Eli Schragenheim

Similar documents
Make-to-Stock under Drum-Buffer-Rope and Buffer Management Methodology

The Five Focusing Steps

Drum-Buffer-Rope in PlanetTogether Galaxy

What can we learn from the development of the profound ideas of Dr. Goldratt?

ThermoFab and DBR: Manufacturing At Warp Speed. A White Paper Report

By Eli Schragenheim Supporting TOC implementations worldwide

CHAPTER 4.0 SYNCHRONOUS MANUFACTURING SYSTEM

THE GOAL. Dr. Eliyahu Goldratt. Theory of Constraints

Linear High Touch Time: A New TOC Application

Drum Buffer-Rope. Based on : R. Holt, Ph.D., PE

Highlights of CCPM - Critical Chain Project Management The TOC way of managing projects By Oded Cohen International Director Goldratt Schools

Justice In Time: Applying TOC to Law Courts Systems. Presented By: Boaz Ronen, Shimeon Pass and Shany Karmy Date: June 2012

Theory of Constraints at Hindalco Industries Ltd Rolling mills division Renukoot This case study covers the successful deployment of Theory of

Drum Buffer-Rope. Skorkovský. Based on : R. Holt, Ph.D., PE

By Eli Schragenheim Supporting TOC implementations worldwide

Lessons for production management for MTO Using G-Sim Simulator

Throughput Accounting (Relevant to PBE Paper II Management Accounting and Finance)

PRODUCTION AND INVENTORY. Capabili. TOC and critical chain methodologies aren t just for manufacturing anymore. 46 March 2005 APICS magazine

The Core Structure of TOC Thinking Processes and their Applications to Improve Systems. Oded Cohen

Infor CloudSuite Industrial Whatever It Takes - Advanced Planning & Scheduling for Today s Manufacturer

Optimizing Inplant Supply Chain in Steel Plants by Integrating Lean Manufacturing and Theory of Constrains through Dynamic Simulation

IT 470a Six Sigma Chapter X

Simulation and Implementation Study of Robust Drum-Buffer-Rope Management System to Improve Shop Performance

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Herbie An Introduction to WiP Limits

THE ROLE OF SIMULATION IN ADVANCED PLANNING AND SCHEDULING. Kenneth Musselman Jean O Reilly Steven Duket

Chapter 17. Synchronizing and Balancing Processes. Level the master production schedule. Production. Time

Copyright is owned by the Author of the thesis. Permission is given for a copy to be downloaded by an individual for the purpose of research and

USING THE THEORY OF CONSTRAINTS TO PRODUCTION PROCESSES IMPROVEMENT

GE Digital Executive Brief. Enhance your ability to produce the right goods in time to satisfy customer demand

Production Management and Scheduling

KEY ISSUES in Advanced Operations Management. Timo Seppälä

UNIT II PRODUCTION PLANNING AND CONTROL AND COMPUTERISED PROCESS PLANNING

Time to Shipment MRP Guide DBA Software Inc.

Technical Operations Engine Maintenance Operations. Meeting Challenges in Engine Maintenance. Gary Adams

JOB SEQUENCING & WIP LEVEL DETERMINATION IN A CYCLIC CONWIP FLOWSHOP WITH BLOCKING

JOB SEQUENCING & WIP LEVEL DETERMINATION IN A CYCLIC CONWIP FLOWSHOP WITH BLOCKING

turning data into dollars

Manufacturing Resource Planning

ITSM and the Theory of Constraints. Stuart James #bcssmsg

Using Little s Law to Understand Flow and Design of TOC Solutions

A SUPPLY CHAIN CASE STUDY OF A FOOD MANUFACTURING MERGER. David J. Parsons Andrew J. Siprelle

MASTER PRODUCTION SCHEDULE (MPS)

COPYRIGHTED MATERIAL OVERVIEW OF THE THEORY OF CONSTRAINTS DEFINITIONS FOR THE OPERATIONAL ASPECTS OF THE THEORY OF CONSTRAINTS

October 31, of 10 BellHawkSystems Corporation

PRODUCTION ACTIVITY CONTROL (PAC)

CHAPTER 1 INTRODUCTION

5.3 Supply Management within the MES

A Roadmap Approach For Implementing Theory of Constraints In Manufacturing Organisations

The Future of ERP and Manufacturing Management

The Revised Focusing Steps of TOC: a Value Creation Approach

WHITE PAPER SIMPLIFIED MARKET-PULL SCHEDULING. Dave Turbide, CFPIM, CMfgE, CIRM

Managerial Accounting Prof. Dr. Vardaraj Bapat School of Management Indian Institute of Technology, Bombay

Critical Chain Project. Webinar

Dr. Eli Goldratt Unplugged

The Strategy & Tactic tree. Retailers. Viable Vision implementations

Stop Planning Semiconductor Chips Like Potato Chips!

Standing on the shoulders of Giants Production concepts versus production applications The Hitachi Tool Engineering Example By Dr.

MIT 2.853/2.854 Introduction to Manufacturing Systems. Multi-Stage Control and Scheduling. Lecturer: Stanley B. Gershwin

Master Production Scheduling - Is it still relevant?

Planning. Planning Horizon. Stages of Planning. Dr. Richard Jerz

MRP System Operation. Introduction (Seminar 10)

By Eli Schragenheim Supporting TOC implementations worldwide. Workshop th October 2015 Paris, France Hosted by Marris Consulting

Revisiting local TOC measures in an internal supply chain: a note

Using Demand Solutions APS for Effective Scheduling in the Food Process Industry

SIMUL8-PLANNER FOR COMPOSITES MANUFACTURING

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 8 Project Time Management - IV

FLEXIBLE PRODUCTION SIMULATION FOR APPLIED SCIENCES

Push vs. Pull: How Pull-driven Order Fulfillment Enables Greater Flexibility in Distribution Operations. Fortna

TOCICO Critical Chain Project Management Certification Webinar

Outline. Push-Pull Systems Global Company Profile: Toyota Motor Corporation Just-in-Time, the Toyota Production System, and Lean Operations

A CLIENT S GUIDE WHERE TO START WHAT HAPPENS ON SITE WHAT ARE THE BENEFITS. 10 Advantages of. Design Build

A PRODUCTION MANAGEMENT EXPERT SYSTEM DEVELOPED IN TIRS

8 Tools to Over Manage the Bottleneck

Justifying Advanced Finite Capacity Planning and Scheduling

A Business Oriented Architecture. Combining BPM and SOA for Competitive Advantage

Production planning and. Unit 3

By: Adrian Chu, Department of Industrial & Systems Engineering, University of Washington, Seattle, Washington November 12, 2009.

Understanding Manufacturing Execution Systems (MES)

Shop Control Guide DBA Software Inc.

Fundamental Concepts of Theory of Constraints: An Emerging Philosophy

PRACTICE PROBLEM SET Topic 1: Basic Process Analysis

Recent Advances in Manufacturing Engineering

Measurements That Count (and Some That Don t) Hank IT DEPENDS Barr CFPIM, CSCP, CLTD, CSCM, 6σBB, C.P.M., CLA/CLT Vancouver BC November 1, 2018

Making. MRP work. Vendors must address long-standing problems with capacity planning, lot sizes and lead-times

Flow and Pull Systems

Managing Systems - Part 1: Structuring system analysis and solution development through the U-shape. Oded Cohen

Sage 200 Manufacturing Datasheet

Chapter 5 Using TOC to improve Distribution System

TOCICO 2009 Conference. TOCICO 2009 Conference TOCICO CONFERENCE Critical Chain: 2009 TOCICO. All rights reserved.

OM (Fall 2016) Outline

Introduction to Operating Systems Prof. Chester Rebeiro Department of Computer Science and Engineering Indian Institute of Technology, Madras

10 WAYS TO REDUCE INVENTORY IN YOUR SUPPLY CHAIN

LOUISVILLE BEDDING COMPANY CASE STUDY

Tim Gutowski, July 8, 2002

The five focusing steps of the Theory of Constraints have been successfully applied to the improvement

ARC VIEW. TCS Seeks to Enable a Digital Integrated Business Planning Process. Keywords. Summary. From IBP to Digital IBP.

PRODUCTION SCHEDULING PART-A

Process design Push-pull boundary 35C03000 Process Analysis and Management Max Finne, Assistant Professor of Information and Service management

Synchronous Flow Helping the Countertop Fabricator to synchronize the business system March 2017 Ed Hill

Transcription:

From DBR to Simplified-DBR Eli Schragenheim elyakim@netvision.net.il i i t il 1

Outline A historical perspective. What to change? What to change to? The toolkit of S-DBR. When S-DBR would not fit? Just a little about how to cause the change. 2

Learning from the development of concepts As TOC has significantly progressed since its initial development in 1985 there must be something we can learn from the way ideas were formed. That initial verbalization was largely based on the OPT thoughtware that was developed in the early 80s. Realizing i software in itself does not change people s mind. Since then TOC has expanded its scope TP, CCPM, Marketing and Sales and lately also Strategy and the concept of the ever-flourishing organization. 3

Learning from the development of concepts Few years ago some important changes to TOC in Manufacturing were introduced. It is beneficial to understand the shift of ideas and especially the change in the focus. The first shift, from OPT to DBR, happened before the TOC and the five steps were verbalized. Then buffer management was introduced. Then the DBR technique has shifted to S-DBR. Then came the development of make-to-availability. All those shifts can be characterized as becoming simpler, and also by moving from detailed planning to setting the priorities right. 4

OPT was all about planning! Execution meant simply py following the schedule Planning means making decisions ahead of time. Which makes some decisions more vulnerable to Murphy. There must be a reason for a specific decision to be taken at the planning session. Most detailed plans suffer from frequent changes in the execution phase. So, what decisions should be included in the planning? and what should be left for the execution? 5

From OPT to DBR DBR was developed as a departure from OPT, which was an early and very sophisticated advanced planning and scheduling software. Eli Goldratt realized the need to be simple with very clear rationale. The emerged understanding backed the idea that there was no need for software. The detailed planning (finite capacity scheduling) was limited to just one resource. None of the other resources were scheduled. 6

From OPT to DBR Buffers were added to protect the sequence of the capacity-constraint-resource (CCR) and the timely shipment to the client. Three buffers were used: 1. The CCR buffer protecting the detailed schedule of the CCR. 2. The shipping buffer protecting the delivery dates. The CCR schedule had to ensure there is enough shipping buffer. 3. The assembly buffer was required to ensure that materials that do not go through the CCR would be released on time. 7

The main insight of TOC Fluctuating market demand A complicated shop floor Raw materials List of orders Murphy The critical insight of TOC is that only ONE bottleneck or capacity-constraint-resource (CCR) really governs the performance of the whole system 8

The buffers in traditional DBR A complicated shop floor Raw materials List of orders The CCR buffer The shipping buffer The assembly buffer 9

The Drum-Buffer-Rope (DBR) planning The Drum is the schedule of the CCR based on the orders at hand. Buffer is a protection mechanism to keep the drum from disruptions. Buffers became a critical part of the planning. Rope is the raw materials schedule forcing the choke of the release. Preventing too much WIP. All in all DBR represented a huge simplification of fthe planning. 10

The appearance of Buffer Management In the early days of DBR there were no guiding rules for the execution phase. Then Eli Goldratt developed the idea of Buffer Management to dictate the priorities in execution. Monitoring the actual consumption of the time buffer. Dividing it to the three colors: Green, Yellow and Red. Management should intervene only to flow red orders out. It took time for us to understand the contribution of Buffer Management. Especially its impact on the distinction between planning and execution. 11

Two conceptual challenges at traditional DBR 1. Should the constraint lie in the market demand or inside the organization? It was assumed we cannot have both at the same time. At the time the thinking was that the strategic constraint is under better control when it is inside the organization. 2. Suppose we do have an active CCR is there a need to schedule it in detail? What is the damage if the sequence is not kept? 12

The relationships between the internal capacity and the market demand The price we pay for having an internal capacity constraint: Delivery times are relatively long. Because of the wait time at the CCR. Due-date performance is threatened. Any interruption on the CCR itself puts the rest of the orders in the queue at a certain risk. Fact of life: clients are not interested that their supplier has a bottleneck - when they feel their deliveries are compromised they look elsewhere. 13

Changing the focus to be on the demand the immediate ramifications Focusing on the market demand is target to achieve the following: Expanding the current (potential) demand. Charging higher price for higher value. For instance, by delivering faster and/or more reliably. Making the shorter and reliable delivery valid at all times! Being able to focus on the demand requires protective capacity even on the weakest link itself! Actually it means the CCR has to subordinate to the market demand! Meeting the commitments t at all times. 14

Challenging the technique of traditional DBR The damage of scheduling the CCR: Inflexibility in dealing with urgent requests and other changes in priorities. Rescheduling causes changes to many orders. The scheduling process itself is batch oriented. Od Orders wait itto be scheduled. d Scheduling the CCR for make-to-availability is especially damaging g because of the inflexibility it imposes. Maintaining three different buffers is difficult to implement and it creates conflicts in priority. 15

Challenging the technique of traditional DBR What prevents us from deciding upon the exact sequencing of the CCR in the last minute? We need to know when to release the orders. Providing enough time to be delivered on time. Providing enough time to ensure the CCR is not starved. We like not to waste too much capacity of the CCR. Do we lose the precious capacity of the CCR if the CCR deviates from the sequence? Only when the CCR is subject to strong sequencedependent-setups there is a waste of capacity of the CCR. Note, the CCR-Buffer protects the sequence on the CCR not just preventing starvation. 16

The direction of the solution The necessary ingredients of the solution for make-toorder: The planning is able to link between the need to meet all the commitments to the market and having enough capacity of the CCR. There is one time buffer per order. The focus in the execution phase is definitely on the market demand. There is one clear list of priorities based on the color code of green-yellow-red. 17

The Planned Load - The tool for checking the capacity The following concept of DBR is still a cornerstone in the proposed S-DBR solution: Complex as the operational system may be, the output is dominated by one resource with the least capacity. Based on that concept, the capacity monitoring, replacing the detailed schedule, is based on the following concept: Definition iti Planned Load: The Planned load is the accumulation of the derived load on the CCR of all the firm orders that have to be delivered within a certain horizon of time. 18

A visual representation of the planned load Order 1-20 hours Orderr 2-14 Order 3-8 hours hours Or rder 5-10 Orde er 4-20 hour rs ho ours Order 6-21 hours Orde er 7-18 hou urs Daily Load (Hours) Time (days) 19

The critical information obtained from the planned-load load The most important feature of the planned load is: A rough estimation of the time for a new order to wait until being processed by the CCR This time estimation allows us to determine a safe-date for which we can commit to complete the new order. We need to add certain time to the planned-load load to provide the order with enough time to be processed by the CCR and the downstream operations. Considering also possible delays and flexibility given to the CCR in deciding when to process that order. The default in S-DBR is to add ½ of the production buffer time to the planned load to determine the safe date. 20

Using the planned-load load to estimate safe delivery dates for new incoming orders All the required CCR load for the orders that have a committed delivery date have been accumulated here. Daily Load 50% of the production buffer The planned load We can safely deliver here Time (days) 21

The subtle difference between the planned - load and the detailed schedule of the CCR The planned-load looks like a schedule because it places the required CCR s operations on the time frame. But, it does not impose the sequence on the operators. Many times the time allotted to an order on the plannedload is not realistic. For instance, when several different operations require the CCR for the same order. All we need the planned-load for is to estimate the earliest due-date for a new order that is pretty certain. And for that the rough estimation is enough. Having capacity requirements and response time together creates an effective tool for monitoring capacity. The overall buffer time provides enough flexibility to maneuver the actual sequence on the CCR. 22

Sales and Production planning in S-DBR The planned-load is used to support decisions on committing to reliable due-dates. d Not necessarily Sales should always offer the safe-date. At peak-times the safe-dates get longer due to the longer queue of work already committed to be delivered. At off-peak times the safe-dates are relatively early. The visibility of the safe-dates should be easily accessed by the sales people as the critical information required from Production. 23

The advantages of S-DBR over DBR The managerial focus is put mainly on the market demand. d Sales are properly supported online by giving a direct access to safe-dates for any new order. Buffer management in S-DBR is much more effective in handling the priorities than the three separate buffers in DBR. S-DBR can be implemented faster bring results sooner. 24

The advantages of S-DBR over DBR S-DBR requires much simpler algorithm from the supporting software than DBR. To illustrate the complexities DBR sometimes faces: Scheduling several CCR operations for one order. Scheduling several non-identical units of the CCR. Scheduling resources like ovens, which take several orders and work on the whole batch rather than one piece at the time. All the above do not complicate the S-DBR algorithm and it remains effective. When the constraint moves to another resource, S-DBR needs only to change the ID for the planned-load. 25

When S-DBR cannot apply The idea of refraining from detailed schedule of the CCR and yet being able to control the CCR s capacity is based on the assumption: The sequence of production does not significantly impact the capacity. The one situation where the above assumption is not valid is called: sequence-dependent setups. The setup time heavily depends on both the previous setup and the next one. This situation calls for having to follow a preferred sequence, which means very limited ability to expedite. Handling this situation is beyond the scope of the webinar. 26

Implementing S-DBR Important insight regarding implementation of a paradigm change is: It is imperative to get results very soon! This means we must plan the implementation so the first steps will already generate significant results. There is definitely no need to identify the weakest link / CCR at the start of the implementation. The first and most important action has to be: choking the release. Limiting the WIP to contain only what has to be delivered within the production time buffer. The default for the initial production buffer is: 50% of the current production lead-time. 27

DBR from a different perspective: guidelines for ANY planning Drum: Identify and carefully plan the critical areas where any deviation would clearly cause damage (to the objectives of the planning). Buffer: Protecting the drum instructions mainly from disruptions at the non-critical areas. Rope: Protects the buffers from over-protection. Usually is means choking the release of work/missions to ensure adequate protective capacity. Note, protective capacity is part of the overall buffering system. The above is true for S-DBR, CCPM and for any type of planning. 28

The road to simple and effective solutions The concepts cepts for managing ag g manufacturing actu organizations were not invented in very short time. Coming out of complexity to recognize the simple rules behind it is not easy. Once we recognize the distinction between planning and execution we move to a simpler, yet effective, scheme. And the basics of TOC still hold! 29

Questions? Eli Schragenheim s new book, together with Bill Dettmer and Wayne Patterson: Supply Chain Management at Warp Speed Will be out in May 2009 Covering the new knowledge in Make-to-order, Make-to- Availability and Distribution. Eli Schragenheim h elyakim@netvision.net.il 30