TNPL Mini Cement Plant (LSFM) EC Compliance Status Report as of 30/09/2015

Similar documents
J-11011/45/2009- IA II (I)

Environment protection measures / technology

Environmental Clearance Compliance Half Yearly Report

Calcom Cement India Limited

THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server.

Mangalam Cement Ltd. (Unit-II) Stack No.

Environmental Clearance Compliance Half Yearly Report

M/s Deccan Cements Limited, Bhavanipuram,Janaphad, Palakeedu, Suryapet. Telangana MoEF No: J-11011/572/2007-IA II(I) Dated

Environmental Clearance Compliance Half Yearly Report

Name of Project: J.K. Cement Works (Unit: J.K. Cement Ltd.), Muddapur (Karnataka)

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

Six Monthly Compliance status of Environment Clearance for Cement Plant (5300 TPD Clinker) at Village Lumshnong, Meghalaya January to June 2013

Environmental Clearance Compliance Half Yearly Report

Environmental Clearance Compliance Half Yearly Report

Mangalam Cement Ltd.(Unit I)

Environmental Clearance Compliance Half Yearly Report

Environmental Clearance Compliance Half Yearly Report

Telefax: 011: Dated:10 th May, 2013

Compliance of Conditions laid down by MoEF for Expansion of Cement Plant (2.0 MTPA to 2.6 MTPA Clinker) at Village Suli April 2017 to September 2017

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL-2016 TO SEPTEMBER F. No. J-11011/309/2011-IA-ll (I)

SreeJayajothi Cements Limited (100% Subsidiary of M/s. My Home Industries Private Limited), Srinagar, Yanakandla , Kurnool Dist, Andhra

F. No. J-11011/480/2007-IA II (I) Government of India Ministry of Environment and Forests (I.A Division)

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT

COMPLIANCE STATUS REPORT

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

(A) Specific Conditions

D:\My Documents\Legislative\Legislation BS\Consents\Six monthly compliance\cement\june 2017\COMPLIANCE STATUS.docx.docx

PROJECT NAME: UTKAL ALUMINA INTERNATIONAL LTD. PERIOD OF COMPLIANCE: APRIL, 2013 TO SEPTEMBER, 2013.

Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi , Taluka - Shirol, Dist Kolhapur, Maharashtra

THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT

Janki Corp. Ltd., Six Monthly Compliance Report

Mangalam Cement Ltd.

BRGD Ingot Private Limited 4, D.L. Khan Road, Block-C, Flat No. 201, 2 nd Floor, P.S. Kalighat, P.O. Bhowanipur, Kolkata

COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated

Cement Manufacturing Company Ltd. Page 1

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS

High efficient ESP s has been provided to maintain an emission level below 100mg/Nm 3 in CPP. Modification of ESPs and.

Chambal Fertilisers and Chemicals Limited CFG3 Project Environment Clearance_ Compliance Report (Feb 28, 2018)

PROJECT NAME: UTKAL ALUMINA INTERNATIONAL LTD. PERIOD OF COMPLIANCE: OCTOBER 2014 TO MARCH 2015.

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

Hind Energy & Coal Beneficiation (India) Ltd.

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

SREE RENGARAAJ ISPAT INDUSTRIES (P) LIMITED MM1,2 &5 SIPCOT Industrial Growth Center, Perundurai, Erode district

Ref: Environment Department, MS, SEIAA Letter SEAC 2010/CR.824/TC-2 Dated 2 nd Nov 2011

Hind Energy & Coal Beneficiation (India) Ltd.

Subject: Half yearly Report for the period of 1 st April 2013 to 30 th Sept., 2013 for Indmax Project

M/s. LAKSHMANAN CEMENTS PVT LTD, Survey Number 69-3, 69-4, Pachanapalli Village, Chittoor Mandal and District, Andhra Pradesh

My Home Industries Private Limited Srinagar, Mellacheruvu (V & M) , Suryapet Dist., Telangana State

From : April 2015 To : October 2015 Status of conditions stipulated in Environmental and CRZ clearance. Adani Vizag Coal Terminal Private Limited

MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL SAFEGUARDS Ministry of Environment & Forests Regional Office (W), Bhopal Monitoring Report Part-I

HALF YEARLY COMPLIANCE REPORT 14 15) ENVIRONMENTAL CLEARANCE (CLINKER 2.48 MTPA TO 2.78 MTPA AND CEMENT 3.30 MTPA TO 3.90 MTPA)

Overburden dumps are stacked separately as per the guidelines and the same will be used for backfilling in mined out area.

6 th MONTHLY COMPLIANCE REPORT OF DIBRUGARH-BHOGPARA AREA

Accord Energy Corporation India Pvt. Ltd.

Mill Expansion Cum Augmentation Project Compliance

ANDHRA PRADESH POLLUTION CONTROL BOARD, REGIONAL OFFICE, TIRUPATI

Telefax: 011: Dated: 8 th March, 2013

Date: M/S Desh Bhakt Ratnappa Kumbhar Panchaganga SSK Ltd, Inchalkaranji, Kolhapur.

A. SPECIFIC CONDITION COMPLIANCE

My Home Industries Private Limited Srinagar, Mellacheruvu (V & M) , Suryapet Dist., Telangana State

Six Monthly Compliance Status Report

Rajasthan State Pollution Control Board

Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu

iii Continuous stack monitoring facilities to monitor gaseous emissions from the process stack shall be provided. After expansion, limit of PM shall b

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

COMPLIANCE REPORT TO THE CONDITIONS LAID IN THE ENVIRONMENTAL CLEARANCE

Compliance Report of EC : Compliance Status

Application of Low and Non Waste Technology in the production process;

Mangalam Cement Ltd. Clearance Letter No. :- F NO. J / 30/ IA II (I), dtd 17/07/2007

PART A. M/s Shree Cement Ltd, (Grinding Unit) village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SHREE CEMENT LIMITED, Compliance Status of 300 MW (2x150 MW) Thermal Power Plant. At Village Andheri Deori, Tehsil-Masuda, District Ajmer (Rajasthan)

Pre-Feasibility Report [Application submitted for obtaining Terms of Reference for Prior Environment Clearance]

Manufacture of Products like Phthalic Anhydride, Benzoic Acid and Power.

Hope you will find the same in order. Thanking You, For EMAMI PAPER MILLS LTD. Authorized Signatory

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

NMDC Iron and Steel Plant, Nagarnar, Dist-Bastar, (C.G.) Six Monthly Progress Report

M/s Balasore Alloys Ltd

Health and safety norms of CPWD should be followed during construction.

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

NATCO PHARMA LIMITED CHEMICAL DIVISION Mekaguda (Village), Nandigama (Mandal), Rangareddy (Dist.)

GENERAL CONDITIONS. 7. The Applicant will adopt the prescribed norms, and standards provided in the national Building Code of India 2005.

Shriram Vinyl & Chemical Industries, : Kota Compliance Report of Environmental Clearance dated 12 th July 2017 and amended on 23 rd November 2017

2 x 300 MW (STAGE-I)

Project Code: Clearance Letter No. : MoEF vide letter No: - J-11015/423/2005-IA-II (M) Dated 18 th May 2006

ENVIRONMENTAL GUIDELINES FOR PREVENTION AND CONTROL OF FUGITIVE EMISSIONS FROM CEMENT PLANTS

Scanned by CamScanner

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative)

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED

J.K. Cement WORKS, MANGROL (RAJ) 25 MW Captive Power Plant & 10 MW Waste Heat Recovery Boiler

Name of the Project:- J&K Mineral Development Corporation Limited.

Proposed Draft Terms of Reference for Preparation of EIA & EMP for Louis Pharmaceuticals Pvt Ltd STANDARD TERMS OF REFERENCE

Your letter ref. no. J-11011/131/2005-IA.II (I) dated A. SPECIFIC CONDITIONS

PRE FEASIBILITY REPORT. Company of production capacity: 14,40,000 CFT/ Year located at Khasra No near Village:

Transcription:

TNPL Mini Cement Plant (LSFM) EC Compliance Status Report as of 30/09/2015 State Environment Impact Assessment Authority, Tamil Nadu vide Order No. SEIAA TN/ F 3082/KAR/ 3(b)/EXP/EC 8/2014 dated 12.03.2015 accorded Environmental Clearance (EC) for the project of modernization/upgradation of TNPL Cement Plant, Kagithapuram for enhancement of cement production capacity from 0.22MTPA (600 TPD) to 0.33 MTPA (900 TPD) at SF Nos. 841, 842,843,844,809 & 837 of Punjai Pugalur Village, Manmangalam Taluk, Karur District. The commercial production of the unit was commenced on 15/12/2012. The unit is in continuous operation. The unit is possessing renewal Consent To Operate order under both Water and Air Acts for the period ending 31/03/2016. The status of compliance to each condition stipulated in the Environmental Clearance as of 30 th September 2015 (for the period 01/04/2015 to 30/09/2015) is given below: SPECIFIC CONDITIONS: SL.NO CONDITIONS STAUS OF COMPLIANCE 1 The modernisation / expansion project shall comply with the new discharge emission standards of MoEF & CC issued vide GSR 612 TNPL Cement plant shall comply with the new emission standards of MoEF &CC issued vide GSR 612 (E) dated 25.08.2014 with respect to (E) dated 25.08.2014 with respect to Particulate Matter, SO2 and NOX prescribed for particulate Matter, SO2, NOx for cement Cement sector. sector. 2 Continuous online stack monitoring facility to monitor gaseous emission from the process kiln stack shall be provided. Bag filter with adequate height of stack shall be provided for the control of particulate emission from the chloride bypass system proposed in the modernization project. It shall be ensured that adequate APC measures are provided for the control of process emissions and the permissible limit of particulate Matter shall be achieved at all time. Low NOx burners shall be provided to control NOx emissions. Regular calibration of the instruments must be ensured. Online monitoring system for SPM has been installed in the main stacks viz. Kiln, Cooler, Coal Mill, Cement Mill and Packaging Plant and linked to TNPCB Care Air Centre since 23.01.2014. The stack emissions from the main stacks are in compliance with the norms prescribed by TNPC Board. TNPL has proposed to install following Air Pollution Control Measures to control process emissions in the upgradation/modernization. Chloride bypass system: 360 Bag filters with stack with a height of 69.3 meters has been proposed for control of Particulate matter from the chloride bypass system. Pre calciner prior to Kiln: The pre calciner is proposed to be installed inline with kiln circuit. So, two more new modules (312 Nos of bags @ 156 bags per module) will be installed in addition to the existing six modules (936 Nos of bags @ 156 bags per module) in the Reverse Air Bag House (RABH) of kiln circuit to meet the emission norms. Secondary Crusher system: Two stacks have been proposed for the secondary crushing system as details below: Secondary Crusher stack 1: 144 filter bags with a stack height of 39.6M have been proposed for the control of Particulate matter from the Secondary crusher Stack I

system. 3 All the pollution control devices/equipment in raw mill/kiln, kiln feeding system, clinker cooler, coal mill, cement mill and cement silo shall be interlocked so that in the event of the pollution control devices/systems not working, the respective unit(s) shut down automatically. 4 Proper and full utilization of CO2 gas present in the gaseous emission from the kiln in the adjacent industry for the production of precipitated calcium carbonate shall be ensured. 5 An interlocking system shall be provided so as to ensure that whenever the ESP is not in operation, the raw material feeder will automatically stop and restart only with the restart of ESP. 6 Secondary fugitive emissions shall be controlled and shall be within the prescribed limits and regularly monitored. Guidelines/Code of practice issued by the CPCB in this regard shall be followed. Secondary Crusher stack 2: 196 filter bags with a stack height of 39.6M have been proposed for the control of Particulate matter from the Secondary crusher Stack 2 system. In order to have a better combustion and controlled flame length, a multichannel burner has been proposed instead of uniflow type. Calibrations of instruments are being carried out periodically. Interlocking facility has been provided to all Pollution control equipments to trip the equipments, viz. Raw mill/kiln, kiln feeding system, clinker cooler, coal mill and cement mill in case of emission level exceeding the stipulated value / Pollution Control devices are not working from the respective operating units. The CO 2 gas present in the gaseous emission from the kiln is being supplied for the production of Precipitated Calcium Carbonate in the M/s Omya India Private Limited located adjacent to TNPL Cement Unit. TNPL has installed reverse air bag house (RABH) for Raw mill / Kiln circuit & ESP in the Clinker Cooler system. Interlocking has been provided for stoppage of Kiln and raw material feeder whenever ESP or RABH is not in operation. Fugitive emissions in the work zone environment are being monitored periodically through independent accredited agencies and the values are found to be within the prescribed limits. In the Cement Plant, raw materials viz. crushed lime stone, coal, clay and gypsum are stored in fully covered/closed sheds. Lime sludge and fly ash (received from TNPL Paper Plant) are stored in closed RCC silos. Clinker and Cement are also stored in RCC silos only. TNPL has installed dust collection and extraction system at all material transfer points to control the fugitive emissions. All material transportations are done in closed pipe and fully closed/covered conveyors. Pneumatic system is in place for transporting fly ash from bowsers to silo and mechanical dosing for adding fly ash to cement mill. About 700 meters long conveyors are utilised internally to transport raw and finished materials. All the conveyors are closed in order to avoid any spillage or fugitive emission. Besides, the following are implemented: No overloading of transport vehicles with materials. Loaded trucks covered with tarpaulin.

Vehicles with valid Pollution under Control Certificates are allowed. A separate Truck Parking Area is earmarked near the Main Gate which is fully concreted. Ramp with BT road is provided at the crusher. All the roads to the tune of 1.68 Kms are concretized. Mechanised road sweeping machine is used regularly for cleaning the roads to avoid fugitive emissions. Water sprinklers are provided in lime and coal handling areas. Wind barricades for a total length of 1260 meters with 20 feet above the compound wall are provided. 7 Arsenic and Mercury shall be monitored periodically in emissions, ambient air and water. 8 The coal storage yard shall be lined and covered. 9 Efforts shall be made to reduce impact of the transport of the raw materials and end products on the surrounding environment. All the raw materials including coal, fly ash shall be transported in the closed containers only and shall not be overloaded. The company shall have separate truck parking area. Vehicular emissions shall be regularly monitored. Periodical monitoring of Arsenic and Mercury are being carried out through independent accredited agencies. The ROA of the latest report carried out during August 2015 were submitted along with EC compliance report. The coal received from the TNPL main plant is stored in a coal shed having adequate storage capacity of 250 MT. The shed is totally covered and also provided with side walls. The Cement Plant material transports are mainly by road networks. Presently, trucks & bulkers/ bowsers are utilized in the Cement Plant for transporting the raw materials as well as finished product cement. The existing Major District Road (MDR), State Highways (SH 84 & 172A) and National Highway 7 are adequate to handle the traffic volume due to the Cement Plant. Also, TNPL is implementing the following measures to control the traffic impact on the surrounding environment : No overloading of transport vehicles with materials. Loaded trucks covered with tarpaulin. Vehicles with valid Pollution under Control Certificates are allowed. A separate Truck Parking Area near the Main Gate which is fully concreted. Mechanised road sweeping machine for cleaning the roads to avoid fugitive emissions. Pneumatic system is in place for transporting fly ash from bowsers to silo and mechanical dosing for adding fly ash to cement mill. Imported coal is being received at TNPL Main Plant through railway sliding (from Pugalur in Southern Railway BG Line Karur Erode Section). As the TNPL Main plant is closely located to Cement Plant, the required coal material is

transported through vehicles covered with tarpaulins. 10 Total fresh water requirement after the proposed modernisation of the cement plant shall not exceed 300 m3/day as reported. The fresh water requirement shall be must from the River Cauvery with proper approval obtained from concerned authority. 11 Efforts shall be made to further reduce water consumption by using air cooled condensers. 12 Existing STP shall be operated continuously and effectively so as bring the quality of treated sewage to satisfy the discharge standards prescribed by Tamil Nadu Pollution Control Board. The treated sewage shall be utilised for dust suppression and green belt development. 13 It shall be ensured that no process effluent shall be generated in the cement plant. No washing of lime sludge received from TNPL paper plant shall be carried out in the cement plant except dewatering/filtring and the filtrate shall be sent to TNPL paper plant thro pipe line for reuse in the paper plant process as reported. 14 Efforts shall be made to make use of rain water harvested. If needed, capacity of the reservoir shall be enhanced to meet the maximum water requirement. Only balance water requirement shall be met from other sources. The total fresh water quantity including domestic requirement shall not exceed 300 M3/day even after modernization/upgradation of the Cement mill. TNPL has been permitted to draw 16 MGD (72,736 cu.m/day) water from River Cauvery vide TN GO (MS) No. 455 dated 29.10.2001. The fresh water demand of TNPL Cement Plant is being met from TNPL main plant and shall not exceed the quantity of 300 cu.m/day. No cooling tower is required for Cement plant operations. Hence, installation of Air Cooled Condenser is not applicable. TNPL Cement Plant had installed a package Sewage Treatment Plant of 20 cu.m/day (Diffused Aeration System) at a cost of Rs.14.25 lakhs (Supplier : M/s. Aqua Engineers and Consultants Pvt. Ltd., Chennai) in its Cement mill premises and the quality of treated sewage is within the norms prescribed by Tamil Nadu Pollution Control Board. The treated sewage is fully utilized for dust suppression and green belt development within the mill premises. The cement production involves only dry process and there is no trade effluent generation from the Plant. Further, the washing of entire lime sludge is done in the Paper plant itself using the process condensate generated in the evaporation plant. For easy transportation, the Lime sludge slurry from TNPL Main Plant (Paper Plant) is pumped with 95% moisture content through a pipeline to the slurry/mud washing plant located in the Cement Plant. In the cement plant, the sludge is simply dewatered and the filtrate is pumped back to the Paper Plant. Thus, there is no process effluent is generated either in Cement Production process or in the lime sludge handling plant. Rain water harvesting measures have been provided to cover 904 sq. m roof tops in Cement Plant as detailed below : Marketing Office Roof 83 Sq.M Administrative Office Roof 276 Sq.M Time office and canteen 115 Sq.M CCR building 430 Sq.M TNPL Cement plant fresh water requirement is met from the TNPL paper plant water reservoir with a capacity of 5 Lac Cu.M. Storm water drains are provided to collect the surface runoffs from the Cement Plant in a collection pit with facility to pump the water to back to the reservoir. Hence, the collected rain water is fully utilized.

15 Regular monitoring on the air quality, water quality and noise on the selected locations in and around the project site as mentioned in the EIA report for creating base line data shall be continued and report in this regard shall be furnished periodically to the Regional Office of MoEF & CC at Chennai & SPCB. 16 All the bag filter dust, raw mill dust, coal dust, clinker dust and cement dust from pollution control devices shall be recycled and reused in the process and used for cement manufacturing. Spent oil and batteries shall be sold to authorized recyclers only. 17 Fly ash generation from TNPL Captive Power Plant shall be utilized completely in the cement plant as per Fly ash Notification, 1999 & its amendment in 2003 & 2008. Efforts shall be made to use fly ash maximum in making Pozzolona Portland cement (PPC). A detailed Periodical Environmental monitoring on the selected locations in and around project site are being carried out through independent accredited agencies. The ROA of the latest report carried out during August 2015 were submitted along with EC compliance report. TNPL has installed the following air pollution control (APC) measures in the Cement Plant : Name of the Stack Existing Limestone Crusher Kiln/Raw Mill APC Measure Bag Filters 70 No. of Bags Installed Reverse Air Bag 936 House (RABH) (6 modules) Coal Mill Bag Filters 231 Cooler ESP Cement Mill Bag Filters 480 Packing Plant Bag Filters 170 Total No. of Bags (existing) 1,887 Additional Measures in Expansion Chloride Bag Filters 360 bypass system Secondary Crusher Bag Filters 144+196= 340 (2 stacks) Inline RABH (two 156*2= Calciner with additional 312 Kiln modules) No of bags proposed in expansion 1012 Total No. of Bags after expansion 2899 Therefore, there will be 2899 bags will be available including 1012 bags proposed in the expansion. The system is designed in such a way that dust collected from these Bag Filters will be Totally recycled within the cement manufacturing process itself. Spent oil and batteries shall be sold to authorized recyclers only. The STP sludge from Sludge Drying Beds (about 50 kg/month on dry basis) is being vermi composted and used as manure for Green Belt development. Thus, there is no solid wastes disposal from the premises. The entire fly ash generated from TNPL captive Power plant shall be fully utilized for manufacturing of Pozzolona Portland cement (PPC). Analysis report of imported coal along with a detailed study on the composition of coal for the Heavy metals and Radioactivity Contents was

study on chemical composition of coal used particularly heavy metal and radio activity contents shall be carried out through a reputed institute and report shall be submitted to Regional Office of the MoEF & CC at Chennai. carried out through M/s SMS Labs India Private Limited, Chennai, a NABL and MoEF accredited laboratory and a copy of the report was submitted along with compliance report. 18 Efforts shall be made to use low grade lime, more fly ash and solid waste in the cement manufacturing. 19 Efforts shall be made to provide flexible fuel feeding system in the inlet of kiln in the modernisation project so as to enable the use of hazardous waste such as oil sludge, cut tyres, etc. 20 The proponent shall examine and prepare a plan for utilisation of high calorific wastes such as chemical wastes, distillation residues, refuse derived fuels, etc., as alternate fuels based on availability and composition. For this, the proponent shall identify suitable industries with such wastes and enter into an MOU for long term utilisation of such wastes as per the EP Act, 1986 and with necessary approvals. 21 As proposed, green belt in an extend area of 6.250 hect (33 % of the total project area) shall be developed within cement plant premises with at least 10 meter wide green belt on all sides along the periphery of the project area, in downward wind direction and along road sides etc. Selection of plant species shall be as per the CPCB guidelines in consultation with the DFO. 22 All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Cement plants shall be implemented. Only low grade lime stone with 75% purity is only used for Cement manufacturing. Further, TNPL Cement plant was installed only to handle the solid wastes such as lime sludge and fly ash under Lime Sludge Fly Ash Management system. The Calciner has been provided with a system to consume alternative fuels. Utilisation of the high calorific hazardous waste shall be complied upon stabilization of post expansion operations and subject to feasibility. Utilisation of the high calorific hazardous waste shall be complied upon stabilization of post expansion operations and subject to feasibility. TNPL Cement Plant is located in an extent of 18.33 Ha of TNPL own land. Green Belt is being developed within the Cement Plant premises as well as in the area between Paper Plant and Cement Plant. TNPL Colony is also having an effective Green Belt. Green Belt and Lawns to an extent of about 6.25 Ha have been developed in the land allocated for the Cement plant. Species : Predominantly local flora/vegetations (about 20 tree species) are planted by keeping in view the agro ecological and edaphic conditions of the area. The guidance of local DFO is also taken. Out of twelve recommendations of the Corporate Responsibility for Environmental Protection (CREP) for Cement Industry, nine have been are complied with. For the balance three recommendations viz. 5, 7 &11, directions are awaited from CPCB, NCBM, BIS etc. 23 All the responses received during public notice of EIA report shall be satisfactorily implemented and a separate budget of Rs. 25 lakhs allotted for implementing the same shall be utilised only for the purposes and a report shall be submitted to the TNPCB, Regional Office of MoEF & CC at Chennai after implementation. 24 The proponent shall prepare a detailed CSR plan for every next 5 years for the existing Out of six works proposed in response to the public notice, four works have been implemented and balance two works are under progress. A status report on implementation was submitted along with compliance report. A detailed completion report shall be issued upon implementation of all projects. In every financial year, at least two percent of the average net profit of the company made during

cum expansion project, which includes villagewise, three immediately preceding financial years is sector wise (Health, Education, being allocated to undertake CSR activities. The Sanitation, Health, Skill Development and amount has been spent under 5 broader heads infrastructure requirements such as viz., Education, Health care, Socio Economic strengthening of village roads, avenue Development and Security, Environment and plantation, etc.,) activities in consultation with the local communities and administration. The CSR Plan will include the amount of 2% retain annual profits as provided for in Clause 135 of the Companies Act, 2013 which provides for 2% of the average net profits of previous 3 years towards CSR activities for life of the project. A separate budget head shall be created and the annual capital and revenue expenditure on various activities of the Plan shall be submitted as part of the Compliance Report to Regional Office of MoEF & CC at Chennai. The details of the CSR plan shall also be uploaded on the company website and shall also be provided in the Annual Report of the Company. Culture and Heritage. As the Companies Act, 2013 mandates every company having net worth of Rs.500 cr. or more or turnover of Rs.1000 cr. or more or a net profit of Rs.5 cr. or more during any financial year, to constitute a CSR Committee of the Board, TNPL has constituted a CSR Committee with the Independent Directors as its Members and the Chairman of the Audit Committee as the Chairman of CSR Committee. A brief note on the CSR activities carried out by TNPL along with the CSR budget for the year 2015 16 was submitted along with EC compliance report. The details on CSR including activities carried out, budget vs utilization, committee members etc were published in page no. 12,13, 31, 56 and 65 of the Annual Report for the year 2014 15. Copies of details on CSR published in the annual report were also enclosed along with EC compliance report. The annual report has been uploaded in the TNPL s website. 25 Risk Assessment and Disaster Management Plan with focus on Disaster Prevention and Safety shall be prepared and a copy submitted to the Regional Office of MoEF & CC at Chennai, SPCB and CPCB. GENERAL CONDITIONS: Copies of Risk Assessment and On Site Emergency Plan for Disaster Management approved by Director, Industrial Safety and Health, Chennai were submitted along with EC compliance report. SL.NO COMLIANCE CONDITIONS a The Project Proponent should advertise at Advertisement were published in the local least in two local newspapers widely newspapers informing that the project has been circulated, one of which shall be in the vernacular language of the locality concerned, accorded environmental clearance and a copy of the clearance letter is available with TNPCB and within 7 days of the issue of the also at the website of the SEIAA, TN. Further, a Environmental Clearance informing that the project has been accorded environmental copy of Environmental Clearance is also uploaded in the TNPL s website www.tnpl.com. clearance and a copy of the clearance letter is available with TNPCB and also at the Website of the SEIAA, TN at http:www.seiaa.tn.gov.in. b A copy of the Environmental Clearance shall Copies of Environmental clearance were furnished be sent by the project proponent to to Kagithapuram Panchayat and those from concerned panchayat, local body, and local whom the responses were received while NGO, if any from whom processing the file. suggestions/representatives, if any were received while processing the proposal. The Environmental Clearance shall also be put on the website of the company. c The State Pollution Control Board should display a copy of the Environmental Clearance This condition has been complied with.

SL.NO COMLIANCE CONDITIONS issued to the project at the Regional office, District Industry Centre and the Collector s office/tehsildar s office for 30 days. d e f g h i j Consent from Tamil Nadu Pollution Control Board shall be obtained before start of modernisation project of the cement plant and also before commencement of enhancement production. All stipulations made by TNPCB and the State government shall be strictly complied with. All the environmental protection measures and safeguards as recommended in the EIA report shall be complied with. The implementation of the project vis à vis environmental action plans shall be monitored by the Regional Office of MoEF & CC at Chennai/TNPCB/CPCB. A six monthly compliance status report shall be submitted to monitoring agencies regularly. Ambient air Quality Monitoring Stations shall be set up in the down wind direction as well as where maximum ground level concentration of RSPM, SO2, NOx, are anticipated. At least four ambient air quality monitoring stations should be established in the core zone as well as buffer zone for monitoring RSPM, SO2 and NOx. Location of the monitoring stations should be decided in consultation with State Pollution Control Board based on the meterorological data, topographical features and environmentally and ecologically sensitive targets and frequency of monitoring etc. Data on ambient air, stack and fugitive emissions shall be regularly submitted online to the regional office of MoEF & CC at Chennai, TNPCB and CPCB as well as hard copy once in six months and display data on RSPM, SO2 and Nox outside the premises at the appropriate place for the general public. Occupational health surveillance of the staffs & workers shall be done on a regular basis and records maintained as per the Factories Act. Application for Consent To Establish was submitted to TNPCB and is under processing. All the stipulations made by TNPC Board and State Government are being strictly complied with. All the environmental protection measures and safeguards such as installation of 360 bag filters with stack for the newly proposed chloride bypass system, two more new modules with 312 bags @156 bags per module for Reverse Air Bag House and 340 bag filters with two stacks for the secondary crusher are being taken up as Environmental Protection Measures and safeguards. The first six monthly compliance report for the period ending 30/09/2015 was submitted on 05/12/2015. TNPCB has identified 6 locations covering both upward and downward directions and periodically conducting survey twice in an year. During the year, TNPCB had conducted Air Quality Monitoring between 06/10/2015 and 07/10/2015 and the ROA of the same is awaited. ROA of Air Quality survey conducted by TNPCB are being submitted to concerned offices. Further, data on stack emissions such as PM, SO 2 & NOx and ambient parameters such as PM10, PM2.5, SO X,NO X and CO are being displayed through electronic display board installed at the entrance of the Cement mill. As part of Occupational Health Surveillance programme, a combined study for both TNPL Main Plant (Pulp and Paper unit) and TNPL Cement Plant has been carried out through SMS LABS Private Limited for the parameters viz., VOC, CO, Noise, Heat stress, RSPM, Oil Mist, NO 2, SO 2, Microbiological load, General Parameters etc. The surveillance report is awaited. Further, the unit is periodically carrying out Occupational

SL.NO COMLIANCE CONDITIONS health survey such as Eye test, Audiometry, Pulmonary Function Test in addition to Preemployment medical examination for new recruits and Master Health Check up for those who have crossed age 40, 50 & 55. k Proper House keeping and cleanliness must be maintained within and outside the cement plant. l Occupational health surveillance programme shall be undertaken as regular exercise for all the employees, specially for those engaged in handling hazardous substances. The first aid facilities in the occupational health center shall be strengthened and the medical records of each employee should be maintained separately. m The overall noise levels in and around the plant area shall be kept well within the standards prescribed for by providing noise control measures including acoustic hoods, silencers, enclosures etc. on all sources of noise generation. The ambient noise levels should conform to the standards prescribed under EPA Rules, 1989 viz. 75 dba (day time) and 70 dba (night time). n CSR activity shall be implemented as committed by drawing a scheme for social upliftment in the surrounding villages with reference to contribution in road construction, providing sanitation facilities, drinking water supply in the government schools nearby, community awareness, establishment of health centers, water supply to nearby villages and employment to local people whenever and wherever possible both for technical and non technical jobs and protection of water sources around the project site etc. Proper housekeeping and cleanliness is being maintained in and around the Cement plant premises. No Hazardous substance is used in the Cement plant manufacturing process. TNPL s Occupational Health Centre has been equipped all latest facilities to provide first aid treatment employees from both TNPL main plant and Cement plant. Further, the medical record of the individual employee is also being maintained. Necessary noise control measures such as acoustic hoods, silencers, enclosures etc., are provided on all sources of noise generation. TNPL is carrying out CSR activities to assist the inhabitants of the surrounding villages by taking part in drinking water supply schemes, construction of retaining walls in the irrigation channels, laying and improving roads, culverts, providing lighting facilities, Development of parks, supply of equipment and instruments to Fair Price Shops and improving infrastructure facilities in Government Schools, conducting medical camps, providing financial assistance to needy people, contributing for cultural programmes, sports activities and temple construction / renovation works. o p q A separate Environmental Management Cell equipped with full fledged laboratory facilities to carry out the various Environmental Management and Monitoring functions shall be set up under the control of Senior Executive. The earmarked amount of Rs. 2.5 crores towards capital cost and Rs. 5 lakhs/annum towards recurring cost/annum for implementing pollution control measures shall be used judiciously to implement the Environment Management Plan as furnished in the EIA report. The funds so provided shall not be diverted for any other purposes. The project proponent shall upload the status of compliance of the stipulated An Environmental Management Cell have been constituted to carry out the Environmental Management and Monitoring functions of TNPL Cement plant. A budgetary provision of 2.5 crores allocated for implementing all the environmental protection measures and safeguards such as installation of bag filters with stack for the newly proposed chloride bypass system, two more new modules with 312 bags @156 bags per module and bag filters with stacks for the secondary crusher as proposed in the EIA will be fully utilized. The status of compliance for the conditions stipulated in the environmental clearance

SL.NO COMLIANCE CONDITIONS environmental clearance conditions, including result of monitored data on their website and shall update the same periodically. It shall including the results of monitored data shall be submitted to Concerned authorities once in six months. The hard copy of the first six monthly simultaneously be sent to the Regional Office status of compliance on the stipulated of the MoEF &, the respective Zonal Office of environmental clearance conditions including CPCB and the SPCB. The criteria pollutant levels namely; RSPM, SO2, NOx (ambient levels as well as stack emissions) or critical sectoral parameters, indicated for the projects shall be monitored and displayed at a convenient location near the main gate of the company in the public domain. r The project proponent shall also submit six monthly reports on the status of the compliance of the stipulated environmental conditions including results of monitored data (both in hard copies as well as by e mail) to the respective Regional Office of MoEF, the respective Zonal Office of CPCB and the SPCB. The Regional Office of MoEF & CC at Chennai, CPCB & SPCB shall monitor the stipulated conditions. s The environmental statement for each financial year ending 31st March in Form V as in mandated to be submitted by the project proponent to the concerned State Pollution Control Board as prescribed under the Environment (Protection) Rules, 1986, as amended subsequently, shall also be put on the website of the company along with the status of compliance of environmental conditions and shall also be sent to the respective Regional Offices of the MoEF by e mail. monitoring data was already submitted to concerned Offices. The details are herewtih uploaded in TNPL website. Further, data on stack emissions such as PM, SO 2 & NOx and ambient parameters such as PM10, PM2.5, SO X,NO X and CO are being displayed through electronic display board installed at the entrance of the Cement mill. The first compliance status for the conditions stipulated in the Environmental clearance for the period between 01/04/2015 and 30/09/2015 was submitted to concerned offices on 05/12/2015. The environmental statement for the period ending 31st March 2015 was submitted along first six monthly compliance report on the conditions stipulated in the Environmental Clearance for the period ending 30/09/2015 accorded for the Cement Plant Expansion. Further, a copy of Form V was also uploaded in the website of the company along with status of compliance to conditions stipulated in the Environmental Clearance. The soft copy of Form V was also forwarded along with the soft copy of EC compliance report to the concerned offices.