EIA Update Report for the Keadby 2 Combined Cycle Gas Turbine Generating Station at Keadby, Lincolnshire. The business of sustainability

Similar documents
Measurements of Effectiveness of Noise Barriers in Route Sections A to G. The business of sustainability. December

Environmental and Social Action Plan. Draft Report. The business of sustainability

Annex A. Consultation Responses

Cross-border Executive Search to large and small corporations through personalized and flexible services

IMPROVING SALES EFFECTIVENESS. John Kieffer Business Transformation Director

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION

hp hardware support onsite global next day response

Process Maturity Profile

Forest Stewardship Council

Forest Stewardship Council

FSC Facts & Figures. December 3, 2018

FSC Facts & Figures. November 2, 2018

Aruba FedEx International Priority. FedEx International Economy 3

FSC Facts & Figures. June 1, 2018

FSC Facts & Figures. September 6, 2018

FSC Facts & Figures. August 1, 2018

FSC Facts & Figures. January 3, FSC F FSC A.C. All rights reserved

FSC Facts & Figures. February 9, FSC F FSC A.C. All rights reserved

FSC Facts & Figures. April 3, FSC F FSC A.C. All rights reserved

FSC Facts & Figures. November 15. FSC F FSC A.C. All rights reserved

FedEx International Priority. FedEx International Economy 3

COMPENSATION REVIEW AND ANALYSIS SERVICES TAKING THE WORK OUT OF YOUR COMPENSATION REVIEW PROCESS

FSC Facts & Figures. December 1, FSC F FSC A.C. All rights reserved

THE ELECTRICITY ACT 1989 (AS AMENDED) - SECTION 36C VARIATION OF CONSENTS UNDER SECTION 36 - CONSENT REQUIRED FOR THE CONSTRUCTION ETC

MERCER EXECUTIVE REMUNERATION GUIDE THE KEY TO DESIGNING COMPETITIVE EXECUTIVE REMUNERATION IN THE MIDDLE EAST

FedEx International Priority. FedEx International Economy 3

St. Martin 2014 SERVICES AND RATES

FSC Facts & Figures. September 1, FSC F FSC A.C. All rights reserved

FSC Facts & Figures. October 4, FSC F FSC A.C. All rights reserved

FSC Facts & Figures. December 1, FSC F FSC A.C. All rights reserved

FSC Facts & Figures. August 4, FSC F FSC A.C. All rights reserved

FSC Facts & Figures. September 12, FSC F FSC A.C. All rights reserved

FedEx International Priority. FedEx International Economy 3

2014 Global COBIT 5 Governance Study 1,245 respondents

FSC Facts & Figures. January 6, FSC F FSC A.C. All rights reserved

FSC Facts & Figures. February 1, FSC F FSC A.C. All rights reserved

FSC Facts & Figures. March 13, FSC F FSC A.C. All rights reserved

St. Martin 2015 SERVICES AND RATES

St. Martin 2017 SERVICES AND RATES

St. Martin 2018 SERVICES AND RATES

Process Maturity Profile

WORKFORCE METRICS BENCHMARK REPORT

FedEx International Priority. FedEx International Economy 3

St. Vincent & The Grenadines 2016

St. Vincent & The Grenadines 2018

FedEx International Priority. FedEx International Economy 3

British Virgin Islands 2019

Siemens Partner Program

FedEx International Priority. FedEx International Economy 3

FedEx International Priority. FedEx International Economy 3

FedEx International Priority. FedEx International Economy 3

Impact of MRCT after ICH E17 fully implement -Industry perspective-

FedEx International Priority. FedEx International Economy 3

FedEx International Priority. FedEx International Economy 3

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT

Manage Centre. Manage your IT operations from a single graphical interface

FedEx International Priority. FedEx International Economy 3

Puerto Rico 2014 SERVICES AND RATES

FedEx International Priority. FedEx International Economy 3

International management system: ISO on environmental management

Solution Partner Program Global Perspective

New Core-Shell Technology

Global IT Procurement and Logistics. Simplifying the complex: an end-to-end IT supply chain solution

Grow your business with Microsoft. Understanding the go-to-market opportunities for Independent Software Vendors

Model Contracts & Binding Corporate Rules: Reflections from Working with Global Organizations

PEFC Global Statistics: SFM & CoC Certification. November 2013

Cisco IT Data Center and Operations Control Center Tour

GLOBAL VIDEO-ON- DEMAND (VOD)

Contents. DYWIDAG Tie Rods DYWIDAG Threadbar Tie Rods... 4 GEWI Steel Waling Tie Rods... 6 DYWIDAG Tie Rods with Strand Tendons...

CDER s Clinical Investigator Site Selection Tool

NEW BRUNSWICK AGRIFOOD & SEAFOOD EXPORT HIGHLIGHTS 2015

FedEx International Priority. FedEx International Economy 3

Staples & OB10. Conference Presentation. Kevin Bourke & Joachim Eckerle Date: Presented by:

Running an RTB Network Across 10 Markets Publisher Opportunities ATTILA BARTA

Dimension Data Managed Cloud Services for Microsoft

FedEx International Priority. FedEx International Economy 3

Nuclear Power Outlook

Global Attraction and Retention Survey

Puerto Rico 2019 SERVICES AND RATES

FedEx International Priority. FedEx International Economy 3

FedEx International Priority. FedEx International Economy 3

FedEx International Priority. FedEx International Economy 3

FedEx International Priority. FedEx International Economy 3

Strategy and Outlook Annual General Meeting. Hubert Sagnières May 5, 2011

2015 MERCER LIFE SCIENCES REMUNERATION SURVEY

Busch Vacuum Technology Oil and Gas Industry

Argus Benzene Annual 2017

HEALTH WEALTH CAREER ROTATOR ASSIGNMENTS: TRENDS, CHALLENGES, AND OPPORTUNITIES FOR ENERGY, ENGINEERING & CONSTRUCTION, AND MINING

Belize FedEx International Priority. FedEx International Economy 3

Total Remuneration Survey. The key to designing competitive pay packages worldwide

PrimePCR Pricing and Bulk Discounts

Trinidad & Tobago 2018

PrimePCR Pricing and Bulk Discounts

Spirax SafeBloc TM. double block and bleed bellows sealed stop valve

Corporate Environmental & Social Due Diligence. EPS Restructuring Project, Serbia. The world s leading sustainability consultancy

PEFC Global Statistics: SFM & CoC Certification.

Belize FedEx International Priority. FedEx International Economy 3

Global Gas Deregulation Ed

Global Connections. Achieving Superior Local Results.

Driving your Growth Phone: (800)

Transcription:

EIA Update Report for the Keadby 2 Combined Cycle Gas Turbine Generating Station at Keadby, Lincolnshire Regarding an application under the Electricity Generating Stations (Variation of Consents) (England and Wales) Regulations 2013 13 th June 2018 www.erm.com The business of sustainability

Keadby Developments Limited EIA Update Report for the Keadby 2 Combined Cycle Gas Turbine Generating Station at Keadby, Lincolnshire Regarding an application under the Electricity Generating Stations (Variation of Consents) (England and Wales) Regulations 2013 FINAL June 2018 Prepared by: Kevin Murphy For and on behalf of Environmental Resources Management Approved by: Dr Kevin Murphy Signed: Position: Partner Date: 13/06/2018 This report has been prepared by Environmental Resources Management the trading name of Environmental Resources Management Limited, with all reasonable skill, care and diligence within the terms of the Contract with the client, incorporating our General Terms and Conditions of Business and taking account of the resources devoted to it by agreement with the client. We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above. This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report, or any part thereof, is made known. Any such party relies on the report at their own risk. Environmental Resources Management Limited Incorporated in the United Kingdom with registration number 1014622 Registered Office: 2 nd Floor, Exchequer Court, 33 St Mary Axe, London, EC3A 8AA

CONTENTS 1 INTRODUCTION AND PURPOSE OF THIS EIA UPDATE REPORT 1 1.1 PURPOSE OF THIS REPORT 1 1.2 APPLICATION HISTORY OF THE KEADBY 2 PROJECT 1 1.3 THE PROPOSED VARIATION 2 1.4 SCOPE OF THIS REPORT 2 2 COMPARISON OF THE PROPOSED VARIATION WITH THE 2017 CONSENT 4 2.1 INTRODUCTION 4 2.2 BUILDING/STRUCTURE DIMENSIONS 4 2.3 BUILDINGS/STRUCTURES LAYOUT 9 3 COMPARISON BETWEEN THE LIKELY SIGNIFICANT EFFECTS OF THE PROPOSED VARIATION AND THE 2017 CONSENT 11

1 INTRODUCTION AND PURPOSE OF THIS EIA UPDATE REPORT 1.1 PURPOSE OF THIS REPORT This Environmental Impact Assessment (EIA) Update Report has been prepared by Environmental Resources Management Ltd (ERM) on behalf of Keadby Developments Limited ( the Company ). It has been prepared to support an application under section 36C of The Electricity Act 1989 in accordance with the requirements of The Electricity Generating Stations (Variation of Consents) (England and Wales) Regulations 2013 ( the 2013 Regulations ). 1.2 APPLICATION HISTORY OF THE KEADBY 2 PROJECT On 10 September 1993, the Company was granted consent ( the Original Consent ) pursuant to section 36 of the Electricity Act 1989 and a Direction under section 90 of the Town and Country Planning Act 1990 providing for the construction and subsequent operation of a 710 MW combined cycle gas turbine generating station at Keadby, North Lincolnshire. The section 36 consent was subsequently varied on 3 rd November 2016 pursuant to section 36C of the Electricity Act 1989 (and the 2013 Regulations) and section 90(2ZA) of the Town and Country Planning Act 1990 ( the 2016 Consent ) to accommodate an increase in the electrical output of the plant, up to 820 MW. The application submitted in relation to the 2016 Consent included an Environmental Statement (ES) that was prepared in accordance with The Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2000 ( the 2000 EIA Regulations ). The Company subsequently sought a further variation to increase the electrical output of the 2016 Consent, up to 910 MW and to deliver a higher efficiency in electricity generation. This was in response to advances in gas turbine technology that had resulted in the availability of larger, more efficient combined cycle gas turbine ( CCGT ) units and the economic and environmental benefits of being able to deploy such units. The application submitted included an EIA Report (dated July that was prepared in accordance with The Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017 ( the 2017 EIA Regulations ). The EIA Report provided a comparison of the likely significant effects of the development (as proposed to be varied) as compared to those set out in the ES for the 2016 Consent. The variation consent was issued on the 21 st December 2017 ( the 2017 Consent ). The 2017 Consent allows for the development to be constructed and operated in either a single-shaft or multi-shaft plant configuration. The 2017 Consent references a Consolidated Parameter Layout Plan that accommodates both configurations and upon which (along with the dimensions at Tables 2.1 and 2.2 of the EIA Report) the EIA of the development was based. 1

1.3 THE PROPOSED VARIATION Since the 2017 Consent was granted the Company has taken the decision to proceed with a multi-shaft plant configuration and a technology provider has been selected. Further detailed design work has also been undertaken, which has resulted in some minor changes to the plant layout and the dimensions of the main buildings and structures, as illustrated by the multi-shaft plan refs. 105_0805_0035_Sheet01_Rev 02 and 105_0805_0037_Sheet00_Rev 00 that form part of the application. In view of the decision to proceed with the multi-shaft plant configuration and the further detailed design work that has been undertaken, the Company is proposing to simplify the consent by changing Condition 13 of the 2017 Consent so that instead of referencing the Consolidated Parameter Layout Plan it references the latest multi-shaft plans. It is also proposed that Condition 13 refers to the updated building/structure dimensions set out within this Report at Table 2.1 below where these supersede those listed at Tables 2.1 and 2.2 of the EIA Report dated July 2017. The changes to Condition 13 will allow for the minor changes to the plant layout and building/structure dimensions and provide greater certainty and clarity to the local planning authority as to the details it will be asked to approve under the condition and the plant that will be built at the site. 1.4 SCOPE OF THIS REPORT The proposed variation does not introduce any significant new or different effects that require assessment; therefore, this Report focuses on the requirements of Regulation 17 of the 2017 Regulations which states: (e) where the application is for a section 36 variation, the main respects in which the developer thinks that the likely significant effects on the environment of the development, as varied, will differ from those set out in (i) any EIA report or environmental statement prepared in connection with the application for the section 36 consent that it is proposed be varied; and (ii) if the section 36 consent has previously been varied by a section 36 variation, any EIA report or environmental statement prepared in connection with the application for that variation; (f) a non-technical summary of the information referred to in subparagraphs (a) to (e). As such the likely significant effects of the proposed variation are as reported in the following documents: Environmental Statement ( ES ) for the Keadby 2 Combined Cycle Gas Turbine Generating Station at Keadby, Lincolnshire, regarding an application under the Electricity Generating Stations (Variation of Consents) (England and Wales) Regulations 2013, Final Report, February 2016; and Environmental Impact Assessment ( EIA ) Report for the Keadby 2 Combined Cycle Gas Turbine Generating Station at Keadby, Lincolnshire, 2

regarding an application under the Electricity Generating Stations (Variation of Consents) (England and Wales) Regulations 2013, 24 July 2017. The remainder of this Report explains how the latest multi-shaft plans that form part of the proposed variation application result in no material changes to the assessment basis used for the EIA of the 2017 Consent or the environmental effects of the Project as now proposed to be built. 3

2 COMPARISON OF THE PROPOSED VARIATION WITH THE 2017 CONSENT 2.1 INTRODUCTION The previous section 36 variation applications, consented on 3 rd November 2016 and 21 st December 2017, proposed both single and multi-shaft configurations. The proposed variation essentially involves withdrawing the plans and drawings that referred to or accommodated the potential for a single-shaft configuration for the power station and retaining only plans and drawings that are relevant to the multi-shaft configuration that now makes up the intended design. The assessment presented in the EIA Report dated July 2017 for the 2017 Consent focused on a multi-shaft configuration. As such the proposed variation and the 2017 Consent have the same basis of assessment in terms of the power station design. The following sections provide verification that the basis of assessment remains effectively unchanged and therefore the conclusions of the EIA Report for the 2017 Consent are equally valid for the proposed variation. 2.2 BUILDING/STRUCTURE DIMENSIONS Table 2.1 compares building/structure dimension information presented in the EIA Report dated July 2017 (Tables 2.1 and 2.2) and used in the topic assessments that required such data. Making a comparison between the values provided in the rows annotated EIA Report Table 2.1 (Proposed columns) with the rows annotated Latest multi-shaft plans (2018), Application Drawing it can be seen that the proposed changes from the 2017 Consent are very small. For the main structures the table also includes the building/structure dimensions provided in the drawings that supported the application for the 2017 Consent. Table 2.1 Building/Structure Dimensions Comparison Description Document / Assessment Height Length Width Steam Turbine Hall 30 50 39 EIA Report Table 2.1 (S36C ES 30 50 39 2017 Consent application drawings: N/A N/A N/A Proposed Change 0 0 0 Air Quality modelling input data (see 28 52 49 Note 1 below) Photomontage input data 30 50 39 4

Description Document / Assessment Height Length Width Turbine hall annex for auxiliaries 12 50 14 EIA Report Table 2.1 (S36C ES 12 50 14 2017 Consent application drawings: N/A N/A N/A Proposed Change 0 0 0 Gas Turbine Hall Air Quality modelling input data The model inputs effectively included this annex as part of the Steam Turbine Hall itself and modelled a worst case in terms of building height at 28 m instead of 12 m. Photomontage input data 12 50 14 EIA Report Table 2.1 (S36C ES 2017 Consent application drawings (see Note 5 below): 27 50 23 27 50 23 30 49.2 22 Proposed Change 0 0.8 1 Turbine hall annex for GT generator Air Quality modelling input data (see 25 49 22 Note 1 below) Photomontage input data 27 50 23 EIA Report Table 2.1 (S36C ES 16 26 19 N/A Table 2.1 only noted the Main Structures of the Proposed Development for purpose of comparison with the Consented Development (see also Note 3 below). 2017 Consent application drawings: 16 25.8 19 Proposed Change 0 0.2 0 Air Quality modelling input data N/A Only structures meeting certain criteria of height/distance from the stack are included in the model (see also Note 3 below). This building is less than one third of the worst case (for air quality) stack height of 75 m. Photomontage input data 16 26 19 5

Description Document / Assessment Height Length Width Heat Recovery Steam Generator building 52 50 30 EIA Report Table 2.1 (S36C ES 52 50 30 2017 Consent application drawings: 52 50 30 Proposed Change 0 0 0 assessed in ES Stack Air Quality modelling input data (see 52 49 28 Note 1 below) Photomontage input data 52 50 30 85 8.5 diameter EIA Report Table 2.1 (S36C ES 75 to 85 8 2017 Consent application drawings: 75 to 85 8 Proposed Change 0 0.5 Air Quality modelling input data 75 8 Photomontage input data (see Note 2 85 8 below) Feed water pumps structure EIA Report Table 2.1 (S36C ES 15 24 20 N/A Table 2.1 only noted the Main Structures of the Proposed Development for purpose of comparison with the Consented Development (see also Note 3 below). 2017 Consent application drawings: 12 23 19 Proposed Change 3 1 1 Electrical Container PCC Air Quality modelling input data EIA Report Table 2.1 (S36C ES N/A Only structures meeting certain criteria of height/distance from the stack are included in the model (see also Note 3 below). 6 19 18 N/A Table 2.1 only noted the Main Structures of the Proposed Development for purpose of comparison with the Consented Development (see also Note 3 below). 2017 Consent application drawings: N/A N/A N/A 6

Description Document / Assessment Height Length Width Proposed Change 0 0 0 Generator transformer Air Quality modelling input data N/A Only structures meeting certain criteria of height/distance from the stack are included in the model (see also Note 3 below). Photomontage input data 6 19 18 EIA Report Table 2.1 (S36C ES 9 31 16 N/A Table 2.1 only noted the Main Structures of the Proposed Development for purpose of comparison with the Consented Development (see also Note 3 below). 2017 Consent application drawings: N/A N/A N/A Proposed Change 0 0 0 Regeneration Plant Air Quality modelling input data N/A Only structures meeting certain criteria of height/distance from the stack are included in the model (see also Note 3 below). Photomontage input data 9 31 16 EIA Report Table 2.1 (S36C ES 8 15 13 N/A Table 2.1 only noted the Main Structures of the Proposed Development for purpose of comparison with the Consented Development (see also Note 3 below). 2017 Consent application drawings: N/A N/A N/A Proposed Change 0 0 0 Cooling Towers Air Quality modelling input data Photomontage input data (see Note 4 below) N/A Only structures meeting certain criteria of height/distance from the stack are included in the model (see also Note 3 below). 8 14 13 28 177 25 7

Description Document / Assessment Height Length Width EIA Report Table 2.1 (S36C ES 28 192 25 2017 Consent application drawings: N/A N/A N/A Proposed Change 0-15 0 Air Quality modelling input data N/A N/A N/A Photomontage input data 28 177 25 NOTE 1 There are some small differences between the current design data and that used for air quality modelling in the EIA Report dated July 2017. For example, the air quality assessment modelled the steam turbine hall and gas turbine hall at heights 2 m less than the design height, and for the gas turbine hall 1 m less in width and length. In theory, this could have slightly underestimated the building downwash effects of these structures. It also modelled the steam turbine hall at 2 m longer and 10 m wider than the design dimensions which could in theory have slightly overestimated the building downwash effects of this structure. The HRSG building was modelled at 1 m less in length and 2 m less in width but at the design height of 52 m. Being the structure closest to the emissions stack and the tallest structure, the HRSG building will have the greatest influence on building downwash and local dispersion of pollutants. Table 4.7 of the EIA Report (July presenting dimensions used in the air quality assessment acknowledged this as follows: Further design evolution since building dimension data were provided to the EIA team for use in the air quality dispersion model has led to small differences in some dimensions of the currently proposed structures versus the modelled ones. The differences are sufficiently small that they are unlikely to materially change the overall assessment findings. NOTE 2 The emissions stack diameter has been increased slightly from 8 to 8.5 m. The stack diameter is designed to optimise the exit velocity of flue gases from the stack. Too narrow a diameter (and therefore too high velocity) and dispersion is compromised; too wide a stack (and therefore too low velocity) and dispersion is also compromised. The optimum stack diameter and exit velocity is based upon the requirements of the installed gas turbines, as recommended by the technology provider. There is a small amount of variation as there are differences in the emission profile between different types of gas turbine. In practice, there may be some small variation in stack diameter as detailed design proceeds (typically plus or minus 0.5 m or less), but the stack diameter will not be substantially changed for the reasons explained above. The final stack diameter will be determined once the exact plant specifications required for the selected turbine has been determined. These details will be finalised ahead of the Environmental Permit being submitted as they are required for that process. It is reasonable to conclude that a small change in stack diameter will not materially alter the findings of the air quality assessment and the information used from that assessment to 8

assess effects on ecological receptors. From a visual perspective, the Landscape and Visual Impact assessment considered a worst-case stack height of 10 m greater than the likely stack height. An increase in stack diameter of approximately 6% will have no bearing on the likely significance of effects in landscape and visual terms. NOTE 3 As explained where relevant in Table 2.1 above, not all the buildings/structures were included in Table 2.1 of the EIA Report (July or the air quality modelling assessment. There were two reasons for this: Table 2.1 of the EIA Report focused on the main buildings/structures of the Project; the air quality assessment only needed to consider other structures that could have a building downwash effect, comprising structures that were more than one third of the stack height modelled. This has no bearing on the conclusion of the EIA Report regarding likely significant effects. NOTE 4 A difference in 1 m in the length of the regeneration plant shown in the photomontages from the design length will make no material difference to the findings of the visual impact assessment. NOTE 5 There were some minor discrepancies between the design drawing data and Table 2.1 of the EIA Report of July 2017 (and the air quality modelling and visual impact input data) for the gas turbine hall. Table 2.1 set the height at 3 m below the design height, but the length and width dimensions 2 m and 1 m greater respectively. The air quality modelling used a height of 5 m less than the design height and a length 1 m greater. The visual impact assessment used a height 3 m below the design height, but the length and width dimensions 2 m and 1 m greater respectively. NOTE 6 Although the drawing shows 85m the design is for 75m. 2.3 BUILDINGS/STRUCTURES LAYOUT The EIA Report (dated July was based on a layout and positioning of the main buildings/structures presented in Figure 2.2 of that Report, reproduced as Figure 2.1 below. Comparison with the latest multi-shaft plans (refs. 105_0805_0035_01_Rev02 and ) shows no material differences. 9

Proposed Development Boundary Site Layout Cooling Tower Land set aside for future carbon capture technology installation Gas Turbine Building Heat Recovery Steam Generator Cooling Water Pipework (underground) Stack Steam Turbine Building 0 20 40 60 80 100 Metres SCALE: See Scale Bar VERSION: A02 SIZE: A3 DRAWN: OB PROJECT: 0280278 CHECKED: RM DATE: 24/07/2017 APPROVED: KM PROJECTION: British National Grid Figure 2.1 Site Layout Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community ± Path: P:\Projects\0280278_KeadbyGIS_GB_KM\MAPS\EIA 2017\0280278_SiteLayout_A02.mxd

3 COMPARISON BETWEEN THE LIKELY SIGNIFICANT EFFECTS OF THE PROPOSED VARIATION AND THE 2017 CONSENT Regarding the basis of assessment and input parameters used for assessing the impacts and effects, there is no material difference between the proposed variation and the 2017 Consent. As such, the proposed variation is predicted to have the same environmental effects as the 2017 Consent, which are as reported in the EIA Report dated July 2017. 11

ERM has over 160 offices across the following countries and territories worldwide Argentina Australia Belgium Brazil Canada China Colombia France Germany Hong Kong Hungary India Indonesia Ireland Italy Japan Kazakhstan Malaysia Mexico The Netherlands New Zealand Panama Peru Poland Portugal Puerto Rico Romania Russia Singapore South Africa South Korea Spain Sweden Taiwan Thailand United Arab Emirates UK US Vietnam ERM s Oxford Office 1-2 Eaton House, Wallbrook Court North Hinksey Lane Oxford OX2 0QS T: +44 (0) 1865 384800 www.erm.com ERM consulting services worldwide www.erm.com