Integrating Asset Management and Growth Planning Ontario West Municipal Conference London, Ontario November 20, 2015

Similar documents
DATE: September 8, 2014 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration

4 Desired Levels of Service (LOS)

City of Brantford Managing Linear Assets

Asse t Man age m e n t P lan. Providing essential services that meet approved standards at minimum cost

DATE: January 16, 2018 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration

COMPREHENSIVE ASSET MANAGEMENT POLICY APPROVED BY COUNCIL ON OCTOBER 10, 2012

ODOT Asset Management Plan 0

Summary of Findings. Bridge Inspection and Monitoring. Introduction. Findings

Developing Your Local Government Asset Management Plan

Corporate asset management strategy: 2016 UPDATE

5 Asset Management Strategy

Introduction. Background

City of Victoria Aging Infrastructure Review and Assessment

GOALS AND PERFORMANCE MEASURES

Asset Management Fundamentals

VISION Create a progressive and safe community in which to live, work and visit.

Linking AMPs to Short- Term and Long-Term Investment Plans

STORM WATER ASSET MANAGEMENT PLAN & PROGRAM

MINISTRY OF TRANSPORTATION ONTARIO MANAGING OUR ASSETS

Desired Levels of Service

MAP-21 National Highway Performance Program Asset Management Plan

NCHRP 8-87 Implementing GIS for Transportation Asset Management. 10 th National Conference on Transportation Asset Management April 28, 2014

Designing the Future of NMDOT

Planning Analytics for Asset Lifecycle Management (PALM)

Integrated Asset Management Strategy. Asset Management Strategy Report

Memorandum Karen Nickols, Project Manager Michigan Department of Environmental Quality (MDEQ) Revolving Loan Section

Drainage Services Master Plan Aspirational Plan May 5, 2014

International Scan on Asset Management: Australia, Canada, England, and New Zealand. April 8-April 23, 2005

Manitoba Infrastructure: Service Delivery Review

Presentation to the Alameda County Board of Supervisors FY Budget Request April 12, 2016

Joint Legislative Transportation Oversight Committee January 6, 2016 Maintenance Operations Performance Analysis Report (MOPAR) Kristin Barnes

Safety Management System for Israel

Transportation BUSINESS PLAN ACCOUNTABILITY STATEMENT

LOU LAMBERT, DEPUTY DIRECTOR BUREAU OF TRANSPORTATION PLANNING

STRATEGIC ASSET MANAGEMENT POLICY

Coordinating Minnesota s Transportation Assets and Climate Change and Extreme Weather Vulnerability

The Corporation of the City of London Proposed Risk Assessment and 2013 Risk-Based Audit Plan. January 31, 2013

Management. VA SITE Annual Meeting June 27, 2013 Jay Styles Performance and Strategic t Planning Manager, Business Transformation Office

Town of Bradford West Gwillimbury Asset Management Plan. Subject to Council Approval

Michigan Department of Environmental Quality (MDEQ) Revolving Loan Section, Attn: Jonathan Berman

Reducing Flood Risk in Toronto. David Kellershohn, M.Eng., P. Eng. Toronto Water, City of Toronto

Management of Aging Wastewater Infrastructure -- Challenges and Strategies --

AASHTO Manual for Bridge Evaluation: Section 3, Bridge Management Systems A Practical Tour

Communicating an Evidence Based Asset Management Program By Daryush Esmaili

Asset Management. (An Overview) Developing best practice asset management plans & programs RESEARCH 2017 PSD ALL RIGHTS RESERVED

Asset Management Plans for the National Highway System

CASE STUDY CITY OF HAMILTON, CANADA

Corporate Asset Management Plan 2016

Livability 2050 Regional Transportation Plan Update. RTPAC #3 July 26, 2018

IMQS SOLUTIONS ASSET MANAGEMENT

2018 Divisional Budget. Infrastructure and Planning Services Division

THE FIVE GOALS FOR SCDOT S STRATEGIC PLAN ARE: GOAL 1: Improve safety programs and outcomes in our high-risk areas.

RURAL CENTER COMMUNITY ROLE COUNCIL ROLE RURAL CENTER ALL COMMUNITIES

CORPORATION OF THE TOWNSHIP OF RUSSELL. By-law# Being a by-law to adopt the Strategic Asset Management Policy.

Good to Great: A More Dynamic and Robust Linear Asset Management Program. Presented By: Jonathan Okafor, P.E. Fairfax County Paul Longo Dewberry

ASSET MANAGEMENT PROGRAM

IBM Maximo Asset Management solutions for the oil and gas industry

COUNTY OF PERTH. Public Works Department Business Plan

City of Edmond Department of Public Works STRATEGIC PLAN FY2017/18. Public Services that Work!

Stormwater Advisory Committee

Summary of transportation-related goals and objectives from existing regional plans

DATE: January 20, 2014 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration

Agenda. Introductions & Background Project Approach & Progress Review of Gaps Development of Priorities & Strategies Funding Strategies Conclusions

SUBURBAN EDGE COMMUNITY ROLE COUNCIL ROLE ALL COMMUNITIES SUBURBAN EDGE

Metropolitan St. Louis Sewer District. Strategic Business and Operating Plan Fiscal Years

IDOT PERFORMANCE BASED PROJECT METRICS. February 2018

Section 8 System Evaluation and Capacity Assurance Plan (SECAP)

City of Brantford Chapter 3 TABLE OF CONTENTS

The environment Water pollution Flooding, drainage, combined sewers Aging infrastructure New mandated and unfunded EPA regulations General fund

Canadian Infrastructure Report 2012: Highlights

Hamilton 2019 D.C. Study: Capital Presentation. Development Charges Stakeholders Sub-committee Meeting January 28, 2019

Business Plan: Drinking Water Supply

STRUCTURE AND BRIDGE DIVISION

Water Supply and Delivery

Maintenance, Construction & Secondary Roads. Terry Gibson, PE Chief Engineer February 20, 2013

10.0 ASSET MANAGEMENT PRACTICES. Table of Contents

TRANSPORTATION DEMAND FORECASTING INFORMATION SESSION

LOCATED IN WASHINGTON COUNTY LAND AREA: 8.75 SQ. MI. POPULATION: 14, C/L MILES ODOT DISTRICT 10 CONTAINS 5 STATE ROUTES 1ST SETTLEMENT IN THE

STAFF REPORT OPERATIONS SERVICES. Kevin De Leebeeck, P.Eng., Director of Operations. THAT Council receive Report OPS Fleet Replacement Strategy;

INVESTMENT SCENARIOS CHAPTER Illustrative Investment Approaches Public Outreach 6-1

Municipal Infrastructure Asset Management Systems: State-of-the-Art Review

Transportation Report to SPC on Transportation and Transit 2017 April 19. ISC: UNRESTRICTED TT Page 1 of 7

Wastewater System Financial Plan. For the Corporation of the City of Thunder Bay

Engineering & Capital Improvements. Shore Acres Civic Association August 21 st, 2017

Using MAP-21/FAST to Strengthen New Mexico DOT s Transportation Asset Management Program

BUILDING A WORLD OF DIFFERENCE. Madison Water Utility Infrastructure Management Plan

The City of Burlington Asset Management Plan

May 14, 2018 WEBINAR QUEBEC

SSO- WDR Compliance Workshop Electronic Reporting: Reporting Requirements & Tips. Sewer System Management Plan Chapter

Existing Conditions Summary and Capital Improvement Plan

Lucas County Sanitary Engineer 2015 Strategic Plan

Infrastructure Asset Management in Action at Onondaga County Department of Water Environment Protection (WEP)

Design and Implementation of a New Bridge Management System for the Ministry of Transport of Québec

SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION. Initial Transportation Asset Management Plan

FHWA s Eco-Logical Process: Uses in Performance-Based planning

Using Integrated Asset Management System to perform Corridor-Level Analysis

Metropolitan St. Louis Sewer District Statement of Policy for Maintenance of Stormwater Sewer Systems

Chapter 5 - Transportation

Comprehensive Asset Management Plan

Chapter 15: Asset Management System

Transcription:

Integrating Asset Management and Growth Planning 2015 Ontario West Municipal Conference London, Ontario November 20, 2015

Presentation Outline 1. The City of Brantford 2. Asset Management Planning at the City 3. Growth Planning 4. Master Servicing Plan 5. Transportation Master Plan 6. Growth Planning Integration 7. Integrating AM Planning & Growth Planning 8. Benefits of a Harmonized Program 2

The City of Brantford Established in 1877 73 square kilometers situated on the Grand River Located on Hwy 403 corridor between Hamilton & London Surrounded by Brant County Population approx. 94,000 (2011 census) Significant student population (Wilfrid Laurier University, Nipissing University, & Conestoga College) Single-Tier Government responsible for all aspects of municipal services & management Extensive infrastructure base 3

4 Setting the Asset Management Stage Centralized asset management planning & activities Centralized asset repositories Quality & Regulatory Compliance Greater alignment & accountability System-wide infrastructure data analysis Optimized resource allocation Enabled focused asset management vision Long-term planning & forecasting

Team Focus & Responsibilities 5

6 Asset Management at the City of Brantford Mission Statement Brantford will efficiently manage its assets to meet the service needs of the present without compromising the sustainability of its infrastructure for the demands of the future by knowing the assets for which the City is responsible, the condition of these assets, how to maintain the assets to maximize useful life and budgeting appropriately so assets can be replaced once they have expired or are not able to consistently provide planned levels of service. Core Values Asset Management is an organizational commitment; Services and assets must be sustainable; Operate in a transparent and accountable manner; Continuous improvement of processes, data and technology; and Minimize risk to levels of service and public health and safety.

7 Strategic Asset Management Initiatives Capital Planning, Budgeting & Forecasting Asset Management Plan State of Local Infrastructure Report Card Financial Reserve Fund Analysis Condition Assessment Programs Financial Tracking Policies Activity Tracking & Data Analytics Hydraulic Modeling & System Analysis Planning for Growth (TMP/MSP) Prioritization Framework(s)

8 State of the Infrastructure Report Inventory Valuation Service Life Condition Rehabilitation Planning Financial Forecasting

9 Scoring the Assets Very Good Good Fair Poor Very Poor Fit for the Future 76%-100% RSL Adequate for Now 51%-75% RSL Requires Attention 26%-50% RSL At Risk 0%-25% RSL Unfit for Sustained Service Less than 0% RSL RSL Estimated Remaining Service Life. Calculated as a weighted combination of known condition (where available) and theoretical remaining service life.

Financial Forecasting Lifecycle Analysis 10

Financial Forecasting Gaps Analysis 11

12 Condition Assessment Activities Staff uses data, studies and analyses to ensure that financial resources are directed to the highest priority assets, ensuring the most efficient use of available funding Studies are incorporated into capital budget forecasts to gain a clearer understanding of future needs and impacts Condition Assessment Activities Detailed Roadway Drivability Assessment Traffic Sign Reflectivity and Inventory Verification OSIM Bridge and Culvert Inspections (approx. 75 structures) Facility Building Condition Audits (approx. 60 buildings Structural Condition Assessments - Lorne Bridge, and Market Parkade CCTV Inspection of Sanitary and Storm mains Sanitary Pumping Station Condition Assessment and Inventory Verification Sidewalk Condition Assessments Stormpond Condition Assessment Landfill Master Plan and Condition Assessment Water Facility Condition Assessments

Project Prioritization & Data-Based Decisions Corporate Facilities 13 Required to Meet Legislated Standards Does the project satisfy Prov. or Fed. mandates? Is the project required for regulatory reasons? Health and Safety Does the project eliminate a risk or hazard to public health? Does the project reduce hazards or risks to users of the facility? Consequence of Failure What is the consequence of failure of the asset (high, medium, low) Levels of Service O&M Impact Improved Efficiency Expansion and Growth Coordinated Project Does the project maintain level of service standards? Does the project affect all customers in a neighborhood or facility? Does the project affect all customers within the City? After completion, will the project increase O&M cost and time? Will the project decrease O&M budgets? Does the project require the hiring of new staff? Will the project increase the efficiency of existing processes? Does the project preserve or extend the life of an existing asset? Does the project use innovative solutions? Does the project increase capacity to meet existing deficiencies? Does the project increase capacity to meet future growth needs? Will the project attract new economies? Will failure to complete the project delay or impact other programs? Is the project required to be coordinated with other projects?

Project Prioritization & Data-Based Decisions Linear Infrastructure 14

15 Predictive Analysis Used to project future condition of assets Based on known condition and standardized life cycle curves Provides long-term visioning, based on current data Powerful education tool Illustrates theoretical future condition based on changing reinvestment levels Example: Road Condition Typical Road Lifecycle Curve

16 Current Road Condition (2014) 3.9% OF ROADS WITH A FAIR TO POOR PAVEMENT CONDITION Time Period Backlog % (% Of Total Road Network) 2015 3.9% 2020 11.4% 2025 34.9%

17 Projected Future Road Condition (2020) 11.4% OF ROADS WITH A FAIR TO POOR PAVEMENT CONDITION Time Period Backlog % (% Of Total Road Network) 2015 3.9% 2020 11.4% 2025 34.9%

18 Projected Future Road Condition (2025) 34.9% OF ROADS WITH A FAIR TO POOR PAVEMENT CONDITION Time Period Backlog % (% Of Total Road Network) 2015 3.9% 2020 11.4% 2025 34.9%

19 Growth Planning Population projections based on Amendment #2 (2013) Growth Plan for the Greater Golden Horseshoe, 2006 - Schedule 2031A Growth Projections allocated by traffic zones and land use Acknowledgement of intensification targets Includes municipal comprehensive review of commercial & employment lands City s Official Plan is currently under review (www.brantford.ca/govt/projects/officalplanreview)

20 Master Servicing Planning Identifies preferred water, sanitary, and stormwater servicing strategic visions to support existing needs and projected growth The MSP provides the business case for the need, timing and cost of servicing and infrastructure in support of the DC By-Law Results in the identification of preferred servicing strategies, net costs of required capital and growth-related capital projects Public consultation & community outreach components www.brantford.ca/govt/projects/masterservicingplan

21 Transportation Master Planning Identifies preferred roadway, transit, and active transportation servicing strategic visions to support existing needs and projected growth Identification of preferred servicing strategies, net costs of required growthrelated capital projects Review & update of transportation policies www.brantford.ca/govt/projects/transportationmasterplan

22 Growth Planning Integration Growth Targets Land Use Goals Land Use Policies 25 Year Growth Plan Water Servicing Wastewater Servicing Stormwater Servicing Based on land use, population projections, & system design standards 5 YEAR RETURN FREQUENCY Initiatives planned for individually but scheduled sequentially Official Plan Master Servicing Plan Development-related net capital costs Costs apportioned to type of development Based on approved growth forecasts Development Charges By- Law Transportation Master Plan Transportation demand management Truck route management Transit improvements Active transportation Parking

23 Integrating AM Planning & Growth Planning State of Good Repair Growth Needs Harmonized Capital Program

Harmonizing Needs Facilitates the optimization of individual asset intervention and the timing of intervention between the underground utilities and roadway SANITARY WATER STORM 24

Spatial Asset & Corridor Rating Tool Developed within a GIS environment Based on database SQL and spatial-sql queries Individual ratings based on defined criteria / KPI s Final risk score for each individual linear section All criteria weighted to allow for real world adjustment / calibration Individual networks aggregated to form singular corridor rating 25

Data Analytics at Work Data analytics is used to consolidate infrastructure needs and determine priorities Analysis & prioritization frameworks are applied consistently across program areas Consistent frameworks & communication build trust in project recommendations Reduces extensive deliberation at the Council table around the value of projects PRIORITIZATION FRAMEWORKS CONSISTENT APPLICATION DATA DEFENDABLE, DATA-DRIVEN CAPITAL PROGRAM 26

Harmonized Program 10 Yr. Capital Forecast 27

28 Benefits of Harmonization Greater return on investment Harmonize State of Good Repair & Growth infrastructure Minimize public disruption Maximize the lifecycle of the assets while minimizing network lifecycle cost Coordinated Planning for optimal infrastructure use Optimize funding mechanisms Maintain Levels Of Service

Summary Asset management at the City is always improving, as we strive towards efficiently managing assets to meet the needs of the present without compromising long-term sustainability Implementing procedures to better understand: The assets and their condition How to maintain them to maximize useful life How to budget appropriately so assets can be replaced when needed The development and implementation of asset management procedures supports: Our progression towards being recognized as a well-managed city The provision of efficient and effective government services while remaining fiscally responsible. CONTINUOUS IMPROVEMENT Modelling & Planning Implementation Reviewing & Monitoring Analysis 29

QUESTIONS? Contact Information Geoff Linschoten, Director of Facilities & Asset Management glinschoten@brantford.ca Tara Gudgeon, Manager of Capital Planning & GIS Services tgudgeon@brantford.ca 30