NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) CHAPTER 1: INTRODUCTION

Similar documents
REPORT TITLE : National Road 3: Keeversfontein to Warden (De Beers Pass Section) Scoping Report

Figure 1.1: Location of Majuba Power Station within the Pixley Ka Seme Local Municipality

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED PHOTOVOLTAIC ENERGY PLANT ON FARM KLIPGATS PAN NEAR COPPERTON, NORTHERN CAPE

1 INTRODUCTION. Figure 1.1: Steve Tshwete Local Municipality

Proposed Windhoek - Gocheganas Road upgrade. Environmental Assessment Scoping Risk Report

VLAKVARKFONTEIN COAL MINE

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA

APPENDIX 1 LETTER CIRCULATED TO MUNICIPALITIES CONCEPTUAL DIAGRAM OF PROPOSED N2 TOLL HIGHWAY ALIGNMENT

1 INTRODUCTION 1.1 PROJECT APPLICANT

2010 EIA Regulations GNR 543 of 18 June 2010, effective 2 August 2010

BASIC ENVIRONMENTAL IMPACT ASSESSMENT for the BEER PROPERTY MANAGEMENT FILLING STATION

ENVIRONMENTAL IMPACT ASSESSMENT. for the proposed NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) DEA ref. no.

3 EIA PROCESS AND METHODOLOGY

DEA Reference Number: To be announced

Background Information Document

Proposed Expansion of the existing Natal Solvent Recovery facility on ERF 7590, Pinetown (10 Clubhouse Place, Westmead) REF: 12/9/11/L44704/4

Annex B2.3. Background Information Document

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

N2 WILD COAST TOLL HIGHWAY ENVIRONMENTAL MANAGEMENT PROGRAMME

PROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD.

INSTALLATION OF A SOLAR PHOTOVOLTAIC POWER PLANT AT ESKOM S DUVHA POWER STATION: ENVIRONMENTAL IMPACT ASSESSMENT

BIOMASS POWER PLANT NEAR MKUZE, KWAZULU-NATAL

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA

1 INTRODUCTION 1.1 PROJECT BACKGROUND

The Project will consist of the following key components: PV solar panels/modules (arranged in arrays); DC-AC current inverters and transformers;

Cape Environmental Assessment Practitioners(Pty) Ltd

PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL

SANRAL DELIVERING TOWARDS ECONOMIC GROWTH IN SOUTH AFRICA. Presenter : Zandile Nene Project Manager : Design & Construction SANRAL : Eastern Region

Figure 4. The proposed location of the Zalu Dam a) basin and b) wall.

NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS: APPLICATION FOR THE MINING OF SAND AT BORROW PIT MR771/8.6/R/80, VAN WYKSVLEI, NORTHERN CAPE.

BACKGROUND INFORMATION DOCUMENT PROPOSED HAZARDOUS SUBSTANCE STORAGE FACILITIES AT THE SALDANHA BAY INDUSTRIAL DEVELOPMENT ZONE

NOVEMBER 2016 REVISION 0. Prepared by: JG AFRIKA (PTY) LTD

BRAAMHOEK TRANSMISSION POWER LINE AND SUB-STATION INTEGRATION ANNEXURE 4: PUBLIC MEETING RECORD (Proceedings including attendance registers)

PROPOSED CAPACITY UPGRADES TO THE N3 FROM LYNNFIELD PARK (KM 30.6) TO GLADYS MANZI (FORMERLY MURRAY) ROAD (KM 6.1) (DEA REF NO: 14/12/16/3/3/1/1966)

11 CONCLUSIONS, RECOMMENDATIONS AND WAY FORWARD Need for the project 11-1

Section Three. Engineering Overview

BACKGROUND INFORMATION DOCUMENT SEPTEMBER 2014 MDEDET REF NUMBER: 17/2/3N-389

BACKGROUND INFORMATION DOCUMENT: EXPANSION OF SINGITA SWENI LODGE

Environmental Impact Assessment for the Proposed Upgrade of the Sani Pass Road (P318): Phase 2

ethekwini Environment al Health Department.

PROPOSED CONSTRUCTION OF A SEWAGE TREATMENT PLANT AT CAPE POINT, TABLE MOUNTAIN NATIONAL PARK

NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE

BACKGROUND INFORMATION DOCUMENT:

Draft Amendment Application Report, Agni Steels SA February 2011 Executive Summary EXECUTIVE SUMMARY

BACK GROUND INFORMATION DOCUMENT

APPENDIX 8 POSSIBLE DEVIATIONS TO DE BEERS PASS ROUTE AVIFAUNAL ASSESSMENT

PUBLIC PARTICIPATION REPORT

Struma Lot 3.2 EIA Development, Working Document

INTRODUCTION PROJECT DESCRIPTION

BRYPAAL SOLAR POWER (PV) PROJECT AND ASSOCIATED INFRASTRUCTURE

EDGE SEMINAR SIP2 Logistics and Industrial Corridor. 19 February 2015

ENVIRONMENTAL IMPACT REPORT JULY DEAT Reference Number: 12/12/20/1399

Annexure E.3. Comment Response Report. Proposed Expansion of Ash Disposal Facility at the Kriel PowerStation, Mpumalanga: Scoping Report

SECTION 1: INTRODUCTION 1.1 BACKGROUND TO THE PROJECT

IMPORTANT NOTICE. Kindly note that:

BACKGROUND INFORMATION DOCUMENT

Background Information Document

BACKGROUND INFORMATION DOCUMENT AND INVITATION TO COMMENT

A comparison of road vs rail investment options on the Gauteng-Durban Corridor

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED REVERSE OSMOSIS PLANT AT HENDRINA POWER STATION, MPUMALANGA EXECUTIVE SUMMARY: FINAL BASIC ASSESSMENT REPORT

KEYSTONE PARK LOGISTICS, WAREHOUSING & LIGHT INDUSTRIAL PRECINCT

THOMAS O BRIEN PERSONAL INFORMATION DIRECTOR: GEOTECH

Purpose of this Document

The PPP has been designed to achieve the following objectives: To ensure that stakeholders are well informed about the proposed development;

PUBLIC PARTICIPATION REPORT PPP SUMMARY

BACKGROUND INFORMATION DOCUMENT FOR A PROPOSED SEWER IN GROOT DRAKENSTEIN, WESTERN CAPE

Proposed establishment of a quarry in the Ngquza Hill Local Municipality, Eastern Cape

13 July

Environmental Management Programme: Langhoogte Wind Farm, Western Cape

ENVIRONMENTAL AND OPERATIONAL MANAGEMENT PLAN

Environmental Impact Assessment for the Proposed Upgrade of the Sani Pass Road (P318): Phase 2

David Hoare Consulting cc Biodiversity Assessments, Vegetation Description and Mapping & Species Surveys

UMGENI RIVER CANALISATION: ENVIRONMENTAL MANAGEMENT PROGRAMME Revision 0.1

Introduction. The Proposed Project

Proposed Establishment of the N.N. Metals (Pty) Ltd Waltloo Metal Reclamation Facility

BOLAND ENVIRONMENTAL CONSULTANTS CC

6. CONCLUSIONS AND RECOMMENDATIONS

Kendal /Kusile to Zeus Environmental Monitoring Report

NOTICE OF INTENT. 2. This notification should be submitted not less than 14 days prior to initiating the basic assessment process.

LINE LINKING TSITSIKAMMA COMMUNITY WIND ENERGY FACILITY TO THE EXTENSION OF THE DIEP RIVER SUBSTATION, EASTERN CAPE PROVINCE

TRAFFIC MANAGEMENT PLAN

BACK GROUND INFORMATION DOCUMENT

Background Information Document

ISSUES WITH TRAFFIC IMPACT ASSESSMENTS

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED EXTENSION OF ASH DAM FACILITY, KRIEL POWER STATION, MPUMALANGA DECEMBER 2010

BASIC ASSESSMENT PROCESS

3 APPROACH TO EIA PROCESS AND PUBLIC PARTICIPATION

EXECUTIVE SUMMARY 1. INTRODUCTION

BACKGROUND INFORMATION DOCUMENT

COMMENT AND RESPONSE REPORT (CRR) VERSION 2

Appendix A: Details of EAP

Mangaung Gariep Water Augmentation Project (MGWAP)

DRAFT BASIC ASSESSMENT REPORT FOR PUBLIC REVIEW 15 MARCH APRIL 2018 VOLUME 1: (MAIN REPORT & APPENDIX A to D)

National Environmental Management Act, 1998: Draft National Biodiversity Offset Policy

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION

DYASON S KLIP SOLAR ENERGY FACILITY 1 (PTY) LTD. TRANSPORT STUDY AND TRAFFIC MANAGEMENT PLAN

BACKGROUND INFORMATION DOCUMENT & INVITATION TO COMMENT JULY 2015

Waste Management Activities. Collection Transportation Storage Re-use, recycling and recovery Treatment Disposal. Waste Management Operators

BASIC ASSESSMENT REPORT. Appendix F: Environmental Management Plan (EMP)

Transcription:

NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) CHAPTER 1: INTRODUCTION 1. INTRODUCTION This (EIR) has been compiled as part of an Environmental Impact Assessment (EIA) that is being undertaken for the proposed N3 De Beers Pass Route (DBPR) between Keeversfontein (just north of the N3 Tugela Toll Plaza) in KwaZulu-Natal via the De Beers Pass area to Warden in the Free State. The total length of the proposed route will be approximately 98 km (see Figure 1-1). Interested and Affected Parties (I&APs) are invited to submit comments on the Draft EIR. The document will then be updated to a Final EIR, having given due consideration to the comments received. This chapter provides background to the proposed project, outlines the Terms of Reference (ToR) for the EIA process, explains the report structure and describes the public participation process associated with the availability of the Draft EIR. 1.1 BACKGROUND TO THE PROJECT In 1971 construction of the dual carriage freeway from Durban to Johannesburg was accepted by Government as part of the new National Road Programme. At that time a dual carriageway already existed between Mooi River and Durban. The existing N3 highway between Heidelberg and Cedara (Pietermaritzburg) is shown in Figure 1-1. The map also shows the remaining portion of the N3 to be completed between Keeversfontein and Warden which includes the new De Beers Pass. Following a route location study between Estcourt and Villiers, in which several alternatives were investigated by the then National Transport Commission, the final route was chosen. In 1974 the basic planning for the N3 highway was finalised, and construction of the most critical portions commenced. However, because of a shortage of funds the completion of construction was delayed. In 1983 the authority to charge tolls on national roads was promulgated in the National Roads Amendment Act 79 of 1983. This resulted in much-needed new funding sources for national roads, allowing projects to proceed such as the N2 Tsitsikamma highway, including its three striking arch bridges. The much-needed Marianhill toll road followed almost immediately. Cave Klapwijk and Associates 1-1

Figure 1-1: Existing route from Heidelberg to Cedara and proposed De Beers Pass Section Cave Klapwijk and Associates 1-2

A concession contract was entered into in 1986 for the design, construction and operation of the N3. This resulted in the upgrading of the older sections of the N3 and the construction of the Frere-Keeversfontein (approximately 50 km) and Warden-Villiers (approximately 100 km) sections. This concession contract was subsequently terminated in 1996. Following a public tender process, the South African National Roads Agency SOC Ltd (SANRAL) appointed the N3 Toll Concession (Pty) Ltd (N3TC) in 1999 as the Concessionaire responsible for the Design, Construction, Financing, Operation and Maintenance of National Route 3 from Cedara in KwaZulu-Natal to the Heidelberg South Interchange in Gauteng as a Toll Highway. The Concession Contract included a requirement to construct the Keeversfontein-Warden section once traffic volumes on the Van Reenen s Pass reached a specified level. The N3TC obtained a conditional environmental authorisation in 1999 for the construction and upgrading of the N3 between Cedara and Heidelberg, including the DBPR, and proceeded to construct the Villiers-Heidelberg section as well as to rehabilitate and upgrade the existing sections. 1.2 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS The N3TC obtained environmental authorisation by means of a Record of Decision (RoD), issued by the Department of Environmental Affairs and Tourism (DEAT), on 26 March 1999, authorising the construction and upgrading of the N3 Toll Road System from Heidelberg to Cedara, comprising two sections, (i) Cedara to Heidelberg (via Van Reenen) and (ii) Keeversfontein to Warden (DBPR). The RoD was issued subject to certain conditions (Volume 2, Appendix A) In particular, the following conditions under the heading De Beers Pass Route were specified: Provision must be made in the EMP for a detailed study on the influence of the new De Beers Pass/Warden route as proposed by Naidoo and Associates; Hydrology and Water Quality. An analysis of the current indicated alignment of the De Beers Pass/Warden route versus alternative routing to avoid wetlands must be done. This needs to be done as part of the detailed road design. Wetland specialists should be consulted. An analysis of improved designs for road drainage versus the offset of investing in appropriate wetland assets elsewhere is to be done as part of the detail road design. Hydrologists and wetland specialists should be consulted. The exact location of the proposed tunnel should be determined and the materials to be removed during the construction should be stockpiled as far away from the gorge as possible. Tunnel entrance lights must be directed so that it has minimal or no impact on the ambience of the area. Cave Klapwijk and Associates 1-3

That the route alignment from the bottom of De Beers Pass to the top of the escarpment be re-evaluated during the detailed design phase so as to ensure that the road and tunnel have the least negative impact on the landscape. The functions of the wetlands in the De Beers Pass section must under no circumstances be negatively impacted on. Further detailed studies should be completed during the detailed design. The results and recommendation of the studies must be approved by this Department as well as provincial environmental departments. Other conditions in the 1999 RoD considered in this EIA are: Provision must be made in the EMP that the influence of the road on Alex Pan will be researched and appropriate mitigation measures must be implemented in order to minimise the effect thereof on the pan and its associated wildlife. Provision must be made in the EMP that a study on the current location of sun gazers in the road reserve, quarries and road camps will be done. A management plan for translocation of sun gazers from known locations and other unexpected sun gazer findings must be developed. This plan must stipulate detailed actions to be taken. The project has the greatest potential on the area s wetland resources at every point where the road will cross a wetland. The critical issue with regard to the mitigation of impacts to wetlands will therefore be the design and placement of drainage structures under the road. Emphasis must be on ensuring that these structures pose minimal disruption to the natural flow patterns of water through the wetland. Inadequate or badly placed structures will result in the loss of wetland functions or values which will be felt some distance downstream, and by most of the users of the wetland. This must be reflected in the EMP. Since new EIA Regulations were enacted in terms of the National Environmental Management Act (No 36 of 1998) (NEMA) in 2006 (and again in 2010), SANRAL and the N3TC jointly approached the Department of Environmental Affairs (DEA), (previously the (DEAT), to clarify the way forward. It was agreed that SANRAL would submit a new Application for Environmental Authorisation for the DBPR, via a full Scoping and EIA study, including consideration of reasonable and feasible alternatives. A new application for environmental authorisation was submitted on 23 July 2010 for the construction of the National Road 3: Keeversfontein to Warden (De Beers Pass Section). In order to facilitate this process Mr. Alan Cave, who was the Independent Environmental Assessment Practitioner (EAP) for the original EIA, was again appointed as the EAP for this assessment. Cave Klapwijk and Associates 1-4

1.3 STRUCTURE OF THE REPORT Chapter 1 of this report provides a general background to the proposed project, ToR for the EIA study and report structure, and outlines the procedure for comment on the Draft EIR. An explanation of the study approach and methodology, together with associated legal considerations, are then dealt with in Chapter 2. A detailed description of the proposed project is presented in Chapter 3, followed by the need and desirability of the project in Chapter 4. Reasonable and feasible alternatives and mitigation deviations are described in Chapter 5, and the receiving environment is covered in Chapter 6. The DBPR and alternatives have been divided into four sections for ease of assessment and reporting. These sections are described in Chapter 3. Chapter 7 contains the findings of the specialist studies and assessment of the impacts for Section 1 of the DBPR and alternatives. Similarly, Sections 2, 3 and 4 are dealt with in Chapters 8, 9 and 10 respectively. The results of the economic assessments are given in Chapter 11, and the synthesis by the EAP is included in Chapter 12 together with a conclusion and recommendations. 1.4 OPPORTUNITY TO COMMENT ON THE DRAFT EIR 1.4.1 I&AP Notification All I&APs on the project database will be notified via personalised letters of the availability of the Draft EIR. All reports, including Specialist Study reports, will be uploaded on the ACER website www.acerafrica.co.za under the N3EIA Draft EIA Report link. They will also be available on www.nra.co.za/environmental Reports/. 1.4.2 Public Open Days Public Open Days will be held in the study area to present the findings on the Draft EIR at the following areas: Ladysmith; Van Reenen; Harrismith; and Warden. 1.4.3 Availability of draft reports at public places The Draft EIR will be made available at various public places similar to the ones used for the DSR as follows: Ladysmith Public Library; Green Lantern Inn (Van Reenen); Harrismith Public Library; and Warden Public Library. Cave Klapwijk and Associates 1-5

1.4.4 Comments on draft Reports For comments to be included in the Final EIR, they should reach the offices of ACER within 90 days of the availability of this document. Comments should be forwarded to ACER at the contact details given below: Bongi Shinga ACER (Africa) Environmental Management Consultants P O Box 503, Mtunzini, 3867 bongi.shinga@acerafrica.co.za Tel: 035 340 2715 Fax: 035 340 2232 Cave Klapwijk and Associates 1-6