Independent Power Producer procurement Improving integration with municipal distributors

Similar documents
Overview of the South Africa s Independent Power Producers Procurement Programme

South African IPP Procurement Programme. December 2016

The South African Renewable Energy Independent Power Producers Procurement Programme (REIPPPP) Lessons Learned

Independent power producer procurement: integrating with municipal distributors

Small scale Hydro Electric Power IPP compliance with legislation and REBID process

7-8 NOVEMBER 2018 CAPE TOWN, SOUTH AFRICA

ACEF Deep Dive Workshop. 5 8 July 2017 Manila, Philippines

Regulatory Framework PPAs and IPPs

Independent Power Producers Procurement Programme (IPPPP) An Overview

Independent Power Producers Procurement Programme (IPPPP) An Overview

business, government and civil society. It is also providing energy at rapidly decreasing cost to the consumer.

Independent Power Producers Procurement Programme (IPPPP) An Overview

Unlocking the Green Economy and Solar PV Industries

Least-cost electricity mix for South Africa by 2040 Scenarios for South Africa s future electricity mix

Least-cost electricity mix for South Africa until 2040 Scenarios to guide the South African power system pathway

Submission from SAIPPA Proposed co-generation (distributed generation) incentive programme

REIPPPP focus on Eastern Cape. at a glance. March 2015 (including Bid Window 4 preferred bidders) New photos. The IPPPP partnership between

How to stimulate the South African rooftop PV market without putting municipalities financial stability at risk A Net Feed-in Tariff proposal

Financial Costs and Benefits of Renewables in South Africa in February 2015

Derisking Renewable Energy Investment

Medium-term System Adequacy Outlook 2017 to 2021

at a glance REIPPPP focus on Eastern Cape Provincial Report Volume 2 September 2016 The IPPPP partnership between

MANCHESTER METROPOLITAN UNIVERSITY, UK VISITING RESEARCH FELLOW, GRADUATE SCHOOL OF BUSINESS LEADERSIP, UNIVERSITY OF SOUTH AFRICA

MEDIUM-TERM SYSTEM ADEQUACY OUTLOOK to 2021

PRESENTATION ON THE INDEPENDENT POWER PRODUCER PROCUREMENT PROGRAMME PORFOLIO COMMITTEE ON ENERGY PARLIAMENT; CAPE TOWN.

Eskom s Single Buyer Office Perspective on renewable energy procurement. Clean Power Africa Conference. 5 September 2012.

Soetwater Wind Farm NERSA PUBLIC HEARINGS. 09 September 2015

The need and desirability of this Project is discussed below, including strategic plans, frameworks and policies applicable to the area and Project.

Future wind deployment scenarios for South Africa

Nxuba Wind Farm NERSA PUBLIC HEARINGS. 10 September 2015

UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES

Are Eskom s concerns relating to Renewable Energy Independent Power Purchase Agreements valid?

NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd

Response to questions around the CSIR methodology to quantify the fuel-saver effect of new power generators in the South African power system

African Utility Week Eskom s s Cogeneration Project. Thursday 31 st May, 2007

Electricity Slide Index Slide 2: Generating Electricity Slide 3: SA Power Grid

The cost and greenhouse gas emissions implications of the coal IPP procurement programme

Solar PV resource for higher penetration through a combined spatial aggregation with wind

Positioning Nelson Mandela Bay for Renewable Energy Manufacturing Opportunities

EMBEDDED GENERATION: THE CITY POWER EXPERIENCE

ERLN Meeting. Renewable Energy and Energy Efficiency. Wolfgang Böhmer. Eskom: Grid Access Unit

Renewable energy: Investing in Africa

Energy Energy Energy Energy Energy Energy Energy

INTERSESSIONAL PANEL OF THE UNITED NATIONS COMMISSION ON SCIENCE AND TECHNOLOGY FOR DEVELOPMENT (CSTD)

Status of CSP and its future in the South African energy mix

NERSA Public Participation Process Klipheuwel Dassiesfontein Wind Energy Facility March 1, 2012

Our Activities, Our Commitment

Economic impacts of South Africa s energy mix

High-renewables scenarios Thought experiments for the South African power system

ELECTRICITY NETWORK TRANSFORMATION ROADMAP: KEY CONCEPTS REPORT SUMMARY DECEMBER 2016

WIND POWER: SOUTH AFRICA S EXPERIENCE AS AN AFRICAN CASE STUDY

The Integrated Resource Plan (IRP) was promulgated in March 2011;

NERSA Consultation Paper

South Africa: Transitioning to a low-carbon economy

Least Cost Electricity Mix for South Africa Optimisation of the South African power sector until 2050

Climate Change and the Carbon Market

GIZ Municipal Solar PV Training Solar Procurement For Local Government

Role in the Independent Power Producer Sector 27 August 2015

Quantifying the capital requirement: 19% RE by 2030

Low Carbon Study South Africa. Xiaodong Wang September 10, 2009

Renewable Energy Auctions: An Overview of Design Options

Renewable Energy Scenarios

Independent Power Producers (IPPs)

Guide and overview to the Independent Power Producer (IPP) Process in South Africa and Eskom. June 2010

COGENERATION PROJECT AT FOUR RAND WATER SITES PRESENTED BY IVEEN MBHELE 29 MAY 2012

South African Mainstream Renewable Power De Aar PV Pty Ltd

Garob Wind Farm. NERSA Hearings Port Elizabeth 10 September NERSA Hearing

Stakeholder Consultation on Draft IEP/IRP 2016

OVERVIEW OF THE ENERGY SECTOR IN ZAMBIA: CASE OF RENEWABLE ENERGY

REFIT comments AND Recommendations to Nersa

Power Purchase Programmes (PNCP & MTPPP)

The Republic of South Africa. Department of Energy

Renewable Auction Mechanism (RAM): New Procurement Tool for Distributed Renewable Generation National Summit on RPS

Exploring waste to energy opportunities. Thembakazi Mali Senior Manager: Clean Energy Solutions

Exploring waste to energy opportunities. Thembakazi Mali Senior Manager: Clean Energy Solutions

South African Renewables Initiative. Unlocking South Africa s Green Growth Potential. Update

(4 November 2016 to date) ELECTRICITY REGULATION ACT 4 OF 2006

Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Planning for the future in uncertain times

Call for Expression of Interest (EOI) to Participate in Proposal Submissions to Build Solar Photovoltaic (PV) Farms in Lebanon

Solar power: The African Opportunity

Solar Energy as a Mitigation Strategy in South Africa. Chipo Mukonza Institute of Corporate Citizenship- UNISA,South Africa

Renewable Energy & Energy Efficiency For Sustainable Human Settlements. SAHF Conference 10 th 13 th October 2010

A mini-integrated resource plan for a commercial entity in Gauteng Province: planning for energy autonomous businesses

Obscure Electricity Planning is Detrimental to South Africa

Sustainable energy solutions for South African local government. A practical guide

Government Gazette Staatskoerant

Carbon Tax Policy Paper. Cecil Morden & Peter Janoska November 2014

Electricity Scenarios for South Africa Presentation to the Portfolio Committee on Energy

Power Integrated Resource Plan Progress Update

RESEARCH REPORT. An assessment of new coal plants in South Africa s electricity future

Market Intelligence Report Renewable Energy 2014

INTEGRATED RESOURCE PLAN UPDATE ASSUMPTIONS, BASE CASE RESULTS AND OBSERVATIONS REVISION 1

Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704)

ACWA Power Business-driven Value Development. May 31, 2016

ELECTRICITY SUPPLY INDUSTRY OF SOUTH AFRICA

CSP Market Status. Solar Thermal Energy Research Group. Alberto Cuellar. Senior Renewable Energy Engineer Mott MacDonald

Renewable Energy in South Africa Resources and Opportunities STIAS Energy Workshop 5 March2013 Stellenbosch

Electricity generation technology choice: Costs and considerations

Transcription:

25 th AMEU Technical Convention 4-7 October 2015 Independent Power Producer procurement Improving integration with municipal distributors Dr Clinton Carter-Brown IPP Office A partnership between: Department of Energy National Treasury Development Bank of Southern Africa Co-authors: John Samuel, Seaga Molepo & Shirley Salvoldi

Role of private sector in procurement of energy Our present generation constraints are severe and debilitating IPPs in partnership with Eskom provide a sustainable and complementary solution to our electricity generation requirements The introduction of private sector electricity generation (complementary to Eskom) offers multiple benefits: Diversifying both the supply and nature of energy production, Introducing of new skills and in new investment into the industry, and Benchmarking of performance and pricing. 2

Context for the IPPPP (Independent Power Producer Procurement Programme) A significant share of South Africa s electricity generation is already produced by Independent Power Producers (IPPs) Required a framework for the procurement of electricity - IPPs to sell power (to Eskom) We have a world-class IPP procurement programme, the results of which have saved South Africa money and reduced loadshedding IPP procurement is being driven by the IPP Office IPPPP The Independent Power Producer Procurement Programme (IPPPP) is a key vehicle for securing electricity capacity from the private Sector for renewable and non-renewable energy sources as determined by the Minister of Energy. 3

Role and mandate of the IPP Office Primary mandate is to secure electrical energy from the private sector for renewable and non-renewable energy sources. - Established (Nov 2010) by the South African Department of Energy (DoE), National Treasury (NT) and the Development Bank of Southern Africa (DBSA) Designed to contribute to the broader national development objectives of job creation, social upliftment and broadening of economic ownership. 4

Procured RE generation capacity REIPPPP capacity procured Capacity (GW) 17.8 GW by 2030 (IRP, NDP) 7 GW procured by 2019 to be operational by 2020 (NDP) 6.9 GW determined 6.3 GW procured (BW 1, 2, 3, 3.5 & 4) 1.9 GW commissioned (operational 1 ) Note 1. As at June 2015 5

IPP competitive tendering (Bid Windows) IPP procurement has been designed with a rolling bid-window programme format which: attracts continued market interest induces increased competitive pressure amongst bidders to offer reduced pricing allows for improvements and lessons learnt with each bid window to be incorporated in the refinement of procurement documentation in the following bid-windows uses standard contracts that avoid negotiations and enables consistency 6

IPP competitive tendering (Bid Windows) cont 7

IPP competitive tendering (Broad benefit) Design of the programme aligns with the National Development Plan to set in motion a virtuous cycle of development growth by recognising the inter-dependency between the desired Vision 2030 outcomes and the socio-economic commitments made by the IPPs in relation to: job creation and skills development economic interest participation by previously disadvantaged persons and local communities localised spend and procurement as well as the general improvement of the lives of people, for example through access to health and education 8

IPP competitive tendering (Procurement of electricity) The IPP programme procures electricity, not a power station: IPP determines the plant location and design (the IPP sits with the associated risks) IPP determines how the plant is designed, constructed and operated IPP manages the risk of delays and cost overruns (impacts their profitability) IPP gets paid for electricity generated (drives efficiency and delivery) The tariff paid to the IPP is firm and fixed for the duration of the Power Purchase Agreement (PPA). The consumer is protected from price increases 9

Renewable Energy REIPPPP progress to date To date there have been 5 Bid Windows (BW) of the REIPPPP BW 1 BW 2 BW 3 BW 3.5 BW 4 Submission date: 4 November 2011 28 preferred bidders 1 425 MW of contracted capacity Signature of the PPAs - 5 November 2012 Submission date: 5 March 2012 19 preferred bidders 1 040 MW of contracted capacity Signature of the PPAs - 9 May 2013 Submission date: 19 August 2013 17 preferred bidders 1 457 MW of contracted capacity Signature of the PPAs - 11 December 2014 (except 2 projects to be signed by mid 2015) Submission date: 31 March 2014 2 preferred bidders 200 MW of contracted capacity Signature of the PPAs - expected mid 2015 Submission date: 18 August 2014 26 preferred bidders 2 205 MW of contracted capacity Announcement of 13 preferred bidders on 16 April 2015 13 additional bidders were announced on 7 June 2015 contributing 6 327 MW in total 10

REIPPP Programme successes (up to June 2015) WITH ONLY THE FIRST 37 IPPs CONNECTED TO THE GRID BY JUNE 2015, THE REIPPPP IS ALREADY CHANGING THE SOUTH AFRICAN ENERGY LANDSCAPE FOR THE BETTER 4.4m Tons CO 2 savings 4.3 Terrawatthours 4.0 Rand billion 1.3 million 19 033 job years 3 Power generated to date using renewable energy procured by the REIPPPP More in financial benefit for the country than its cost 1 Homes equivalent 2 powered by electricity generated from RE Employment opportunities for South African citizens during construction and operation Note 1. Calculated financial benefit (As a result of fuel savings when displacing coal and diesel powered alternatives and the economic benefit of avoiding unserved energy during severe shortfalls what would have resulted in power cuts if RE was not available) minus tariff payments made to IPPs (not reflecting any socio economic or secondary industry benefits); Assessment concluded by Council of Scientific and Industrial Research (CSIR), published August 2015. Note 2. Annual consumption per household based on Eskom data for residential sector. Note 3. Equivalent of a full time employment opportunity for one person for one year. 11

The REIPPPP has attracted significant investment in BW 1, 2, 3, 3.5 & 4 Planned (Total project cost 1 ) Total project costs 193 Rand billion Actuals 2 (Achieved during construction phase) 45 Rand billion Constructions costs to date Local content of which locally procured 65 22 Rand billion Rand billion Local content to date Note 1. IPP data reflects cumulative values over the construction phase and projected operational life (production phase) of the projects (i.e. 20 years). Note 2. Actuals reported for period up to June 2015 12

Pleasing renewables price path Note 1. Contracted (at which power is sold to Eskom) price (in 2015 terms) per IPP was weighted with consideration of the technologies and their relative, projected annual energy contribution (P50). BW3 estimated rate incorporates the peak tariff (270% of base rate) applicable to CSP. Note 2. MAC Consulting report (extract presented by Eskom), EIUG analysis on a levelised cost scenario of Eskom s New Build programme, NERSA media statements (2012). Latest industry estimates are about R1.05/kWh (SAWEA), i.e. R1.23/kWh in April 2015 terms. ) 13

Non-Renewable IPPs In May 2011, the DoE gazetted the New Generation Regulations under the Electricity Regulation Act (ERA). This includes: 2 500 MW designated from coal-fired plants 800 MW of cogeneration increased to 1800MW 3 126 MW of Gas-fired power plants The IPP base-load Coal Programme was released in Dec 2014. It follows the successful bid window approach implemented in the Renewable Programme Co-generation Programmme released in June 2015 Gas Programme is due to be released shortly 14

IPP Programmes and Municipal integration The REIPPPP inherently targets large utility scale renewable energy projects that are generally located in rural areas supplied directly by Eskom. Exceptions include the landfill gas projects The Cogeneration cogen Programme is anticipated to see increasing numbers of projects within municipal distributors There is a need for increased communication and integration with Municipal Distributors The remainder of this presentation is focused on the Cogen Programme and some of its salient design features Further engagement is required with the Municipal Distributors. 15

Eskom (Buyer) PPA Contracting arrangements examples Eskom / Municipality TxA / DxA Implementation Agreement RSA Government Water Authority/ Municipality Water Supply Agreement Project Company Financing Lenders O&M Agreement EPC Agreement Lease/ Land Purchase O&M contractor EPC contractor Land owner 16

What is CoGen? CoGen is the generation of electricity from a generation facility that is integrally linked to a host industrial process and is classified under the following technologies: Type 1: Waste to Energy Type 2: Combined Heat and power Type 3: Industrial biomass 17

Type 1: Waste to Energy Characterized by an energy resource that consists of waste heat or gases from an industrial process Energy resources may be either high temperature exhaust gases that feed a heat recovery steam generator, or gases that may be used as a fuel as they contain a combustible component. 18

BOILER INDUSTRIAL PROCESS Type 2: Combined Heat and Power Simultaneously produce heat/steam for the underlying host industrial process (Host) and electricity for Host consumption, with any excess electricity available for export into the grid ELECTRICITY FOR EXPORT ELECTRICITY OWN USE AND EXPORT EXHAUST STEAM Fuel STEAM TURBINE 19

BOILER INDUSTRIAL PROCESS Type 3: Industrial Biomass Utilise renewable fuel such as by-products from the pulp and paper industry or the sugar industry and can use agricultural or forestry residue of the primary inputs to the industrial process ELECTRICITY FOR EXPORT ELECTRICITY OWN USE AND EXPORT OPTIONAL EXHAUST STEAM Renewable Fuel byproduct STEAM TURBINE 20

CoGen Bid Window 1 Procurement of quick energy BW1 focused on the procurement of additional energy from existing generators Designed to procure additional energy in excess of an existing base-line from existing brown-field cogen installations Maximum 12 Month duration from bid award to Commercial Operation Minimalist approach for bid development and submission Tariff Cap applied to each Technology Type Energy must be supplied into the Host Facility 21

Electrical Connection 22

Year - 5 Year - 4 Year - 3 Year - 2 Year - 1 M 1 M 2 M 3 M 4 M 5 M 6 M 7 M 8 M 9 M 10 M 11 M 12 M 1 M 2 M 3 M 4 M 5 M 6 M 7 M 8 M 9 M 10 M 11 M 12 M 1 M 2 M 3 M 4 M 5 M 6 M 7 M 8 M 9 M 10 M 11 M 12 M 1 M 2 M 3 M 4 M 5 M 6 M 7 M 8 M 9 M 10 M 11 M 12 M 1 M 2 M 3 M 4 M 5 M 6 M 7 M 8 M 9 M 10 M 11 M 12 HIstoric Monthly Energy Output [MWh] Energy baseline Aggregate of Year -5 is Baseline Annual Energy Output Energy Output profile of Year -5 is adopted as the Baseline Monthly Energy HISTORIC GENERATION PROFILE FOR 5 CONSECUTIVE YEARS 23

Grid Connection Grid upgrades are scoped by the Network Service Provider via the typical grid connection application and quotation processes The IPP development timeframes and scheduled commercial operation date would need to consider grid timeframes Any grid upgrades may be a key constraint of the Cogen Programme delivery, and requires careful consideration Even if there is no export of power into the utility grid (all Cogen power is consumed by the Host Plant), it is plausible that grid upgrades may still be required given that the generation may impact network fault levels, power quality and protection Prospective IPPs have been informed of this potential dependency, and have been encouraged to engage accordingly with their Network Service Provider 24

Codes and Agreements CoGen facility must be compliant with the RSA Grid Code and the Utility Interconnection Standards The agreements that will need to be entered into include: Supply, Connection and Use of System Agreements between the Host Facility and the Municipal Distributor Reconciliation Agreement between the Host Facility and Municipal Distributor Reconciliation Agreement between the Municipal Distributor and Eskom 25

Eskom Reconciliation of accounts Physical Power Flows Municipal Distributor Eskom Municipal billing Adjusted by Cogen production Host Facility Host Facility billing adjusted by Cogen production Co-Generator Reconciliation Agreement sets out the terms and conditions on which the energy purchased by Eskom is to be added back onto the Host Facility s electricity account 26

Way forward IPPs are already playing an important role in the South African generation mix Dispersed generation, embedded in Distributor Networks, will increase Such generation presents Distributors with challenges and opportunities Introduces new potential revenue streams (Generation and Wires Charges) Supports efficiency and sustainability Municipal Distributors will need to play an increasingly important role Need to improve communication and integration with Municipal Distributors 27

Thank you for your attention 28

Pleasing renewables price path The REIPPPP is delivering energy at increasingly cost competitive rates BW1 BW2 BW3 BW3.5 BW4 Onshore Wind 1.42 1.12 0.82 0.71 Solar PV 3.44 2.05 1.10 0.86 Solar CSP 3.35 3.13 1.82 1.70 Landfill Gas 1.04 Biomass 1.55 1.52 Small Hydro 1.28 1.17 29

Key REIPPP Energy Triangle 1 facts (for period 11/2013 06/2015) 4 294 GWh REIPPP 2 Actual energy contributed to National Grid of which 1 991 GWh Wind (46%) 2 219 GWh Solar PV (52%) 62 GWh CSP (1,5%) 22 GWh Small Hydro (0.5%) ENERGY Energy access and security Civil society 15% of the Renewable Energy production is available during system peak time (as defined by the Megaflex tariff) Economic growth and development Industry Physical Energy sources Carriers Markets & demand sectors Social Boundary constraints Government R 9.2 billion REIPPP Total payment to all IPPs of which R 2.4 billion In this reporting quarter Environmental sustainability 4.4 Mton CO 2 equivalent RE emissions reduction achieved relative to Eskom generated power (grid EF of 1.015 tco 2 /MWh 3 ) Note 1. Source: World Economic Forum Global Energy Architecture Performance Index Report (2013); Note 2. Energy production (as per contracts) with a 50% probability (P50) of being achieved (refer to explanatory notes at end of this report). Note 3. Carbon accounting for South Africa, UCT, Energy Research Centre (ND)

Contributing to socio-economic and enterprise development Planned (Total project 1 ) Socio-economic development 19 Rand billion Projected (Average per annum over project life 1 ) 955 Rand million Actuals 2 R 76 million (contributed by 37 of 62 operational IPPs that have come online over the last few months) Enterprise development 6 Rand billion 299 Rand million Actuals 2 R 31 million (contributed by 37 of 62 operational IPPs that have come online over the last few months) Note 1. 20 years operational life. Note 2 Actuals will grow exponentially as more projects reach COD; Actuals reported for period up to June 2015 31