Bidding Strategy I Day-Ahead Market 8 th February 2017 I New Delhi

Similar documents
California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

Welcome to Presentation on Integration of RES to the WR grid. 02 nd Sept, 2015 Taj Lands End, Mumbai

The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT. David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009

RENEWABLE ENERGY INTEGRATION IN TAMILNADU

Solar, Wind and Market Power in the New Zealand Electricity Market (and hydro lake dynamics) Mina Bahrami Gholami and Stephen Poletti

PORTFOLIO OPTIMIZATION MODEL FOR ELECTRICITY PURCHASE IN LIBERALIZED ENERGY MARKETS

MARKET MATTERS HVDC UTILISATION REPORT OCTOBER 2018

regulatory NEWS 03 Power Market Update: January 15 In this Issue...

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring

Impact of Renewable Energy Certificate (REC) Mechanism in India

REGULATORY NEWS. More information: Consumer Category FY 16-17

The Future of Electricity: A Market with Costs of Zero? Marginal

Stephen Batstone THE NZ ELECTRICITY MARKET: TEETERING ON THE EDGE OF TRANSFORMATION?

Data collected February 2019 Report published March 2019

The Future of Electricity: A Market with Costs of Zero? Marginal

Energy Uplift (Operating Reserves)

California ISO 2009 Annual Report on Market Issues and Performance

Electric Forward Market Report

Flexible Resource Adequacy Criteria and Must-Offer Obligation

Impacts of the EU ETS on Electricity Prices

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Keeyask Generation Project. Public Involvement. Supporting Volume. Environmental Impact Statement

SECTION 6 - ANCILLARY SERVICE MARKETS

Flexibility in the Swiss Electricity Markets. Jan Abrell Energieforschungsgespräche Disentis 2019,

PJM ENERGY PRICES 2005 Response to Howard M. Spinner Paper

2001 Annual Report on the New York Electricity Markets

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

Role of Emerging Technologies for Energy Challenges in India

A Bulk Energy Storage Resource Case Study with 40% RPS in 2024

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

EXPLANATORY NOTES FOR DRAFT GUIDELINES FOR OPERATION OF MERIT ORDER DESPATCH

August 22, 2014 FIRE ISLAND WIND

Energy Savings Analysis Generated by a Real Time Energy Management System for Water Distribution

Electricity market regulation: lessons learnt (by me) a 20 years journey

Load Shift Working Group.

System Needs: An Energy Planning Perspective. Randy Reimann

Ancillary Service Markets

Ancillary Service Markets

May 24, 2018 I Industry Research. Power: Yearly Update and Outlook. Graph 1 Electricity Generation Mix (FY18)

Energy Uplift (Operating Reserves)

Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012

Virtual Workshop on PJM ARR and FTR Market 2017/2018

Pumped hydro Storage Plants

Operations Report. Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, PJM 2018

The Confluence Model. Presentation to Modeling and Forecasting Working Group January 21, 2015

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Pricing Behavior in the Balancing Market. Alan Isemonger Manager, Market Information

Open Access Regulations & Operationalization

Operations Report. Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, PJM 2018

ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE

ACKNOWLEDGEMENT. The following staff members of the Department of Market Monitoring contributed to this report:

Leveraging Ahuroa and managing a fluid gas book

Estimation of the Capacity Value for Wind Power Generation in India Wind Discussion Forum August 22, 2014 New Delhi

Executive summary. Value of Smart Power Generation for utilities in Australia. A white paper by Wärtsilä and Roam Consulting

Draft 2011 Long-term Transmission Plan. Stakeholder Session June 20, 2011

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Woking. q business confidence report

For Bandon Utilities Commission

PRODUCTION FORECAST AND METHODOLOGY NUCLEAR

Integrating Energy Efficiency and Demand Response

California ISO. Q Report on Market Issues and Performance. November 1, Department of Market Monitoring

Procurement Guidelines Report Procurement Guidelines Report

TSO Recommendation System Services. 26 th June 2013

ABC of ABT - AVAILABILITY TARIFF

2007 State of the Market Report Midwest ISO. Midwest ISO

PJM Wind Integration Initiatives

Overview Of PJM Demand Response and Energy Efficiency. Issues September 22, Susan Covino, Senior Consultant Market Strategy

Price Formation. Eric Ciccoretti Attorney-Advisor Office of Energy Policy and Innovation Federal Energy Regulatory Commission June 13, 2017

Regulatory Developments in Singapore

The Implications of Lower Natural Gas Prices for the Electric Generation Mix in the Southeast 1

The New Jersey Clean Energy Conference September 26, PJM Overview. Kenneth W. Laughlin VP Markets Coordination PJM

REVENUE MANAGEMENT IN MARRIAGE HALL RAGUPATHY A SARAVANAN V.K-27047

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Alberta Capacity Market

Pay for Performance Regulation Year 1 Design Changes. Draft Final Proposal

Emerging issues relating to RE grid integration beyond F&S regulations

Technologies to Enable Wind Power Integration. John Kehler Technical Lead System Performance

Congestion and Marginal Losses

IUK is key infrastructure in physically connecting pipeline systems and markets

Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704)

Congestion and Marginal Losses

Chapter 6 Planning and Controlling Production: Work-in-Process and Finished-Good Inventories. Omar Maguiña Rivero

Half Hour Gate Closure. Issues & Possible Straw Man Solutions

Congestion and Marginal Losses

Operations Report. Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, PJM 2018

Assessment of Marginal and Long-term Surplus Power in Orissa A Case Study

Renewable Grid Integration Assessment Overview of Thailand Case study

Solving Climate: The Need for Zero Carbon On-Demand Power

Energy Efficiency & ESCO Services

Resource Adequacy Enhancements Straw Proposal - Part 1. Stakeholder Call January 23, 2019

Storage as a Transmission Asset:

Review of Interconnection Assistance Reliability Benefits. May 12, NPCC CP-5 Working Group

NON-TREATY STORAGE AGREEMENT

ESD 126. ESD 126 Economic Markets for Power

Further Analyses of the Exercise and Cost Impacts of Market Power In California s Wholesale Energy Market

Outline of Talk. Dynamic vs. Time-of-use pricing. Dynamic vs. Time-of-use pricing

Further Analyses of the Exercise and Cost Impacts of Market Power In California s Wholesale Energy Market

Evolution of RPO and REC Mechanisms : Indian Experience

Reforming the Mexican Electricity Market: Design and Regulatory Issues

Transcription:

Bidding Strategy I Day-Ahead Market 8 th February 2017 I New Delhi Rajesh K Mediratta Business Development +91-9654125157 I rajesh.mediratta@iexindia.com 1 For office use

In this presentation Type of Market Participants Bidding Strategy Discom OA Consumer Generator 2

Market Participants BUY SELL Electricity Trader/Member Open Access Consumer Industries with CPP DISCOM Electricity Trader/Member CPP/IPP Inter-State GS/State GS DISCOM 3

Power Purchase through IEX Power Exchanges provides a competitive option for purchase of power Better demand management can be done by purchase through power exchange High liquidity on exchange ensuring assured supply 4

Uniform Price Discovery Win-Win for both Buyer and Sellers 20 18 16 14 12 10 8 6 4 MCP: Rs 2.5 2 0 Demand (Buy) Supply (Sell) All the buyers with Bid> Rs. 2.5/u are selected and they pay Rs 2.5/u 0 50 100 150 200 250 300 All the buyers with Bid < Rs. 2.5/u are selected and they get Rs 2.5/u MCV: 120 MW 5

Volume in MW Volume profile on a typical day (01/11/2016) 16000 14000 Purchase Bid (MW) Sell Bid (MW) Cleared Volume (MW) 12000 10000 8000 6000 4000 2000 0 0 10 20 30 40 50 60 70 80 90 Time Blocks 6

15 min wise Price trend of a typical day in December 16 (22 nd Dec 16) Daily Average Clearing Price for December - 2016 3.50 3.00 2.50 2.00 1.50 1.00 0.50 0.00 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93

Avg Hourly Volume (MW) High Liquidity in Volume at IEX (Avg. Hourly Volume in MW) 1,130 698 394 *Data upto Dec 31, 2016 1,334 1,302 704 1,919 2,371 1,347 2,842 2,539 1,571 4,456 3,956 2,554 4,737 5,741 3,302 4,942 4,689 3,212 4,907 6,434 3,878 5,450 8,810 4,592 MCP (Rs/kWh) Purchase Bid (MW) Sell Bid (MW) Cleared Volume (MW) IEX Wt. Avg Price (Rs/kWh) 10,000 8.00 7.16 9,000 7.00 8,000 6.00 7,000 5.33 6,000 5.00 5,000 3.58 3.47 3.73 3.46 4.00 4,000 3,000 2,000 2.89 2.71 2.37 3.00 2.00 1,000 1.00 0 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17* 0.00

Data as on 31 Dec 2016 Monthly Price Trend FY2014-15 FY2015-16 FY2016-17 5.00 4.00 3.00 2.00 3.61 2.91 2.68 3.89 3.28 2.62 2.56 2.32 2.31 4.49 3.76 2.74 2.82 2.16 2.17 4.18 4.17 3.68 3.03 2.43 2.46 3.21 3.01 2.82 2.85 2.82 2.67 2.56 2.52 2.30 2.61 2.32 2.31 1.00 0.00 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

DISCOM : Bidding Strategy

Discom s Options For Power Procurement Long-term 25-year PPA - Tariff on cost-plus or competitive bid Medium Term Short Term (OTC) Day-Ahead Market (most preferred) Intra-day 3 Month- 3 Years Tariff covers : Fixed Cost + Variable Cost+ Mark Up (< long term) Intraday- 3 Months to be procured through competitive bidding only Single tariff covering Tariff covers Fixed Cost+ Highly liquid and transparent marketplace More accurate load management Last-minute adjustments (Gate closure 4 hours) Less liquid 11

Option with the Discoms: Utilising Exchange Market Two ways in which short term market can assist Discoms: 1. Meeting demand shortfalls or selling surplus at the Exchange i. Discoms should tie-up PPA only to manage their base demand ii. iii. Many Discoms have tied PPAs to meet their peak demand as well. The Discoms have to pay the capacity charge for this quantum even in the off peak time. So for optimum utilisation, Long Term PPA should be only for base demand and remaining energy (for peak and variations in forecast) should be bought through other available market options. 2. Optimising the available energy by scheduling based on merit order including Exchange prices i. Scheduling of power to be done on merit order basis after including the prices available at the Exchange

Meeting Shortages/Surplus through Short Term Market Maximizing efficiency Ideal Scenario (Monthly) Surpluses/Deficits - Balance physical supply and demand 7000 Base (MW) Short Term (MW) Load (MW) 6000 5000 4000 Short Term/Exchange for peak load 3000 2000 1000 0 PPA (Base Load Contract) 1 2 3 4 5 6 7 8 9 10 11 12 Month

Meeting Shortages/Surplus through STM Maximizing efficiency Ideal Scenario (Hourly) Surpluses/Deficits - Balance physical supply and demand 3500 3000 2500 2000 Base (MW) Short Term (MW) Load (MW) Short Term/Exchange for peak load 1500 1000 PPA (Base Load Contract) 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Meeting Shortages/Surplus through STM Maximizing efficiency Ideal Scenario Surpluses/Deficits - Balance physical supply and demand 36 34 32 Forecasted demand Day Ahead Buy Intra Day Market Buy Real-time demand Ancillary Service 30 Sell Sell 28 26 24 Short Term Market (for Peak Load) 22 PPA (Base load) contract 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Forecasted Demand Curve of the Discom Actual Demand Real time variations

SMART Buy through IEX in Power Procurement Under long term & medium term PPA : two part tariff Capacity charges (commitment charges): paid irrespective of whether discom purchase power from these plants or not Energy charges : Paid corresponding to the number of units of power purchased from that particular plant Discoms can replace costlier long term power by procurement from IEX, if, Energy charge of power plant is greater than IEX rates During night hours prices at IEX are further low and savings can be enhanced Discoms can replace ISGS first, keeping import constraint in consideration Discoms can continue paying fixed charge to Long Term PPAs and substitute where energy charge is higher than IEX price

Merit order dispatch schedule to be prepared based on Variable cost and considering Exchange Prices Capacity Tied up by Discom Long Term Contracts PPA I Variable Cost PPA 1 I 3.70 Bilateral Contracts Contract 1 I 4.70 Exchange IEX Price I 2.45 PPA 2 I 4.06 PPA 3 I 3.00 Contract 2 I 3.50 Must Run Plants (includes all hydro, nuclear or other take or pay type contractual plants) Merit Order Baseline PPA 4 I 1.99 PPA 5 I 2.00 Contract 3 I 2.10

Merit order dispatch schedule to be prepared based on Variable cost and considering Exchange Prices Contract 1 I 4.70 PPA 2 I 4.06 PPA 1 I 3.70 Contract 2 I 3.50 PPA 3 I 3.00 IEX Price I 2.45 Contract 3 I 2.10 PPA 5 I 2.00 PPA 4 I 1.99 Must Run Plants (includes all hydro, nuclear or other take or pay type contractual plants) Merit Order Baseline Increasing Variable Cost To be dispatched in this Order based on Energy Demand of the Discom

Cumulative Capacity (MW) Merit Order for a Discom Above Rs. 2/kWh, volume of 1935 MW is available for replacement and above Rs. 2.50 replaceable volume is about 516 MW 8000 7000 6000 5000 4000 3000 2000 1000 Peak Load: 6000 MW Base Load: 4200 MW 3,263 3,463 3,565 3,648 3,758 2,788 2,230 5,078 5,127 5,149 5,269 6,497 6,548 6,608 6,625 6,661 6,793 6,876 7,013 Above Rs 2.50/kWh, 516 MW is replaceable Above Rs 2.00/kWh, 1,935 MW is replaceable Above Rs 3/kWh, 137 MW is replaceable 0 Must Run 1.14 1.43 1.44 1.72 1.74 1.75 2.05 2.38 2.45 2.47 2.58 2.61 2.75 2.75 2.76 3.00 3.23 3.31 Energy Charge (Rs/kWh)

Power Purchase Optimization Process Assess Generation availability and Demand Forecast for next day (15 min block) Generation data for Long Term (LT) I Medium Term (MT) I Short Term (ST) Calculate Surplus and Shortage to prepare Regular Bid Prepare schedule with maximum back down possible for LT & MT For every plant identify maximum back down possible considering all constraints Technical I Must Run status I Contractual I Transmission ( Intra / Inter-state) Give technical minimum schedule to these plants and identify Replacement Bid quantum Submit Bid at Exchange (1000 Hrs-1200 hrs) Regular Bid: For Regular Shortage/Surplus depending on the demand and Generation cost Replacement Bid: Price sensitive bids ( based on Variable cost) for every plant Two Bid Options Single Bid: For every 15 min time block separately. May lead to non uniform schedule Block Bid: All or none principle for clubbed time blocks. Will ensure uniform schedule Post IEX result- finalize schedule ( after 1500 Hrs) If Replacement bid not selected: Revise the schedule from the plants whose bid is not selected If Replacement bid selected: No change and retain the earlier schedule (max possible back down)

Consumer : Bidding Strategy

Industries Options For Power Procurement Discom (Existing) Medium Term Short Term (OTC) Exchange (most preferred) Regulated Tariff approved by Respective SERCs 3 Month- 3 Years Tariff covers : Fixed Cost + Variable Cost+ Mark Up (< long term) Intraday- 3 Months to be procured through competitive bidding only Single tariff covering Tariff covers Fixed Cost+ Highly liquid and transparent marketplace More accurate load management through Day Ahead Market Self Generation Costly fuel / less efficient units Much higher costs 22

Open Access option Full Open Access Surrender demand with the Discom and doesn t pay demand charges No more a Discom consumer Pays Wheeling charge Discom no more a fall back option Partial Open Access Maintain the Demand with Discom and continue to pay Demand Charges Pays Wheeling charge Discom is a fall back option, hence consume prefer this option 23

1.27 1.57 1.66 1.89 1.92 1.96 2.06 2.21 2.46 2.63 2.72 2.75 2.98 3.14 3.25 3.39 3.54 3.55 3.61 3.72 3.83 3.85 3.95 4.08 4.12 4.15 4.16 4.62 1.93 5.01 4.14 0.68 4.39 2.77 1.99 1.67 2.47 3.27 1.32 4.15 2.56 1.45 2.29 1.56 4.14 3.69 2.13 2.32 2.50 0.75 3.13 3.04 0.75 2.09 Bid Price & Cleared Price Sensitivity <Rs 1/u > Rs 2/u >Rs 3/u >Rs 4/u 5.89 3.50 6.67 6.03 2.60 6.35 4.83 5.10 4.204.13 5.99 4.07 7.13 5.70 4.70 5.68 5.10 7.69 7.30 5.85 6.156.35 4.70 7.21 7.16 4.90 6.25 Sorted in ascending order of break-even bid rate Bid Rate (Rs/kWh) Open Access charges (Rs/kWh) Energy Charge (Rs/kWh) 24

OA Consumer Bid Consideration Consumer bid around the break even rate Bid only selected if the exchange price <= bid price 14.00 12.00 10.00 8.00 6.00 4.00 2.00 Karnataka Open Access Buy (MU) Daily Price (Rs/kWh) Break-even rate (Rs/kWh) 0.00 1-Apr-16 1-May-16 1-Jun-16 1-Jul-16 1-Aug-16 1-Sep-16 1-Oct-16 1-Nov-16 1-Dec-16 1-Jan-17 25 Break even rate Rs 4.16/kWh 7.00 6.50 6.00 5.50 5.00 4.50 4.00 3.50 3.00 2.50 2.00 1.50 1.00 0.50 0.00-0.50-1.00-1.50-2.00-2.50-3.00-3.50-4.00-4.50-5.00-5.50-6.00-6.50-7.00-7.50-8.00-8.50-9.00-9.50-10.00

Generators : Bidding Strategy

Bidding Strategy/Consideration Generators Bid at variable cost For generation over and above the technical minimum Bid < variable cost Tied up part generation which is less than the technical minimum of the unit Additional volume required to achieve technical minimum will be bid as must sell 27

Price (Rs/kWh) Revenue Maximization through Pump Storage Power Plant 5 4 3 Buy Volume: 300 MW Buy time blocks: 11-22 Actual Area price: Rs 1.35/unit Landed price: Rs 1.78/unit Cost of Power: Rs 5.35 Lacs Sell Volume: 225 MWh Actual Area price: Rs 3.63/unit Landed price: Rs 3.31 Total Revenue: Rs 7.45 Lacs Total Saving Rs 2.1 Lacs in a day 2 1 1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 15 min time blocks for 25th February 2016 There is a potential to operate PSP purely on merchant basis at IEX, by pumping water during off peak (buy from IEX when prices are low) and generate during the peak (Sell when prices are high). With the significant difference in the IEX prices in off-peak & peak duration there is scope of good revenue generation.

Thank You www.iexindia.com Follow us @IEXLtd Use IEX Mobile Application to track prices Reach me @ +91-9654128299 Rajesh.mediratta@iexindia.com Register for Daily SMS alerts Register for IEX Monthly Bulletin 29

Bidding Consideration by Generator 14.00 12.00 Meenakshi Energy Sell (MU) Avg Price (Rs/kWh) 8.00 6.00 4.00 10.00 2.00 8.00 6.00 4.00 2.00 0.00-2.00-4.00-6.00-8.00 0.00 1-Apr-16 1-May-16 1-Jun-16 1-Jul-16 1-Aug-16 1-Sep-16 1-Oct-16 1-Nov-16 1-Dec-16 1-Jan-17 30-10.00