Bill of Quantity. Unit Price in words (Nu) Unit Price (Nu) Code Description Unit Quantity. Amount (Nu) CP-AR-

Similar documents
Bill of Quantities. Bill 1: Site Preparatory Works. Page No. 1/7. Bill 1 Page 1/1. Contract No.

Contract Identification No. and Package 1. SUHEP-067/68-Lot No.1-AR: Package B 2. SUHEP-067/68-Lot No.1-AR: Package C

Earth Retaining System

ITEM No. D E S C R I P T I O N UNIT QTY. 5-E343.2 In class III material m³ 1,260 - Max. Depth: m For disposal

Figure Inlet protection (Source: Minnesota DOT)

Special Provision No. 405F03 March 2005

Construction Inspection Checklists

SECTION EROSION AND SEDIMENTATION CONTROLS

Requirements for Measuring and Pricing of Structural Concrete

Method of Measurement for Road Works Series MM Earthworks

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS

MagnumStone Specifications Gravity

B Insurance against injury to persons, property and works item 1. C Performance Bond 5% of Contract amount item 1. D Security and transport item 1

APPENDIX 5: CONSTRUCTION CHECKLISTS

TABLE OF CONTENTS. 0 Structural calculations 0.1 General 0.2 Safety concept 0.3 Calculations for waterfront structures

FOUNDATIONS. Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION

Welded Mesh Gabions and Mattresses River Protection Design Guide Anping County Zhuoda Hardware Mesh Co.,Ltd. Wire Mesh Industrial Zone, Anping

Pulaski County, Virginia

MECHANICALLY STABILIZED EARTH (MSE) WALL SYSTEMS

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES

Gravity Wall. A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures

8.01. SUB TOTAL 1 1,168, ADD 16% VAT 187, TOTAL 1,356, Total Carried Forward to Form of Tender:

HUITEX GEOCELL INSTALLATION MANUAL

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

Straw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow

378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE

freestone eco Prestige & quality DIY vertical wall Large blocks - 10/m 2 Smooth surface finish No concrete footings

Specialty Applications. for Keystone Walls

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS

Retaining Walls. Made Easy

FACING OPTIONS FOR REINFORCED STEEPED SLOPES

Description Unit Quantity Rate Kshs. Amount Kshs.

SECTION SPECIFICATION FOR MECHANICALLY STABILIZED EARTH TWO STAGE WALL SYSTEM

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

Guide on Risk Mitigation Works

Jericho Agro Industrial Park

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

Stone and Masonry Veneer

A.2.a Random Riprap... Table

TION GUIDE ALLA T INS

Method of Measurement for Road Works Series MM Structural Concrete

EROSION CONTROL GENERAL NOTES EC JAN 2017 C.B.

Installation Guidelines

A complex reinforced structure applied at hilly road repair case in Taiwan

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES

FREESTONE ECOTM. Retaining Wall SystemTM. No one knows Blocks and Pavers better

Topic: Site Formation

WATER QUALITY. Our Focus Today. Erosion Control Technologies & Solutions. What is Soil Erosion. Federal Regulations

A Complete Retaining Wall Solution >

Specialising in Ground Engineering & Slope Stabilisation

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

Tips with Creation of your Erosion and Sediment Control Plan

Design and Installation Guidelines for Retaining Walls. 1 P age. Geo Products, LLC 8615 Golden Spike Lane Houston, TX Phone:

ADDRESS: 122 LIPSCOMBE ROAD, DECEPTION BAY, QLD,

Index to Technical Specifications

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS

SECTION EROSION CONTROLS

GEOTECHNICAL ENGINEERING ECG 503 LECTURE NOTE 05 TOPIC : 2.0 SLOPE RISK ENGINEERING

TITLE: SLAUGHTER HOUSE SEPTIC TANK. ITEM No. D E S C R I P T I O N UNIT QTY

LM2-18 Site Photos Laura Creek

CONSTRUCTION SPECIFICATION FOR TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES

CONTRACT NO. : MTK11/2017 REHABILITATION OF MSAULI ASBESTOS MINE SCHEDULE OF QUANTITIES SECTION 1: PRELIMINARY AND GENERAL

Appendix B.2. Construction Specifications for Infiltration Practices

Construction works for Establishment of School in Al-Najaf M 2 2,600 M 2 750

Statement of Special Inspection Requirements

INSTALLATION GUIDE SLABS

5-20 FOUNDATION REPORT/GEOTECHNICAL DESIGN

a. Unless otherwise specified, all lengths shall be horizontal distances.

Scanned by CamScanner

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

SPECIFICATION FOR REINFORCED SOIL WALL

reinforced besser block retaining walls

1.02 RELATED WORK: Refer to the following sections for related work:

CITY OF ORANGE PUBLIC WORKS DEPARTMENT GRADING FIELD INSPECTION REQUIREMENTS

1. Remove worn-out old plaster (or any other finishing).

CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION Edition

The design of soil nailed structures to AS4678

North Umpqua Hydroelectric Project (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form

Construction works for Establishment of School in Al-Latifiyah. Al-Latifiyah BoQ for constructing a 6-pre-fab Classroom School

BELMURO WALL SYSTEM INSTALLATION GUIDE

CLEARING & GRADING GENERAL NOTES CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS SHEETNUMBER BCP PROJECT NO.: DATE: 11/1/18

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Properly constructing and maintaining a road drainage system is the most effective ways to reduce flood damage

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

CONSTRUCTION SPECIFICATION

CONSTRUCTION SPECIFICATION FOR TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES

C231 Subsoil and Foundation Drains

Fence Stone. Self locating Wall System

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION

F500 Steeplechase Waterjump with Valve Option

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00

AN ISO 9001 & COMPANY TENDER DOCUMENT. TENDER No: EPI/WRO/CON/757/0119 FOR

q Item meets standard Project ID: X Item not acceptable Contractor: N/A Item not applicable Inspector: C Item requires engineer s cert.

Transcription:

in 02 03 RS-AR- 04 RS-AR- 05 06 07 Access track rehabilitation, to Vegetation clearing as necessary for both the track section to undergo rehabilitation, and track section to be extended/created Earthworks according to TS for creation of track for sections to be extended/created including extension to base of Reldri School landslide. Preparation of suitable track base camber and management of surface water Periodic maintenance during construction site duration Access track surface layer, to Supply, laying, and compaction of 10cm layer of gravelly material along entire track length, for both the track section to undergo rehabilitation, and track section to be extended/created. Thickness refers to compacted thickness. Periodic maintenance of this surface layer during construction site duration as specified in TS Earthworks at Reldri School Road, to All vegetation clearing necessary for earthworks All earthworks and excavations to required elevation levels and using means as described in Technical. Removal of excavated material to deposit area as Surface layer application at Reldri School road, to Supply, laying, and compaction of 10cm thick gravelly layer of material of grade 2/100. Thickness refers to compacted thickness. Excavation earthworks for nailed wall, to Vegetation clearing for vegetation including all trees below 300mm girth as described in the Technical Tree removal for trees above 300mm girth as described Levelling of mounds at top of the landslide Excavations in preparation for wall, carried out using the means Removal of surplus excavated material to deposit as described in Technical Infill using sandbags to create earth platform between profiles 7 and 8, to Infill by earth platform creation using sandbags between profiles 7 and 8 as required m 3 4,800 m² 4,800 m 3 1,100 m² 400 m 3 53,000 m 3 500

in Construction of nailed wall, to 08 Supply and installation of wall facing reinforcement in the form of welded wire mesh Supply and installation of formwork including lost formwork where required 09 08-10 11 EW003 0/31 Supply and application of shotcrete for wall facing, including supply and installation of equipment required for shotcreting, accessories such as spacing devices to ensure required steel coverage and width dimensions, and shotcrete provision for compensation terrain-wall layer where required Supply and installation of nail head devices (plate, nuts ) Control tests relating to the construction of the nailed wall, in particular the conformity and control tests on the grout and concrete Borehole drilling and installation of soil nails, to Borehole drilling for wall nails, including supply, installation, and use of drilling equipment and necessary accessories to drilling Supply and installation of wall nail bars of diameter 40mm, including all accessories required (such as spacers, grout socks as described in Technical, all grout ) Control tests relating to the construction of the nailed wall, in particular the conformity and control tests on the soil nails Construction of parapet at top of wall, to All supplies and work relating to the masonry work for the parapet construction at the wall top Construction of sub-horizontal drains, to Borehole drilling for sub-horizontal drains, including supply, installation, and use of drilling equipment and necessary accessories to drilling Supply and installation of pipes in conformity with the Technical Construction of weephole drainage pipes, to Supply and installation of pipes as required for nailed wall, as Excavations for large gabion dams, including: Excavation for foundation of dam using means described in TS m² 1,620 ml 5,250 m 3 150 ml 590 U 338 m 3 300

in Supply of all materials, installation in situ, and filling of AR-12 required volume of principal dam gabions in manner required Supply of all materials, installation in situ, and filling of required volume of thin anti-scour gabions of thickness 0.4m in manner required m 3 1,400 AR-13 EW003 0/31- Backfill for large gabion dams, including: Installation of backfill with compaction to 50% volume as Filling at back of dam at a maximum slope of 7 in conformity with the Technical Excavations for large sandbag dam foundations, to Excavation for foundation of dam using means described in Technical m 3 1,050 m 3 350 AR-14 Sandbags required for large sandbag dams, filled with sand, to Supply of all materials, filling, and installation in situ of required volume of sandbags for centre of structure in manner required m 3 820 AR-15 AR-12- Sandbags for large sandbag dams, filled with sand/soil mix, to Supply of all materials, filling with earth/sand mix, and installation in situ of required volume of surface layer sandbags with gunny bags in manner required in the Technical Fill between the sandbags at surface layer as described Gabions of thickness 0.4m for large sandbag dams, to Supply of all materials, installation in situ, and filling of required volume of thin, anti-scour gabions of 0.4m thickness in manner required in the Technical m 3 820 m 3 200 AR-13- Backfill for large sandbag dams Installation of backfill with compaction to 50% volume as Filling at back of dam according to slopes described in the Technical m 3 2,300

in Sandbags required for small sandbag dams, filled AR-14- with sand, to Preparation of platforms to receive small dams AR-15- Supply of all materials, filling, and installation in situ of required volume of sandbags for centre of structure in manner required Sandbags required for small sandbag dams, filled with sand/soil mix, to Supply of all materials, filling with earth/sand mix, and installation in situ of required volume of surface layer sandbags with gunny bags in manner required in the Technical Fill between the sandbags at surface layer as described m 3 70 m 3 70 AR-13-02 AR-16 Backfill for small sandbag dams, to Backfill to the dams as described in the Technical Bioengineering, phase 1, on areas of active erosion, to Preparation of the areas to be planted m 3 76 AR-17 sowing seeds and live staking Fencing including the area to be vegetated All seed sowing and planting activities, including supply and installation of geotextile jute mat sowing/planting where necessary. Bioengineering, phase 2, on areas already partially vegetated, to Preparation of the areas to be planted all sowing and planting activities as described in the Technical section 2.2.3. All seed sowing and planting activities sowing/planting for each type of planting, where necessary. m² 30,200 m² 84,000

in Bioengineering, phase 3, on facing of all sandbag AR-18 dams, to Preparation of the slope to be planted AR-19 sowing seeds and live staking All seed sowing and planting activities, including supply and installation of geotextile jute mat sowing/planting where necessary. Bioengineering, phase 4, in saturated gully beds behind small dams, to Preparation of ground for planting purposes planting seedlings and bamboo culms All planting activites Maintenance work on planting and fencing for a period of one year to include a phase of replacement planting where necessary m² 1,910 m² 800