AUTHORIZATION H (Cast Iron/Cast Aluminum)

NR CHECKLIST Rev. 1. QAM IMP References NBIC Part 3, 1.8 Y N Y N a. Organization. Company Name/Certificate Number: Page 1 of 26

Quality Control Manual Submission Information

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS

Quality Control Manual Submission Information

1.0 Purpose: To provide a method of assuring that Section XI Repair and Replacement activities. 3.1 ASME B&PV Code, Section XI, Article IWA-4000

Welding Performance Testing Administrators GUIDE FOR ASSESSMENT OF QUALITY CONTROL MANUALS

2004 NBIC Interpretations

Guide for the preparation of quality programs for licensing of companies performing BPE regulated work.

Living with ITAAC. ASME Nuclear Technical Seminars: Blueprint for New Build June 5-8, 2011 Columbia, SC

GUIDE FOR ASME REVIEW TEAMS FOR REVIEW OF APPLICANTS FOR ASME RP CERTIFICATE OF AUTHORIZATION. The American Society of Mechanical Engineers

Washington Association of Building Officials. Standard 1702 Steel Fabricator Registration Program

Certified Welding Fabricator (CWF) Program Information

Frazier Reliability Solutions

Regardless of any alternative pricing provided, a quotation for the items specified herein shall be provided.

Buongiorno! ASME N3 & NQA-1Certification Benefits to D&D Ventures. Dr. Dirk Kölbl. Authorized Inspector Supervisor NQA-1 Lead Auditor

Presented by: Gary Scribner Manager of Technical Services. Shanghai April The National Board of Boiler and Pressure Vessel Inspectors

HOW TO CONSTRUCT ASME BOILER BY THAI ASSOCIATION OF BOILOER AND PRESSURE VESSEL

B Contractor Licensing GUIDE FOR APPLICANTS

ASME NQA-1 Certification. Matthew Vazquez September 4, 2017

QUALITY ASSURANCE PROTOCOL (QAP)

Welding Performance Testing Administrators GUIDE FOR ASSESSMENT OF QUALITY CONTROL MANUALS

Regardless of any alternative pricing provided, a quotation for the items specified herein shall be provided.

INFORMATION AND PROCEDURES FOR OBTAINING N, NA, NPT, NV, N3 & NS NUCLEAR CERTIFICATES AND CERTIFICATION MARK CLASS l, 2, 3, MC, CS, CC &TC

Pressure Points. Governing Code Edition Section I Table of Contents

Business Energy Rebates Application

NB-435 Rev. 1 Page 2 of 5

NUCLEAR QUALITY ASSURANCE MANUAL

M9C 1A3 VELO (PH) (FX)

National Board Authorization and Accreditation Programs

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS

ACCREDITATION OF MANUFACTURERS OF NUCLEAR ITEMS

INFORMATION AND PROCEDURES FOR OBTAINING AN ASME CERTIFICATE OF ACCREDITATION AS AN AUTHORIZED INSPECTION AGENCY

Presented by: Gary Scribner Manager of Technical Services. August The National Board of Boiler and Pressure Vessel Inspectors

Conformity Assessment. Jon Labrador & Paul Lang ASME Perspective & Benefits September 2016

Conformity Assessment. Paul Lang & Mike Frediani ASME Perspective & Benefits February 2017

OWNER USER INTEGRITY MANAGEMENT SYSTEM WRITTEN DESCRIPTION CHECKLIST AB-512(b)

SECTION III DIVISIONS 1 AND 2

SUPPLIER QUALITY SCOPE AND FACILITY QUESTIONNAIRE. Bantrel Co. Project #:

REVISIONS. App Sud. App PC. App Thom 2011/12/31 AA 2011/12/31 NK 2012/08/09 N/A AA 2015/07/20

Nuclear Fabrication Supply Chain

Pressure Piping Construction Requirements QMS written description verification CHECKLIST AB-518b

Conformity Assessment

Certification, Testing, Approval and R&D work on the Absorber Safety

QUALIFICATIONS NEEDED TO DESIGN, CONSTRUCT AND MANUFACTURE NUCLEAR SYSTEMS AND EQUIPMENT. Cosmos M. Voutsinos, P.Eng.

ASM AEROSPACE SPECIFICATION METALS, INC NW 34 th Place #B28 Terrace Pompano Beach, Florida Tel: Fax:

Accreditation of Hot Tap Organizations

Water Services Guidelines

JOHN WOOD UNCONTROLLED COPY: THE JOHN WOOD COMPANY PO BOX HIGHLAND AVENUE OAKS, PENNSYLVANIA 19456

SUPPLIER QUALITY ASSESSMENT

HSB Global Standards ASME Code Changes and Discussions ASME Code Section VIII-1 and Referencing Code Section IX

Subcontractor / Supplier Pre-Bid Qualification All fields must be filled out unless otherwise noted.

Procurement Engineering Standard Purchase Clause

Procurement Engineering Standard Purchase Clause

Overview of Draft API Standard 20M

BILLING TIME LOG. Inspector's No: Inspector's Name: Site Address: Contractor's Name: Date Start time End Time Total Hours Comments

Tech Ord Supplier Quality Survey. Supplier Survey Evaluation

002 Supplier Quality System Compliance with Rocker Quality System for Suppliers is required for this Purchase Order.

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6

Manufacturing % Distribution % Broker % Other % Do you have liability Insurance? Contact Name Direct Telephone/Extension

Procurement Engineering Standard Purchase Clause

Pressure Equipment Repair and Alteration Requirements

Procurement Engineering Standard Purchase Clause

Procurement Engineering Standard Purchase Clause

AMERICAN WELDING SOCIETY NATIONAL ACCREDITED TESTING INFORMATION

Review for S, A, PP, E, M, H (other than Cast Iron and/or Cast Aluminum), HLW, U, UM, U2, U3, RP and T Certificates

B Contractor License GUIDE FOR ASSESSMENT TEAMS & APPLICANTS

Quality Manual 2012 `

Business Energy Rebates Application

UNCONTROLLED QUALITY CONTROL MANUAL FOR. FISHER CONTROLS INTERNATIONAL, LLC, VALVE DIVISION 1702 SOUTH 12 th AVENUE MARSHALLTOWN, IA 50158

(Name and address of Manufacturer) (Name and address of Purchaser) (Name and address)

Supplier Evaluation Program Doosan QA Team / Jeong Sun Kim

Procurement Engineering Standard Purchase Clause

Pressure Piping Construction Requirements

Boiler and Pressure Vessel Code

WELDING ENGINEERING FABRICATION

TABLE OF CONTENTS. 1.0 INTRODUCTION Page SCOPE Page REFERENCES Page REQUIREMENTS Page QUALITY ASSURANCE Page 8

Water Services Guidelines

Procurement Engineering Standard Purchase Clause

1.0 Purpose. 2.0 General notes 3.0 QUALITY SYSTEM REQUIREMENTS. Approved by: G. Stugart Prepared by: Schelert

October Purpose

Procurement Engineering Standard Purchase Clause

Maintenance Program Guideline for Owners of Ammonia Plants

Practical Skills/Experience Sign-Off Document. Zip Line Mechanics (Under Ontario Regulation 187/03, Technical Standards and Safety Act, 2000)

Supplier / Vendor / Repair Agency Self-Evaluation Questionnaire

Basement Flooding Protection Subsidy Program

Procurement Engineering Standard Purchase Clause

Procurement Engineering Standard Purchase Clause

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018

Transcription:

345 Carlingview Drive PRINT Click to clear On completion, send this form to the attention of Boilers and Pressure Vessels Safety at the top left TSSA address. Company: (Legal Company Name and Corporation No.) Division: (If required) Facility Address: (Including street, city, state, country, postal / zip code) Billing Address: (If different from Facility Address) Nuclear Class 1 1C 2 2C 3 3C 4 (Check all applicable) Code Effective Date: CSA N285.0 Edition Update This application is for Shop and ASME Edition Addenda Field Sites Certified by TSSA (All current locations to be listed on page 3) (Check all applicable): New Certificate Renewal Certificate If renewal: Current certificate number(s) Expiration date(s) Type of Certificate of Authorization for which application is being made (check all applicable): Nuclear Certificate Type Nuclear Components: (N Type) Certificates Scope Vessels Piping Systems Storage Tanks Pumps Line Valves (Cat. C Fittings) Subcontracting Type only for which overall responsibility is retained and for which all fabrication and installation is subcontracted to other appropriate certificate of authorization holders Nuclear Pressure Relief (NV Type) Requires design capability (Fitting Category G) Pressure Relief Valves Part Piping Subassembly Rupture Discs Tubular Products Welded with Filler Metal Nuclear Parts: (NPT Type) Rev. 0 January 2018 Page 1 of 5

Nuclear Supports: (NF Type) Standard Welded Non-standard Non-Welded Nuclear Assembly: (NA Type) Field Installation limited to field sites defined in the Quality Assurance Manual Shop Assembly Category Nuclear Fittings CSA standard seamless fittings, except for Category C & G, may be treated as material Manufacture or Supply. If CSA standard Fittings are to be treated as material, complete the Application for Metallic Material Organizations in addition to this application form A B D E F H Standard Fitting to a material & dimensional standard Seamless Welded Without Filler Metal Non-Welded Non-standard Welded With Filler Metal Nuclear Repair and Modification Repair Modification Welded Non-Welded Special Processes: Nuclear Pressure Relief Valve Repair Only Machining Welding Heat Treatment Test Media: Steam Air/Gas Liquid Nuclear Certificate Scope Addition (check all applicable): Add Material Manufacture or Material Supply activities to this Program. Not applicable to N Type Subcontracting. (Complete the Application for Metallic Material Organizations in addition to this application form) Rev. 0 January 2018 Page 2 of 5

Subcontracted Activities (Identify the activities that are intended to be subcontracted - check all applicable): Design Examination (NDE) Auditing Welding Heat Treatment Fabrication Material Testing Calibration Installation Testing (Proof, Hydro, etc.) Others Corporate Certificates Corporate Certificate Yes Corporate certificate extension for certificate number(s) Additional Activities Performed at Other Locations (attach additional sheets if required): Location Activity Name of Authorized Inspection Agency (AIA) of Record Do you have a signed Inspection Services Agreement with the above listed AIA? YES NO Company Abbreviation (if used on nameplate or stamping): FEES: Ontario applicants, please include a cheque for the Survey fee deposit with this application as shown below. A Pro- Forma Quote will be provided with additional charges that will be invoiced. Applicants outside of Ontario are required to use the correct application and contact TSSA for a quote (additional fees will apply). Description Deposit Required Amount Submitted (All Nuclear Surveys except Metallic Material Organization) $6,840.00* Rev. 0 January 2018 Page 3 of 5

CANCELLATION / POSTPONEMENT FEES: Cancellation or postponement, by an applicant, of a scheduled N285.0 Nuclear Survey in Ontario, which occurs 30 working days or less from the agreed site implementation Survey date, will be invoiced as follows. The cancellation fee, also if applicable, any additional charges due to airfare charges, plus applicable taxes will be deducted from the Survey fee deposit. The applicant will be invoiced for the outstanding balance upon completion of the Survey. NOTES: - Nuclear Component Survey cancellation or postponement fee $1920.00* 1) Total Survey charges will include the above deposit amount plus hourly billing at the current inspection rate as outlined in the Boilers and Pressure Vessels Fee Schedule for the Quality Assessment Specialist, Authorized Nuclear Inspector and Authorized Nuclear Inspector Supervisor s travel, expenses and Survey time. 2) Team Leader time at location and for review of the manual and travel cost is included in the above deposit amount however, if air travel is required then airfare and expenses are extra and not included in the deposit amount. 3) Any Extra time for team leader due to additional location and follow-ups will be billed per current inspection rate as outlined in the Boilers and Pressure Vessels Fee Schedule. 4) Time for Pre-survey is not included and will be billed separately per current inspection rate as outlined in the Boilers and Pressure Vessels Fee Schedule. 5) The following activities related to the Survey such as: Quality Manual pre-reviews, meetings and/or consultations, pre-survey inspections (and/or site visits), and post-survey follow-ups (site visits and/or document review) will be billed at the current inspection rate as outlined in the Boilers and Pressure Vessels Fee Schedule. 6) Time in excess of 8 hours per day will be billed at the overtime rate (1.5 times hourly inspection rate in effect at the time of the Survey), per TSSA Survey team member. 7) Each Certificate of Authorization will be invoiced at a cost of $89.00 per certificate, upon completion of a successful Survey. 8) *13% HST is applicable to the Survey fee, hourly inspections billing, and cancellation/postponement fees. 9) Applications for each of the following certificate programs requires a separate quality program implementation demonstration, on a demonstration item or production work in progress, to show all aspects of the program applied for, in current operation to a TSSA survey team. Applicants should ensure that the written program is accepted by Authorized Nuclear Inspector Supervisor & fully implemented at each location before requesting TSSA to perform a survey. a) Each location street address for which a nuclear construction or fabrication certificate of authorization is requested (e.g. N, NV, NPT, NA, NS type certificates, including N Subcontracting type) b) All supporting location addresses where procurement, QA and/or engineering activities are being controlled, managed and administered; including those support activities performed at sites other than the main certificate holder location street address. c) Field Site location implementation demonstration at locations remote from any other shop location street address in (a) above when Field installation at nuclear sites certified by TSSA is requested by the applicant for the certificate of authorization. d) For each shop location street address that wishes to include nuclear Material Supply or Material Manufacture including material warehousing, secure storage, and quarantine capabilities; the addition of each of the following activities shall be individually documented in the manual with implementation of the program controls satisfactorily demonstrated by the applicant, before they can be included in a certificate.: Shipment of Material from Qualified Material Organizations to other parties ; Qualification of Non-certified Material Organizations ; Utilization of Unqualified Source Material ; Approval and Control of Suppliers e) For field locations not active at the time of a TSSA survey an additional site visit and implementation demonstration is required. TSSA shall be contacted for a certification survey immediately upon commencing work at each such location. Rev. 0 January 2018 Page 4 of 5

By signature below and as a part of TSSA accreditation, the applicant accepts all conditions related to the issue and Use of each Certificate of Authorization provided by TSSA and agrees to unannounced TSSA surveys of the program at TSSA s discretion. Name: Phone: Signature: Title: Email: (Must be signed by a Senior Company Officer or Designee) Date: Rev. 0 January 2018 Page 5 of 5