EXTRACT. MONITOR. CONTROL.

Similar documents
Assessment of Impacts from Groundwater Control Projects

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

Pumping tests for construction dewatering in chalk

27 Land and groundwater contamination

Framework for Managing Dewatering and Accidental Artesian Aquifer Interception

Case Study HST Shaft: Llanberis WwTW

Oversized quarry sumps can be used to store run-off during

Numerical Groundwater Flow Model Report. Caloosa Materials, LLC 3323 Gulf City Road Ruskin, Florida 33570

11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE

CONSTRUCTION SPECIFICATION FOR DEWATERING

South London Energy from Waste, Beddington Lane Initial Contaminated Land Assessment, July 2011

The influence of large scale inhomogeneities on a construction dewatering system in chalk Dr Toby Roberts. CTRL Thames Tunnel

Hydropower Guidance Note: HGN 4 Designated Sites

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Supplemental Guide II-Delineations

8 Geology, Hydrology & Hydrogeology

Dewatering Fly Ash for Remediation: Two Approaches

Feasibility Study for Groundwater Availability for Spring Creek Creation at Squalicum Creek Park

Developers Guide for Surface Water Management.

Environment Agency Guidance on Requirements for Land Contamination Reports. July 2005

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

Edithvale and Bonbeach Level Crossing Removal Project

in brief corrs Policy What it means for developments in april 2012

Groundwater Control for Design & Construction

E2. Water quantity, allocation and use

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

CHAPTER 2. Objectives of Groundwater Modelling

(No. of pages excluding this page = 10)

Sustainability Statement

Florida Department of Environmental Protection. Bureau of Mining and Minerals Regulation. Regulation of Mines. Howard J. Hayes, Program Administrator

Appendix 14-I Description of Stream Crossing for Electrical Interconnect

Regulation of Mines In South Florida

This chapter assesses the likely impact of the proposed power plant in relation to ground conditions and potential contamination.

Environment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance

E7. Taking, using, damming and diversion of water and drilling

REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

A tank filtration and settling system set up to dewater groundwater for excavation work near the Upper Truckee River.

Numerical Groundwater Model for the Kaweah Delta Water Conservation District

Crossrail Line 1 Assessment of Water Resource Impacts Technical Report

IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY WATER MANAGEMENT OF CONSTRUCTION SITE Patil V.A*, Gawade S.

Abstract. Introduction

ATTACHMENT 5 AQUIFER INTERFERENCE POLICY AND WATER LICENSING ADDENDUM

Selection of Proprietary Shoring Equipment

Form 1: Application for resource consent

Remediation of the Former Gasworks, High Wycombe, UK

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM 4417 DEWATERING IN CONTAMINATED GROUNDWATER

Environmental Information Worksheet

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION

14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring

OAR Table 240-1

Comparison of dewatering schemes for foundation pits under complex hydrogeological conditions

Irish Water VARTRY WATER SUPPLY UPGRADE PROJECT. EIS Screening Report

E4. Other discharges of contaminants

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

Assessment and Restoration of the BP Llandarcy Refinery Landfill Martin Chapple, URS Corporation Ltd., Bristol, UK

Addendum Geotechnical Report Dewatering and Settlement Sanitary Sewer Improvements at Bush IAH, Project No. 699 HVJ Project No.

Hydropower Guidance Note: HGN 7 Competing Schemes

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications

DEVELOPMENT OF AQUIFER TESTING PLANS. Brent Bauman, P.G. / Erin Lynam, Aquatic Biologist

Implementation Plan and FAQs for the Guide to Water Act Authorizations Required for Dugouts, Borrow Pits and other types of Pits/Excavations

Site Location AQUARION WATER COMPANY CANNONDALE WELL FIELD WILTON, CONNECTICUT

BS8582, Code of Practice for Surface Water Management for Development Sites

AM-PR-003 Construction Environmental Management Plan (C-EMP)

Comprehensive experimental study on prevention of land subsidence caused by dewatering in deep foundation pit with hanging waterproof curtain

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence;

BERRY CREEK WASTEWATER INTERCEPTOR PROJECT. December 11, 2018

LAKE LABELLE DEWATERING MODEL. AUTHOR Gail Murray Doyle, P.G. September Murray Consultants, Inc 769 Skyview Dr Hayesville, NC

Groundwater 3/16/2010. GG22A: GEOSPHERE & HYDROSPHERE Hydrology

GRADING, EROSION AND SEDIMENTATION CONTROL

Science Olympiad. Mentor Invitational Hydrogeology ANSWER KEY. Name(s): School Name: Point Totals

CHAPTER 7 WATER RESOURCES AND DRAINAGE NORTHAMPTON GATEWAY

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

Drainage Strategy Report

Trenchless Crossing of a Failure Prone Watermain in Poor Soil Conditions

Surface Water Guidance for Developers

Draft Greater Sydney Region Plan

FAX

New Connections Services Charging Arrangements

Glossary. September 11,

WASTEWATER DRAINAGE BYLAW

GROUND WATER. Practice Note # water. sensitive. urban. design \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \ \

8 Geology, Hydrology, Hydrogeology

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

CLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS

Waukesha Water Supply. Frequently Asked Questions

REQUIRED SEPTIC DRAWINGS

10.1 Introduction This chapter describes the effects of the proposed Edinburgh Tram Line One on water resources along the route including:

Mercia EnviRecover PROPOSED DEVELOPMENT OF A RENEWABLE ENERGY PLANT ON LAND AT HARTLEBURY TRADING ESTATE, HARTLEBURY, WORCESTERSHIRE

BLOCKING AND FILLING SURFACE DRAINAGE DITCHES

The Mineral Industry Environmental Protection Regulations

Appendix 8: Best Practicable Environmental Option (BPEO) Assessment

HOTEL KANATA 140 HEARST WAY KANATA, ONTARIO STORMWATER MANAGEMENT REPORT. Prepared for: David Johnston Architect. Prepared By:

Jan van Wonderen Mott MacDonald

1.0 Introduction. 1.1 The Stream Depletion Issue. 1.2 Purpose of the Guidelines

For inspection purposes only.

Water in Mining. A view from the West. Mike Harold Principal Advisor - Policy and Governance Inside Infrastructure

Pollution Prevention. Getting your site right. September 2009

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

16.3 An Agricultural Land Classification Report is included in ES Volume 2.

Transcription:

GUIDANCE OF ABSTRACTION AND DISCHARGE PERMITS FOR OPERATIONS When considering any potential dewatering requirement, it is necessary to consider the following questions: Are we allowed to abstract groundwater, and will the pumping impact third parties? Where can we dispose of the water, and what needs to be done to allow discharge? What can be done to minimise water disposal costs? Does the water need to be treated prior to discharge? EXTRACT. MONITOR. CONTROL.

Abstraction for Dewatering Abstraction for Dewatering Prior to the enactment of the Water Act (00), construction dewatering was exempt from requiring an abstraction licence. This is now not the case, but the type of licence and level of effort required to make an application is dependent upon the nature of the individual project and the perceived level of risk. For a small minority of short-term schemes which operate for less than 8-days, a Temporary Licence can be obtained. In the majority of cases, a Transfer Licence will be appropriate unless the water is used for an intervening use, such as Dust Suppression. If the For guidance, the Environment Agency considers a scoring system, based on aquifer characteristics, locality of water-dependent conservation sites, water-resource availability and dewatering abstraction flows: Tier (Basic) Effort Required Groundwater conceptual model developed using easily available data Suggested Design Tools Analytical equations, as set out in CIRIA C55 Weighted Score 0 to 0 discharged water is used for a secondary process and not returned back to the environment, a Full Licence will be required. An application for a licence will require a hydrogeological impact assessment (HIA), which is then summarised in an Environmental Statement to support the application. The amount of work required for the HIA is assessed using a tiered approach, and can also have an impact on the tools used to design a dewatering system, with groundwater modelling required in more complex cases. Tier (Intermediate) Conceptual model tested using more detailed data from limited field investigations Tier (Detailed) Conceptual model tested using numerical modelling techniques Simple D steadystate models D modelling, such as MODFLOW, with time dependent analysis to 0 to 0

Abstraction for Dewatering Abstraction for Dewatering Criteria and Classes Score Weight Aquifer Characteristics Karst Principal (Major) Aquifer Secondary (Minor) Aquifer Unproductive Strata Water-Dependent Conservation Sites Habitats Directive (Natura 000) Sites Sites of Special Scientific Interest Other Designations (Including National Parks and AONB) None Water Resource Availability Status Over-Abstracted Over-Licensed No Water Available Water Available Dewatering Quantity Very Large (> 5,000 m /d) Large (,500 to 5,000 m /d) Medium (,000 to,500 m /d) Low (<,000 m /d) Working through three common dewatering scenarios we might encounter, we would expect the following: Case (A Small Wellpoint Scheme): A contractor requires dewatering for a simple trench excavation to install 00m of drainage pipes and manholes up to.5m deep, in superficial silty sand deposits. There are no known conservation areas locally. The expected duration for the drainage works is weeks. A wellpoint system is proposed with flows of 5 l/sec (m /day). In this instance, a Temporary Licence should be sufficient as the dewatering works are less than 8 days duration. Should there be a concern over potential programme delays, and we used the proposed scoring system, a Tier study should be sufficient. Case (Cofferdam Depressurisation): A contractor plans to excavate a 0 x 0m sheet-pile cofferdam for the installation of an underground tank at a wastewater treatment works. The excavation is founded in clay, but below the clay is a layer of highly permeable sandy gravels (e.g. River Terrace Deposits, classed as a minor aquifer) with a sufficient pressure to cause a risk of basal uplift. The expected duration for the works is 0 weeks. In order to depressurise the underlying sandy gravels, a deepwell scheme is proposed with a total flowrate of 0 l/sec (50m /day). There is an adjacent wetland conservation area, but not in direct hydraulic continuity with the confined aquifer. Based on the scoring system, a Tier assessment is sufficient, despite the high expected flowrates involved.

Abstraction for Dewatering Abstraction for Dewatering Case (Deep Shaft Dewatering): A deep shaft is being constructed for a tunnel with an The process for the hydrogeological impact assessment should follow the flow chart below: invert level below the top of the confined chalk aquifer in an urban area with other nearby licenced abstractors. Working on a range of bulk permeability estimates for the Chalk, the overall flowrate for a proposed deep well system could range from 0 to 00 l/s (70 to 8600m /day). As the aquifer is confined, there is expected to be no direct impact on water-dependent conservation sites. The works involves a major aquifer with potentially high flows, so a Tier assessment is required. Detailed sensitivity analysis may be required to Step : Establish the regional water source status Step : Develop a conceptual model for the dewatering operation and surrounding area Step : Based on the conceptual model, identify all potential water features which are susceptible to flow impacts establish the range of impacts due to the uncertainty on the flowrates. Aqufier Characteristics Water-Dependent Conservation Sites Water Resource Availability Dewatering Quantity Case Case Case Score Weight Total Score Weight Total Score Weight Total 9 9 TOTAL 5 9 Step 6: Assess the significance of the net flow impacts Step 7: Define the search area for drawdown impacts Step 5: For the relevant water features, allow for the mitigating effects of any discharges associated with the abstraction to arrive at net flow impacts Step 8: Identify all features within the search area which could potentially be impacted by drawdown Step : Apportion the likely flow impacts to the water features, again based on the conceptual model Step 9: For all these features, predict the likely drawdown impacts

Abstraction for Dewatering Abstraction for Dewatering Step 0: For the relevant water features, allow for the effects of any measures being taken to mitigate the drawdown impacts Step : Assess the significance of the net drawdown impacts Step : Assess the water quality impacts As designers and specialist sub-contractors, the Project Dewatering Limited team have the capabilities to carry out the hydrogeological impact assessment associated with our designs. Importantly, any groundwater modelling work carried out is only as good as the input parameters and understanding of the aquifer conditions; inevitably, a high quality study would require information from pumping tests to calibrate the model, and further validation of the model, using monitoring data during the actual dewatering operations. Step : Develop a monitoring strategy, focussing on the features likely to experience flow or drawdown impacts Step : If necessary, redesign the mitigation measures to minimise the flow and drawdown impacts Top tip: Always engage with the Environment Agency as early on as possible to ensure the correct application is made and sufficient time is available to complete the process. Hydrogeological impacts assessments from dewatering should consider:. Detrimental impacts on surface water features sustained by groundwater. Derogation of existing abstractors. Contamination of groundwater and surface water

Discharge of Groundwater Discharge of Groundwater Disposal of clean, uncontaminated groundwater is usually carried out to either a surface water body, such as an adjacent river, or to sewer. Sewer discharge is often the least preferable option in terms of the expense accumulated through volumetric discharge charges, remembering that dewatering is a -hour, 7 day per week operation. Discharge rates can be as high as 0.70 per m for some areas of the country. Both the local sewer connections and wider network will have a limit on the flowrate that can be accepted; in many urban areas there is simply not sufficient capacity for the required dewatering discharge rate. An assessment will be made by the water company responsible for the network as part of the application process, and will take into account both the quality and quantity of water. In order to provide details on the expected quality, groundwater sample analysis results are essential. A discharge consent will place limits of the water quality parameters and contaminant concentrations that can be accepted, but are less stringent than for a discharge licence to surface water body. Top Tip: Where dewatering is expected, always include groundwater sampling as part of any pumping test or site investigation works to assist with discharge applications Discharge to rivers or estuaries can be a convenient and relatively cost effective way to dispose of water where the site is located nearby. Even where the discharge location isn t directly adjacent to the site boundary, specialist temporary pipe infrastructure can often be used, although there are planning issues to consider when running pipe work outside of the site boundary. The costs of installing pipework are still likely to be less than the costs of sewer discharge for longer duration projects with high flowrates. Discharge pipe arrangement in a busy city centre for large-scale dewatering. Project Dewatering Limited can design and install complex discharge pipelines to cross roads and structures.

Discharge of Groundwater Discharge of Groundwater A Regulatory Position Statement has recently been published by the Environment Agency on Recharge back to the ground via reinjection wells is an option that can be considered where February 06 entitled Dewatering Building Sites and Other Excavations: Environmental ground conditions are suitable. This is ideal where there is a physical cut-off wall between the Permits. This allows temporary discharge of clean dewatering water to a surface water body dewatered area and the location of the recharge wells, where there are water-bearing for up to months without a permit where the discharge does not: strata separated by a lower permeability layer, or a combination of both. Commonly, Pollute surface water or adversely affect aquatic life, or designated sites or species recharging of the water will lead to some increase in overall rate of abstraction required and Result in the spread of non-native invasive species, parasites or disease on larger schemes a groundwater modelling exercise is recommended to fully understand Cause flooding from surface water Cause erosion of the banks or bed of surface water the flow balances. In all cases, the Environment Agency should be consulted if a recharge scheme is considered. Enter the surface water feature less than 500m upstream of a designated conservation site (including SSSI, SAC, SPA, Ramsar, Nature reserves, wildlife sites) Where there is legacy contamination in the groundwater, treatment of the abstracted groundwater is likely to be required prior to disposal. In this event, a Mobile Plant Permit is For longer periods of discharge, or where there is known contamination, a bespoke required to allow operation of a temporary treatment plant, and a Deployment Notice needs environmental permit will always be required. to be submitted to the Environment Agency prior to commencement.

For more information about how we can design, implement and manage your dewatering project, please give us a call on 07 658807 or email enquiries@project-dewatering.co.uk Published: March 06 Correct at the time of going to print References: Environment Agency (007), Hydrogeological impact appraisal for dewatering abstractions, Science Report SC0000/SR Preene et al. (000), CIRIA Report C55: Groundwater Control Design and Practice, Construction Industry Research and Information Association https://www.gov.uk/guidance/dewatering-building-sites-and-other-excavations-environmental-permit. Published Feb 06