AMAS Task Handover Procedures

Similar documents
IMAS Post-clearance documentation

Afghanistan Mine Action Standards - AMAS Battle Area Clearance

AMAS Land Release. Mine Action Coordination Centre of Afghanistan (MACCA) Post Box : 520 Kabul Afghanistan. Website:

AMAS Quality Management

AMAS Storage, Transportation and Handling of Explosives

GENERAL MINE ACTION ASSESSMENT, SURVEY AND HAZARDOUS AREA MARKING

IMAS Chief United Nations Mine Action Service (UNMAS) United Nations, FF-360, New York, NY 10017, USA

IMAS Land Release

IMAS Land Release

IMAS First Edition 01 October 2001 Incorporating amendment number(s) 1

MEMORANDUM of UNDERSTANDING

Landmines a big constraint for Development

Contents. 1. Certification of Materials 2. Supply of Materials

Company QESH Management Representative

2 Corporate Governance

INTERNAL AUDIT DIVISION REPORT 2018/133. Audit of engineering projects in the United Nations Mission in the Republic of South Sudan

TERMS OF REFERENCE. International Consultant-Gender and Program Development Advisor. 3 September 2018 and 20 February 2019

ELGEYO MARAKWET COUNTY PUBLIC SERVICE BOARD

DECISION TO ACCREDIT

Ammunition Safety and Security in the OSCE Area

Procedure: Managing GMP Regulation Changes

Principles Criteria Protocol. for the designation QUALIFIED ARBITRATOR

The PAIP TFSU would like to issue the following Addendum to the bidding documents of the above named tender:

NATURE OF CONTAMINATION

Submission from the Royal Institute of British Architects to the Grenfell Tower Inquiry s consultation on the Terms of Reference of the Inquiry

ASBESTOS POLICY & MANAGEMENT PLAN UNIVERSITY OF ESSEX HUMAN RESOURCES / ESTATE MANAGEMENT SERVICE

HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE

Materials and Qualification Procedures for Ships

IMAS Second Edition 01 April 2009 Amendment 4, June 2013

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE

CONSTRUCTION MANAGER

Quality Management Systems See also the OTAC Safety Management Systems

HEALTH, SAFETY AND ENVIRONMENT MANAGEMENT SYSTEM MANUAL

LANDMINES AND LIVELIHOODS IN HERAT AFGHANISTAN

IMAS Mine Risk Education Best Practice Guidebook 6 COMMUNITY MINE ACTION LIAISON. International mine action standards IMAS.

Managing Contractors Policy (ratified by Full Governing Body 7 th July 2015)

CDM COMPETENT QUESTIONNAIRE FOR PRINCIPAL DESIGNERS Companies with less than 5 employees

Royal Decree of 29 April 1999 on the authorisation of external services for technical inspections at the workplace (Belgian Official Gazette 2.9.

Materials and Qualification Procedures for Ships

Engaging Professional Consultants

IMAS First Edition 01 October 2001 Amendment 5, June 2013

WHS Manual Insert Business Name & Logo

Work Health and Safety Management Systems and Auditing Guidelines

Quality Assurance Manual

Section 7: Drinking water quality complaints

ABSENCE MANAGEMENT POLICY

Construction Waste Management

Occupational Health and Safety Management Manual v2.2

(d) Please ensure that the Mobile No. and address of the contact person is mentioned in the forwarding letter of the application.

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations

IBT TRAINER APPLICATION FORM FOR APPROVAL AS AN 1. ORGANISATION DETAILS. (Information provided may be subject to formal review at any time by RSA)

INSTRUCTIONS TO BIDDERS

SAMOA INSTITUTE OF ACCOUNTANTS QUALITY ASSURANCE (QA) FOR AUDIT REVIEWER (CONTRACTOR SERVICES)

CHAPTER 10 FACILITIES EVALUATIONS (PRE-AWARD) SURVEYS PART 1 INTRODUCTION

ALASKA DEPARTMENT OF LABOR AND WORKFORCE DEVELOPMENT LABOR STANDARDS AND SAFETY DIVISION OCCUPATIONAL SAFETY AND HEALTH AKOSH PARTNERSHIP PROGRAM

EUROPEAN PARLIAMENT AND COUNCIL

Materials and Qualification Procedures for Ships

CARGO SERVICE GENERAL TERMS

MINE RISK EDUCATION QUESTIONNAIRE

ISO 9001:2000 What does it mean in the supply chain?

Path Construction Project Checklist

(d) Please ensure that the Mobile No. and address of the contact person is mentioned in the forwarding letter of the application.

Management of Health and Safety Files

Airworthiness Standards Department CAMO Change/Variation Approval Process Form. S/N Activity Started Completed Initial Remarks*

DoES-QW1 Suitability Assessment Questionnaire and Declaration

Apprenticeships Safeguarding Policy

AB 14. RIBA stage AB AB 14 ESTABLISH HEALTH AND SAFETY STRATEGY 1. DEFINITION 2. PURPOSE

AB 14 ISSUE/REVISION LAST MODIFIED 15 November 2012 DATE PRINTED

Quality Assurance Policy

Procedure 11 Recruitment and Training

A COMPREHENSIVE UXO CLEARANCE QUALITY ASSURANCE PLAN TRACADIE RANGE, NEW BRUNSWICK, CANADA

APPLICATION NUMBER: STV. Application for a Stevedoring licence issued in terms of section 57 of the National Ports Act No.

WORK PLACEMENT AGREEMENT

Supplier Quality Manual

Good manufacturing practices

CASE STUDY ACHIEVING ISO 9001 CERTIFICATION: A NON-GOVERNMENTAL ORGANISATION S EXPERIENCE

MEMBERSHIP & BIENNIAL HEALTH, SAFETY, ENVIRONMENTAL & QUALITY AUDIT

BAFE SP203-1 Assessment Check List

DIPLOMA IN LABOUR LAWS & LABOUR WELFARE

RISQS Audit Protocol. Plant Operations Scheme. Document no.: RISQS-AP-004. Plant Operations Scheme

NORMATIVE INSTRUCTION N# 25, JUNE 27 TH, 2017

COSBEDMO19 - SQA Unit Code FM75 04 Manage project completion and handover in built environment design management

Land Release: A guide for mine and ERW. affected countries

STATE UNIVERSITY CONSTRUCTION FUND

EXPRESSION OF INTEREST ( EoI ) APPLICATION FORM

1. Introduction. 2. Objective. Cost Auditing Standard 102 Cost Auditing Standard on Cost Audit Documentation

J&P OMAN COMPANY ORGANISATION P.110 PROCEDURE. Page: 1 of 16. Document Title: Issue Date: 13/04/2014. Revision Date: 06/06/2016 Revision No.

SQF Code Food Safety Management System Implementation Workbook

BHARATI VIDYAPEETH DEEMED TO

Work Based Training Policy and Procedure

APPENDIX T.2 SACPCMP The South African Council for the Project and Construction Management Professions

Verify Category A Audit Content

CR-XRL-Z7-GPD-CR

ISO 9001:2008 Certification of National Authority India. Cabinet Secretariat Government of India

EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Customs Policy, Legislation, Tariff Customs Legislation INFORMATION DOCUMENT

PORTFOLIO WORKBOOK SELF ASSESSMENT AND RPL GUIDE TO ACHIEVE THE STATEMENT OF ATTAINMENT FOR WORK SAFELY IN THE CONSTRUCTION INDUSTRY CPCCOHS1001A

1. INTRODUCTION. 1. Development and implementation of an accident prevention program

DEMOLITION OF BUILDINGS

Lay Observers are independent, unpaid and work an average of 2-3 days per month depending on the needs of the organisation and the individual.

IMAS First Edition 01 August 2005 Amendment 3, June 2013

Transcription:

Task Handover Procedures Mine Action Coordination Centre of Afghanistan (MACCA) Post Box : 520 Kabul Afghanistan Website: www.macca.org.af Page 1 of 6

CONTENTS 1. INTRODUCTION... 3 2. SCOPE... 3 3. HANDOVER OF CLEARED AREAS... 3 4. PURPOSE OF TASK HANDOVER DOCUMENTATION... 4 5. CUSTODY AND MAINTENANCE OF HANDOVER DOCUMENTATION... 5 6. HANDOVER OF PORTIONS OF CLEARED AREAS... 5 7. HANDOVER OF AREAS USED FOR UXO DISPOSAL AND STOCKPILE DESTRUCTION... 5 8. HANDOVER OF COMMERCIAL DEMINING TASKS... 6 9. PARTICIPATION OF AFFECTED COMMUNITIES... 6 10. REFERENCES... 6 Page 2 of 6

Task Handover Procedures 1. Introduction There is an urgent need to make cleared land in Afghanistan available for productive use without delay. However, before cleared land can be handed-over, there are a number of procedures to be completed. These include: a) The marking of cleared areas. b) If necessary, the inspection of the cleared land. c) The collation of all clearance documentation. d) The production of handover documentation. The Mine Action Coordination Centre of Afghanistan (MACCA), as the authority for mine action within the country, is charged with the responsibility for the regulation, management and coordination of the handover of cleared land within Afghanistan. To this end, the MACCA has developed set procedures for the handover of tasks within Afghanistan. 2. Scope This chapter describes the procedures that require to be followed for the handover of tasks and cleared land within Afghanistan. 3. Handover of Cleared Areas Prior to cleared land being handed-over, the following preliminary actions require to be carried out: a) The cleared area and any hazardous areas yet to be cleared or unable to be cleared shall be marked in accordance with AMAS 05.03. b) A completion survey is to be conducted by the demining organisation and an IMSMA completion report is compiled. A copy of the IMSMA Completion Report is included in the AMAS 08.02. c) The IMSMA Completion Report, all relevant worksite documentation and the original tasking documentation provided by the AMACs shall be compiled into a single task dossier. The Task Dossier/Folder is to include the followings: i. The original tasking documentation (task folder). This should include the clearance requirements i.e. specified area, specified depth and quality of clearance. ii. Team Attendance Sheet/ Blood Group List of Team Members iii. A copy of the IMSMA Technical Survey Report. iv. The MACCA IMSMA Completion Report. v. Details of the clearance organisation. vi. A summary of the procedures and equipment used to clear the area. Page 3 of 6

vii. Reports from Quality Management (QM) checks conducted during the task. This is to include details of the body which conducted external QA, the methods used and reports provided. viii. Details of reduced and cancelled area(s). ix. Details of any incidents and accidents which occurred during clearance. d) A Cleared Area Completion and Acceptance Certificate shall be raised by the demining organisation. This certificate is to be attached to the Task Completion Report and forwarded to the relevant AMAC. This is to be done within three days of the clearance task being completed. An example of the Cleared Area Completion and Acceptance Certificate is included AMAS 08.02. e) When required, the inspection of the cleared land is completed by an inspection team to ensure that the clearance has been conducted to the required quality. Detail of the requirements for the inspection of cleared land is covered in AMAS 03.01. Once any required inspection has determined that the area has been cleared to the required quality, the Cleared Area Inspection Final Report is added to the Task Completion Report. f) On receipt of the satisfactory Cleared Area Final Inspection Report, the AMAC will sign the Cleared Area Completion and Acceptance Certificate and formally accept the land from the demining organisation. This should include an on-site handover which, for humanitarian demining, should include landowners or community representatives. g) The signed Cleared Area Completion and Acceptance Certificate is then added to the Task Completion Report and the original forwarded to the MACCA and copies provided to the AMAC and demining organisation.. h) The details from the Task Completion Report are entered into the MACCA Management Information System (MIS) and the report is then filed by the MACCA. Land is considered to have been handed-over by the demining organisation once the AMAC has signed the Cleared Area Completion and Acceptance Certificate. 4. Purpose of Task Handover Documentation The handover documentation described above achieves four purposes: 1) Formal declaration by the demining organisation that the land has been cleared over the specified area, to the specified depth and to the specified quality. 2) Recognition by the MACCA that the demining organisation has satisfactorily completed the task. 3) Formal acceptance by the MACCA of the cleared land. 4) Except as detailed in a commercial contract, recognition by the MACCA that residual risk for the cleared area no longer lays with the demining organisation. This is the responsibility of mine action organization to make sure that the necessary task handover documentation is raised and completed as required. Page 4 of 6

5. Custody and Maintenance of Handover Documentation Responsibility for the custody and maintenance of all task completion and handover documentation rests with the MACCA. 6. Handover of Portions of Cleared Areas On occasions, urgent humanitarian or development needs may require the progressive handover of portions of a larger hazardous area. This progressive handover increases the difficulties of management and control in the hazardous area but is achievable provided clearly-defined procedures for the handover of the cleared portions are followed. The procedures to be followed when handing over a portion of a larger hazardous area are: a) The cleared portions to be handed-over are clearly marked in accordance with chapter 05.03 of AMAS, Marking Systems. b) A completion survey is conducted by the demining organisation on the areas to be handed-over and an IMSMA Completion Report compiled. The IMSMA Completion Survey Report is to clearly identify that it relates to only a portion of the total hazardous area. c) A Cleared Area Completion and Acceptance Certificate is raised for that portion of the larger area to be handed-over. All other demining worksite or task allocation documentation is retained by the demining organisation. d) If required, the inspection of the portion of cleared land is completed by an inspection team and the Cleared Area Inspection Final Report is added to the IMSMA Completion Survey Report. e) On receipt of the satisfactory Cleared Area Inspection Final Report the AMAC will sign the Cleared Area Completion and Acceptance Certificate and formally accept the portion of land from the demining organisation. f) This signed Cleared Area Completion and Acceptance Certificate, Cleared Area Final Inspection Report and IMSMA Completion Survey Report are retained by the AMAC. All other handover action is deferred until the complete area has been cleared. It is stressed that all documentation must clearly identify that only a portion of the total hazardous area has been cleared and handed-over. Once the total hazardous area has been cleared, all necessary documentation is raised for those areas not previously handed-over. This documentation, along with that raised for the areas previously handed-over, is collated and compiled into a single Task Completion Report and the actions detailed above are completed. 7. Handover of Areas Used for ERW Disposal and Stockpile Destruction The handover of areas used for Abandoned Explosive Ordnance (AXO) disposal and stockpile destruction operations warrants some additional control measures. In addition to the procedures detailed in Sections 3 and 4, the following is to occur before handover: a) The organization that conducted the destruction is to conduct a thorough check of the entire area to ensure that no hazardous components of mines or ordnance remain. Page 5 of 6

b) The area is to be refurbished in accordance with the requirements of the local communities. As a minimum, this is to include the recovering and disposal of all large items of scrap and where practicable, the filling in of any pits or craters made by the disposal operations. c) Any areas where there may be residual non-explosive hazardous material left in the ground should be fenced off and marked. 8. Handover of Commercial Demining Tasks The case of the handover of cleared areas under a commercial demining contract differs slightly in that the client may be prepared to accept land as cleared without all the preliminary steps described in section 3 having been completed. This, and the issue of liability, is a matter for the client and the demining contractor. However, the MACCA will not formally accept that an area has been cleared until the steps detailed in section 3 have been completed. 9. Participation of Affected Communities Whenever possible, affected communities shall be invited to participate in any handover briefings, visits or formal ceremonies. Community Liaison Team may also assist in liaison and coordination for task handover activities. 10. References AMAS 08.02 Copy of the IMSMA Completion Report AMAS 08.02 Cleared Area Completions and Acceptance Certificate AMAS 05.03 Marking AMAS 03.01 Detail of the requirements for the inspection of cleared land Page 6 of 6