Table OCO 8.1 Air Quality Management. Audit Check. Ref Subject Reference Control Activity Responsibility Timing Performance Measure

Similar documents
BELL BAY PULP MILL MANAGEMENT PLAN

Table OCO 4.1 Acid Sulphate Soils Management

Draft Dust Management Plan

BEST MANAGEMENT PRACTICES PLAN FOR FUGITIVE DUST Greenwood Aggregates Company Limited Violet Hill Pit > Town of Mono, ON

DUST MANAGEMENT PLAN MILLER PAVING LIMITED BRAESIDE QUARRY. Prepared by: Church & Trought Inc. 885 Don Mills Road, Suite 106 Toronto Ontario M3C 1V9

Environmental Program

Crushing and Screening Management Procedure Environment

APPENDIX I DUST SUPPRESSION/CONTROL PLAN

Air Quality Management Plan

Hastings District Council. Whakatu Arterial Link Construction Environmental Management Plan

Dust Management Procedure Environment

Gunlake Quarry. Air Quality Management Plan

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT

Construction Environment Management Plan

CCR RULE FUGITIVE DUST CONTROL PLAN

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

8 AIR AND CLIMATE Introduction

Matrix of Environmental Management Plan, Rehabilitation of Lehumo Lake Embankments

Environmental Program

Borrow Pit and Quarry Management Procedure Environmental

NELSON PLANT CCR FUGITIVE DUST CONTROL PLAN

Murra Warra Wind Farm Project Environmental Management Plan

ENVIRONMENTAL GUIDELINES FOR PREVENTION AND CONTROL OF FUGITIVE EMISSIONS FROM CEMENT PLANTS

INDEX FOR SPECIFICATIONS FOR AGGREGATE FOR BITUMINOUS PAVEMENT SCOPE... 2

Environmental Management System Integrated Pollution Control. Origination Date 1 st February Area: The Group

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

Job Name: London School of Hygiene & Tropical Medicine, Tavistock Place, London

FUGITIVE DUST CONTROL PLAN DUNKIRK GENERATION STATION 106 POINT DRIVE NORTH DUNKIRK, NEW YORK. PREPARED FOR: Dunkirk Power, LLC Dunkirk, New York

AIR QUALITY MANAGEMENT PLAN CORAKI QUARRY

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

Introduction. Brett McLennan EMM Consulting Pty Ltd PO Box 21 St Leonards NSW 1590

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES

Permit with introductory note

This summary and the Report subsequently inform the recommended mitigation contained in Section 28 and will inform the Project conditions.

Subsection or plan to be revised: 7-1, 7-8, , On page(s): 27-31(2006), 48-49(2003)

SECTION 7: CLIMATE AND AIR QUALITY

NOISE MANAGEMENT PLAN

FUGITIVE DUST CONTROL PLAN FOR SMP-32 JULY 31, 2017

Asbestos: Strategies for the identification and remediation of asbestos-contaminated materials

Works, services and infrastructure code

Mondi Richards Bay: Fugitive Dust Management Plan

Fugitive Dust Management Plan

FUGITIVE DUST CONTROL PLAN HUNTLEY GENERATION STATION 3500 RIVER ROAD TONAWANDA, NEW YORK. PREPARED FOR: Huntley Power, LLC Tonawanda, New York

FUGITIVE DUST CONTROL PLAN FOR VULCAN MATERIALS COMPANY PLEASANTON FACILITY

Environmental Control Plan

Environment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance

SECTION AIR POLLUTION AND HAZARDOUS WASTE CONTROLS

EF10 Site Environmental Audit - 1 / 8

Dust Management Plan

AM-PR-003 Construction Environmental Management Plan (C-EMP)

Conditions of Approval for the MDP for the brickworks at Perth Airport

CCR Fugitive Dust Control Plan

ENVIRONMENTAL GUIDANCE NOTES: CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN (CEMP)

Pollution Incident Response Plan

Intermodal Logistics Centre at Enfield Environmental Assessment CHAPTER 12 AIR QUALITY ASSESSMENT

Kurnell Refinery Conversion Project

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

RUNWAY 7L/25R RUNWAY SAFETY AREA (RSA) AND ASSOCIATED IMPROVEMENTS PROJECT MITIGATION MONITORING AND REPORTING PROGRAM 2017 PROGRESS REPORT

Last updated September Fugitive Dust. Fugitive Dust. Training Presentation

8 ENVIRONMENTAL MANAGEMENT PROGRAMME (PROJECT ENVIRONMENTAL SPECIFICATION)

SPECIFICATION FOR ENGINEERED FILLS

Resource Consent Application - Removal/Remediation of Flare/Blowdown Pit at Kapuni Well site KA2 for Shell Todd Oil Services Ltd

Emergency Contact Numbers: Police, Fire, Ambulance 000 SES Vic Roads EPA Vic 1300 EPA VIC ( ) Safe Work Method Statement

Environmental Bill of Rights Draft Version DRAFT - For Consultation Purposes Only Ministry of the Environment

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV

Barr Road Quarry (Site N) Frequently Asked Questions Last updated: November 19, 2007

PORT OF PORT HEDLAND - BULK PRODUCT MANAGEMENT PROCEDURE

Appendix 11. Erosion and Sediment Control Management Plan. Appendix 11

Presented by: Chris Ethridge District Supervisor Air Quality Division MDEQ Southeast Michigan District Office

Alberta Transportation The City of Edmonton The City of Calgary

February 21, Permit: APC-82/1209-CONSTRUCTION (Amendment 5) Petroleum Coke Storage and Handling Complex

Stage 2: WestConnex M5 King Georges Road Interchange Upgrade. Appendix B6 Construction Air Quality Management Plan

Environmental Policy

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

Targeted Constituents Sediment Nutrients Trash Metals Bacteria Oil and Grease Organics. Potential Alternatives. EC-5 Soil Binders

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Odour Management Plan. November 2009

ENVIRONMENTAL MANAGEMENT PLAN. Developed for National Asphalt (Pty) Ltd. Generic Requirements

10.0 AIR QUALITY AND CLIMATIC FACTORS

106 CONTROL OF MATERIALS SECTION 106 CONTROL OF MATERIALS

Construction Environment Management Plan (CEMP) Requirements

Last updated Sept. 15, Fugitive Dust. Cassie Archuleta and Jenna Channel

DUST CONTROL MEASURES

Appendix 12. Assessment of Air Quality Effects. Appendix 12

24 August Leanne Cross Senior Environmental Planner KDC Via

CONSTRUCTION PERMIT. PERMIT NO: 09LP0202F Final Approval

Hazard Identification & Risk Assessment

Site-Specific PM 10 Ambient Air Monitoring Plan

16/07/2016 Annual review Sharmaine Cunningham Glenn Lein

JSP Construction Ltd CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN City Road Cardiff CF24 3BJ

New Administration Building

FUGITIVE DUST CONTROL PLAN

Environmental Code of Practice For the Sale and Use of Pulverised Fuel Ash (PFA)

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

8 AIR QUALITY ASSESSMENT

Air Quality Assessment Report Paris Grand Development County of Brant, Ontario

MINING OPERATION SERVICES

Final Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Heat Treatment Furnace at Scaw Metals High Chrome

FUGITIVE DUST CONTROL PLAN

Transcription:

These tables set out the operational controls required to achieve the objectives and targets set out in Program 08 Air Quality Management. BBA will, as a minimum, implement the control activities and performance measures set out below. Table OCO 8.1 Air Quality Management Table OCO 8.1 Air Quality Management INDUCTION AND TRAINING 1. Design Consultant briefing CEMP 10 The Design Consultants will be briefed on the design aspects of this Control Document Design Director Prior to start of design. Briefing record 2. Project and site induction CEMP 13 All employees, consultants and subcontractors involved will be inducted into the environmental aspects and controls related to this Control Document. Construction Director or Project, as applicable Prior to personnel commencing work on site Induction records Start up for Early Works 3. Staff Construction Management Plan induction CEMP 13 All relevant staff will be inducted into the requirements of the Construction Management Plan and all associated documents. Construction Director or Project, as applicable Prior to staff commencing work on site Induction records BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 1 of 10

4. Awareness training CEMP 13 CEMP 14 Conduct awareness instruction of relevant BBA staff, contractors and field personnel. Objectives of Air Quality Management awareness training include: Project As per Training Plan Training records Dust Management Plan provisions Purpose and operations of dust web cam system Importance of minimising the area of exposed soil. Maintaining haul road moisture levels. Observing speed limits. The responsibility of all staff to be aware of the potential for nuisance dust emissions Reporting of observed dust emissions and direct remediation of dust emissions where practical. 5. Briefings CEMP 13 CEMP 14 briefings shall emphasize sitespecific control requirements. Prior to working in a specific area Record of Briefing. (eg SEP Briefing) CONSTRUCTION Earthworks and topsoil stockpiles 6. Limit exposed areas As far as is possible, plan the works to limit the area of exposed soil to the minimum required for the immediate works. Ratio of stripped area to works area. 7. Timing of topsoil stripping operations. As much as possible, time topsoil stripping operations when soil is moist. Also avoid days when there is the potential for wind to carry dust toward residential or commercial areas. Use of appropriate plant BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 2 of 10

8. Topsoil stockpile location buffer of 100 m wherever practicable 9. Minimise time lapse between topsoil stripping and earthworks 10. Complete earthworks quickly 11. Compact surface of fill areas when left 12. Establish Protective Cover Quickly 13. Water trafficked earthworks areas 14. Water stockpiles in sensitive areas. As much as possible, locate topsoil stockpiles as far away from residential and commercial areas as possible. Preferably, a minimum buffer of 100 m should be used. Where this cannot be achieved, measures should be taken to prevent wind erosion of the topsoil. The time lapse between stripping topsoil and the commencement of the main earthworks should be kept to the absolute minimum. Complete earthworks as quickly as possible. Vic EPA Pub 480. LU1, Part 3, Sect 2, 2AM6.1, pg 78, (Seq pg 91) LU2, Part 3, AM1.2, pg 19, (Seq pg 233) LU3,Part 3, AM1.1, pg 37, (Seq pg 276) LU4, Part 3, AM1.1, pg 38, (Seq pg 327) Compact the surface of fill areas when the area will be left exposed for long periods. Establish protective cover over completed earthworks as quickly as possible. Water earthworks areas where they are being trafficked. Water stockpiles in sensitive areas during windy conditions where they are a source of dust. Appropriate location of stockpiles Short time lapse Minimum time lapse Compacted surface of fills at appropriate times Completed earthworks protected Moistened haul roads Moistened stockpiles BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 3 of 10

15. Avoid contaminated run-off. Whenever watering is used as a dust suppression measure, care will be taken to ensure it does not create contaminated run-off. No contaminated run-off 16. Out of hours dust control. Watercarts are to be available out of hours in situations where unacceptable amounts of dust could be generated eg. Summer months, winds and extended periods without rain. Arrangements should be in place to be able to mobilise these watercarts at short notice. Project Duration Dust mitigated out of hours to minimised impact on sensitive receivers 17. Modify or suspend activities in extreme conditions. LU1, Part 3, Sect 2, 2AM6.1, pg 78, (Seq pg 91) LU1, Part 3, Sect 3, 3AM11.1, pg 107, (Seq pg 120) LU1, Part 3, Sect 3, 3AM11.2, pg 107, (Seq pg 120) Modify or suspend activities during extreme dry and/or wind conditions if dust is a problem, e.g. if additional dust control measures are ineffective in prevention of emission of nuisance dust. Activities modified appropriately LU1, Part 3, Sect 4, 4DS1.1, pg 143, (Seq pg 156) LU1, Part 3, Sect 7, 7AM2.1, pg 168, (Seq pg 181) LU2, Part 3, AM1.2, pg 19, (Seq pg 233) LU3, Part 3, AM1.1, pg 37, (Seq pg 276) Crushing and screening plant BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 4 of 10

18. Dust from crushing and screening plant LU1, Part 3, Sect 3, 3AM12.1, pg 108, (Seq pg 121) Dust produced by the operation of all crushing and screening plant will be controlled by the use of one or more of the following methods to the extent necessary to prevent environmental nuisance being caused: (a) the installation of fixed water sprays at all fixed crushers and at all points where crushed material changes direction due to belt transfer; (b) the installation of dust extraction equipment at all fixed crushers and at all points where crushed material changes direction due to belt transfer, and the incorporation of such equipment with all vibrating screens; (c) the enclosure of the crushing and screening plant and the treatment of atmospheric emissions by dust extraction equipment; and/or (d) any other method that has been approved in writing by the Director of Management. Inspection records Haul Roads 19. Construct crushed rock haul roads Vic EPA Pub 480. Construct long term haul roads of crushed rock or other suitable material in locations adjacent to residential and commercial areas. Gravel haul roads in sensitive areas 20. Water haul roads Water haul roads as required to suppress dust. Moistened haul roads 21. Maintain haul roads. Regularly maintain haul roads as required, using graders. Haul roads maintained 22. Limit speed on haul roads Limit speeds on haul roads if necessary to reduce dust generation. Speed limits employed BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 5 of 10

On road transport of fill, muck or quarry products 23. Cover loads Vic EPA Pub 480 Cover loads as necessary to contain dust. Dampen loads if necessary to prevent escape of dust from trucks. Truck operator As required. No escape of dust from trucks. Screening plants, batch plants, pug mills, etc 24. Controls to be developed LU1, Part 3, Sect 3, 3AM12.1, pg 108, (Seq pg 121) Vic EPA Pub 375.2 Dust produced by the operation of all crushing and screening plant will be controlled by the use of one or more of: (a) the installation of fixed water sprays at all fixed crushers and at all points where crushed material changes direction due to belt transfer; (b) the installation of dust extraction equipment at all fixed crushers and at all points where crushed material changes direction due to belt transfer, and the incorporation of such equipment with all vibrating screens; (c) the enclosure of the crushing and screening plant and the treatment of atmospheric emissions by dust extraction equipment; and/or (d) any other method that has been approved in writing by the Director. As required. Controls in place Controls for batch plants and pug mills will be developed if and as necessary. Plant exhaust emissions 25. Equipment Vehicles, machinery and equipment will be well maintained to minimise greenhouse gas emissions Ongoing Equipment inspections BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 6 of 10

26. Visible smoke less than 15 seconds Visible smoke from construction plant shall not persist for longer than 15 seconds (for off road plant) and 10 seconds (for plant registered for use on public roads). Plant that is seen to exceed this requirement shall be removed from use until the issue is rectified. Ongoing Minimal visible smoke from plant 27. Include requirements in procurement documentation Personnel involved in the procurement of plant, including hired in plant, shall ensure this requirement is included in procurement documentation. Procurement Personnel Before subcontractor engagement / hire of plant. requirements included in procurement documents Excavation of Contaminated Soil 28. Odour Control s Detailed in SEPs Where it is anticipated that contaminated soil to be excavated will emit offensive odours, preventive measures shall be taken to reduce the impact on nearby residential and commercial areas. s will be included in site specific Site Plans. They may include the use of neutralising sprays, covering exposed areas of offensive material when excavation is interrupted, avoiding excavation when the wind is blowing toward sensitive areas, etc. Before excavating contaminated soils. Planning in place INCIDENTS BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 7 of 10

29. Potential environmental harm CEMP incident response procedures Class 1: An actual adverse effect on the health or safety of human beings that is of a high impact or on a wide scale; an actual adverse effect on the environment that is of a high impact or on a wide scale; an actual loss or property damage of an amount, or amounts in aggregate, exceeding ten times the threshold amount ($5,000); an environmental nuisance of a high impact or on a wide scale; an actual adverse effect on the health or safety of human beings that is not negligible; an actual adverse effect on the environment that is not negligible - cease relevant activities across all sites until the problem is fully understood and rectified; follow incident response procedures Class 2: The emission of a pollutant that unreasonably interferes with, or is likely to unreasonably interfere with, a person's enjoyment of the environment; any emission specified in an environment protection policy to be an environmental nuisance; an actual loss or property damage of an amount, or amounts in aggregate, exceeding the threshold amount ($5,000) - cease relevant activities at the site of occurrence until the problem is rectified; follow incident response procedures Ongoing Incident response records BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 8 of 10

30. Potential permit breach CEMP incident response procedures Class A: A permit condition has been breached and either the environmental consequences are significant or the breach is due to a wilful or negligent failure to attempt to satisfy the condition cease relevant activities across all sites until the problem is fully understood and rectified; follow incident response procedures Class B: A permit condition has been technically breached but the intent of the condition has been or will be achieved and environmental consequences of the breach are not significant cease relevant activities at the site of occurrence until the problem rectified; follow incident response procedures Class C: Compliance with the permit has been raised as an issue but the intent and requirements established by the permit condition have been met examine the significance and potential for corrective action; follow incident response procedures Ongoing Incident response records EVALUATING PERFORMANCE 31. Monitoring LU1, Part 3, Sect 2, 2MN3.3, pg 63 of 201 (Seq. 71) LU2, Part 3, Sect 2, GN11.4, pg 16 of 25 (Seq. 230) LU3, Part 3, 3.3, pg 19 of 50 (Seq. 258) LU4, Part 3, 3.3, pg 20 of 52 (Seq. 309) LU1, Part 3, Sect. 3, 3AM11.2, pg 107 of 201 (Seq. 120) Conduct monitoring of dust as described in Dust Management Plan (GNS-PLN-1000-1400-0001) and Construction Monitoring Plan (BBA-PLN- 1000-1400-001H), including real time particle monitoring, web cam visual monitoring and regular visual inspection on site. If fugitive nuisance dust emissions are occurring, arrange for additional targeted dust mitigation measures until nuisance dust emissions cease. Site Officer Ongoing Monitoring Records LU1, Part 3, Sect. 3, 3AM13.1, pg 108 of 201 (Seq. 121) BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 9 of 10

32. Inspections CEMP 16 Inspect the condition of protection and control measures and arrange maintenance, as required. 33. Reporting CEMP 17 Report on the implementation of this EP in the environmental section of the monthly Project Report. 34. Assess monitoring results CEMP 19 Evaluate and assess monitoring results against specified targets Site Officer Daily Weekly list Ongoing Monthly report Ongoing Reports 35. Corrective action CEMP 19 Take corrective action, where required Project As required Action taken Revision Status Revision Date Revision Description Prepared Reviewed Approved A0 27 April 2007 Draft for Consultation IW A1 9 May 2007 Draft for DTAE review IW B0 22 October 2007 Revised for submission to DTAE following auditor s comments IW JD JC B3 21 January 2008 Revised following DTAE comments JRD JD CF BBA-OCO-1000-1400-0008-B-03 Air Quality Management Page 10 of 10