Port Moresby Power Grid Development Project.

Similar documents
Prepared by State Joint Stock Company UzbekEnergo for the Republic of Uzbekistan and the Asian Development Bank.

Environmental and Social Monitoring Report. SOL: Solar Power Development Project

PAK: Power Distribution Enhancement Investment Program, Tranche 2

TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT

Bhutan: Rural Renewable Energy Development Project (Part D Biogas Plants)

Environmental Safeguard Monitoring Report

Sri: Sustainable Power Sector Support Project

Programme of Activities (PoA) for Sustainable Renewable Energy Power in Papua New Guinea (PNG)

UZB: Second Central Asia Regional Economic Cooperation Corridor 2 Road Investment Program

NEPAL POWER DEVELOPMENT PROJECT P043311

Environment Assessment and Measures. Papua New Guinea: Town Electrification Project

PAK: Jamshoro Power Generation Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

SOUTH ASIA REGIONAL DEPARTMENT SAFEGUARDS INFORMATION LOG FOR SAUW PROJECTS

Bi-annual Environmental Monitoring Report. Kyrgyz Republic: Toktogul Rehabilitation Phase 2 Project (financed by Asian Development Bank)

Land Acquisition and Resettlement Due Diligence Report. IND: Kolkata Environmental Improvement Investment Program (TR2 WS24)

DRAFT FOR CONSULTATION OCTOBER 7, 2014

Tanahu Hydropower Limited

Papua New Guinea: Pilot Border Trade and Investment Development Program

VAN: Inter-Island Shipping Support Project

GEO: Batumi Bypass Road Project Financed by the Asian Development Bank and Asian Infrastructure Investment Bank

2622-BAN: Natural Gas Access Improvement Project, Part A: Ashuganj and Elenga Compression Station

DRAFT ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK EXECUTIVE SUMMARY

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

KGZ: Toktogul Hydropower Plant Rehabilitation Phase 2 Project

Bi-annual Environmental Monitoring Report

Bi-annual Environmental Monitoring Report. Kyrgyz Republic: Toktogul Hydropower Plant Rehabilitation Phase 2 Project

PNG FORESTRY REVIEW TEAM CLOUDY BAY (CENTRAL PROVINCE)

PAK: Jamshoro Power Generation Project

BANGLADESH: DISTRIBUTION SYSTEM UPGRADE AND EXPANSION PROJECT

SRI: Integrated Road Investment Program Tranches 2 & 3 PIC 02 North Western and North Central Provinces

AFGHANISTAN RING ROAD PROJECT Financed under Grant 0081: Road Network Development - Project 1, and Grant 0012: Qaisar-Bala Murghab Road Project

Japanese ODA Loan. Ex-Ante Evaluation

Safeguard Requirements And the Framework Process

Alberta Electric System Operator Needs Identification Document Application

Bi-annual Environmental Monitoring Report

KGZ: CAREC Corridor 3 (Bishkek Osh Road) Improvement Project, Phase 4

Bi-annual Environmental Monitoring Report. Kyrgyz Republic: Toktogul Rehabilitation Phase 2 Project (financed by Asian Development Bank)

Environmental and Social Management System Manual. Uzbekistan: Affordable Rural Housing Program

LAO PEOPLE S DEMOCRATIC REPUBLIC PEACE INDEPENDENCE DEMOCRACY UNITY PROSPERITY

FAQs on ESIA of CASA-1000

Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process

Indigenous People Planning Document. India: Rajasthan Urban Sector Development Investment Program

THE UNITED REPUBLIC OF TANZANIA MINISTRY OF AGRICULTURE FOOD SECURITY AND COOPERATIVES

LOCAL AUTHORITY AND SUBPROJECT SELECTION CRITERIA

IND: MFF - North Karnataka Urban Sector Investment Program - Tranche 2

Ex-Ante evaluation 1. Name of the Project 2. Background and Necessity of the Project

KPDC KRIBI POWER DEVELOPMENT COMPANY

ECONOMIC TRANSFORMATION AND INSTITUTIONAL CAPACITY BUILDING ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK

INDIAN RENEWABLE ENERGY DEVELOPMENT AGENCY. Environmental and Social Management System for ADB Line of Credit

FOR DISCUSSION ONLY. (A) ADB Safeguard Policy Statement. (C) Extent of Equivalence 2

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI

Environmental Management Plan

Environmental and Social Assessment of Storm Water Drains for the Selected Areas of Corporation of Chennai. Executive Summary

AN OVERVIEW OF TANAHU HYDROPOWER PROJECT. Presented by: Achyut Ghimire TANAHU HYDROPOWER PROJECT TRADE TOWER, THAPATHALI, KATHMANDU

IND: MFF - North Karnataka Urban Sector Investment Program - Tranche 2

PNG FORESTRY REVIEW TEAM

VIE: Mong Duong 1 Thermal Power Plant

IND: MFF - North Karnataka Urban Sector Investment Program - Tranche 4

PROJECT PREPARATORY TECHNICAL ASSISTANCE

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project

Papua New Guinea LNG Project

Pteragen Canada Inc.

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

Kendal /Kusile to Zeus Environmental Monitoring Report

Safeguards and Social Dimensions Summary. Mongolia: Ulaanbaatar Green Affordable Housing and Resilient Urban Renewal Sector Project

INDIAN RENEWABLE ENERGY DEVELOPMENT AGENCY. Environmental and Social Management System for ADB Line of Credit

Resettlement Due Diligence Report. CAM: Urban Water Supply Project Kampot Subproject

Cambodia: Provincial Water Supply and Sanitation Project Proposed Siem Reap Wastewater Subproject

C. Project Description [from section 3 of PCN] The proposed project would comprise of the following three components:

Key WCS PNG Contacts

Tanahu Hydropower Limited

PNG FORESTRY REVIEW TEAM AMANAB BLOCKS 5&6 (WEST SEPIK)

Terms of Reference - Procurement and Contract Implementation Support

Georgia: Secondary Road Improvement Project

NEP: Secondary Towns Integrated Urban Environmental Improvement Project

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

Abbot Point Stormwater Return Dam (EPBC 2010/5561) Operation Annual Compliance Report, January 2016

Electricity Networks Corporation (Western Power) Electricity Transmission Licence (ETL 2) Performance Audit Report

SUMMARY INITIAL ENVIRONMENTAL EXAMINATION REPORT. for the TALA-DELHI POWER TRANSMISSION PROJECT (INDIA)

Electricity Networks Corporation (t/a Western Power)

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

TERMS OF REFERENCE FOR CONSULTANTS

BAN Power System Expansion and Efficiency Improvement Investment Program: MFF Tranche 1

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED PHOTOVOLTAIC ENERGY PLANT ON FARM KLIPGATS PAN NEAR COPPERTON, NORTHERN CAPE

Social Safeguards Monitoring Report. TIM L-2857/2858: Road Network Upgrading Project Contract Packages R3 Dili Tibar - Liquica Road

IND: Tamil Nadu Urban Flagship Investment Program (TNUFIP) Due Diligence Report for Water Treatment Plant

Full application form. Infrastructure Grants

Grievance Redressal Mechanism

PNG FORESTRY REVIEW TEAM

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Kabeli Transmission Project

Supporting Kerala s Additional Skill Acquisition Program in Post-Basic Education (RRP IND 47334)

Environmental Assessment and Review Framework. Nepal: Disaster Risk Reduction and Livelihood Restoration for Earthquake-Affected Communities

Improving Safeguard Policy Applications in South Asia Developing Member Countries

LOWER SOUTH ISLAND RELIABILITY INVESTMENT PROPOSAL. Attachment F Summary of Stakeholder Engagement

PNG: Highlands Region Road Improvement Investment Program (Tranche 1)

TERMS OF REFERENCE FOR CONSULTANTS I. CONSULTING FIRM

Mining Environmental Impact Assessment Guidelines. May 2018

SECTOR ASSESSMENT (SUMMARY): POWER Sector Performance, Problems, and Opportunities

PNG FORESTRY REVIEW TEAM NUNGWAIA BONGOS (EAST SEPIK PROVINCE)

Transcription:

Environmental and Social Monitoring Report Semi-annual Report January 2018 Port Moresby Power Grid Development Project. Prepared by PNG Power Limited for the Asian Development Bank. This Semi-annual Environmental and Social Monitoring Report is a document of the Borrower. The views expressed herein do not necessarily represent those of ADB Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Loan Number: L2998/2999 Project Number: 43197-013 Report: Semi-annual Semi-annual Environmental & Social Monitoring Report (Reporting Period: July to December 2017) PORT MORESBY POWER GRID DEVELOPMENT PROJECT Prepared by: PNG Power Limited for Asian Development Bank Submission date: 31 January 2018

Table of Contents ABBREVIATIONS... 20 1.0 INTRODUCTION... 22 2.0 BACKGOUND OVERVIEW... 22 3.0 MONITORING PURPOSE... 23 4.0 BACKGROUND... 24 4.1 Affected People... 24 4.2 Relocation... 24 4.3 Compensation... 24 4.4 GRM... 25 5.0 METHODOLOGY... 25 6.0 PROJECT STATUS... 25 7.0 MONITORING RESULTS AND ACTIONS REQUIRED... 25 7.1 Update on SP1 AP... 25 7.2 SP1 Land Title... 26 8.0 METHODOLOGY... 28 9.0 PROJECT STATUS UPDATES... 28 10.0 MONITORING RESULTS AND FINDINGS... 28 11.0 ENVIRONMENTAL MONITORING COMPONENT... 29 11.1 SP1 Environmental Update... 29 11.2 SP3 Environmental Update... 30 11.3 SP4B Environmental Update... 30 11.4 SP5 & 6 Environmental Update... 30 12.0 GRIEVANCE REDRESS... 30 13.0 CONCLUSION & RECOMMENDATION... 31 13.1 Social... 31 13.2 Environment... 32 14.0 ACTION PLAN... 32 15.0 APPENDICES... 32 Tables Table 1: Status Update: Kilakila Sub Station and 66 kv Transmission Line... 25 Table 2: Access to Transmission Tower Sites... 26 Table 3: PPGDP Subproject Status Update... 28 Table 4: PPGDP Regulatory Compliance... 29 Table 5: Summary of SP1 CEMP Document Transmittal... 30 Table 6: Follow-up Action Plan... 32 Figures Figure 1: POM Power Grid Development Site Plan... 23 Figure 2: GRM Flow Chart... 31

ABBREVIATIONS ADB Asian Development Bank AP Affected People CBD Central Business District CEMP Construction Environmental Management Plan CEPA Conservation and Environment Protection Authority DEC Department of Environment and Conservation DLPP Department of Lands and Physical Planning DRS Deed of Release and Sale EMP Environmental Management Plan EP Environment Permit EPAR Environment (Prescribed Activities) Regulation 2002 GoPNG Government of PNG GRM Grievance Redress Mechanism HPP Hydropower Plant IEE Initial Environment Examination ILG Incorporated Land Group IPBC Independent Public Business Corporation KCH Kumul Consolidated Holdings kv Kilovolt NCD National Capital District NGO Non-Government Organisation PMU Project Management Unit PNG Papua New Guinea PPGDP Port Moresby Power Grid Development Project PPL PNG Power Limited PSB Pestech Sdn Bhd RP Resettlement Plan RoW Right of Way SP Subproject SPS 2009 Safeguard Policy Statement 2009 SSO Social Safeguard Officer TD Tender Document TL Transmission Line TLI Transfer of Land Instruments Transmission Tower

1.0 INTRODUCTION The Asian Development Bank (ADB) is supporting Papua New Guinea (PNG) to develop and expand its energy sector in the Port Moresby Power Grid Development Project (PPGDP) through a sovereign loan fund. The designated implementing agency is PNG Power Ltd (PPL), a fully integrated power authority responsible for the generation, transmission, distribution and retailing of electricity throughout Papua New Guinea. The project will upgrade and extend the transmission and distribution grid, improve substation capacity, as well as upgrade and rehabilitate two hydropower plants. It is aimed at reducing fossil fuel consumption, increasing access to energy supply and improving network reliability in the Port Moresby power grid. 2.0 BACKGOUND OVERVIEW The Port Moresby Power Grid Development Project (PPGDP) is funded by ADB loan L2998/2999 1. The PPGDP agreement was signed between ADB, the Independent Public Business Corporation (IPBC) 2, and PPL on the 28th of May 2013. The loan and counterpart funding provided by the Government of PNG (GoPNG) is managed by PPL through its Project Management Unit (PMU). The PPL PMU has technical assistance from an international consultancy firm namely Fichnter GmbH Limited Consultant. The project intent is to achieve significant improvements in power generation, supply, efficiency, and reliability The Port Moresby Power Grid Development Project is subdivided into six subprojects that entail significant investments into power, transmission, distribution, and generation. The project proposes the construction of new facilities and the rehabilitation of existing facilities serving Port Moresby. The ADB project safeguards categorization for PPGDP is Category B environmental and social component as per the Safeguards Policy Statement 2009 (SPS, 2009), because the potential adverse impacts are less likely to occur and mostly site specific, in particular Kilakila Substations whereby land acquisition is required and hydropower plants. The Transmission Line (TL) will also have a minor impact as a small area will be cleared for mounting of poles and the lines will run overhead with no impact to flora and fauna. The project components are: i) Kila Kila Substation and 66kV Transmission Line; ii) Substation Capacitor Addition; iii) Upgrade of 11kV System to Open Loop Mesh; iv) A) Loss Reduction Program; B) Energy Access; v) Rouna 1 Hydropower Plant Rehabilitation & Upgrade; vi) Sirinumu Hydropower Plant Upgrade. 1 ADB Loan L2998/2999: Port Moresby Power Grid Development Project. 2 IPBC is now known as Kumul Consolidated Holdings (KCH).

Subprojects (i) to (iv) will take place in and around the Port Moresby area in the National Capital District (NCD). Subprojects (v) and (vi) are respectively located about 20km and 35km north east of Port Moresby along the Laloki River valley. Figure 1: POM Power Grid Development Site Plan 3.0 MONITORING PURPOSE Monitoring ensures that the PPGDP subprojects are socially and environmentally compliant to meet ADB s safeguard requirements, as well as PNG government regulations on social and environmental sustainability; to reduce, minimise, mitigate and/or avoid adverse impacts at the project level. Therefore, negating or minimising the impact of the construction on the affected persons as well as the project sites.

I. SOCIAL MONITORING 4.0 BACKGROUND 4.1 Affected People The affected people (APs) of SP1 belong to 3 clans namely, Vaga, Iarogaha and Uhadi Iarogaha. The total numbers of families are 198 with a population of 744 individuals. All members of the first clan (Vaga) are residents of Kilakila village while the latter 2 clans (Iarogaha and Uhadi Iarogaha) are residents of another village called Korobosea. The two pieces of land are registered in 3 Incorporated Land Groups (ILGs).The proposed land for acquisition is not currently utilized by the AP s for purposes such as growing food. The APs include several who live overseas. Fuel wood is collected from around their resident villages and from other land parcels held by clan members. Studies indicate that the AP s have sufficient land available nearby for food gardens and to collect fuel wood (RP 2012). The project due its moderate impacts has been categorize under ADB categorization as B category that is not significant but requires some works to be done on acquiring land but no displacement of people. 4.2 Relocation All six (6) sub projects within the PPGDP do not require relocation of households except for SP1 Kilakila Sub Station and 66kV Transmission line which requires the use of customary land. A total of 0.064 hectares was acquired for the Sub Station and approximately 14.86 hectares for the Transmission Line route. The Transmission Line Route was re-diverted from its original route to avoid existing squatters and was resurveyed and was registered on 14/06/2017 4.3 Compensation Compensation payments were made in part payments for the land acquisition of SP1 and that includes the Transmission Line and the final payment was made after the signing of the Deed of Release and Sale (DRS) and Transfer of Land Instruments (TLI). The transfer was facilitated by PPL and executed by DLPP Officers.

4.4 GRM A Grievance Redress Mechanism was setup as stated in the Resettlement Plan (September, 2012) and coordinated and implemented accordingly by the PPL Lands and Social Safeguard Officer (SSO). 5.0 METHODOLOGY The social monitoring report is written with data gathered from several sources with primary data gathered through observation, discussions through consultations with the AP and from sources within PPL. There were few visits to the project site during this period of Monitoring, as noted not much activities were conducted during the second semester of 2017. 6.0 PROJECT STATUS Table 1: Status Update: Kilakila Sub Station and 66 kv Transmission Line Activity Date Status Registration of ROW Survey 14/06/2017 CLOSED ( Refer to Appendix 1) Letter of Assurance of the processing & Issuance of Lease Title. 19/07/2017 CLOSED ( Refer to Appendix 2) Ground Breaking Ceremony 10/11/2017 CLOSED ( refer to Appendix 4) Joint Site Inspection with Contractor ( PESTECH) Civil Works on Construction Site 27/10/2017 Completed ( Refer to Appendix 3) Active ( On going) 7.0 MONITORING RESULTS AND ACTIONS REQUIRED 7.1 Update on SP1 AP There have been no major impacts or issues amongst the AP s during this monitoring period. No encumbrance or issuing relating to the acquired land have been reported or redressed as such PPL and the VAGA ILG have a strong working relationship and maintains a close communication to ensure all works carried out are free from any hindrance.

7.2 SP1 Land Title The Department of Lands & Physical Planning has written to PPL on the 19/07/2017 to Assure PPL that a Leasehold Title will be given once the National Land Board Meets. Unfortunately this has not eventuated since the National Land Board was suspended by the new Minister for Lands. However the Assurance Letter was given to the Contractor to commence with civil works on the substation site and to assure them that the land is owned by PPL and free from any customary issues/obligations. 7.3 SP1 Ground Breaking Ceremony A ground Breaking Ceremony was done on 10/11/2017, which the customary land was customarily handed over by the Customary Land Owners (VAGA ILG) to Government of PNG. The Ground Breaking Ceremony was officially done by the Minister for State investment and Public Enterprise. 7.4 SP1 Transmission Tower Accessibility Joint Site Inspection was carried out on the 27/10/2017 by PPL Safeguard Officer and PESTECH to ascertain the accessibility of the Transmission Tower () route. The following Table shows the accessibility route for each. Table 2: Access to Transmission Tower Sites Accessibility Remarks Accessibility Remarks 56 YES NO encumbrances 08 YES No Encumbrances. 00 YES NO encumbrances 09 YES No Encumbrances 01 YES Area Fenced (Developer to be Notified by VAGA ILG) 10 YES Accessible (Developer to be Notified by VAGA ILG) 02 PARTIAL Construct a Linking Access to location 11 PARTIAL Accessible through 10 but needs linking access to location.

03 YES Access needs levelling to access 12 NO NO Access, however access can be linked via 13 (VAGA ILG Land owners to be Notified) 04 PARTIAL Construct a Linking Access to location, from the main highway. 13 PARTIAL Access needs levelling and Construct a Linking Access to location 05 PARTIAL Construct a Linking Access to location, from the main highway 14 YES Access needs levelling to access 06 PARTIAL Construct a Linking Access to location, from the main highway 15 PARTIAL Partial Access (Access along Pari Road, next to Kilakila Cemetery, VAGA to be notified) 07 YES Accessible from Taurama Road 16 YES Area Fenced (Developer to be Notified by VAGA ILG) 6.4.1 T56, T0,T1,T3,T7,T8,T9,T10,T14 T2,T4,T13,T5 and T6 and T16 are accessible. 6.4.2 T1 & T16 have the area fenced and VAGA ILG have already informed developers who are aware of the construction. PPL awaiting feedbacks. 6.4.3 T 7, 12, 15 are accessible, but will need permission from VAGA ILG to do linking access which will pass through VAGA Land.

II. ENVIRONMENTAL MONITORING 8.0 METHODOLOGY The methodology that is used to assess environmental risk activities are as follows: Review of CEMP identifying hazard and response in line with work activity on site. Project site visit Checklist inspection (per the EMP/CEMP guidelines) Clearance or revised response according to checklist result Data collated Site visit report and monitoring report. 9.0 PROJECT STATUS UPDATES Table 3: PPGDP Subproject Status Update PPGDP Subproject Date Status 1 Kila Kila Substation and 66kV Transmission Line 19/06/17 EMP transmitted to PBS 31/01/18 CEMP from PBS under review by PPL 10/11/17 Ground Breaking Ceremony for Subproject. 2 Substation Capacitor Addition Has moved to the Loss Reduction Team within PPL. 3 Upgrade of 11kV System to Open Loop Mesh 31/01/18 CBD Switching Station land yet to be confirmed 31/01/18 ADB responded to PMU that Commercial TDs must be submitted with the Technical TDs. Currently in preparation. 4 A) Loss Reduction Program; Has moved to the Loss Reduction Team within PPL B) Energy Access 31/01/18 Bids for Supply of Equipment received and Evaluation completed. The successful candidate is awaiting Board approval and contract award. 5 & 6 Rouna 1 Hydropower Plant Rehabilitation and Upgrade; & Sirinumu Hydropower Plant Upgrade 02/01/18 Technical evaluation report submitted to ADB awaiting response. 31/01/18 Awaiting CEPA response for EP regulation and PPL audit. 10.0 MONITORING RESULTS AND FINDINGS In the environment component of the project there have been no adverse impacts or negative responses from the APs during this reporting period. The general sentiment from the public and AP is that they are looking forward to the commencing of construction of each subproject. The PMU has a good working relationship with CEPA that has adhered to their compliance

requests and instructions. No complaints or setbacks in regards to environmental safeguards have been recorded within this period. 11.0 ENVIRONMENTAL MONITORING COMPONENT All subprojects under PPGDP have had an Initial Environmental Examination undertaken during the pre-feasibility stage with the conclusions from these studies remaining unchanged. With the CEPA permit process additional assessments were done to each subproject to classify the level of activity under the PNG Environment Act 2000 and Environment (Prescribed Activities) Regulation 2002. The outline of activity level for each is given in the table 2 below: Table 4: PPGDP Regulatory Compliance PPGDP Subproject 1 Kilakila Substation and 66kV Transmission Line 3 Upgrade of 11kV System to Open Loop Mesh B) Energy Access 5 & 6 Rouna 1 Hydropower Plant Rehabilitation and Upgrade; & Sirinumu Hydropower Plant Upgrade Classification under EPAR CEPA Environmental Assessment Category under SPS ADB Environmental Assessment Level 2 EMP Category B IEE & EMP 11.1 SP1 Environmental Update PSB received the EMP on the 19 th of June 2017, apart from it being included in the Tender documents. In response to this they submitted their CEMP for the project on the 30 th of October 2017. This was considered the 1 st draft and was reviewed by the PMU Environmentalist. Comments on this draft were sent back to them on the 15 th of November 2017. The 2 nd draft was reverted on the 15 th of December 2017 and was again returned to PSB with comments. The 3 rd draft was submitted on the 18 th of January 2018 and is currently under review, pending finalisation. A summary of the CEMP document transmittal is presented in Table 3 below.

Table 5: Summary of SP1 CEMP Document Transmittal CEMP RECEIVED 1 st Draft 30/10/17 2 nd Draft 15/12/17 3 rd Draft 18/01/18 11.2 SP3 Environmental Update The EP for SP3 will specifically be for the construction of the CBD Switching Station located in down town Port Moresby. The land for SP3 has not been secured as yet. Once the land has been acquired the permit process will commence. The PMU is working closely with the PPL management to secure a piece of land for the CBD Switching Station. Progressive updates will be provided in the next reporting period. 11.3 SP4B Environmental Update The energy access project SP4B will not require an EP according to its EPAR activity classification; however, a CEMP will be drafted for use during construction which is scheduled to begin in the first quarter of 2018. 11.4 SP5 & 6 Environmental Update The EP for the Rouna Cascade, which is an amalgamation of Rouna 1-4 and Sirinumu Power Stations is yet to be rendered by CEPA, as PPL has to undergo an environmental audit of its operations. Previously water use permits were issued by DEC (now known as CEPA) for each station. They all expired in 2008 except for Rouna 4 which expired in 2013. It is now upon the PMU under CEPA directive to combine all HPP permits into one EP for the cascade, which has already been initiated by the PMU. Due to CEPA s internal issues with realigning its operational functions from a Government Department to a separate Authority, there have been delays on their part in keeping pace with the processing of applications. Currently, the Pom Grid Environmentalist is in close liaison with the Senior Permitting Officer to progress the EP for this subproject. 12.0 GRIEVANCE REDRESS The Grievance Redress Mechanism (GRM) for both social and environmental grievances is shown in figure 4 below. The first point of contact is the PMU and designated site contractor. In the case of land issues it is usually passed on to the landowners (community leaders) as a first point of contact, before the PMU/SSO

There have been no grievance notices received from the affected communities during this reporting period. In SP1, because the land acquisition has already been completed and all issues redressed prior to December 2016 there are no issues. Figure 2: GRM Flow Chart 13.0 CONCLUSION & RECOMMENDATION 13.1 Social PPGDP SP1 Kilakila Substation and Transmission Line has commenced construction with PSB as the contractors. The official ground-breaking ceremony was held on the 10 th of November 2017. With the construction still at its initial stages no major issues have been raised or brought to the PMUs attention. Developers of areas that are fenced along the TL route have been notified of the construction that will take place, especially near the proposed sites.

13.2 Environment The CEMP for SP1 is now on its 3 rd draft and is under review to be finalised. The status of the SP3 EP has remained unchanged. The SP3 EP application has not been prepared due to the unavailability of land. Once a project site has been secured a site assessment will be conducted leading on to the application of the EP. The status of the SP5/6 EP has remained unchanged. The SP5/6 EP is under CEPAs internal review and realignment process and should be rendered once the EP regulation has been approved and finalised. This is also under CEPAs audit of PPLs operations. 14.0 ACTION PLAN Table 6: Follow-up Action Plan No. Items (issues) Actions to be Undertaken 1.0 SP1 Gender and Health Awareness to APs during construction period. 2.0 SP5 & 6 Financial Training Awareness Social PMU / Health Department/NGO PMU / Safeguard Unit By Whom Philip Omaro Philip Omaro When (Completion date) First quarter 2018 First Quarter 2018 3.0 SP1 Set up of GRM Committee PMU / VAGA ILG Philip Omaro First Quarter 2018 Environment 4.0 SP1 Review of CEMP by Review Leilah Naris 28/02/18 Pestech. 5.0 SP1 Environmental Inspection Checklist Complete Leilah Naris 28/02/18 6.0 SP4B EMP Complete Leilah Naris 28/02/18 7.0 SP5 & 6 EP Follow-up Leilah Naris 28/02/18 15.0 APPENDICES Appendix 1 Appendix 2 Appendix 3 Appendix 4 Registered Survey Plan Right of Way Assurance Letter Site Inspection Photographs Ground Breaking Ceremony Photographs

APPENDIX 1 Registered Survey Plan Transmission Tower Route (Right of Way)

APPENDIX 2 Assurance Letter

APPENDIX 3 Photograph of Transmission Tower Access

APPENDIX 4 SP1 Ground Breaking Ceremony Photographs