Internal Audit Follow-Up Report

Similar documents
Internal Audit Report. Rail Project Management TxDOT Office of Internal Audit

Internal Audit Follow-Up Report

Internal Audit Report. Contract Administration - Closeout Phase TxDOT Internal Audit Division

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report

Internal Audit Report. Vegetation Management: Non-Contracted Herbicide Operations TxDOT Office of Internal Audit

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report

Internal Audit Report. Contract Administration TxDOT Office of Internal Audit

Internal Audit Report

Internal Audit Report. Unified Transportation Program TxDOT Office of Internal Audit

Internal Audit Follow-Up Report

Internal Audit Report

Internal Audit Follow-Up Report. Compass TxDOT Office of Internal Audit

Internal Audit Report. Toll Operations: FHWA Reporting TxDOT Office of Internal Audit

Internal Audit Follow-Up Report

Internal Audit Report. Bulk Fuel Management and Reporting TxDOT Internal Audit Division

Internal Audit Follow-Up Report

Internal Audit Report

RAIL HIGHWAY AGREEMENTS

Internal Audit Follow-Up Report. General Controls - IT TxDOT Office of Internal Audit

Internal Audit Report. Post Implementation Review PeopleSoft Project Costing TxDOT Internal Audit Division

Internal Audit Report

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report

Internal Audit Follow-Up Report

TxDOT Internal Audit Letting Programming and Scheduling Function (1101-2) Department-wide Report

Internal Audit Report. CDA Monitoring Process TxDOT Audit Office

Internal Audit Report

Internal Audit Follow-Up Report

Why specify Surface Aggregate Classification A (SAC-A)?

Internal Audit Follow-Up Report

VALUE ENGINEERING FOR TxDOT PROJECT MANAGERS

RFID Applications for Tolling and Congestion Management

Internal Audit Follow-Up Report

Internal Audit Report. Contract Administration: 601CT Contracts TxDOT Internal Audit Division

The University of Texas at Tyler. Contract Administration Audit

TEXAS TRANSPORTATION PLAN

Internal Audit Follow-Up Report. Toll Operations Contract Management TxDOT Internal Audit Division

Report on. Texas Bridges. as of September Prepared by the Bridge Division Texas Department of Transportation

Standard Operating Procedure for Complying with CMP Requirements

DEMOLITION PLANS. Aaron Garza, P.E.

TxDOT Internal Audit Follow-Up Report Tuition Assistance Program

The Texas A&M University System Internal Audit Department

South Carolina Department of Transportation. Engineering Directive

TEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION

Recycled Materials Resource Center

ALTERNATIVE PROJECT DELIVERY

TxDOT Internal Audit Travel Division Operations Audit (1405-1) Department-wide Report

7.0 Stakeholder and Public Outreach

Rail Division. Riding the Rails

determine their mutual responsibilities in carrying out the metropolitan transportation planning process;

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND

Internal Audit Report. Professional Engineering Procurement Services (PEPS) Consultant Procurement Process TxDOT Internal Audit Division

Internal Audit Report. Post Implementation Review PeopleSoft Accounts Payable TxDOT Internal Audit Division

TXDOT Environmental Management System Verification Audit - Results. TxDOT Short Course October 16, 2013

Eagle Ford and Barnett Shale Activities. Impacts to the Transportation System

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit

EARLY AGE CRACKING IN HMAC Short Course Gisel Carrasco, P.E., CST-M&P

Wage Floor Discussion. City Council Briefing September 2, 2015

PRE-REQUEST FOR PROPOSAL (RFP) MEETING GENERAL ENGINEERING CONSULTANT (GEC) FOR I-2/I-69C INTERCHANGE PHARR DISTRICT

TEXAS TRANSPORTATION PLAN DEVELOPMENT

TWDB Description, Summary & Example of Agency Reports

Audit Plan for Fiscal Year 2014 TxDOT Audit Office

PEPS QUARTERLY CONSULTANT WEBCAST. Martin L. Rodin, P.E. PEPS Division Director March 22, 2016

E2 D0 U 1 C 3 A E T D IUOCNA A T IL O S N E A R L I E S S E R I E S HUB/DBE/SBE R A I L

TxDOT Internal Audit ROWAPS Contracts Audit (1104-1) Statewide Report

CITY OF CORPUS CHRISTI

Procurement and Contract Administration Challenges

INVOICE DEVELOPMENT AND SUBMITTAL PROCESS

Internal Audit Report

Prestressed Member Fabrication Plants (Multi-Project) Material Producer List Construction Division Materials & Pavements Section

OPEN DATA & PROJECT TRACKER. Michael Chamberlain TPP, Data Management

Contract Management Handbook. Texas Government Code, Title 10, Subtitle F, Chapter Statewide Contract Management

TEXAS BOARD OF NURSING CONTRACT PROCUREMENT AND MANAGEMENT HANDBOOK JULY 2018

Preparing a Reevaluation Using the Documented Reevaluation Checklist (DRC)

20. Security Classif. (of this page) Unclassified

PROJECT SUMMARY. Summary of Significant Results

What happens to your application after you leave it with us?

TxDOT Internal Audit Consultant Engineering Contract Administration Function (1103-1) Department-wide Report

Evolution of TxDOT s Quality Assurance Programs

ITEM 164 SEEDING FOR EROSION CONTROL

2015 Ozone Standard. David Brymer. Air Quality Division. Presented to the 2016 Texas Transportation Planning Conference June 16, 2016

MTP Policies. January 26,

TxDOT Internal Audit Internal Audit Report Purchase of Services Audit

FY 2016 Annual Audit Report

CITY OF PALO ALTO OFFICE OF THE CITY AUDITOR

TEXAS-OKLAHOMA PASSENGER RAIL STUDY

North Central Texas Council of Governments 157

Control Finding & Reporting Deficiencies

Overview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations

Internal Audit Report

Case Histories on Geogrid Reinforced Pavements to Mitigate Problems Associated with Expansive Subgrade Soils

Texas A&M Health Science Center: Review of Environmental Health, Safety, and Security PROJECT SUMMARY. Summary of Significant Results

OBSERVATIONS, RECOMMENDATIONS, AND RESPONSES

Technical Report Documentation Page 2. Government 3. Recipient s Catalog No.

Seattle Public Schools The Office of Internal Audit

TxDOT s Programmatic Quality Assurance Program for Design-Build Projects and Implementation Guide

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E.

Transcription:

Internal Audit Follow-Up Report Rail Project Management TxDOT Internal Audit Division

Objective Assess the status of corrective actions for high risk Management Action Plans (MAPs) previously communicated in Rail Project Management audit report dated July 15, 2014 and the MAP Follow-Up engagement dated June 2015. Summary Results Testing included an evaluation of 2 MAPs to determine if corrective actions were implemented as agreed. MAP Status Comments 2 Closed Corrective actions have been completed. Scope This engagement fieldwork was conducted with the Rail Safety Section under the Traffic Operations Division. Rail projects that were closed with a letting date after December 1, 2014 were included in the sample tested. Testing included the rail signature authority for Amarillo, Atlanta, Corpus Christi, Dallas, El Paso, Fort Worth, Laredo, Pharr, and Tyler Districts for March 2015. The engagement was performed by Tim Owen and Jill Emery (Engagement Lead). The engagement was conducted during the period from December 3, 2015 to January 22, 2016. Methodology The methodology used to complete the objectives of this engagement includes: Interviewed MAP owners from the Traffic Operations Division including the Division Director, Rail Safety Section Director, and Rail Safety Section Manager Reviewed training materials provided to district personnel on September 30, 2015 to verify it included instructions for Texas Railroad Information Management System (TRIMS), Rail Invoice Processing, and Railroad Agreements Judgmentally selected a sample of 10 finished rail projects to determine if documents have been uploaded into the Texas Railroad Inventory Management System (TRIMS) Background This report is prepared for the Texas Transportation Commission and for the Administration and Management of TxDOT. The report presents the results of the Rail Project Management MAP Follow-Up engagement, which was conducted as part of the Fiscal Year 2016 Audit Plan. Traffic Operations Division (TRF) is responsible for maintaining a complete rail project file utilizing the Texas Railroad Inventory Management System (TRIMS) to electronically store project documents including executed agreements, work orders, invoices, and inspections. Both the Rail Safety Section and each rail coordinator in the district are responsible to upload project documentation into TRIMS. Each rail coordinator is also responsible for August 2016 2

reviewing and approving all rail invoices prior to payment processing by the Financial Management Division (formerly Finance Division). We conducted this follow-up engagement in accordance with Generally Accepted Government Auditing Standards and in conformance with the International Standards for the Professional Practice of Internal Auditing. Those standards require that we plan and perform the engagement to obtain sufficient, appropriate evidence to provide a reasonable basis for our conclusions based on our engagement objective. Recommendations to mitigate risks identified were previously provided to management during the original engagement to assist in the formulation of the management action plans referenced in this report. The Internal Audit Division uses the Committee of Sponsoring Organizations of the Treadway Commission (COSO) Internal Control Integrated Framework version 2013. August 2016 3

Detailed MAP Follow-Up Status MAP Status: Closed Corrective actions have been completed. Original Audit Finding Number 1: Rail Management Contract Process MAP Owners: Luke Chisenhall, Rail Safety Section Director, Traffic Operations Division (TRF) Robert Travis, Rail Highway Safety Manager, Traffic Operations Division (TRF) MAP 1.1: TRF will provide additional training and oversight of District personnel responsible for review and approval of railroad invoices to ensure they have the appropriate training to review and approve the invoices for payment. The rail coordinators that will get training include those that have never used Texas Railroad Information System (TRIMS), were part of this audit, and any new employees. We will continue to monitor to see if more training is needed and when new staff is brought on. * The Districts will continue to be responsible for construction management, inspection, and oversight of work performed and completed by the railroad companies. Districts will continue to be responsible for review and approval of railroad invoices submitted to FIN by the railroad companies for payment. TRF will assume full contract management responsibilities as the Office of Primary Responsibility (OPR) to ensure a complete project file is maintained for each rail-highway project. This includes ensuring documentation of review and approval of all railroad invoices is received from the Districts. TRF will utilize the TRIMS project management tool to maintain a signed copy of the contract (including the original paper copy), work authorizations, supplemental agreements, work orders, invoices, correspondence, and a record of events that may affect the work. New financial controls for review and approval of railroad invoices from Finance Division (FIN) to the responsible District office have already been established and are now in effect. In addition, FIN will copy TRF on all invoices submitted to the District for review and approval, and the District will provide TRF with a copy of the approved invoice to be retained in the TRIMS project record.* New procedures, for the state s contractor obtaining the Railroad Right of Entry (ROE) agreement and project reporting from contractor-to-district-to-fin and TRF, are being piloted by the Construction Division (CST) and TRF through use of a new set of bid specifications. The new process will trigger notification of project completion so TRF can monitor and assist in the final acceptance of the railroad work by the District, and it will better ensure FIN and TRF are notified when construction projects are complete. As part of this effort, TRF will work with CST and the Districts to ensure the rail related project documents are maintained with the construction records. TRF will update and utilize policy and procedures manuals to train new and existing District railroad project coordinators in preparing project plans, specifications and estimates, issuing work authorizations, conducting inspections, verifying work performed meets agreement terms, coordinating project manager s comments on work progression August 2016 4

statements, and obtaining consensus for District approval of invoices before forwarding to FIN for payment. Training will also include final inspection and acceptance for final certification, final plan review, and preparing as-built plans. The Districts will continue to perform final inspection and acceptance of project work performed by railroad companies. TRF will provide management oversight, guidance, and support to the Districts in performing final inspection and acceptance of rail-highway projects for making final payment to the railroads. This includes monitoring the work for contract compliance and providing TRF personnel as needed for conducting final inspection and acceptance of the work to support final payment and project close-out. TRF will ensure final inspection is performed by the District on a timely basis by having TRF staff monitoring progress of work and current project schedule and having open communication with District staff to understand workload. The open communication will allow TRF staff to assist in conducting final inspection when District rail coordinators have too much work to conduct final inspections in a timely manner. TRF will ensure all changes to the rail-highway contract management process (including those listed above) will be communicated and done in all Districts. *Items that are italicized were considered complete during the last MAP Follow-Up. Original Completion Date: August 15, 2014 Revised Completion Date: August 15, 2015 Original Audit Finding Number 2: Signature Authority MAP Owners: Luke Chisenhall, Rail Safety Section Director, Traffic Operations Division Robert Travis. Rail Highway Safety Manager, Traffic Operations Division Bill Hale, P.E., Chief Engineer Brian Crawford, P.E., District Engineer, Amarillo District Robert Ratcliff, P.E., District Engineer, Atlanta District Christopher Caron, P.E., District Engineer, Corpus Christi District Kelly Selman, P.E., District Engineer, Dallas District Robert Bielek, P.E., District Engineer, El Paso District Brian Barth, P.E., District Engineer, Forth Worth District Pedro Alvarez, P.E., District Engineer, Laredo District Toribio Garza, Jr., P.E., District Engineer, Pharr District Dennis Cooley, P.E., District Engineer, Tyler District MAP 2.1 : The Traffic Operations Division (TRF) will coordinate through Finance Division, Contract Services Office, and the District Engineers to update the delegation of signature authority for approving railroad company invoices. It is our recommendation that the responsibility for review and approval of railroad invoices remain with the District responsible for the construction, inspection, and final certification that the work is complete. TRF will update policy/procedures manuals and training materials for new District railroad coordinators to ensure delegation of signature authority is continued in the future. Original Completion Date: August 15, 2014 Revised Completion Date: July 15, 2015 August 2016 5

Closing Comments The results of this MAP Follow-Up engagement were discussed with the Rail Safety Section Director and Rail Highway Safety Manager on March 31, 2016, and provided to the Chief Engineer, Amarillo, Atlanta, Corpus Christi, Dallas, El Paso, Fort Worth, Laredo, Pharr, and Tyler Districts. The Internal Audit team appreciates the cooperation and assistance received from the Traffic Operations Division and the districts during this engagement. August 2016 6