Underpinning. Underpinning

Similar documents
Advanced Construction Techniques. Underpinning. Underpinning

UNDERPINNING A CRANE FOUNDATION

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program

twenty four foundations and retaining walls Foundation Structural vs. Foundation Design Structural vs. Foundation Design

The Construction of the Langham Place in Mong Kok An Introduction

The designer shall also submit additional information required by the University as described and underlined below.

SPECIAL INSPECTION AND OBSERVATION PROGRAM City of Walnut Creek Building Division. Project Address:

Construction of a Semi-Buried Building A Super-sized Shopping Mall : The Festival Walk

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No

Atlas-Helical & ATLAS RESISTANCE PIERS. LOOK OUT! New House Headed South!

FOUNDATIONS. Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1

A cofferdam is a temporary structure designed to keep water and/or soil out of the excavation in which a bridge pier or other structure is built.

Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013

A. Section includes temporary excavation support and protection systems.

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Temporary Structures. Excavations and Excavation Supports

Appendix C. Gallery Place Chinatown Station Structural Assessment

Misan University - College of Engineering Civil Engineering Department

Dewatering & Foundations. Water. Low tech

STATEMENT OF SPECIAL INSPECTION FORM

Construction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay

National Truss for Historic Preservation

Figure 5 - A shoring tower is made by assembling end frames with diagonal braces

Table of Contents. List of Drawings

twenty seven concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

Helical Design. Theory, Applications & Seismic Testing 5/2/2017. Helical System. Helical System. Common Helical Piles/Anchors Components

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications

Case Study. The Challenge. Deep Micropile Installation Under Existing Multistory Building

Client Project Job # Wall Loc. SBWall Report deg 120 pcf 950 psf deg 0.0 ft. 6.0 ft 6.0 ft 2.0 ft. W16x50.

PRECAST CONCRETE GIRDER ERECTION

Project Address: Name of Person Completing Form:

Earth Retention Systems

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.)

REGULATIONS FOR RESIDENTIAL OPEN WOOD DECKS

Structural Engineering

Project Findings: Appendix 2

THE FLORIDA BUILDING CODE

DISCUSSION ON UNDERPINNING (28/3/12)

Steel Expansion. Located along the Grand River in

.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.

Building Division Informational Handout

SOIL AND FOUNDATION INVESTIGATION PROPOSED DUPLEX 3966 VRAIN STREET DENVER, COLORADO

ICBO Evaluation Service, Inc Workman Mill Road, Whittier, California

10 EXTREME BASEMENT PANELS

Structural Inspection

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

Page 4-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD DETERMINATION

Structural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

BUILDING CODES Presented by CORUM ENGINEERING

BUILDING PERMIT REQUIREMENTS FOR: RESIDENTIAL DECKS CITY OF ESCONDIDO BUILDING DIVISION 201 N. BROADWAY, ESCONDIDO, CA (760)

Residential Deck Guide

2016 Port of San Francisco Building Code

Rehabilitation of Masonry Piers at Nipigon, Ontario

SEATTLE CENTRAL COLLEGE BROADWAY PERFORMANCE HALL SEATTLE, WASHINGTON STRUCTURAL EVALUATION FOR PREPARED BY PCS STRUCTURAL SOLUTIONS

PHASE 1 Foundation & Drainage New Construction Phased Inspection Report John & Mary Doe 5237 Clinton Street, Denver, CO 80238

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage

CONSTRUCTION SPECIFICATION FOR TUNNELLING

Thesis Proposal. Nasser Marafi. Center & Facility Service Building. St. Joseph Hospital of Orange Patient Care. Proposal

2012 VIRGINIA TECH SCHEDULE OF SPECIAL INSPECTIONS

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

HOME FALLOUT SHELTER modified ceiling shelterbasement

Pulaski County, Virginia Typical Carport Enclosure Details Based on the 2012 International Residential Code

FOOTINGS AND FOUNDATIONS

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

4 EXTREME FOUNDATION PANELS

Eidem Farm Brooklyn Park, MN

Date: September 27, 2018 Project No.:

181 Fremont San Francisco, CA. Tech Report 1 9/12/2014. Caroline Klatman Structural Option Advisor: Dr. Thomas Boothby

A Solid Foundation Solution for Homeowners. from

National Occupational Standards Development Pack for Sub-Structure Work Occupations (Construction)

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes.

Atkinson Engineering, Inc.

Project Seismic Vulnerability Assessment For SFCC District Building 33 Gough Street San Francisco, California 94103

RYAN BIGGS CLARK DAVIS

* RESIDENTIAL PLAN REVIEW *

Building Construction

See the IRC for additional information. See CPD-DS Information Bulletin 100 for Requirements for 1 & 2 Family Dwelling plan submittals.

Residential Patio Cover Specifications

Supplemental Concrete Tilt Up Retrofit Plan Check Correction Sheet (2014 LABC)

Combined Pile Foundation System for a Residential Complex

SPECIAL INSPECTION AND OBSERVATION PROGRAM CITY OF CONCORD BUILDING DIVISION. Project Address:

Thesis Proposal. Matthew R Peyton

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax:

Mandatory Wood Frame Soft-story Retrofit Program PERMITTING AND INSPECTION PROCESS GUIDELINES

Prepared by Elie F. Issa, Eng. D.E.C. August 2016

July 5, 2018 Project No

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

BACKGROUND: SUBSURFACE CONDITIONS:

aggregate piers / vscs

Transcription:

is the installation of temporary or permanent support to an existing foundation to provide either additional depth or an increase in bearing capacity. There are several existing conditions which may lead to the need for underpinning: Construction of a new project with a deeper foundation adjacent to an existing building Settlement of an existing structure Change in use of a structure Addition of a basement below an existing structure 2 Spring Quarter 2018 1

Settlement of existing structures in many cases is caused by lowering of the water table due to tidal fluctuations, wells for a water district, etc. This lowering of the water table can cause the tops of timber piles to decay over time and will require remedial underpinning. 3 With certain soil profiles, rising of the water table can effect a decrease in bearing capacity of the soil causing settlement and require underpinning. Construction of structures on unsuitable bearing material or over compressible layer (peat, organic silts, or poorly compacted backfill) may cause settlement. 4 Spring Quarter 2018 2

Cracks in Buildings Foundation settlement 5 Cracks in Buildings Foundation settlement 6 Spring Quarter 2018 3

To prevent any unexpected settlement of a new structure, it is of utmost importance that proper field investigation be performed, including: Test borings Test pits Laboratory soil tests 7 may also be necessary if the requirements of a structure have changed: When heavier floor loads are imposed When additional floors are added to an existing building Another use of underpinning is to provide extra basement space under existing buildings Exterior walls are underpinned and the interior columns or wall loads are transferred to new columns, resting on new footings placed at the lower elevation. 8 Spring Quarter 2018 4

Determining the Need for When a structure starts showing signs of settlement or distress, it is of utmost importance to establish level readings and offset readings on a daily, weekly, or monthly basis, depending on the severity of the movements. Plotting of these readings will indicate if the movements are decreasing or increasing, and by analysis, determining the need for underpinning or other measures to protect the structure. 9 Methods of Prior to the start of excavation for a new structure, it is advisable to have a professional examine all structures in close proximity to the construction site, to determine whether or not underpinning is necessary. Different methods of underpinning support are: Temporary support with maintenance Jacking Bracket Pile 10 Spring Quarter 2018 5

Temporary Support with Maintenance Jacking If settlement occurs in light structures (i.e., wood-frame garages) that fall within the influence line of an adjacent excavation, the structure will be kept at the same level by means of mechanical or hydraulic jacks. At completion of the work in the adjacent lot, the jacks are replaced with short steel columns and the void is filled with concrete. 11 Methods Temporary support with Maintenance Jacking 12 Spring Quarter 2018 6

Timber-Pile Foundations Existing foundation condition prior to underpinning Step 1: Shore existing construction, excavate approach pit, and expose existing timber piles. Remove top portion of the piles and cut piles at new cutoff elevation. 13 Timber-Pile Foundations Step 2: Install steel plates, drypack, and wedging strut. Transfer load into pile by means of steel wedges. Blown-up detail load transfer Step 3: Placement of concrete encasement, backfill approach pit. 14 Spring Quarter 2018 7

Methods Bracket Pile When both the existing and future structures belong to the same owner, the use of bracket piles is very economical (most municipal building codes do not allow a building to be supported on the foundation that is located on someone else s property). 15 Methods Bracket Pile The steel bracket piles are driven or placed adjacent to the future structure in pre-augured holes which are then backfilled with a lean sand-cement mix. The load is transferred from the structure into the pile through a steel bracket welded to the side of the pile. 16 Spring Quarter 2018 8

Methods Bracket Pile A combination of steel plates, wedges, and drypack is installed to ensure a tight fit between the structure and the bracket. 17 Methods Bracket Pile This type of underpinning can be utilized for structures up to two stories high, depending on the weight of the building and the the quality of the bearing material at subgrade or the new structure. The toe penetration of the piles is determined by the vertical load distribution of the bracket pile. 18 Spring Quarter 2018 9

Methods Bracket Pile The spacing of the piles depends on the load distribution in the existing structure. The maximum spacing should not exceed 8 feet. 19 California Palace of the Legion of Honor San Francisco, California Legion of Honor Memorial, originally built in 1922. The construction of new galleries underneath the existing courtyard required shoring the perimeter of the building with conventional soldier beams, tiebacks and lagging. 20 Spring Quarter 2018 10

California Palace of the Legion of Honor San Francisco, California The courtyard colonnades, the entrance arch and the porch structure of the building needed to be supported during construction. The contractor supported the structures with needle beams spanning between drilled soldier beams and/or existing walls. The structures were jacked to transfer the load to the underpinning elements. [Colonnade: a row of columns supporting a roof] 21 California Palace of the Legion of Honor San Francisco, California New service and ventilation tunnels were added inside and underneath the existing building which required underpinning a total of 46 columns with load of up to 250,000 pounds. of the columns was done using different systems including hand dug piers, rakers supported on heel blocks, shear plates bolted to existing columns spanning between support frames, and drilled piles supporting shear walls built from top down. 22 Spring Quarter 2018 11

Questions? Kamran M. Nemati nemati@uw.edu Architecture Hall Room 130J Spring Quarter 2018 12