SECTION SECONDARY UNIT SUBSTATIONS

Similar documents
Houston First Corporation Package 1 SECTION MEDIUM VOLTAGE FUSED SWITCH INTERRUPTER

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein.

SECTION SECONDARY UNIT SUBSTATIONS

SECTION BUSWAYS

SECTION LOW-VOLTAGE TRANSFORMERS

SECTION to 5000 AMPERE PLUG-IN AND FEEDER BUSWAYS - SPECTRA. A. Low-Voltage Plug-in Busway to 5000 ampere, 600 VAC

A. Section includes busway and fittings including plug-in units.

FIELD TEST AND OPERATIONAL CHECK SECTION A. Refer to Section 16010, Electrical General Requirements.

SECTION LOW-VOLTAGE SWITCHGEAR

B. Provide liquid-filled secondary substation transformers as indicated on drawings.

Point Eight Power, Inc. Switchgear Specification Low Voltage UL 1558 Metal-Enclosed Switchgear

SECTION GROUNDING

SECTION METAL-ENCLOSED BUS MEDIUM VOLTAGE

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number

SECTION ENCLOSED BUS ASSEMBLIES

SECTION AUTOMATIC TRANSFER SWITCH

BUSWAY LOW VOLTAGE (POW-R-WAY III) SECTION SECTION 16466

SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard

a) Line and load compartments must be separated by a stable barrier.

1 29SEP03 ALL General update with miscellaneous changes in entire document.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

CONTENTS. B. System Design and Performance Requirements

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SECTION MOTOR CONTROL CENTER

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

LOW-VOLTAGE SERVICE ENTRANCE SWITCHBOARDS SECTION D

SECTION ENCLOSED BUS ASSEMBLIES

37-SDMS-01 REV. 03 SPECIFICATIONS FOR

A. This Section includes the following types of dry-type transformers rated 600 V and less, with capacities up to 1000 kva:

SECTION REQUIREMENTS FOR ELECTRICAL INSTALLATIONS

DIVISION 16. Electrical Specifications

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT

SPECIAL SPECIFICATION 6499 Environmentally controlled Communications Building

SERVICE ENTRANCES. OPPD S Electrical Service Designer (ESD) shall designate the Point Of Entrance.

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1

ADDENDUM NO. 1 BID AND CONTRACT DOCUMENTS FOR. BID No. 2019PW299

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

SERIES 800 / 810 SPECIFICATION 15KV & 25KV PADMOUNTED LIQUID-INSULATED VACUUM LOAD INTERRUPTER ASSEMBLIES

ELECTRIC METERING GENERAL

UNIFIED FACILITIES GUIDE SPECIFICATIONS. Use for Southeast projects only **************************************************************************

SECTION MEDIUM VOLTAGE TRANSFORMERS

SPECIFICATION FOR SIMPLEX SWITCHBOARDS

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Medium Voltage Switchgear. Basis of Design.

SECTION (16071) - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

OVERHEAD SERVICES - SECONDARY

SECTION FIELD PANELS

OPERATING PROCEDURE NO. 310

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION PART 1 GENERAL

Equipment Specifications Low Voltage. Active Harmonic Filter

56-SDMS-01 REV. 01 SPECIFICATIONS FOR

SECTION PARK NON-SEGREGATED BUS SPECIFICATION

PRIMARY UNIT SUBSTATIONS SECONDARY 1000 V AND ABOVE SECTION SECTION

UNIFIED FACILITIES GUIDE SPECIFICATIONS

METERING INSTALLATION

SECTION CONVECTORS

SECTION GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL

Standard of Practice - Campus Electrical Distribution System

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION

UFGS (August 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION GROUNDING AND BONDING

SECTION SECONDARY UNIT SUBSTATIONS SECONDARY LESS THAN 1000 V

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Important Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008

31-SDMS-03 REV. 01 SPECIFICATIONS FOR

SECTION INTEGRATED POWER ASSEMBLY (IPA)

Capital Projects Group Liquid Filled Transformer Specification

A. Basket Cable Tray: A fabricated structure consisting of wire mesh bottom and side rails.

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

SECTION EXTERIOR ATHLETIC LIGHTING

August 2011 DSC DeLand Campus COOP # SECTION INTERIOR DISTRIBUTION SYSTEM

SECTION OVERHEAD CONDUCTOR RAIL

SECTION FIBERGLASS REINFORCED PLASTIC (FRP) ENCLOSURE

Section 70 Airport Transformer Vault and Vault Equipment (FAA L-109)

1. Telecommunications mounting elements. 2. Backboards. 3. Telecommunications equipment racks and cabinets. 4. Grounding.

SECTION GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION WIRE, CABLE AND BUSWAYS. A. This section specifies providing wire, cable and busways.

16300 HIGH VOLTAGE DISTRIBUTION

ELECTRICAL INSPECTION BULLETIN (Effective )

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL).

(Condensed from National Electric Code)

MANUFACTURING TECHNICAL INSTRUCTIONS SAFETY Subject: DESIGN, MAINTENANCE AND INSPECTION OF SECONDARY ELECTRICAL DISTRIBUTION SYSTEMS

SECTIONAL OVERHEAD DOORS SECTION SECTIONAL OVERHEAD DOORS PART 1 GENERAL

ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS

OVERHEAD SERVICES - RESIDENTIAL & GENERAL SERVICE. See Chapter 3, Section 3.01 for more information about point of entrance (POE).

Instruction Manual. Ventilated Dry-Type Transformers. 600 Volts & Below

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control

15kV Metal-Clad Switchgear and Power Control Room Specification

UNDERGROUND SERVICES SECONDARY

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

SECTION GROUNDING AND BONDING

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

SERVICES CHAPTER 35. wire. For all other installations, the rating of the ungrounded conductors shall be not less than 60 amperes.

SECTION ELECTRIC FOUR FOLD DOORS MODEL 46 FLAT SHEETED

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL

Transcription:

SECTION 26 12 16 SECONDARY UNIT SUBSTATIONS PART 1 GENERAL 1.1 SUMMARY This section describes metal-clad, indoor or outdoor, secondary unit substations with integral primary fused disconnect switches, dry-type (indoor) or oil-filled (outdoor) transformers, main and feeder secondary circuit breakers and associated metering and accessories. Refer to purchase order document for details on sizing and service. 1.2 REFERENCES A. General: For all reference publications listed below, refer to editions currently adopted by federal, state, and local government agencies with jurisdiction over the project. For references that are not part of government codes, refer to most recent editions. B. American National Standards Institute (ANSI) Publications: 1. C2, National Electrical Safety Code 2. C12.10, Physical Aspects of Watthour Meters Safety Standard 3. C37.20 Switchgear Assemblies Including Metal-Enclosed Bus 4. C57.12.00, General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers 5. C57.13, Requirements for Instrument Transformers C. National Electrical Manufacturers Association (NEMA) Publications: 1. 201, Primary Unit Substations 2. 210, Secondary Unit Substations 3. TR 1, Transformers, Regulators, and Reactors 4. TR 27, Commercial, Institutional and Industrial Dry-Type Transformers 5. TP1, Guide for Determining Energy Efficiency for Distribution Transformers D. National Fire Protection Association (NFPA) Publication: NFPA 70 National Electrical Code. E. Underwriters Laboratories, Inc. (UL) Publication: 467 Grounding and Bonding Equipment, Electrical F. Related Work 1. FDG 33 71 73.33: Electricity Metering Guidelines February 2009 Page 1 of 7 2018 FDG Section 26 12 16

2. FDG 33 71 49: Medium Voltage Cable G. Quality Assurance 1. Switchgear Tests: ANSI C37.20. Design, production, and conformance tests of switchgear shall be made. For power circuit breakers, after completion of interrupting tests at full rating there shall be no evidence of damage to any part, except for minor burning of arcing contacting tips. Breakers shall be satisfactory for immediate return to service at full rating without repairs or maintenance of any kind. 1.3 SUBMITTALS 2. Transformer Tests: NEMA TR1 and TR 27 3. Routine Tests: Routine tests shall be made by the manufacturer on each transformer to ensure that design performance is maintained in production. 4. Design Tests: Design test reports will be accepted as proof of compliance with design test requirements. A. General: Manufacturers' data on the following items shall be submitted to the Project Manager: 1. Meters 2. Fuses 3. Circuit breakers 4. Switches 5. Enclosures B. Shop Drawings: 1. Shop drawings of the following items shall be submitted to the Project Manager: a. Transformers b. Unit substations 2. Shop drawings for substations shall indicate, but shall not be limited to the following: a. Overall dimensions, front view and sectional views. b. Bus arrangements, including dimensions and ampere ratings of all bus bars. c. Type and spacing of bus supports. d. Maximum short circuit bracing. e. Circuit breaker type, interrupting rating, trip setting. f. Ratings and sizes of lugs, impedance taps, and fans. g. Elementary diagrams and wiring diagrams with terminals identified and with internal wiring for each item of equipment and interconnections between items indicated. February 2009 Page 2 of 7 2018 FDG Section 26 12 16

C. Field Tests Reports: Two (2) certified copies of reports of relay settings and dielectric tests shall be submitted to the Project Manager for approval. 1. Relay Setting and Testing: The Project Design Engineer and/or Design-Build Contractor shall furnish the recommended breaker/relay settings to provide coordinated protection for the power distribution system. 2. Breaker / relay testing shall be performed by an independent contractor with NETA certification. 3. The Contractor shall provide the Project Manager with two certified copies of the final breaker and relay calibration and setting report. PART 2 PRODUCTS 2.1 General A. The unit substation shall be complete, grounded, continuous duty, unitized integral assembly, metal clad, dead front, dead rear types, with dry-type (indoor) or oil-filled (outdoor) transformers. B. Ratings shall be not less than required by the NEC and not less than shown on the drawings. Short circuit current ratings shall be not less than the maximum short circuit currents available, where the substation is being installed, as shown on the drawings. C. Provide substations that conform to the arrangements and details shown on the drawings and to the space designated for installation. D. Contractor shall coordinate the components of the substations and their arrangements electrically and mechanically. Coordinate all circuit entrances into the substations, including methods of entrance and connections. E. The substation equipment shall have the capability to withstand and interrupt fault currents supplied by the primary connection. F. Incorporate interlocking as shown on the drawings and as required for the safe operation of the substations. G. The substation shall be assembled and prewired by the manufacturer at the factory. H. Contractor shall coordinate the high and low voltage sections with their associated transformers. Sections shall be fabricated by a single manufacturer. I. Bolts, nuts and washers shall be rustproof metal, corrosion resistant (zinc chrome plated). J. All access covers for normal inspection and maintenance shall be hinged. K. The arc-flash rating per NFPA 70E shall be clearly labeled on all accessible sections. L. All components shall be rated for Seismic Zone 4 earthquake forces. February 2009 Page 3 of 7 2018 FDG Section 26 12 16

2.2 Incoming Section: A. Incoming circuit shall be connected to transformer through a fused medium voltage air interrupter switch. B. Provide viewing window(s) for the fused primary switch and a set of spare primary fuses. C. Air interrupter switch shall be manually group-operated, three-pole, single-throw, fused load-interrupting device. Air interrupter switch shall have adequate interrupting and fault close ratings. D. Conductor terminations shall be clamp-type terminals with provisions for single feed and arranged for proper conduit entry. E. Fuses shall be current-limiting type coordinated to the transformer provided. F. Interrupter switch shall have locking provisions. G. Independently support each cable by a clamp to a structural support within 6 inches of the termination to relieve any strain imposed by cable weight or movement. See FDG 33 71 49 for type of primary cable used. H. Transition section shall be included with incoming section if required for proper connection and alignment. Connections shall be adequately sized and braced to withstand specified available fault current. 2.3 Transformer Section: A. Transformers shall be ventilated dry-type indoor or oil-filled outdoor, self-cooled, 60 hertz, 3-phase, 4160 or 12470 volts primary-connected delta to 120/208 or 277/480 volts secondary-connected wye. B. Transformers shall be rated for operation without forced-air cooling. If forced-air cooling fans are provided, shall have automatic temperature control relay. C. Low-voltage neutral bushings shall be provided on units having wye-connected lowvoltage windings. D. Transformer shall have corrosion-resistant diagrammatic nameplate. E. In addition to the requirements of NEMA, transformer shall be designed according to ANSI C57.12.01. F. Taps (de-energized operation): Taps shall be provided. Transformer shall deliver rated kva at any tap setting. Taps shall be two each 2-1/2 percent full capacity above and two each 2-1/2 percent below rated voltage. G. Transformer shall be equipped with NEMA standard maintenance devices. 2.4 Outgoing Section: A. Outgoing section shall consist of low-voltage power circuit breaker or molded-case circuit breaker switchgear. B. Main secondary breaker shall be interlocked with primary switch to prevent operation of primary switch when main secondary breaker is closed. Each steel unit forming part of switchgear structure shall be a self-contained housing having individual breaker or February 2009 Page 4 of 7 2018 FDG Section 26 12 16

instrument compartments, full-height rear compartment for buses, instrument transformers, and outgoing cable connections. The structure shall be designed so that future additions, if required, may be added. Engraved circuit designation plate shall be provided on each individual circuit breaker compartment door. C. Phase Buses and Connections: 1. Bus structure shall be mounted on insulated supports of high-impact, non-tracking insulating material and braced to withstand the mechanical forces exerted during short circuit conditions. 2. Bus bars shall be high conductivity copper or aluminum with plated joints. Bus bar connections shall be made from main buses to incoming circuit breaker. 3. Secondary circuits including heater circuits shall be wired to terminal blocks. Terminal blocks shall be readily accessible for making external connections as required. Neutral bus shall be sized one-hundred percent (100%) of full load amperes. D. Copper ground bus shall be provided secured to each vertical structure and extending the entire length of switchgear and shall effectively ground all non-current-carrying metal, including circuit breakers, air interrupting switches, switchgear housing, etc. Ground bus shall be sized to meet the requirements of the NEC, with driven ground rods and cable connections to complete the station ground. E. Main secondary breaker shall be insulated case type, manually or electrically operated and shall have an interrupting rating not less than the available fault level. Breaker shall be equipped with solid state trip device having long-time, short-time, instantaneous, and where required, ground fault tripping characteristics so that branch breakers will normally trip first on overload and at lower fault-current levels. F. Secondary feeder breakers shall be insulated case or molded-case type with suitable interrupting rating. Breakers shall have a quick-make, quick-break operating mechanism and shall be equipped with ambient-compensated thermal magnetic or solid state trip device having long-time delay, instantaneous pickup, and ground fault pickup where required. Circuit breaker shall trip free of the handle, and the handle position shall indicate whether the breaker is "on", "off", or "tripped". Circuit breaker shall be mounted so that when removed, bussing will not be disturbed. An overload in one phase shall cause all three phases to trip. G. Space shall be provided for future installation of an additional twenty percent (20%) of feeder breakers. 2.5 Metering A. Refer to FDG 33 71 73.33 for metering requirements. B. The metering compartment at the main breaker shall be equipped with hinged door and barriers from any energized 480V or 208V main bussing. C. Provide analog ammeters for the secondary main breaker and all feeder breakers. D. Main breaker status shall be connected to Customer s SCADA system through digital input of revenue meter. February 2009 Page 5 of 7 2018 FDG Section 26 12 16

2.6 Ground Fault Protection Ground fault protective devices consisting of current transformers, fault protection relays with time delay suitable for protecting circuit components against phase to ground faults, and a system monitor panel shall be provided for 480/277 volt systems. A. Special care shall be used in grounding the neutral so as not to defeat the proper operation of ground fault protective devices. B. Ground fault protection may be internal with circuit breakers. 2.7 Strip Heaters Strip heaters, rated 240 volts but connected to 120 volts, shall be provided in each switchgear section for outdoor substations. Heaters shall be of sufficient capacity to control moisture condensation in compartments and be controlled by thermostat or humidistat located inside secondary switchgear section. Thermostats shall be industrial type, with range of 60ºF to 90ºF, and shall operate on temperature fall. Humidistats shall have a range of thirty percent (30%) to sixty percent (60%) relative humidity. 2.8 Nameplates Laminated plastic nameplates shall be provided for each relay, switch, and device to identify its function, and where applicable, its position. A. Laminated plastic shall be 1/8-inch thick plastic, black with white center core. Surface shall be matte finish. All corners shall be square. B. Lettering shall be accurately aligned and engraved into the white core. C. Nameplates shall be fastened with a minimum of two machine screws. Adhesive fasteners shall not be used. 2.9 Terminal Boards Identified terminal boards with engraved plastic terminal strips shall be provided for all external wiring between components and for all internal wiring between removable assemblies. Terminal board identification shall be identical in all similar units. External wiring shall be color coded consistently for all similar terminal boards. 2.10 Paint and Finish A. Indoor Substation shall be thoroughly cleaned, phosphate treated and painted at the factory with rust-inhibiting paint and baked enamel or lacquer light gray finish or color specified in purchase document. B. Outdoor Finish the substation according to ANSI standard (C57.12.28/29) for surface preparation, primer, and paint durability. Exterior color: Kelly Moore 1245-407 acrylic low sheen carbon or approved equal. February 2009 Page 6 of 7 2018 FDG Section 26 12 16

PART 3 EXECUTION 3.1 INSTALLATION A. General: Electrical installations shall conform to ANSI C2, NFPA 70, and the requirements specified herein. B. Substation Grounding: A bare copper grounding electrode not smaller than 4/0 AWG shall be provided not less than 24 inches below grade connecting to ground rods. Grounding electrode shall be at least 25 feet long. At least two each ten (10) foot by ¾- inch ground rods shall be provided, with one in the primary switch section and one in the secondary section. C. Space Requirements: Space shall be provided on all sides of equipment to allow proper ventilation, permit passage of personnel, and to provide clearance for equipment and maintenance. D. Anchorage: Anchor equipment in accordance with Section 26 05 00. 3.2 FIELD QUALITY CONTROL A. General Testing: The Contractor shall show by demonstration in service that all circuits and devices are in good operating condition. B. Equipment and Apparatus Tests: Unless specific factory-witnessed tests are specified, tests normally made by the manufacturer will be acceptable for all equipment and apparatus. END OF SECTION February 2009 Page 7 of 7 2018 FDG Section 26 12 16