GUIDE TO THE PREPARATION OF A WORKING PLAN WASTE TRANSFER / TREATMENT FACILITY

Similar documents
GUIDE TO THE PREPARATION OF A WORKING PLAN SCRAPYARD / ELV FACILITY

Modification Number: M1

EF10 Site Environmental Audit - 1 / 8

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Accident Management Plan. November 2009

Supporting Guidance (WAT-SG-15)

Guidance on the Standards for Storage and Treatment of End-of-life vehicles

Amersham Waste Transfer Station, Amersham, Buckinghamshire. Environmental Permit (EP) Application Operating Techniques SLR Ref:

Environmental Conditions. Mushroom Farms

LICENCE REG NO. W HAS BEEN TRANSFERED

Standard rules SR2012 No13 Treatment of Incinerator Bottom Ash (IBA)

The applicant has estimated a total of vehicle movements per day.

Management Plan: Hazardous Materials Removal & Demolition

Waste Licensing Waste Recovery/Disposal Activities (Other than Landfill Sites)

Pollution prevention (land and water)

Environmental Management Plan

AMENDMENT UNDER S76(4) OF THE WASTE MANAGEMENT ACTS 1996 TO 2005

Notice of variation with introductory note

"UTH d BERTENVIRONMENTAL

Subsection or plan to be revised: 7-1, 7-8, , On page(s): 27-31(2006), 48-49(2003)

INSPECTORS REPORT DRAFT PD REGISTER NUMBER

Comhairle Contac Thiobraid Arann Thuaidh North Tipperary County Council

WASTE LICENCE. Headquarters, P.O. Box 3000, Johnstown Castle Estate County Wexford, Ireland 158-1

LIQUEFIED NATURAL GAS FACILITY REGULATION 146/2014

Application Pack 5. How to apply for a Connection to a Public Sewer/Lateral Drain

Waste Licensin Waste Recovery/Disposal Activities (Other than Landfill Sites)

LOSTOCK SUSTAINABLE ENERGY PLANT VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY ACT 1989

Sewerage connections guidance notes

DEMOLITION TRADE SPECIFICATION

Eurobitume UK. Site Inspection for Delivery of Bitumen

Demolition of an Agricultural Portal Building at Sevenacres, Kilwinning

WASTE LICENCE. Headquarters, P.O. Box 3000, Johnstown Castle Estate County Wexford, Ireland Waste Licence Register Number: Licensee:

TRANSFER STATION WASTE LICENCE. Headquarters P.O. Box 3000 Johnstown Castle Estate County Wexford Ireland 193-1

POLLUTION PREVENTION GUIDELINES PREVENTING POLLUTION ON INDUSTRIAL SITES: PPG11 1. LEGAL FRAMEWORK 2. INTRODUCTION

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Environmental Guidelines for Construction Sites

AM-PR-003 Construction Environmental Management Plan (C-EMP)

WASTE LICENCE LANDFILL FOR NON-HAZARDOUS WASTE. Headquarters P.O. Box 3000 Johnstown Castle Estate County Wexford Ireland

Pollution Prevention: Private, commercial and military airfields.

DIRECTION UNDER SECTION 90(2ZA) OF THE TOWN AND COUNTRY PLANNING ACT 1990 TO VARY THE CONDITIONS OF THE 2012 DEEMED PLANNING PERMISSION (TRACK CHANGE)

Building Standards Customer Journey

PETROLEUM STORAGE AND DISTRIBUTION FACILITIES STORM WATER REGULATION 168/94

Compliance Document for New Zealand Building Code Clause G15 Solid Waste

The licensee shall take the actions specified to close out the non-compliances and observations raised in this Site Visit Report.

Permit with introductory note

Pollution Prevention. Getting your site right. September 2009

LIST OF CONDITIONS FOR PROPOSED EXTENSION OF THE EXISTING C PALMAR MAURITIUS HOTEL (EX LE GRAND SABLE HOTEL) BY LAGON DE REVE LTEE [ENV/DOE/EIA/1776]

PROCEDURE (Essex) / Linked SOP (Kent) Asbestos Management. Number: U 1005 Date Published: 22 July 2015

The licensee shall take the actions specified to close out the non-compliances and observations raised in this Site Visit Report.

Loss Prevention Standards

Acceptance guideline 16: Stormwater contamination/first flush collection and stormwater bypass

PROPOSED DECISION WASTE LICENCE. Headquarters P.O. Box 3000 Johnstown Castle Estate County Wexford Ireland

LICENCE REG NO W HAS BEEN TRANSFERRED

Fife Council Balbarton Landfill Leachate Treatment Plant. Permit Application

Beauly-Denny Replacement Transmission Line Project

EPA Application Form

Background. AEM Tier 2 Worksheet Pesticide Storage, Mixing & Loading. Glossary. AEM Principle:

APPENDIX 22C: CYANIDE MANAGEMENT PLAN

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

AEA Comparison Chart for Part 145 CASA Notice of Proposed Rule Making

INTEGRATED POLLUTION CONTROL LICENCE

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

Environmental Conditions Laboratories (for commercial use) Group

Environmental Permitting Regulations (England & Wales) 2016

Town of Whitby Public Works Department

2003 No. 319 WATER AND SEWERAGE. The Control of Pollution (Silage, Slurry and Agricultural Fuel Oil) Regulations (Northern Ireland) 2003

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Government Gazette Staatskoerant

The permit decrees that have been amended are indicated in italics. Permit decrees for the prevention of contamination

INTERPRETATION OF TERMS...2

Report by the Executive Director of Community and Environmental Services

The permit decrees that have been amended are indicated in italics. Permit decrees for the prevention of contamination

Please read these guidance notes carefully before completing the attached application form.

Lunan Valley Area Dunkeld- Blairgowrie Lochs Special Area of Conservation

Interim Guidance on the Regulation of In-situ Disposals of Radioactive Waste and Residual Radioactive Contamination on Nuclear Authorised Premises

Notice of transfer with introductory note The Environmental Permitting (England & Wales) Regulations 2010 Red Industries RM Ltd Walleys Quarry Landfil

FREQUENTLY ASKED QUESTIONS

F Rev L MONTHLY STORE & SAFETY EQUIPMENT INSPECTION

Regarding the issuing of a building consent for the separation of surface water drainage to 39 and 39A Towai Street, Kohimarama, Auckland

Guidance note completing form WRC consent to investigate a groundwater source

The Pipelines Regulations, 2000

SEPA Interim Technical Guidance Note Capping for Landfill Sites

ATTACHMENT B GENERAL

Waste Duty of Care Guidelines Including Hazardous Waste Disposal Guidance

The following documentation was tabled:

CONSENT UNDER SECTION 36 OF THE ELECTRICITY ACT one or more heat recovery steam generators;

Guidance notes for developers

Environmental Policy 2016

Standard terms and conditions

Table 4.7.2(II) BREF Document on Best Available Techniques on Emissions from Storage, July 2006

Headquarters P.O. Box 3000 Johnstown Castle Estate County Wexford Ireland WASTE LICENCE 185-1

GOOD WHOLESALING PRACTICE FOR WHOLESALERS, DISTRIBUTORS and BONDEDWAREHOUSES

A positive, collaborative airport-wide approach is essential to minimise pollution. Heathrow Pollution Prevention Code of Practice

DRAFT IMPLEMENTING DECREE. of 2016

Annual Environmental Report (Period 1 st January 2008 to 31 st December 2008)

(a) One combined cycle gas turbine generating station of up to 820MW about 710MW consisting of:

ARCHIVED. Compliance Document for New Zealand Building Code Clause G15 Solid Waste. Prepared by the Department of Building and Housing

Permit with introductory note

BEVERAGE CANS REVESBY

CHAPTER 15 PLUMBING CODE

Appendix Illustrative Construction Programme

Transcription:

GUIDE TO THE PREPARATION OF A WORKING PLAN WASTE TRANSFER / TREATMENT FACILITY A working plan is an essential document and consists of a written statement accompanied by plans, drawings and specifications detailing how the site is to be designed, engineered, operated, monitored and restored. The working plan is referred to in waste management licence conditions and the licence holder may only vary it by notification to, and in some respects with the prior consent of, SEPA. SEPA s Guide to Waste Management Licensing gives further guidance on waste management licensing and working plans. It is essential that applicants discuss the need for site engineering and development works with SEPA at an early stage of preparing a licence application. The site will require engineered design features such as gates, fences, drainage and concrete hardstanding. An indication of the engineering works that will be required is given in this Guidance Note. The application of Quality Assurance and Quality Control procedures form an important part of any waste management practice and applicants should bear this in mind when preparing their working plan. This is particularly applicable to the installation of site infrastructure. The Working Plan is likely to require amendment as the site develops, it will therefore be helpful to write the statement in sections with numbered paragraphs and pages, submitted in loose leaf form so that subsequent approved changes are easier to incorporate. The information which must be included in the working plan is as follows, and should correlate with plans as listed in paragraphs 2.1-2.3 below: SEPA suggests that the Working Plan follows the format outlined below. 1. WRITTEN STATEMENT The written statement forms an important part of the working plan. It must describe clearly and unambiguously all aspects of the operation of the site. A correctly written statement should contain sufficient information to enable anyone unconnected with the site to understand how it will be operated. 1.1 General Considerations General details of the site should include; a) A brief history of the site giving its previous uses, including any previous waste management activities. b) The proposed operating hours at the site including the proposals for Bank Holiday and other public holiday working, for accepting, treating and removing waste and the maintenance of plant, buildings and equipment. c) The types of waste that will be accepted and the maximum quantity of each type of waste that will be accepted, stored and treated (as appropriate) each day. A throughput rate for wastes should also be indicated. WML-G-WT revision 2 October 2011 Page 1 of 5

d) The number of staff to be employed on the site and the minimum number of people required to operate the site. Details should be provided of how the technically competent management will control the site including detail on those involved and a copy of the relevant certification / references. 1.2 Site Infrastructure Fencing The license holder should provide perimeter fencing or some other means of preventing unauthorised or accidental access. Surfaces To prevent the pollution of water, areas used for the storage and treatment (where applicable) of certain wastes must take place on an impermeable pavement, i.e. concrete. Specifications of thickness, quality and falls to the drainage system must be given. To avoid liquids escaping from the perimeter of the concrete, raised kerbs may be required to bund the areas for complete containment. Internal concreted areas may require sealing at doorways by small barriers, if the fall directs liquids to the doorway. Drainage To prevent the pollution of water, concreted surfaces which are not under cover must be drained to a sump or to an oil/water interceptor with final discharge to a sewer, soakaway or watercourse under consent from SEPA or Scottish Water, as appropriate. Other Infrastructure Where appropriate, the standard and location of the following infrastructure should be detailed; a) Site roads b) Weighbridge c) wheel cleaning facilities d) fuel and waste storage tanks and associated bunds e) waste storage areas f) services (water, electricity, telephone etc.) g) lighting h) Litter control provisions i) buildings (including laboratory facilities, where applicable) If it is considered more convenient, buildings and other infrastructure can be detailed as annotations on the site plan(s). The working plan should make it clear whether the waste storage area is in the open air, covered, enclosed, or in a building, with details of any structure. 1.3 Waste Reception A full detailed description should be given of the following points, where relevant:- WML-G-WT revision 2 October 2011 Page 2 of 5

a) Method of waste transfer and/or treatment processes, including (where appropriate) the way in which the waste is to be accepted, deposited, sorted, stored and re-loaded. b) Measures taken to ensure the segregation of incompatible wastes. Applicants are advised to refer to guidance produced by the Health and Safety Executive and in particular to HSE Guidance Note HS(G) 71. c) The provisions for waste to be checked to ensure it is acceptable under the terms of the licence and that it complies with any documentation accompanying the load, how the quantity is to be measured and recorded, and details of any tests carried out. A quarantine area for loads to wait whilst appropriate sampling, testing and analysis is carried out may also be necessary. d) The procedures to be carried out in the event of waste being delivered which is not permitted by the licence or not capable of being handled by the equipment currently available. 1.4 Site Operations Information on the day-to-day operations should include: a) The location and types of treatment processes to be carried out. b) The method of containment of the waste (i.e. containers, drums, tanks etc.) c) The maximum time that waste will be stored at the facility. It is important for certain categories of waste to be systematically removed from the site to avoid infestation of rodents and pests. The working plan must specify how wastes are to be removed from the site within an acceptable timescale. d) If waste is to be sorted and stored for sale or re-use, type and maximum quantity of reclaimed material and its storage location. e) The type, location and size of any waste handling machinery and details of how it is to be used. f) Measures to warn of plant malfunctions or overfilling the procedures to be implemented in the event of any plant or machinery breaking down or being unavailable. g) Any sampling and analysis to be undertaken to confirm the nature of wastes received at the site. h) The arrangements for the storage, handling and disposal of any residues or by-products produced at the site. The operator must make adequate provisions for the maintenance and upkeep of the site and all plant and equipment. The working plan must provide full and precise details of such maintenance provisions to satisfy SEPA of their suitability. Details of inspections of infrastructure and storage areas should also be stated. 1.5 Pollution Control This section should detail the measures to be taken to monitor and/or control the following; a) Vermin b) Insects c) Noise d) Dust WML-G-WT revision 2 October 2011 Page 3 of 5

e) Spillages f) Odours g) Mud h) Litter i) Fires Details of any consents, from SEPA or Scottish Water, held to discharge to any watercourse or sewer should be appended to the working plan. 1.6 Site Completion The proposals for restoring the site after operations have been concluded should be included, where applicable. 1.7 Monitoring This section should include details of any monitoring it is proposed to carry out, including the location and frequency of monitoring and the methodology of sampling and analysis. 1.8 Records This section should include details of the manner in which records relating to the site activities will be kept. In particular the system for recording the types and quantities of waste received, processed and removed from the site should be detailed. 2. PLANS Where indicated the scales suggested for the following sections are strongly recommended, although in some circumstances alternative scales may be more appropriate. Applicants should discuss alternative plans or scales with SEPA prior to the submission of the application. All plans should bear a unique identification number. The plans required for the Working Plan are as follows: 2.1 Site Location Plan A plan to identify the site in comparison to the surrounding area. This should be A4 in size and usually at a scale of 1:1250. It must show the area around the site to a distance of at least 250 m and include all roads, buildings and other developments. A red line should be placed around the whole area to be licensed, and a blue line placed around any other areas of land owned or occupied by the applicant. The area to be licensed must be identical to, or fall within the boundaries of the area that has been granted, or applied for, in the planning permission, application or equivalent authorisation. 2.2 Site Survey Plan An appropriately scaled plan to show details of the site including:- a) The gradient of the surface of the site. WML-G-WT revision 2 October 2011 Page 4 of 5

b) Existing drainage, sumps and outfalls. c) The location of any surface water features including springs and seepages. d) Location of previous contamination and sampling points. e) Public services, and any other features under, on, above or around the site. 2.3 Site Operational and Engineering Plan(s) Appropriately scaled plans showing location of operations and details of the site infrastructure and its engineering specification including: a) Gates and boundary fencing. b) Details of intended drainage provisions, to include foul and surface water connections and any interceptors, sumps or settlement tanks. c) Access and vehicle circulation routes, form and construction of site roads. d) Position of notice board. e) Reception facilities, site control office and mess facilities, laboratory and other buildings or fixed equipment on site including wheel cleaner and weighbridge. f) Provision for daytime and overnight parking, including quarantine area for loads to wait whilst being checked. g) Location, construction, size and capacity of storage and treatment areas to include tanks, bunds, sumps, pipework, pumps and valves. h) Waste discharge facilities (including location of machine and vehicle). i) Location of external lighting, water supplies, fire extinguishers etc. j) Areas for the storage of waste inadvertently deposited at the site pending removal. k) Location for the storage of material recovered from the waste and segregated for re-use or resale, if appropriate. l) Litter and noise abatement equipment, dust suppression or extraction equipment. m) Areas set aside for the storage of empty skips, if appropriate. In the interests of clarity it may be appropriate to detail the information on a series of plans. NOTE TO APPLICANTS SEPA will usually discuss with the applicant any details in the submitted working plan which it considers to be unacceptable. If SEPA cannot be satisfied with any of the contents of the working plan it will incorporate conditions within the waste management licence which will override the working plan in respect to those points. License Holder s Responsibilities Notwithstanding any requirements of SEPA for site engineering, the applicant should be aware of his responsibility for ensuring the integrity of such works. Compliance with SEPA s minimum standards does not remove the liability of the licence holder for any water pollution or other environmental damage which may result from the activities on site. WML-G-WT revision 2 October 2011 Page 5 of 5