Geotechnical, Hydrological and Environmental Assessment

Similar documents
THE VALLEY HOSPITAL 223 NORTH VAN DIEN AVENUE BLOCK 3301 LOT 51 VILLAGE OF RIDGEWOOD, NEW JERSEY PREPARED: JUNE 19, 2013 PRESENTED: JULY 16, 2013

6.13 Utilities and Service Systems

GRADING PERMIT CITY OF RAPID CITY 300 SIXITH STREET RAPID CITY, SD ID NO: (605) PIN NO:

APPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014

MINNESOTA POLLUTION CONTROL AGENCY REMEDY DECISION DOCUMENT. Washington County Landfill Lake Elmo, Minnesota

COMMON WORK RESULTS FOR EXISTING CONDITIONS SCHEDULES FOR EXISTING CONDITIONS

Boise City Public Works General Drainage Plan Review Requirements Checklist

Outfall at Lagoon between Lake of the Isles and Lake Calhoun

Ordinance No Lot Surface Drainage

Protecting, maintaining and improving the health of all Minnesotans MEMORANDUM

SECTION TRENCHING

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1

November 9, Tredyffrin Township Stephen Burgo, PE Township Engineer 1100 Duportail Road Berwyn, PA

Union County Vocational - Technical Schools Scotch Plains, New Jersey

RESPONSIBLE PLANNING FOR FUTURE GROUND WATER USE FROM THE GREAT FLATS AQUIFER : TWO CASE STUDIES: THE GEP ENERGY

OAR Table 240-1

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA)

REQUEST FOR CONSTRUCTION BIDS February 22, 2010

Ground Improvement of Titanium Dioxide Waste Spoils and Compressible Organics with In-Situ Mixing with Portland Cement and Surcharging

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

Table 5-1: Availability of Public Sanitary Sewer. Are plans underway to provide Public Sewer?

Detailed Estimating-Introduction. Dr. Al-Hammad

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

PUBLIC NOTICE PROFESSIONAL ENGINEERING SERIVCES: DESIGN OF TURF FIELD

GEOTECHNICAL INVESTIGATION

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

Surface Water Impacts from Groundwater Withdrawals. Presented by: Al Pratt Steve Howe

Technical Data

Misan University - College of Engineering Civil Engineering Department

GRADING, EROSION AND SEDIMENTATION CONTROL

CHAPTER 7 PHYSICAL INVENTORY OF THE CITY

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

STORMWATER AND EROSION CONTROL PERMIT

20 North Main Alpine, UT (Phone) (Fax) SITE PLAN

STORMWATER AND EROSION CONTROL PERMIT

A. Exemptions from the Geotechnical/Geological Engineering Report submittal requirements are:

LOT GRADING GUIDELINES FOR COMMERCIAL, INDUSTRIAL, INSTITUTIONAL, MEDIUM AND HIGH DENSITY RESIDENTIAL PROPERTIES

The Hydrogeology Challenge: Water for the World TEACHER S GUIDE

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

Infiltration Guidelines

LOT GRADING. LOT GRADING REQUIREMENTS The following lot grading requirements came into effect on May 1, 2007:

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report

PLAN CHECK CORRECTION SHEET FOR METHANE MITIGATION SYSTEMS 2017 LAPC

APPENDIX 8-A. Valued Component Selection Rationale

Case Studies of Dewatering and Foundation Design: Retail Warehouses in Taiwan

BEFORE THE OHIO POWER SITING BOARD

Stormwater Design for Karst Terrain

atertech Banff, AB. April 29-May 1, 2009

Environmental Information Worksheet

ALLIANT ENERGY WISCONSIN POWER AND LIGHT NELSON DEWEY GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT.

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

Natural Resources 14.1 INTRODUCTION 14.2 FEIS FINDINGS

Department of Administration State Construction Office SITE PREPARATION AND GRADING CRITERIA

The Biggest Environmental Risk You Missed

Submittal Requirements. Post Construction Verification Document Plan Requirements

Steel screw settlement reduction piles for a raft foundation on soft soil

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION

BNSF North SIG Intermodal Improvement Project. Seattle, Washington

Addendum Geotechnical Report Dewatering and Settlement Sanitary Sewer Improvements at Bush IAH, Project No. 699 HVJ Project No.

PLAN CHECK CORRECTION SHEET FOR METHANE MITIGATION SYSTEMS 2014 LAPC

6. ENGINEERING SYSTEMS REQUIREMENTS G10 SITE PREPARATION

B. SOILS, TOPOGRAPHY AND GEOLOGY. 1. Existing Conditions. a. Topography Of Site

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

New York State Department of Environmental Conservation. Receive Site Fact Sheets by . See "For More Information" to Learn How.

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

List of Figures... xii. List of Tables... xiii. List of Appendices...xv. Glossary... xvii Project Summary and Facility Overview...

WELLHEAD PROTECTION DELINEATION REPORT FOR THE VILLAGE OF BEAR LAKE DECEMBER 2002

Pond Closure - Case Study[TP1]

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

Permit Application Review Permit No Received complete: March 19, 2019

Land Use Office, PO Box 197, 6683 County Road 13, Conejos CO Phone #: Fax:

New York State Department of Environmental Conservation. Receive Site Fact Sheets by . See "For More Information" to Learn How.

SECTION DRILLED CONCRETE PIERS AND SHAFTS

Potential effects evaluation of dewatering an underground mine on surface water and groundwater located in a rural area

REPORT ON PHASE I ENVIRONMENTAL SITE ASSESSMENT 1358 COKER STREET OSGOODE WARD, GREELY CITY OF OTTAWA, ONTARIO. Submitted to:

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA)

ONTARIO MUNICIPAL BOARD

GROUNDWATER DISCHARGE

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY

August 3, The proposed action thus includes Site Plan approval for the Fire Department and Amended Site Plan approval for the Ambulance Corps.

Grading Requirements City of Red Bluff Table of Contents. Introduction and Scope...1. Permit Exempt Work...1. Permit Application Submittals...

Chapter DRINKING WATER

A. Aquifer: a geologic formation composed of rock, sand, or gravel that contains significant amounts of potentially recoverable water.

6. ENGINEERING SYSTEMS REQUIREMENTS G10 SITE PREPARATION

Workshop 1 Our Groundwater and Surfacewaters are Connected and We are What We Drink Hosted by: Lackawanna County Conservation District

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

Review Zone Application for D&R Canal Commission Decision

City of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development

Carpinteria Valley Water District Carpinteria Advanced Purification Project

patersongroup 1.0 Field Investigation Consulting Engineers December 14, 2015 PG3700-LET.01

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

6 ALTERNATIVES 6.1 INTRODUCTION

LACHEL FELICE & Associates. Advances in Finite Element Modeling Using PLAXIS SILVER REEF HOTEL/CASINO EXPANSION

Implementation of Underground Injection Control Program Regulations for Class V Shallow Disposal Systems

Regulatory Setbacks and Buffers RIDEM OWTS

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

Application for On-Site Wastewater Treatment System Permit

Groundwater basics. Groundwater and surface water: a single resource. Pore Spaces. Simplified View

Transcription:

Geotechnical, Hydrological and Environmental Assessment Presented by Moustafa Gouda, P.E., D. GE, F.ACSE Director of Geotechnical & Environmental Engineering Services Maser Consulting P.A. Planning Board Meeting, April 16, 2013 2

Assignment from The Valley Hospital Geotechnical analysis of subsurface condition Hydrological Study Environmental assessment of the site 3

Information Reviewed Prior soil boring data and area geology New soil boring data Well water data 4

Issues Evaluated Soil ability to support the proposed buildings Excavation of soil and rock Dewatering Disposal of excavated materials and water 5

Findings and Conclusions Soil Support Geology indicated that the hospital site and surrounding sites are covered with same geologic formation: Glacial drift over sandstone bedrock. Soil borings confirmed this geology and revealed that soil is dense sand and gravel and will support all buildings on conventional foundations. Excavations for underground structures may require a soil support system, unless safe slope can be provided. All tie-backs required for the system s stability will be located entirely on the hospital property. 6

Basis For Findings and Conclusions of Soil Support Approximately 100 soil borings: B borings performed in 1995 B 100 and 200 series performed in 2007 and 2009 TB 500 and 600 series borings performed between 2010 and 2013 All borings evaluated to determine subsurface soils and rock conditions, as well as bearing capacity. 7

Basis For Findings and Conclusions of Soil Support 8

Basis For Findings and Conclusions of Soil Support 9

Basis For Findings and Conclusions of Soil Support 10

Findings and Conclusions Excavation of Subsurface Materials Approximately 120,000 cubic yards of soil will need to be removed. Versus former calculation of 331,000 cubic yards Minimal amount of rock (less than 200 CY) may need to be removed from two spots: northeast corner of North Building and southwest corner of new garage. Versus former calculation of 2,519 cubic yards of rock throughout the building footprints 11

Findings and Conclusions Excavation of Subsurface Materials Approximately 120,000 CY of soil equate to 8,000 to 8,200 trucks (15-cubic yard capacity). Versus Council s calculation of 22,000 trucks in earlier plan Soil was tested and complies with NJDEP Residential Site Standards. Excavated materials can be removed and used as clean fill. 12

Basis For Findings and Conclusions Excavation of Subsurface Materials Took proposed building plan and added Finished Floor Elevations and Bottom of Excavation Elevations for all buildings. Finished Floor Elevation: From Mean Sea Level to top of building s lowest floor Bottom of Excavation Elevation: Finished Floor Elevation plus one to five feet of additional excavations depending on location Evaluated approximately 100 soil borings to determine subsurface soil conditions and determine the top of rock contours. Used underground rock contours to develop Top of Rock Exhibit, which incorporates building and top of rock elevations. Calculated quantity of subsurface materials to be removed. 13

Basis For Findings and Conclusions Excavation of Subsurface Materials 14

Basis For Findings and Conclusions Excavation of Subsurface Materials 15

Basis For Findings and Conclusions Excavation of Subsurface Materials 16

Basis For Findings and Conclusions Excavation of Subsurface Materials 17

Basis For Findings and Conclusions Excavation of Subsurface Materials Method of Rock Removal if required: The Project is still under design. The Architect and Structural Engineer, after review of all available information, may be able to minimize rock excavations There are a variety of methods to remove rock. The appropriate method will be selected based on desire to mitigate noise and vibration impact on the hospital and the neighborhood 18

Basis For Findings and Conclusions Excavation of Subsurface Materials Harmonic Frequency is an amplified vibration that can be associated with potential rock dislodging. It is not an issue on this site because the existing surrounding structures are not supported directly on rock. 19

Findings and Conclusions Dewatering Dewatering will be required for Central Plant portion of North Building. Dewatering may be required for the North Building, depending on season and natural fluctuations of water table. Dewatering may not be required for Phillips garage. 20

Findings and Conclusions Dewatering Dewatering amount ranges from 0 GPD to 300,000 GPD, dependent on season and natural fluctuations of the water table, with an average of 200,000 GPD for six months. Versus prior amount of as much as 570,000 GPD for one year Maximum decrease in water table under any area home through hospital pumping will be LESS than the decrease in the water table caused by natural water table fluctuations over the past two years. Dewatering will be accomplished through the use of a well point system and continuous pumping, with pumps placed at several locations, all on hospital property. 21

Findings and Conclusions Dewatering Water tested and meets NJDEP Residential Site Standards so it can be disposed of directly into Ridgewood s Sanitary or Storm Water system, or directly injected into the ground. Proposed methods of disposal: Village of Ridgewood s Storm Water system Village of Ridgewood s Sanitary Water system In case of catastrophic failure of Ridgewood s Sanitary or Storm Water Sewer system, or in the event of a extraordinary storm that overwhelms Ridgewood s systems, water will be directly injected into the ground via injection wells located entirely on the hospital s property. 22

Basis For Findings and Conclusions Dewatering Water was tested for contaminants and found to meet the NJDEP Residential Site Standards. The hospital can discharge 300,000 GPD of water flow into the Village Stormwater System, subject to obtaining a NJDEP Permit. Village Engineer has confirmed that Village Sanitary Sewer system can accommodate more than the anticipated maximum flow of 300,000 GPD of additional water flow and is willing to accept such flow. 23

Basis For Findings and Conclusions Dewatering Injection Tests were conducted and established that pumped water can be injected into wells placed entirely on the hospital s property without adverse impact on the ground water levels, if faced with a catastrophic failure in Ridgewood s systems. 24

Basis For Findings and Conclusions Dewatering Performed Groundwater Elevation Study from June 2010 to date, via monitoring four ground water wells installed on the Hospital property. The wells were equipped with data loggers that monitor the water level in the wells 24/7. The Study established that water table elevation fluctuated during that period from a low elevation of 78 feet above Mean Sea Level (or approximately 26 feet below ground) to a high elevation of 89 feet above Mean Sea Level (or approximately 15 feet below ground). 25

Basis For Findings and Conclusions Dewatering Took proposed building plan, which included Bottom of Excavation Elevations for all buildings and added 2 feet of additional depth to determine volume of water to be removed per day. Plotted on a plan the underground contours of the ground water table surface that would result from the dewatering of the excavations. The surface of the water contours was plotted around the proposed excavations and under the homes in the area. This is commonly referred to as Cone of Depression. 26

Basis For Findings and Conclusions Dewatering The Plan establishes that the largest decrease in the water table under any area home as a result of dewatering is 10 feet, which is LESS than the natural fluctuation of the water table. Additionally, both the evaluation of the soil borings and the Rutgers University Soil Survey establish that soil composition below the hospital and the surrounding area consists of dense sand and gravel, which is not susceptible to settlement because of loss of buoyancy. 27

Basis For Findings and Conclusions of Dewatering 28

Basis For Findings and Conclusions of Dewatering 29

Basis For Findings and Conclusions of Dewatering 30

Basis For Findings and Conclusions of Dewatering 31

Basis For Findings and Conclusions of Dewatering 32

Conclusion Review Soil Support Soil borings reveal that soil is dense material consisting of sand and gravel and will support all buildings as proposed. Excavations for underground structures may require a soil support system, unless safe slope can be provided. All tie-backs to contain soil during excavation will be located entirely on hospital property. 33

Conclusion Review Excavation of Subsurface Materials Approximately 120,000 cubic yards of soil will need to be removed. Versus former calculation of 331,000 cubic yards Minimal amount of rock (less than 200 CY) may need to be removed from two spots: northeast corner of North Building and southwest corner of new garage. Versus former calculation of 2,519 cubic yards of rock throughout the building footprints 34

Conclusion Review Excavation of Subsurface Materials Approximately 120,000 CY of soil and the 200 CY of rock equate to 8,000 to 8,200 trucks (15-cubic yard capacity). Versus Council s calculation of 22,000 trucks in earlier plan Soil was tested and complies with NJDEP Residential Site Standards. Soil and rock can be removed and used as clean fill. 35

Conclusion Review Dewatering Dewatering will be required for Central Plant portion of North Building. Dewatering may be required for the North Building, depending on season and natural fluctuations of water table. Dewatering may not be required for Phillips garage. 36

Conclusion Review Dewatering Dewatering amount ranges from 0 GPD to maximum 300,000 GPD, dependent on season and natural fluctuations of water table for six months. Note average will be less. Versus prior amount of as much as 570,000 GPD for one-year Maximum decrease in water table under any area home through hospital pumping, will be LESS than the decrease in water caused by natural water table fluctuations over the past two years. Dewatering can be accomplished via a well point system and continuous pumping with pumps placed at several locations, all on hospital property. 37

Conclusion Review Dewatering Water tested and meets NJDEP Residential Site Standards so can be disposed of directly into Ridgewood s Sanitary or Storm Water system or directly injected into the ground. Proposed methods of disposal: Village of Ridgewood s Storm Water System Village of Ridgewood Sanitary Water System In case of catastrophic failure of Ridgewood s Sanitary or Storm Water Sewer System, or in the event of a extraordinary storm that overwhelms Ridgewood s systems, water will be directly injected into ground via injection wells located entirely on hospital property. 38