EXHIBIT NO. 1 BUILDING REMEDIATION AND REDEVELOPMENT PLAN. Category #1: Work that must be done to cure dangerous and hazardous conditions

Similar documents
OBJECTIVE 1.1: To establish the acceptable use and capacity of each building.

Business License Application

Town of Falmouth FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage COSTS FOR SUBSTANTIAL IMPROVEMENTS / REPAIR OF SUBSTANTIAL DAMAGE:

Lealman Community Redevelopment Area Non-Residential Improvement & Demolition Grant Program Application Package

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

University of Akron. Addendum No. 2. For. Zook Hall Renovation Phase 2A Abatement & Demolition Project #: UAK120015

CITY OF CRANSTON RESIDENTIAL PERMIT PROCEDURE BASEMENT RENOVATION

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

Connecticut Housing Finance Authority. Construction Guidelines: Environmental & Hazardous Materials Review 2018

NEW MIDDLE SCHOOL PROJECT

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

Commercial Tax Abatement

TOWNSHIP OF UPPER DEERFIELD

COMMISSION ON CHICAGO LANDMARKS NOTICE OF A REGULAR MEETING

CODE ANALYSIS REPORT SECOND FLOOR

ONE AND TWO FAMILY DWELLING PERMIT APPLICATION REQUIREMENTS

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

City Of Mendota Construction Procedures

Table of Contents Chapter 1 INTRODUCTION Chapter 2 DEFINITIONS Chapter 3 DELIVERABLES Chapter 4 BASIS OF DESIGN

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

CITY OF TARPON SPRINGS, FLORIDA SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNERS

Appendix 2: Term Sheet. SECTION 37 TERM SHEET FOR CITY SPACE AT THE CONDOMINIUM TO BE CONSTRUCTED AT 200 DUNDAS STREET EAST (the "Project")

NEW MIDDLE SCHOOL PROJECT

DOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.

SAVE YOURSELF TIME AND MONEY! PLEASE READ THE FOLLOWING INFORMATION:

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS

City of Galax BUILDING PERMIT APPLICATION

ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES

ORDER OF AN EXECUTIVE OFFICER UNFIT FOR HUMAN HABITATION

MATERIAL ALLOWANCES AND UNIT PRICES

TOWN OF BELMONT, NH - TOWN CENTER FACILITIES - CONCEPTUAL PROJECT BUDGET December 20, 2018

TRIAD ENGINEERING CONSULTANTS, INC.

CTA Capital Construction Update August 8, 2007

COMMERCIAL SUBMITTAL PACKET

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

ADDENDUM 2 - JULY 14, 2015

ADDENDUM NO. 1 FOR RENOVATIONS TO LINCOLN ANIMAL SHELTER RFP # February 1, 2018

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE Information and Required Forms for Structures in Flood Zones AE & VE

MECHANICAL M-1 LEGEND AND DETAILS M-2 FLOOR PLAN - DUCTWORK M-3 FLOOR PLAN - PIPING

APPENDIX 3C DOMINION HOTEL SPECIFICATIONS

NOTICE TO APPLICANT WARNING TO OWNER AND AFFIDAVIT

Administrative Offices

SUBSTANTIAL IMPROVEMENT

DIVISION 02 SELECTIVE DEMOLITION

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

REQUEST FOR QUALIFICATIONS ARCHITECTURAL/ENGINEERING SERVICES

Are any structural assemblies fabricated off-site? Yes No

DESIGN. Challenges of Aging Infrastructure 6/24/2014. Al Tursi, Property Development Specialist / YMCA of the USA

1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department.

ORDER OF AN EXECUTIVE OFFICER CLOSED FOR TENANT ACCOMMODATION PURPOSES

Hazardous Materials G

PLUMMER ELEMENTARY SCHOOL

DRAFT 9/28/09 ALLEY MAINTENANCE Q

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION

LUFacilities Policy Service Level Agreement v1.1

CITY OF TROY, MISSOURI Building Permit Application. Type of Permit: Residential Commercial. Company: Contact person: Address # Street Name:

2016 SAN FRANCISCO EXISTING BUILDING CODE AB-110 ADMINISTRATIVE BULLETIN. Building Façade Inspection and Maintenance

LASALLE - BACKUS EDUCATION CAMPUS

COMMERCIAL PROJECT INFORMATION

Columbia County Health Care Center Added Amenities

Building Inspection Report

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

MAURY ELEMENTARY SCHOOL

SUNY Hospitals & A Healthier New York. Capital Briefing March 1, 2013

CITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

UCC CONSTRUCTION PERMIT APPLICATION INSTRUCTIONS

8.0 Maintenance Administration

STATE UNIVERSITY CONSTRUCTION FUND

Property Condition Assessment

Appendix J - Custom Uniformat for EDU Migration

Commercial Submittal Packet

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

Exclusively For Sale. Burlington Free Press Complex College Street, Burlington, Vermont

Change of Coordinating Registered Professional (CRP) or Registered Professional (RP)

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE

Lot#_ Subdivision/Land Development: Phase: Section:_. NON-RESIDENTIAL (Commercial)

Chapter 13C GREEN BUILDING REQUIREMENTS

NEWPORT OFFICE CENTER Washington Boulevard, Jersey City, New Jersey

Phoenix Building Construction Code Updated Amendments to the Administrative Provisions

* RESIDENTIAL PLAN REVIEW *

BUILDING PERMIT APPLICATION

CITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS STATEMENT OF QUANTITIES. Item No. Description Quantity Estimated Mobilization 1 LS

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Franklin Hall Renovation TABLE OF Document Indiana University Bloomington

BUILDING ASSESSMENT REPORT for NMSU GREENHOUSES at NEW MEXICO STATE UNIVERSITY LAS CRUCES, NEW MEXICO

Commercial Construction Reference Guide

2) These Standards are available on the University s website at:

PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION

HISTORIC AND ARCHITECTURAL REVIEW COMMISSION Administrative Approval Guidelines 1

DESIGN & CONSTRUCTION GUIDELINES

Minimum Standards for Building Occupancy. Safety Resources

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements

Kastenmeier Federal Courthouse. Milwaukee Courthouse Renovation

Minnesota Healthcare Engineers Association, Fall Conference. Bob Dehler, P.E. Engineering Program Manager September 14, 2017

ADDENDUM No. 1 July 11, 2013 ASBESTOS ABATEMENT SPECIFICATIONS. Crawlspace Abatement and New Beginnings Academy

Transcription:

EXHIBIT NO. 1 BUILDING REMEDIATION AND REDEVELOPMENT PLAN Category #1: Work that must be done to cure dangerous and hazardous conditions identified by the City. This work must begin immediately upon receiving preliminary approval from NPS and completed by the dates listed below: Exterior masonry work, west elevation Begin work on repair and restoration of the entire Western building elevation facade by August 26, 2016. Repair and restore entire western building elevation facade by Oct 31, 2017. Repair (a) the entire west elevation facade, (b) that part of the east elevation facade over the Congress Expressway and (c) the underside of the building over the Congress Expressway by June 30, 2018. Repair the underside of the building located above the rail line platform and rail line tracks Complete temporary stabilization repairs to remediate all imminently hazardous conditions detailed in the Klein and Hoffman, Inc Condition Assessment Report titled "Parcel H (Old Post Office)" dated March 5, 2014 to that portion of the K~~

underside of the building over the rail line platform and rail line tracks by March 31, 2017. After consulting with Amtrak, provide the City with a written plan and schedule for the iepair of that portion of the underside of the building over the rail line platfoim and fail line tracks. This task shall become effective within 180 days after the Effective Date of the Agieed Order. Repair that portion of the underside of the building over the Easement area pursuant to Item #17 above by June 1, 2018. Temporary Roof 2017. Remove the existing roof and install the new temporary roof by March 1, Elevators The term "operating elevators" means elevators that have been inspected and certified on a temporary basis by the Department of Buildings and Fire Department. By December 31, 2016, use best efforts to provide at least three (3) operating elevators to provide access to the building by emergency responders. The three elevators shall be: (1) Passenger Elevator #17 along the Harrison side of the building; (2) Freight Elevator #10 near the middle of the building and (3) another ~:

passenger elevator on the Van Buren side of the building. In the event 601W is unable to finish the aforementioned work by the deadline contained herein, then 601W shall provide the Fire Department a timetable and new deadline by which 601W will provide an operating passenger elevator on the Van Buren side of the building. By August 31, 2020, inclusive of the three elevators referenced in the foregoing elevator work, provide at least six (6) operating elevators, with at least one (1) on each side of the building and at least one (1) in the middle of the building, to provide access to the building by emergency responders. Two (2) of the operating elevators shall be located along the Van Buren side of the building; Two (2) of the operating elevators shall be located along the Harrison side of the building and Two (2) of the operating elevators shall be located in the middle of the building. Install new elevators by August 31, 2020. Category #2: Work that must be done following approval by state and feds to avoid jeopardizing availability of tax credits. Part II application to be submitted to NPS by July 31, 2016. Work to be started immediately after Part II approval received given by NPS: Begin work on demolition of all ductwork, piping and overhead passageways and asbestos removal by August 15, 2016. 37

Begin inspection of the northern, southern and eastern building elevation facade and, thereafter, begin work on repair and restoration of the facade by September 1, 2016. Remove all damaged walls by June 30, 2017. Begin work on installation of new windows by March 1, 2017. Install new windows by March 2, 2020. Install new HVAC system by October 5, 2020. Complete all interior demolition woik and properly dispose of all asbestos materials by using licensed asbestos abatement contractors by April 17, 201J. Renovate the historic lobby, building amenities aild interior and exterior common areas by October 1, 2020. Install new permanent roof by December 21, 2019. By March 1, 2017, remove the existing exhaust fans and install new fans and ductwork where necessary and install new Fans #5a and 5b before installing any other new fans. Category 3: Work that can begin immediately which does not require NPS approval:

Provide temporary utility service throughout the building by September 5, 2016. Remove all moldy carpeting by February 28, 2017. Install new fire alarm system by May 31, 2019. Install new electrical system by October 5, 2020. Install new plumbing system by October 5, 2020. By March 1, 2017, use best efforts to maintain exhaust fans in a safe, sound and working condition at all trines until the new fans are installed. The phrase "at all times" means 24 hours per day, seven days per week. Conduct weekly tests and evaluations to ensure the exhaust fans are operating at the optimal level of efficiency. The decommissioning of existing exhaust fans and the installation of any new exhaust fans shall be pie-approved by Amtrak and the Fire Depaitinent and individually sequenced to ensure 601W's compliance with this Agreed Order and the Easement. 601W has completed the work to repair of Exhaust Fan #2. Staring on the Effective Date of this Agreed Order, maintain Exhaust Fan #5A and 5B and keep in operation subject to the work referenced in this exhibit regarding removal of the existing exhaust fans and installation of new fans and ductwork where necessary and installation of new Fans #5a and 5b.

Final rehabilitation work must be completed by 2021 Rehabilitate the entire building in accordance with City approved plans and permits and bring the Subject Property in full compliance with the Municipal Code of Chicago by December 31, 2021. Additional Work Maintain the existing dry standpipe system, which includes but is not limited to all access points and existing standpipes, until a new sprinkler system is installed. Remove all damaged flooring to the extent the work does not affect applications for Historic Landinaik tax credits by September 30, 2017. Begin work on installation of the new electrical, plumbing, HVAC and fire protection systems by November 1, 2017. Begin work on renovation of the historic lobby, building amenities and interior and exterior common areas by November 1, 2018. By December 31, 2018, repair (a) the entire north elevation facade; (b) the entire east elevation facade; (c) the entire south elevation facade; and (d) submit a ' final critical examination report to the Building Department once all facade work is completed.

Install the first 12 new high-speed elevators by December 31, 2018. 41