OSHA S NEW CRANE STANDARD

Similar documents
MOUNT RAINIER CHAPTER FEDERAL SAFETY AND HEALTH COUNCIL

Cranes and Derricks Standard Summary. April, 2010

ASSEMBLY / DISASSEMBLY POWER LINES POWER LINES. Identify Work Zone. Work Zone

Crane 101. An introduction to mobile cranes by Anthony Crane USA

Cranes & Derricks in Construction. AIHA/ASSE September 17, 2010

Presentation Handouts

Presentation Title. OSHA Cranes & Derricks Subpart CC. October 1, Presenter Name Presenter Title Event Name

Presentation Title. OSHA Cranes & Derricks Subpart CC. Washington Metropolitan Area Construction Safety Association.

THE NEW CRANE STANDARD

Crane Certification FAQs

This page intentionally blank

Effective Date: 10-January Table of Contents

Crane & Derrick Operation Procedures for Construction

Crane Facts. Associated Training Services, Corp.

NCCCO Guide to OSHA s Personnel Certification and Qualification Requirements

Cranes and Derricks in Construction The New 2010 Standards Presented by Rick Callor. URS Safety by Design Webcast

PAGE 1 OF 10 HEALTH, SAFETY & ENVIRONMENTAL MANUAL PROCEDURE: S370 Mobile Cranes Procedure REV /14/2012

Document Revision Change Table Revision Number

CRANE OPERATOR CERTIFICATION BY NOVEMBER 10, 2018

Load Handling (Hoisting) Policy

Introduction. Human Error. Root cause of 90% of construction accidents. The focus of efforts to learn from past mistakes.

CRANE OPERATOR CERTIFICATION BY DECEMBER 9, 2018

Cranes and Derricks in Construction OSHA Narrative on Articulating/Knuckle-Boom Truck Cranes

OSHA Issues Comprehensive Cranes and Derricks in Construction Rule

CONSTRUCTION HEALTH AND SAFETY, AND INJURY PREVENTION Prevent hazards when working with cranes, lifting appliances and rigging on construction sites

Maryland s New Crane Regulation

Load Handling (Hoisting) Policy

Scaffolds. OSHA Office of Training & Education 1

PS 02 PLANT AND EQUIPMENT

Presentation Overview. Background. Coast Crane Company Background. Coast Crane Company TOWER CRANE INSPECTIONS

Scaffolds. OSHA Office of Training & Education 1

The following is Copyright 2009 The Queen s Printer, Saskatchewan

Job Safety Health Quarterly Job Safety & Health Quarterly

Understanding Crane Accident Failures: A report on causes of deaths in crane-related accidents

Dr. Ahmed Hussien Elyamany 2017 Questions

SAFETY FACT SHEETS. Working with and around High Risk Plant Safety Non Negotiable. G-HS-ST Working with and around High Risk Plant

XVI. Attachment 4a Documented Inspection for Wire Rope Slings. Sling #: Capacity (safe working load): Length:

FACILITIES MANAGEMENT OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY AERIAL WORK PLATFORM POLICY 09/06/17 Last Revision

Self-Erecting Tower Cranes. September 2017 Draft Revisions

1 IMHOFF CUSTOM SERVICES INC. AERIAL LIFT POLICY

I. Introduction/Welcome to MAPP

(Construction) Level 2 NVQ Diploma in Plant Operations (Cranes and Specialist Lifting) Level 2 NVQ Diploma in Plant Operations (Extracting)

References. EM , Sections 22 OSHA 29CFR (Subpart L ) UFGS [Latest] ANSI A

CUSP Base Exams and T&D Endorsement Exam Sample Questions and Format

Phone:

Title: Scaffolding Safety Policy. University Division/Department: Environmental Health & Safety Effective Date: October 6, 2017 Page: 1 of 15

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 7

Peter Juhren Corporate Service Manager Morrow Equipment Co. L.L.C. Salem, OR USA. What s New in Tower Crane Standards?

Rocky Top Materials, Inc.

Section 16 TABLE OF CONTENTS Load Handling Equipment (LHE) 16.A General B Personnel Qualifications

Standards Summary Sheet

Mobile Crane Operator (HYDRAULIC) On-the-Job Training Guide

Chubb Construction Risk Engineering. Crane Management

"CAUGHT-IN/BETWEEN HAZARDS IN CONSTRUCTION ENVIRONMENTS"

Scaffolding Safety. Scaffolding

SECTION 16. Load Handling Equipment (LHE)

Below-the-Hook Lifting Devices. July 2017 Draft Revisions

CAL/OSHA ELECTRICAL HIGH VOLTAGE

Lifting Appliances of Ships and Offshore Installations

OCTOBER APRIL 2013 TRAINING PROGRAMS FOR: ON SITE PROGRAMS: Lift Director Assembly/Disassembly Director NATIONALLY ACCREDITED CERTIFICATIONS:

Copies of the written program may be obtained at Where are copies of this written plan kept? (Insert building/room, etc.).

Guideline No.: G-01(201510) G-01 CRANES. Issued date: October 20,2015. China Classification Society

BOOM-SUPPORTED ELEVATING WORK PLATFORM PROGRAM

STANDARD PRACTICE INSTRUCTION

In This Document. Scaffolds Lesson Plan. Overview

Aerial and Scissor Lift

WORKING AT HEIGHT PROCEDURE

Lattice Boom Crane Operator On-the-Job Training Guide

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES

EASTERN MICHIGAN U N I V E R S I T Y AERIAL WORK PLATFORMS PROGRAM

SICKLESTEEL C R A N E S I N C. Experience the Difference. Quality Service Since 1937

ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION

The following is Queen's Printer for Ontario, Occupational Health and Safety Act - R.R.O. 1990, Reg. 851

Mechanic killed by excavator bucket during maintenance

National Safety Council Construction and Utilities Division May 21, 2018

Reliant Holdings Ltd Safety Management System

Scaffolding Procedures

Presentation Outline Latest Requirements on Safe Lifting Operations. Presentation Outline

CRANES & MOBILE LIFTING EQUIPMENT

Scaffolding Safety Procedures

OCCUPATIONAL HEALTH AND SAFETY ACT SCAFFOLDING REGULATIONS

Safe Work Method Statement. 14/4/16 Approved by (Snr Management Rep):

Overhead Power Lines. Corporate Safety Policy Overhead Power Lines. (Cont.)

Subj: WEIGHT HANDLING EQUIPMENT THIRD PARTY CERTIFICATIONS; PREPARATION FOR

SERIOUS: GENERAL RULES, PART 1, RULE 114(1): An accident prevention program was not developed, maintained, and coordinated with employees ---

Are designed to provide a safe working environment, and Govern use of fall protection procedures and equipment.

Rapid Axial Load Testing of Drilled Shafts

Part 2: Mobile cranes

NEW YORK CITY DEPARTMENT OF BUILDINGS. Notice of Public Hearing and Opportunity to Comment on Proposed Rule

Powered Industrial Truck/Forklift Operations Standards and Procedures. Disaster Cycle Services Standards & Procedures DCS SP DMWT

AERIAL LIFT MANUAL. Environmental Health & Safety. Oklahoma State University

State of Queensland (Department of Industrial Relations) 2006

RP 3.0: INSPECTION AND CERTIFICATION OF MASTS. A Recommended Practice (RP) for the Canadian Well Servicing Industry

Orientation to the Trade Annotated Instructor s Guide

BECx Construction Phase Safety

Slings, Rigging and Lifting Equipment

Tailgate Topic Review

RMM 307 Scaffolds/Suspended Scaffolds and Powered Elevated Platforms Safety Program Page 2 November 2016

Operate a dozer (wheeled and tracked)

"WORKING SAFELY WITH SUSPENDED SCAFFOLDING"

Transcription:

OSHA S NEW CRANE STANDARD HOW WILL IT AFFECT ADSC MEMBERS? Disclaimer: The statements and materials provided hereinafter are for general information only. Any statements expressed are those of the author(s) of this document and do not necessarily represent The views of ADSC: The International Association of Foundation Drilling (ADSC-IAFD), nor does the ADSC-IAFD take any responsibility for the accuracy or validity of any statement contained within this document. 1

Introduction Mobile cranes are usually one of the most important, productive, and expensive pieces of equipment used on deep foundation installation projects. Crane operations typically bear the greatest potential for disaster, perhaps more than any other activity on a construction project. 2

Introduction Please note that this presentation is one of many possible interpretations of the new OSHA crane standards. In addition, it only addresses changes made to the federal OSHA standards and may not address any individual state OSHA plan requirements, which may differ. Please consult your state and local requirements as well as the federal requirements before you make changes to your business operations. 3

Overview Crane accidents are often the most costly of construction accidents when measured either in dollars or worse... LIVES! This is a primary reason why OSHA has set into place a new set of safety standards regarding the use of cranes in the United States. 4

Crane-Related Deaths in Construction From 1992-2006 632 crane-related construction worker deaths, from 611 crane incidents 17 multiple deaths incidents resulting in 38 deaths Source: U.S. Bureau of Labor Statistics Census of Fatal Occupational Injuries Researched by the CPWR (The Center for Construction Research and Training) 5

Crane-Related Deaths in Construction 1992-2006 Cause of Death Number of Deaths Percentage Overhead power line 157 25% electrocutions Struck by crane loads 132 21% Struck by crane or crane parts 125 20% Crane collapses 89 14% Falls 56 9% Caught in/between 30 5% Other causes 43 7% Total 632 100% (rounded) 6

History Of Crane Standards In The US 1916 ASME Code of Safety Standards for Cranes (American Society of Mechanical Engineers) Between WW I & WWII - US Army & Navy created Military Crane Safety Standards 1943 ANSI B 30.2 Safety Codes for Cranes, Derricks, and Hoists (American National Standards Institute) 1968 - PCSA Standard #2 Mobile Power Crane and Excavator & Hydraulic Crane Standards (Power Crane and Shovel Association) 1968 - ANSI B30.5, Safety Code for Crawler, Locomotive and Truck Cranes 7

History Of Crane Standards In The US Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, that this Act may be cited as the Occupational Safety and Health Act of 1970. Public Law 91-596 - December 29, 1970 This Act shall take effect one hundred and twenty days after the date of its enactment.(april 28, 1971) 8

History Of Crane Standards In The US OSHA s federal crane and derrick standard for construction has been virtually unchanged since 1971. In late 1998 the 15 member Advisory Committee on Construction Safety & Health (ACCSH) formed a Crane Work Group. In late 2000, the Crane Work Group recommends to ACCSH for OSHA to form a Negotiated Rulemaking Committee. In a July 2002 notice of intent to create a negotiated rulemaking committee, OSHA acknowledged that industry consensus standards had been updated and crane technology had changed considerably over three decades. 9

History Of Crane Standards In The US On June 12, 2003, OSHA announced its decision to establish a Crane and Derrick Negotiated Rulemaking Advisory Committee (C-DAC) under the Negotiated Rulemaking Act (NRA), the Occupational Safety and Health Act (OSH Act) and the Federal Advisory Committee Act (FACA). The Committee would be composed of no more than 25 members including OSHA representatives and a facilitator with an appropriate balance of interests for negotiated rulemaking. Between July 30, 2003 July 9, 2004, OSHA held eleven C-DAC meetings. At 3:15 p.m. EDT on July 9th 2004, C-DAC reached final consensus on all issues. 10

ADSC Participation in Rulemaking 1998 2000 Member of the Crane Work Group 2003-2004 Provided testimony to C-DAC to prevent Drill Rigs from inclusion in the definition of a crane, ground conditions, allow boatswain s chair usage, and power unit mounting on rear of crane. 2009 Provided testimony to OSHA at Public Hearings, endorsing the new proposed rule, as written, including mandatory drug testing similar to DOT testing.

Why Is A New Standard Needed? OSHA 1910.180 and 1926.550 are 39 years old There have been only minor revisions since original publication There were some oversights in the original There have been many technological advances for crane equipment in the last four decades The new standard gets away from SHOULD and includes more SHALL statements Focusing on competent persons and giving more defined descriptions of personnel s responsibilities Use of multiple ANSI/ASME standards and creating their own (some are more stringent) 12

Where Is The Proposed Rule? http://www.osha.gov/doc/proposedrule/cranes_derricks_propos ed_rule.html This is the 1100+ page document describing OSHA s rationale for each section of the proposed rule. The actual standard is the last 100+ pages. 13

Comparison Of Standards OSHA 1910.180 OSHA 1926.550 ASME B30.5 New Subpart N 17 pages 15 pages 46 pages 119+ pages 14

Comparison Of Standards Operator Qualifications 1910.180 nothing 1926.550 nothing 1926.1400 8 pages 15

Comparison Of Standards Floating Cranes 1910.180 nothing 1926.550 1 page 1926.1400 9 pages 16

Comparison Of Standards Crane Signaling 1910.180 nothing 1926.550 nothing 1926.1400 3 pages Use of standard signals is mandatory (special conditions apply) Signalers must be qualified 17

Comparison Of Standards Wire Rope 1910.180 nothing 1926.550 nothing 1926.1400 3 pages 18

Comparison Of Standards Ground Conditions 1910.180 nothing 1926.550 nothing 1926.1400 1 page 19

Comparison Of Standards Assembly & Disassembly 1910.180 nothing 1926.550 nothing 1926.1400 6 pages 20

Comparison Of Standards Power Lines 1910.180 nothing 1926.550 ¼ page 1926.1400 11 pages 21

Comparison Of Standards Inspections 1910.180 4 pages 1926.550 nothing 1926.1400 11 pages 22

Comparison Of Standards Personnel Platforms & Boatswain s Chair 1910.180 nothing 1926.550 8 pages 1926.1400 12 pages 23

What s New? Inspection Criteria Fall Protection Signal Person Qualification Power Line Safety Ground Conditions Authority To Stop Operations Operational Aids Operator Certifications 24

What Cranes Are Included? Types Of Cranes We Use: Crawler Mount Lattice Boom Carrier Mount Lattice Boom Crawler Mount Telescopic Boom Carrier Mount Telescopic Boom Rough Terrain Telescopic Boom 25

Lattice Boom Crawler 26

Carrier Mount Lattice Boom 27

Crawler Mount Telescopic Boom 28

Carrier Mount Telescopic Boom 29

Rough Terrain Telescopic Boom 30

Other Types Of Cranes Pedestal Mount and Conventional Tower Cranes 31

Other Types Of Cranes Cranes On Rails 32

Other Types Of Cranes Carry-deck Cranes Locomotive Cranes 33

Other Types Of Cranes Cranes On Barges Floating Cranes 34

Other Types Of Cranes Derricks 35

Other Types Of Cranes Pedestal Crane Side Boom Tractor 36

Is This A Crane? YES! The new standard defines this type of dedicated or selfcontained hydraulic pile driver as a crane. This is primarily because of its limited lifting capabilities, which are regulated by their load charts. 37

Is This A Crane? YES! This is a Crane with a drill attachment suspended from, and attached to, the crane. 38

What Is Not Defined As A Crane Forklifts Track Loaders Excavators (Track Hoe/Backhoe) Concrete Pump Trucks w/boom Power Shovels Digger Derricks Tow Trucks Vehicle Mounted Work Platforms Self-propelled Elevating Work Platforms Stacker Cranes Mechanic s Trucks With Hoisting Devices Come-A-Longs and Chain Falls Gin Poles For Communication Tower Work Tree Trimming and tree removal work Anchor handling with a vessel or barge using an affixed A-frame Roustabouts 39

Is This A Crane? NO! This is a dedicated or selfcontained drill rig or in OSHA speak Dedicated Drilling Rig used for the installation of drilled shafts, drilled piers or caissons. While it may have some very limited lifting capacities, it is NOT a crane. See exclusion #11 under section 1400 - Scope 40

What Do We Do With Our Cranes? Load and Unload Materials & Equipment Drive & Extract Piling Drill CFA Piling Drill Shafts (Caissons) Set & Extract Casing Set Reinforcing Cages Pour Concrete (Bucket or Tremie Pipe) Others??? 41

Cranes Used to Drill Shafts & Piles 42

Cranes Used To Drive Casing & Piling 43

Cranes Used to Set Rebar Cages 44

New Definitions for Employees A/D Supervisor Appointed Person Competent Person Dedicated Spotter Operator Qualified Evaluator Qualified Person Qualified Rigger 45

Ground Conditions (Before) Most often, the deep foundation contractor is one of the first to arrive to a jobsite. Typically, the site needs some improvement. If underground utilities, vaults, poor soil conditions are not identified before we get onsite, or dealt with once we arrive, bad things can happen to cranes. 46

Ground Conditions (Now) The controlling entity shall: Ensure that ground preparations necessary to meet the requirements in paragraph (b) of this section are provided. (b) The equipment shall not be assembled or used unless ground conditions are firm, drained (except for marshes / wetlands), and graded to a sufficient extent so that, in conjunction (if necessary) with the use of supporting materials, the equipment manufacturer s specifications for adequate support and degree of level of the equipment are met. Locate all hazards that are identified in all available documents and inform the crane user of them. 47

Ground Conditions (Now) Controlling Entity: A prime contractor, general contractor, construction manager or any other legal entity which has the overall responsibility for the construction of the project - its planning, quality and completion. 48

Crane Assembly / Disassembly Lengthy Procedures For Crane Assembly/Disassembly Requirements For Supervision Knowledge and Authority Crew Training And Instructions No Person Under The Boom During Pin Removal Proper Outrigger Blocking Is Mandatory 49

Crane Assembly / Disassembly No part of crane, line or load may be able to reach within 20 feet of a power line during setup. Exceptions: de-energized and grounded power lines or - use of a dedicated spotter or - proximity alarms. Assembly/disassembly below power lines is prohibited, unless line is de-energized and grounded. 50

Power Lines In Crane Operations You must identify work zone and either mark boundaries, use range limiting devices or range control warnings You must determine if any part of crane, line or load could get within: 20 feet of a power line 350kV or less 50 foot for all lines over 350kV If yes, you must either: De-energize and ground Maintain 20 or 50 foot clearance Use Table A and conduct a planning meeting with crew 51

Power Line Minimum Clearances Table A Voltage (kv) Minimum Clearance Distance (feet) Up to 50 10 50 to 200 15 200 to 350 20 350 to 500 25 500 to 750 35 750 to 1000 45 Over 1000 As established by the line owner 52

Power Lines In Crane Operations Some special requirements for working below power lines include training of operators and crew on: Procedures to follow after power line contact Danger of a potential energized zone Operator s emergency procedures Safest means to evacuate equipment Need for crew to avoid approach Safe clearance from power lines 53

Power Lines In Crane Operations All power lines are presumed to be energized unless confirmed to be de-energized by the utility owner/operator AND visibly grounded at the worksite. All power lines presumed to be un-insulated. Shall understand limitations of insulating links, proximity alarms and range control devices, if used. Dedicated spotters shall be trained. There must be at least one electrocution hazard warning sticker conspicuously placed in the cab of the crane. 54

Crane Inspections After Modification After Repair Or Adjustment Post Assembly Each Shift Monthly Annual Comprehensive 55

Crane Inspections Monthly Inspections Documented Kept on file for three months Annual Inspection Documented Detail inspection criteria Functional testing Kept on file for 12 months or next annual inspection 56

Crane Inspections Severe Service Shock load, corrosive atmosphere, etc. Inspect exposed items/conditions Document Not In Regular Use Idle more than three months Monthly inspection must be performed Document 57

Wire Rope Inspection Shift Inspection Monthly Inspection Annual Inspection 58

Safety Devices Mandatory Equipment Crane level indicator Boom stops (except hydraulic booms) Jib stops Locks for foot pedal brakes Integral check valves for hydraulic outriggers Rail clamps and stops for equipment on rails 59

Operational Aids Required equipment must be in service except where specified temporary alternative measures are met: Boom hoist limiting device Luffing jib limiting device Anti two-block device (cranes manufactured after 2/28/92) Exception: lattice booms used for dragline, clam shell, scrap magnet, drop ball, marine operations and pile driving work 60

Operational Aids Boom angle or radius indicator Jib angle indicator (luffing jibs) Boom length indicator (telescopic booms) Load weighing devices (load moment indicators, rated capacity indicators or rated capacity limiters cranes manufactured after 3/29/03 Outrigger position indicators (cranes manufactured after 1/1/08) Hoist drum rotation indicator (if drum is not visible to operator) 61

Fall Protection Fall protection above six feet, with exceptions: While at a work station or going to and from a work station When walking point to point along a horizontal lattice boom that has been lowered to the ground and supported 62

Fall Protection Fall protection is required above 6 feet during non-assembly/ disassembly work, w/exceptions: Employee is at or near the draw-works (when the equipment is running) In the cab On the deck 63

Fall Protection Fall protection must be used when working over 15 feet during the assembly/disassembly process, except when the employee is: At or near the draw-works In the cab, or On the deck 64

Fall Protection Anchorages may be any substantial part of the boom or to any substantial piece on the equipment (using correct fall protection equipment). A fall arrest system is permitted to be anchored to the crane/derrick s hook or other part of the load line where the following requirements are met: A qualified person has determined the set-up and rated capacity meets or exceeds the anchorage requirements The operator is aware it is being used for this purpose 65

Operator Certification / Qualification No physical examinations or mandatory drug testing requirements Re-certification / qualification must be completed every five years Four acceptable methods of certifying employees 66

Operator Certification / Qualification Option (1) certification by an accredited crane operator testing organization Accredited by a nationally recognized accrediting agency Certification is portable Valid for five years Program must be reviewed by a nationally recognized accrediting agency every three years 67

Operator Certification / Qualification Option (2) qualification by an audited employer program Developed or approved by an auditor certified by an accredited crane operator testing organization Auditor is not an employee of the employer Tests should be administered per nationally recognized test administration standards Program shall be audited within the first three months, then once every three years Qualification is not portable and valid for five years 68

Operator Certification / Qualification Option (3) qualification by the US military Qualification is not portable Valid for the period of time stipulated by the issuing entity 69

Operator Certification / Qualification Option (4) licensing by a government entity Must meet or exceed requirements of this subpart Valid only within the jurisdiction of the government entity Valid for time specified by the government entity, but no longer than five years 70

Operator Certification / Qualification Certification / Qualification Criteria: Written Testing on: Controls and operational performance Ability to calculate the load/capacity Procedures for power line contact Site preparation Ability to read manuals/charts relevant to the equipment being operated 71

Operator Certification / Qualification Certification / Qualification Criteria: Pass practical examination Ability to perform a pre-shift inspection Operational and maneuvering skills Application of load chart information Application of safe shut down and securing procedures 72

Operator Certification / Qualification Employer must revoke operators certification if they have reason to believe the employee is not qualified to operate. All programs shall have provisions for retraining employees. The current training records must be on file during the operator s employment. 73

Operator Certification / Qualification Many States, and/or Cities now require operators of essentially all cranes to provide proof of license in addition to certification upon request by an investigator. An employer may be cited by the governing entity for a violation of the requirements, as well as the revoking of the license from the operator. 74

Operator Training Examples Of Training Topics: Identification Of Crane Types Crane Definitions: Rated Strength, Ultimate Strength, Etc. Component Identification Crane Application Operating Procedures Quadrants Of Operation & Their Adverse Effects: "Over Side", "Over Rear" Or 360 Preparing For A Lift Describe How To Pre-plan A Crane Lift ANSI Signal Chart The Principles Of Leverage And Stability The Concepts Of Structural Competence Or Strength Of Materials Understanding Load Charts Wire Rope - Construction, Types, Inspection How To Change Boom Sections (Lattice Boom Cranes) Pick And Carry Operations Perform Crane Inspections Be Able To Answer Questions Pertaining To The Crane Or Its Attachments Know What Required Maintenance Must Be Performed 75

Operator Certification / Qualification There will be a four year phase in process for the employer to get their operators to obtain certification. New operator training will be allowed under the continuous supervision of a certified operator with some minor exceptions. 76

Authority to Stop Operations Whenever there is a concern for safety, the crane operator shall have the authority to stop and refuse to handle loads until a qualified person has determined that safety has been assured. 77

Signal-Person Qualification Training Requirements Know and understand signals to be used, as well as all forms of signals (i.e., voice, hand, radio, etc.) Be competent in the application of the type of signals to be used Have basic understanding of crane operation and limitations, including the crane dynamics involved in swinging and stopping loads and boom deflection from hoisting loads Must be able to effectively communicate to crane operator (i.e., English-English, Spanish-Spanish, etc.) A qualified evaluator must conduct the training 78

Wire Rope Inspection Competent person to conduct visual inspections before each shift, monthly and annually Categorize deficiencies in: Category I Category II Category III 79

Wire Rope Inspection Shift Inspection Before each shift Monthly Inspection All wire ropes, including running ropes (Documented) Annual Inspection At least every 12 months, unless not feasible due to set-up. More detailed, including wire rope that is normally hidden during daily/monthly inspections, etc. (Documented) 80

Wire Rope Category I (A) Significant distortion of the wire rope structure such as kinking, crushing, un-stranding, bird caging, signs of core failure, or steel core protrusion between the outer strands. (B) Significant corrosion. (C) Electric arc (from a source other than power lines) or heat damage. (D) Improperly applied end connections. (E) Significantly corroded, cracked, bent, or worn end connections (such as from severe service). 81

Wire Rope Category I If a Category-1 deficiency is identified, an immediate determination shall be made by the qualified person as to: Replacement of the wire rope, or If the deficiency is localized, the wire rope may be severed at the bad spot and may be continued to be used. 82

Wire Rope Category II Deficiencies in this category are: Visible broken wires, as follows: 1. In running wire ropes: six randomly distributed broken wires in one rope lay or three broken wires in one strand in one rope lay. 2. In rotation resistant ropes: two randomly distributed broken wires in six rope diameters or four randomly distributed broken wires in 30 rope diameters. 83

Wire Rope Inspection Crushed Rope Broken Strands Damaged wire rope must be taken out of service 84

Wire Rope Category II (3) In pendants or standing wire rope: More than two broken wires in one rope lay located in rope beyond end connections and / or one or more broken wire in a rope lay located at an end connection. 85

Wire Rope Category II If a category II deficiency is identified an immediate determination shall be made by the qualified person as to: Based on manufacturer recommendations, either remove or monitor the wire rope for continued deterioration 86

Wire Rope Category II The qualified person determines when to replace the wire rope (no more than 30 days after the deficiency is identified). A qualified person assesses the deficiency in light of the load and other conditions of use and determines it is safe for continued use. A qualified person establishes the parameters of use. All workers who conduct shift inspections are notified. The qualified person s findings and procedures are documented. 87

Wire Rope Category III Category III deficiencies are: Electrical contact to power line Core protrusion or other distortion indicating core failure in rotation resistant wire rope Broken strand 88

Wire Rope Category III If a category III deficiency is identified, operations involving use of the wire rope shall be prohibited until: Wire rope is replaced (ALWAYS with power line contact). Deficiency is localized and problem corrected. 89

Multiple Crane Lifts A multiple-crane lift must be planned with the following requirements: Plan must be developed by a competent, qualified person Plan must be designed to ensure that the requirements of the Subpart are met Lift must be supervised by a competent and qualified person 90

Mobile Cranes On Water Lifting a load that is already on the barge can cause the barge to list when the crane swings or changes the boom angle, changing the equilibrium between the weight of the crane and the weight of the load. The listing of the barge will also cause the suspended load to swing (increase the radius). The crane operator must expect and compensate for this swinging motion. Mobile cranes on barges must use the on water load charts and shall be positively secured 91

Working On The Water Floating Cranes/Derricks & Land Cranes/Derricks on Barges Additional Requirements: Inspections Working with a diver Design requirements of the barge, pontoon, vessel or other means of flotation Defines maximum list and trim 92

Hoisting Personnel (1) When using equipment to hoist employees, the employees shall be in a platform that meets the requirements of paragraph (e). Exceptions: A personnel platform is not required for hoisting employees: Into and out of drill shafts that are up to and including 8 feet in diameter (see paragraph (0) for requirements for hoisting these workers). In pile driving operations (see paragraph (p) for requirements for hoisting these workers). Solely for the transfer to or from a marine worksite in a marine hoisted personnel transfer device. 93

Hoisting Personnel For Drilled Shaft Entry: A signal person shall be stationed at the shaft opening. The employee shall be hoisted in a slow, controlled decent and ascent. The employee shall use personal fall protection equipment, including a full body harness, attached independent of the crane/derrick. The fall protection equipment shall meet the applicable requirements in 1926.502. The boatswain s chair itself (excluding the personal fall arrest system anchorages), shall be capable of supporting, without failure, its own weight and at least five times the maximum intended load. 94

Mandatory Training Overhead power lines Signal persons Competent/qualified persons Operators Crush/pinch points Tag-out 95

Summary Many operators still believe that their seat of the pants feeling will be sufficient to avoid an accident. Nearly half of all crane accidents are caused by improper support. Site managers often know less about the crane s lifting capacity than the operator does, but who is giving the orders? Many operators cannot read and interpret the load chart information correctly. We constantly require at least 100% of the machine 100% of the time we use them. This presentation is a 101 or Cliff Note version of the new OSHA crane standard. You need to read it and interpret it for yourself. 96