SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

Similar documents
SECTION 10 - TRENCHING AND BACKFILLING

SECTION TRENCHING & BACKFILLING

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 10.0 PIPE TRENCHES Excavation and Preparation of Trench

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

Union County Vocational - Technical Schools Scotch Plains, New Jersey

SECTION TRENCHING

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES

The developer/contractor shall be responsible for replacing all fences which must be disturbed for the installation of sanitary sewer or water lines.

TRENCH EXCAVATION AND BACKFILL

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

C. Foundation stabilization for pipe and utility structures.

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

Construction Specification for General Excavation

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL

TRENCH EXCAVATION AND BACKFILL

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

SECTION EXCAVATION AND FILL

SECTION EXCAVATION, TRENCHING AND BACKFILL

DIVISION 4100 SITEWORK

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

SECTION EARTHWORK. B. Removal of subsoil and excavating all classes of material encountered.

SECTION 14 EMBANKMENT

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION TRENCHING AND BACKFILL

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

SECTION TRENCI-JING PART 1 GENERAL

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION EXCAVATION, BACKFILLING AND COMPACTING

SECTION TRENCHING AND BACKFILLING. A. Earth excavation and backfilling for construction of pipe and appurtenances, and for required removals.

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

EXCAVATION AND BACKF1LL

SECTION 1 GENERAL NOTES

SECTION SOILS REPORT

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION ASPHALT CONCRETE

SECTION EMBANKMENT

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

The Six-Inch Layer Compaction Method

SECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

City of Thomasville Water, Sewer & Natural Gas Specifications SECTION TRENCH EXCAVATION AND BACKFILL

ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING

ITEM I - EXCAVATION. Section VI - Technical Specifications Trenching and Excavation Regulations

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

TABLE OF CONTENTS

DUKE UNIVERSITY CONSTRUCTION STANDARDS

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

A. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):

SECTION STRUCTURAL EXCAVATION FOR STRUCTURES

STANDARD SPECIFICATIONS SECTION 16 STORM SEWER SYSTEMS

CITY OF ELIZABETHTON Building Department Excavations and Cuts Permit Application

San Antonio Water System Standard Specifications for Construction ITEM NO. 804 EXCAVATION, TRENCHING AND BACKFILL

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

SECTION TRENCH EXCAVATION AND BACKFILL

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING AND COMPACTING

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION GRAVITY WASTEWATER LINES

SECTION BUILDING EARTHWORK

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION EXCAVATION AND BACKFILL, GENERAL

Chapter 7 GENERAL CONSTRUCTION SPECIFICATIONS FOR CONVEYANCE SYSTEMS

ST. TAMMANY PARISH COUNCIL ORDINANCE

INDEX DESCRIPTION MATERIALS APPROVAL FOR BASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6

SECTION TRENCHING, BACKFILL AND COMPACTION

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.

SECTION WASTE WATER DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-Place Concrete.

EXCAVATION & BACKFILL SPECIFICATION

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS

SECTION 500 STRUCTURES

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

SECTION EROSION CONTROL DEVICES

SECTION EXCAVATION AND FILL

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations and the Ontario Building code.

SECTION STRUCTURE EXCAVATION AND EARTHWORK

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

STANDARD SPECIFICATIONS SECTION PAVEMENT REQUIREMENTS

Transcription:

SECTION 02221 TRENCHING, BACKFILLING AND COMPACTION PART 1 GENERAL 1.01 WORK INCLUDED A. Excavation for piped utility material. B. Provide necessary sheeting, shoring and bracing. C. Prepare trench bottom with appropriate materials. D. Dewater excavation as required. E. Place and compact granular beds, as required, and backfill. 1.02 RELATED WORK A. Section 02110: Clearing and Grubbing B. Section 02210: Grading and Excavation C. Section 02513: Asphaltic Concrete Paving D. Section 03001: Concrete Work 1.03 PRECAUTIONS A. Notify utility companies when necessary to disturb existing facilities and abide by their requirements for repairing and replacing. B. Protect all vegetation and other features to remain. C. Protect all benchmarks and survey points. PART 2 PRODUCTS 2.01 BEDDING AND BACKFILL MATERIALS GRAVITY SEWERS A. Class I Material: Angular, ¼ to 1 inch graded stone including a number of fill materials that have regional significance such as crushed stone, cinders, slag and crushed shells. 10/08 02221-1 Trenching, Backfilling, & Compaction

B. Class II Material: Coarse sands and gravels with a maximum particle dimension of 1½ inch including variously graded sands and gravels containing small percentages of fines, generally granular and non-cohesive, either wet or dry. C. Class III Material: Fine sand and clayey gravels, including fine sands, sand-clay mixtures, and gravel-clay mixtures. D. Class IV Material: Silt, silty clays and clays, including inorganic clays and silts of medium to high plastically and liquid limits. E. Class V Material: Organic soils, as well as soil containing frozen earth, debris, rocks larger than 1½ inches and other foreign material. 2.02 BEDDING AND BACKFILL MATERIALS STORM SEWERS A. Class A Material: Continuous concrete cradle constructed in conformity with details shown on drawings, consisting of 3000 PSI concrete as specified in Section 03000. B. Class B Material: Sand or natural sandy soil, all passing a 3/8 sieve with not more than 10% passing a No. 200 sieve; or stone, gravel, chert or slag of Gradation C or D of T.D.O.T. specifications. C. Class C Material: Natural ground or compacted embankment at a depth of at least 10% of the outside vertical pipe diameter. D. In rock cuts or other areas where free drainage bedding or backfill materials are required, use crushed stone, slag or washed gravel of size 6, 7, 8, 57 or 78 of T.D.O.T. specifications. E. For crushed stone pavement and shoulder replacement, use crushed stone meeting Type A, Grading D, of T.D.O.T. specifications. PART 3 EXECUTION 3.01 PREPARATION A. Install barriers and other devices to protect areas adjacent to construction. B. Protect and maintain all benchmarks and other survey points. 3.02 EXCAVATION TRENCHES A. Perform in such a manner as to form a suitable trench in which to place the pipe and so as to cause the least inconvenience to the public. B. Maximum width at the crown of the pipe 2 feet plus the nominal diameter of the pipe. 10/08 02221-2 Trenching, Backfilling, & Compaction

C. Cut pavement along neat, straight lines with either a pavement breaker or pavement saw. D. Trench depth: for water lines sufficient to provide minimum cover of 30 inches over the top of the pipe; for sewer lines as shown on the Plans or as specified. E. Align trench as shown on the Plans unless a change is necessary to miss an unforeseen obstruction. F. For water pipe, shape the bottom of the trench to provide uniform bearing of the pipe on undisturbed earth throughout its entire length. Dig bell holes to aid in securing uniform support of the pipe. G. For sewer pipe, fill the bottom of the trench with granular material as specified herein. H. When unstable soil is encountered at the trench bottom, remove it to a depth required to assure support of the pipeline and backfill to the proper grade with coarse aggregate AASHTO M 43, Size No. 2 or 3. This will be a pay item under crushed stone for undercutting material. I. Remove rock encountered in trench excavation to a depth of 6 inches below the bottom of the pipe barrel, backfill with an approved material and compact to uniformly support the pipe. In no case shall solid rock exist within six (6) inches of the finished pipeline. J. When rock borings or soundings are provided, they are for information only and do not guarantee existing conditions. Make such investigations as deemed necessary to determine existing conditions. 3.03 SHEETING, SHORING AND BRACING A. When necessary or when directed by the Engineer, furnish, put in place and maintain such sheeting, bracing, etc., as may be required to support the sides of the excavation and to prevent movement. B. Take care to prevent voids outside the sheeting. C. If voids are formed, immediately fill and ram to the satisfaction of the Engineer. D. Devise plans for performing this work subject to the approval of the Engineer. E. Unless adjacent facilities will be injured, remove all sheeting, shoring and bracing after backfill has been placed to a depth of 18 inches over the pipeline. F. Cut shoring off at the top of the pipe and leave the lower section in the trench. 10/08 02221-3 Trenching, Backfilling, & Compaction

3.04 USE OF EXPLOSIVES A. Conduct all blasting operations in accordance with prevailing municipal, state or other agency regulations, codes, ordinances or laws. B. Exercise due caution when blasting adjacent to existing structures and pipelines. C. If structures or pipelines are damaged, promptly replace or repair them at no expense to Owner. D. Do not conduct blasting operations within 25 feet of water, sewer, gas or other utility lines, unless otherwise directed by the Engineer. E. Cover all shots with blasting mats to prevent flying material. 3.05 DISPOSAL OF EXCAVATED MATERIAL A. Satisfactorily dispose of all excess excavated material that cannot be used for or is not suitable for embankments. 3.06 UNAUTHORIZED EXCAVATION A. All excavation outside or below the proposed lines and grades shown the Plans or directed by the Engineer. B. Backfill areas of unauthorized excavation with the type material necessary (earth, rock or concrete) to insure the stability of the structure of construction involved. C. Unauthorized excavation or backfill to replace it shall not be a pay item. 3.07 REMOVAL OF WATER A. Keep excavated areas free of water while work is in progress. B. Well-pointing shall be performed if required. C. Take particular precautions to prevent the displacement of structures or pipelines as a result of accumulated water. 3.08 OBSTRUCTIONS A. Obstructions shown on the Plans are for information only and do not guarantee their exact locations not that other obstructions are not present. B. When utilities or obstructions are not shown on the plans but are present off the roadway at the location of the proposed pipeline route, the Contractor may request to relocate the pipeline in the roadway if necessary to avoid disturbing the utility or obstructions. 10/08 02221-4 Trenching, Backfilling, & Compaction

C. Exercise due care in excavating adjacent to existing obstructions and do not disturb it unless absolutely necessary. D. In the event obstructions are disturbed, repair or replace as quickly as possible to the condition existing before their disturbance. This repair or replacement will not be a pay item. E. If desired by the utility company, pay for the repair or replacement work performed by the forces of the utility company or other appropriate party. F. If replacement or repair of disturbed obstructions is not performed after a reasonable period of time, the Owner may have the necessary work done and deduct the cost of it from payments to the Contractor. 3.09 STORM SEWER BEDDING A. Use Class A or B bedding, whichever is shown on the Plans. If not shown, use Class B bedding. B. Construct Class B bedding in a trench cut in natural ground or compacted embankment. 1. Bed pipe of 6 of Class B material and sufficient additional Class B material accurately shaped by a template to fit the lower part of the pipe exterior. 2. Ram and tamp in layers not over 6, in loose thickness, around the pipe to a minimum depth of that shown on the Plans. 3. When bell and spigot pipe is to be placed, dig recesses in the bedding material of sufficient width and depth to accommodate the bell. 3.10 GRAVITY SANITARY SEWER BEDDING A. Always maintain proper grade and alignment during the bedding and tamping process. 1. The Contractor at his expense shall replace any pipe dislodged during this process. 2. Dig bell holes to assure uniform support of the pipe. B. Bedding for PVC 1. Completely encapsulate each sewer pipe section with 6 of granular material on the top, both sides and the bottom of the pipe. 2. For PVC sewer pipe, use Class I angular material or material as recommended by the manufacturer. C. Bedding for Ductile Iron Pipe Sewers: 1. Lay each sewer pipe section on a 6 bed of granular material and backfill to the spring line of the pipe with granular material. 2. In unimproved areas, use Classes I or II granular material. 10/08 02221-5 Trenching, Backfilling, & Compaction

3. In improved areas, use Class I angular material. 3.11 BEDDING FOR WATERLINES A. Bed in a trench cut in natural ground. B. Dig bell holes to assure uniform support throughout the entire length of pipe. C. Excavate the trench in such a manner as to form a suitable bed on which to place the pipe. 3.12 BACKFILLING AND COMPACTION A. Do not begin backfilling before the Town Engineer or the designated representative has inspected the grade and alignment of the pipe, the bedding of the pipe and the joints between the pipes. If backfill material is placed over the pipe before an inspection is made, reopen the trench in order of an inspection to be made. B. Jetting, water settling, puddling and/or settling of backfill materials as compaction methods are not acceptable. C. Perform backfilling by hand, together with tamping, until fill has progressed to 18 above the top of the pipe. D. Any discrepancy between these specifications and the manufacturers recommended installation procedures should be brought to the attention of the Town Engineer for a resolution of the discrepancy. E. Stabilizing trenches with extra depth soil cement will not be accepted or permitted without the written consent of the Town Engineer. 3.13 COMPACTION OF GRAVITY SANITARY SEWER A. Deposit Class I granular material (where required) or loose soil free from lumps, clods, frozen material or stones in layers approximately 8 thick. B. Compact by hand, or with manually operated machine tampers, actuated by compressible air or other suitable means. C. Use tamps and machines of a suitable type, which do not crush or otherwise damage the pipe. D. Backfill from 6 above the top of pipe to 24 above the top of pipe to be compacted to 85% relative density as determined by ASTM D-1557 modified proctor. 10/08 02221-6 Trenching, Backfilling, & Compaction

E. Backfill from 24 above the top of the pipe to finished grade or pavement sub-grade with clean suitable fill material in loose lifts not more than 8 thick. Compact material in proposed pavement areas to 95% of maximum dry density as determined by the modified proctor compaction test (ASTM D1557). Compact fill in yards or unimproved areas to 85% modified proctor. The moisture content shall be maintained to within 2% of optimum. 3.14 COMPACTION OF STORM SEWER BACKFILL A. Backfill from the spring line of the pipe to 12 above the top of the pipe with clean suitable fill material to be compacted to 85% relative density (ASTM D-1557) Modified Proctor. B. Backfill from 12 above the top of the pipe to finished grade or pavement sub-grade with clean suitable fill material in not more than 8 loose lifts. Compact fill material in proposed pavement areas to 95% of maximum dry density as determined by the modified proctor compaction test (ASTM D1557). Compact fill in yard or unimproved areas to 85% modified proctor. Maintain moisture content to within 2% of optimum. 3.15 COMPACTION OF WATER MAIN BACKFILL A. Water mains and other utility trenches shall be backfilled with clean suitable fill materials. Compact to 95% modified proctor in proposed pavement areas and 85% modified proctor in lawn or unimproved areas. 3.16 FINAL BACKFILLING A. Backfilling in Unimproved Areas (as approved on site): 1. Dispose of and replace all soft or yielding material that is unsuitable for trench backfill with suitable material. 2. Deposit backfill material in 8 lifts and compact to 85% modified proctor as determined by (ASTM D1557) Density, testing frequency in un-improved areas will be determined by Town Engineer. 3. Proof rolling with a loaded dump truck or front-end loader may be required to locate soft spots. 4. Dispose of surplus excavated material. 5. Before final acceptance, remove all mounds to the elevation of the surrounding terrain. B. Backfilling beneath driveways and streets where non-rigid and rigid type surfacing is to be replaced: 1. Use Class I granular material of either crushed limestone or crushed gravel of high weight and density. 2. Carefully deposit in uniform layers, not to exceed 8 thick. 3. Compact each layer thoroughly by rolling, ramming and tamping with tools suitable for that purpose in such a manner so as to not disturb the pipe. 10/08 02221-7 Trenching, Backfilling, & Compaction

C. Backfilling of shoulders along streets and highways: 1. Backfilling methods and materials for shoulders along streets and highways shall be in accordance with the requirements of governing local, county or state departments maintaining the particular roadway or highway. 2. Replace with similar materials, all shoulders that may be damaged or destroyed as a result of pipe trenching. D. Crushed Stone for Pavement Maintenance and Shoulder Replacement: 1. Where possible, salvage and reuse all base material that is removed during construction. 2. Wet and thoroughly compact crushed stone and blade to tie into the existing surface before final acceptance. 3. Base material placed as a portion of pavement replacing items, will not be directly measured for payment unless traffic whips out the base material placed shall be paid for as crushed stone for pavement maintenance. 3.20 COMPACTION TESTING FOR TRENCHES A. In-place density tests should be performed at fill grade (12 above the top of the pipe) and at every 8 lift of back fill to finished grade for every 50 linear feet of pipe and shall be tested at random as directed by the Town Engineer or his representative to ensure compliance with compaction requirements. B. The Town Engineer may stop excavation of trenches if backfill does not comply with specified density requirements until the defective material is removed and the work is continued correctly. C. The contractor shall assume full responsibility for obtaining an approved testing laboratory to conduct all testing requirements and to provide geo-technical recommendations the project may require unless provided by Town. D. The contractor s testing lab shall submit copies of test reports and geo-technical reports to the Town Engineer. E. The contractor shall provide a safe trench for engineer and testing lab. 3.21 FIELD QUALITY CONTROL A. Compaction: The degree of bedding or backfill compaction shall be as specified. Maximum dry density will be determined by (ASTM D1557) Modified Proctor. The moisture content of bedding or backfill materials shall be within + or 2.0 percent of optimum as determined by ASTM D1557. Compaction testing shall include moisture density relations, and density in place. If compaction testing; or other visual observations, indicate the possibility of inadequate compaction at a lower depth, the Engineer may require the Contractor to re-excavate to a lower depth to conduct additional testing. 10/08 02221-8 Trenching, Backfilling, & Compaction

When requested by the Engineer the Contractor shall proof roll the trench with a loaded front-end loader or truck of sufficient size to determine if soft spots exist. If the tests indicate inadequate compaction, the Contractor shall re-compact the material. In cases where there is repeated failure to achieve the required state of compaction, the Engineer may require that the backfill be removed and re-compacted to 6 lifts or replaced with imported material at Contractors expense. Testing frequency shall be as required to assure the completed work meets specifications. END OF SECTION 10/08 02221-9 Trenching, Backfilling, & Compaction