STUDY REPORT SR234 (2010) Investigation into the Performance of Brick Veneer Walls Installed with Urea Formaldehyde Foam Insulation A Case Study

Similar documents
Adhered Veneers and Inward Vapor Drives: Significance, Problems and

Adhered Veneers and Inward Vapor Drives: Significance, Problems and

Regarding the compliance of three types of schist wall cladding systems proposed for future houses located in the Queenstown and Arrowtown areas

Bonaldi (Australia) Pty Ltd

National Construction Code Series (NCC) Building Code of Australia (BCA)

wall underlay Product BRANZ APPRAISAL No. 695 (2010) Scope Thermakraft Industries (NZ) Ltd PO Box Botany Manukau 2163 Auckland

WATERGATE-PLUS 295 FIRE RETARDANT WALL UNDERLAY. Product. Scope. Appraisal No. 695 [2017]

Wall Selection Guide Section 1.1

SOLITEX EXTASANA WALL PROTECTION MEMBRANE. Product. Scope. Building Regulations. Appraisal No. 822 [2013] Appraisal No. 822 (2013) Amended 06 May 2014

Determination 2015/048

Determination 2015/069

STUDY REPORT SR 299 (2013) Rigid Sheathing and Airtightness in New Zealand. GE Overton

Brick Walls MTI. Rainscreen Retrofit for. Flood Recovery Hurricane Recovery Restoration Flood Resilient Retrofit. Guide to Wet Flood-Proofing

Specifications. Some details shown in this document have been reproduced from CCANZ document CP 01.

The refusal to grant a building consent for retrofitting foam wall insulation in a house at 192 Vinegar Hill Road, Kamo

MASONRY. masonry wall construction. chapter 10 SUBJECT

PRODUCT CERTIFICATE THIS IS TO CERTIFY THERMAKRAFT STEELWRAP 290 WALL UNDERLAY

PAULOID SYNTHETIC ROOFING UNDERLAY. Product. Scope. Building Regulations. Appraisal No. 984 [2017] Appraisal No. 984 (2017) BRANZ Appraisals

Concrete Soffit Direct Fix

The code-compliance of top vented cavities proposed for the wall cavities to two Gisborne school buildings

SYNTHETIC SELF SUPPORT ROOFING UNDERLAY

NZ Brick Distributors Canterbury Clay Bricks Clay Bricks Ltd Brick and Stone Imports T/A Midland Brick NZ Full contact details are given on page 9.

Henri Fennell, CSI/CDT ABX 2015

WATERTIGHT ROOF UNDERLAY. Product. Scope. Building Regulations. Appraisal No. 938 [2017] Appraisal No. 938 (2017) BRANZ Appraisals

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING

Index. STP779-EB/Jul. 1982

TRADE-COURSE DPC AND FLASHING. Product. Scope. Building Regulations. Technical Specification. Appraisal No. 849 [2014] Appraisal No.

Building Regulations

Acceptable Designs for Timber Framed Parapet Walls

PINK BATTS INSULATION. Product. Scope. Building Regulations. Appraisal No. 238 [2012]

Evolution of Wall Design for Controlling Rain Penetration

Figure 2. By John H. Koester

Groundwater Seepage. Causes of Basement Seepage and Leaks Hydrostatic Pressure

Flood Resistant Construction Using Closed-Cell SPF

nu-wall aluminium vertical cladding system

PREVENTING MOISTURE PROBLEMS IN TIMBER-FRAMED SKILLION ROOFS. Issue525

1. The matter to be determined

NU-WALL ALUMINIUM VERTICAL CLADDING SYSTEM. Product. Scope. Appraisal No. 556 [2007] Appraisal No. 556 (2007) Amended 20 November 2015.


SOLITEX EXTASANA ADHERO SELF-ADHESIVE UNDERLAY. Product. Scope. Appraisal No. 989 [2017] Appraisal No. 989 (2017) BRANZ Appraisals

SUPERCOURSE 500 DAMP-PROOF COURSE AND CONCEALED FLASHING. Product. Scope. Building Regulations. Appraisal No. 329 [2016]

Determination 2013/034

WHOLE-WALL R-VALUES IAN R. COX-SMITH

CAVIBAT ROOF BATTENS. Product. Scope. Building Regulations. Appraisal No. 992 [2017] Please Note: Roof underlay not shown under flashing for clarity.

Refusal to issue a building consent for a house with insulated concrete walls at 11 York Road, Riversdale, Southland

Product. BRANZ APPRAISAL No. 789 (2012) Scope. Hard as Rocks Ltd PO Box 1703 Taupo 1351

FirstEnergy Program Overview

WeatherSmart Air Barrier Installation Guide

THERMAL MASS CHAPTER 6. Understanding thermal mass. Seasonal effects of thermal mass

PREMIER INSULATION. Product. Scope. Building Regulations. Technical Specification. Appraisal No. 509 [2014]

How do you install yours?

THE THERMAKRAFT ONE WRAP SYSTEM. Product. Scope. Appraisal No. 962 [2017] Appraisal No. 962 (2017) BRANZ Appraisals

Keene Building Products

TECHNICAL SHEET. The material properties and use of clay brick. Teaser

DuPont Tyvek Wall Underlay Install Guide

ECOPLY BARRIER FOR STEEL. Product. Scope. Appraisal No [2018] Appraisal No (2018) BRANZ Appraisals

Innovative Passive Ventilation Water-Resistive Barriers How Do They Work?

BUILDING SCIENCE CORPORATION DIGEST OF INSULATED METAL PANELS PERFORMANCE REDEFINED

Pella 250 Series. Wood Frame Construction with Vinyl Siding... V250-ID-888 Wood Frame Construction with Brick Veneer...

Incorporating Insulating Sheathing into the Design of the Thermal and Moisture Management System of the Building Enclosure

weathertex weatherboard direct fixed

QUICKFLASH READY- MADE FLASHINGS. Product. Scope. Building Regulations. Appraisal No. 688 [2018]

Drainage and Retention of Water by Cladding Systems

GypLyner. GypLyner. Metal framed wall lining system. All our systems are covered by SpecSure when using genuine Gyproc and Isover products.

EZYCORNER CAVITY FLASHING. Product. Scope. Building Regulations. Appraisal No. 920 [2016] Appraisal No. 920 (2016) BRANZ Appraisals

A Study of the Rainscreen Concept Applied to Cladding Systems on Wood

Detailed heat, air and moisture transport modelling in cavity walls ::::::: M. Van Belleghem, M. De Paepe M. Steeman L. De Backer & A.

ECOPLY BARRIER RIGID AIR BARRIER. Product. Scope. Building Regulations. Appraisal No. 827 [2014] Appraisal No. 827 (2014) Amended 21 August 2017

METRA INTER- TENANCY WALL SYSTEM. Product. Scope. Appraisal No. 985 [2018] Appraisal No. 985 (2018) BRANZ Appraisals

Regarding the code-compliance of stone cladding proposed for the recladding of a house in Remuera, Auckland

SIKAFLEX MS (BUILDING SEALANT) Product. Scope. Appraisal No. 311 [2013]

Building Science Control Layer Glossary. Façade Visible exterior face of a building, usually vertical or nearly so, but imprecisely used.

Insulation Installation

EXTERIOR WALLS. exterior wall systems, cladding w/ masonry. chapters SUBJECT

Bituminous Building Paper

MLC MASONRY AND BRICK PLASTER SYSTEM. Product. Scope. Appraisal No. 839 [2013] Appraisal No. 839 (2013) BRANZ Appraisals

Refusal by a building consent authority to amend a building consent for re-cladding of a house at 117 Waldorf Crescent, Orewa

Moisture risks of passive retrofitting one town house for the adjacent conventional neighboring structures

Insulating Basements: Part 1 Fundamentals

Specification & Installation Guide June 2011

Innovating Continuous Exterior Insulation. Theresa A. Weston, PhD. 1

WHATEVER THE CHALLENGE, PHILLIPS HAS YOU COVERED.

Thermakraft FIRE RETARDANT SELF SUPPORTING ABSORBENT BREATHABLE SYNTHETIC NON-WOVEN ROOF UNDERLAY STRENGTH BREATHER SHEET WATER RESISTANCE

BEAL Appraisal Certificate The PLASTERCRETE AAC Wall Panel System

FLASHCLAD HORIZONTAL WEATHERBOARD CAVITY CLADDING SYSTEM. Product. Scope. Appraisal No. 800 [2013] Appraisal No. 800 (2013) Amended 05 February 2016.

Expires MAY 2017 ThermaX B - a thermal break for use on steel framing. Description of Product

ThermaX B - a thermal break for use on steel framing

weathertex sheet Product BRANZ APPRAISAL No. 514 (2006) Scope Weathertex Pty Ltd P O Box 21 Raymond Terrace NSW 2324 Australia

11/09/2018 LBP licence classes

A Sto QA Form is required to be filled out by the various parties involved for the Sto Warranty.

MONOTEK SHEET - CAVITY CONSTRUCTION

Refusal of a code compliance certificate for a building with a monolithic cladding system: House 9

Building Enclosure Concept Design Checklist

STUDY REPORT No. 152 (2006)

nu-wall direct fixed Product BRANZ APPRAISAL No. 557 (2007) Scope Aluminium Product Brands NZ Limited 15 Gabador Place Mt Wellington Auckland

External Steel Stud and Top Hat Walls. Details SYSTEMS 176 NON-FIRE RATED SYSTEMS 176 FIRE RATED SYSTEMS 178 BRICK VENEER SYSTEMS 183 INSTALLATION 185

Laboratory tests and modelling to investigate the effect of flooding on mineral wool cavity insulation batts in masonry walls

SURESILL WATER MANAGEMENT GUIDE

THERMAKRAFT ALUBAND WINDOW FLASHING TAPE. Product. Scope. Building Regulations. Appraisal No. 878 [2014]

Transcription:

STUDY REPORT SR234 (2010) Investigation into the Performance of Brick Veneer Walls Installed with Urea Formaldehyde Foam Insulation A Case Study M.J. Bassett, I Cox-Smith, M.E. Hearfield, M.S. Jones, S McNeil, N.J. Marston & G.E. Overton BRANZ 2010 ISSN: 1179-6197

Contents Page 1. EXECUTIVE SUMMARY... 3 2. LABORATORY STUDIES... 3 2.1 Effect of Airfoam on Water-Managed Cavity... 3 2.2 Effect of Airfoam on Humidity and Timber Moisture Content... 7 3. LIMITATION... 10 4. REFERENCES... 10 Figures Page Figure 1: Water applied through a porous tube (D4864)... 5 Figure 2: Leakage observed 2 minutes after start of test (D4864)... 6 Figure 3: Leakage observed 6 minutes after start of test (D4864)... 6 Figure 4: Leakage well established 43 minutes after start of test (D4864)... 7 Figure 5: Brick veneer cladding on BRANZ test building... 8 Figure 6: Thermal image of brick veneer test sample during drying stage after Airfoam installation... 8 Figure 7: Framing and instrumentation layout for test building sample... 9 Figure 8: Average Results from Brick Veneer Walls in Test Hut... 9 Tables Page Table 1: Observations during test... 5

1. EXECUTIVE SUMMARY Work to evaluate the properties of urea formaldehyde foam insulation (UFFI) and the effect UFFI has on the moisture management processes within brick veneer construction has been completed. This work examined the tendency for water running down the inner face of a brick veneer wall to be transported across cavity fill insulation to the position of the wall wrap. The results indicated that the foam fill in the water managed cavity has provided drainage paths to the wall wrap position, and so does not meet New Zealand Building Code criteria in that there should be no systemic water bridging from the back of the cladding to the wall wrap position. Further work to monitor the humidity and timber moisture content of cavity filled brick veneer walls has also been completed. The results indicate that the drying of the timber framing after UFFI installation is a slow process with timber moisture contents still above the pre-uffi levels several weeks after installation. A more detailed assessment of the weathertight characteristics of cavity filled brick veneer walls would be needed to understand the range of application in buildings that would be consistent with clause E2 External Moisture of the New Zealand Building Code. This would involve an examination of field evidence and the potential for ventilation drying from the back of the cladding. This is outside the scope of this report. 2. LABORATORY STUDIES 2.1 Effect of Airfoam on Water-Managed Cavity A sample wall (D4864) was constructed using 2.4m x 2.6m flat panels with 95mm x 45mm H3.1 timber frames clad with red Monier 90 series bricks on a stepped concrete foundation to give a 40mm weathertightness cavity. The wall was constructed with galvanised brick ties and weep holes at appropriate intervals, and had clear Perspex sheets fixed as a building underlay. UF foam was injected into the weathertightness cavity from the outside, using holes drilled through the mortar joints of the brick veneer by an Airfoam applicator on 12 February 2010. The UF foam was installed behind the brick veneer and in front of the clear Perspex sheet. The measurements described examine the tendency for water running down the inner face of a brick veneer wall to be transported across cavity fill insulation to the position of the wall wrap. Airfoam insulated the water managed cavity of a brick wall 2.4 m wide by 2.7 m high with UF foam in a laboratory at BRANZ (D4864). After a period of two months to dry out the insulation, water (coloured with fluorescein dye) was applied to the back of the brick veneer to test for the transfer of water back to the plane of the wall wrap. The test applied was an adaption of the Water Management Testing procedure in verification method E2/VM1 1 for cavity walls. It applied the criteria that there should be no systemic water bridging from the back of the cladding to the wall wrap position. A more detailed assessment of the weathertight characteristics of cavity filled brick veneer walls would be needed to understand the range of application in buildings that would be consistent with clause E2 External Moisture of the New Zealand Building Code. This would involve an examination of field evidence and the potential for ventilation drying from the back of the cladding. This is outside the scope of this report.

During the 1980s work was undertaken 2 at CSIRO by E.R. Ballantyne and D.R. Dubout investigating the suitability of various insulation materials to fill the cavity in double brick cavity construction. The problem with this practice is that introducing any material into a cavity designed for moisture management may increase the tendency for water to bridge the cavity, leading to damp interior linings. The work of Ballantyne proposed two test methods and water flow schedules to determine the likelihood of water transport in a given material. Both methods involve containing the insulation against the face of a brick wall representing the outer leaf of a double brick building. Where the two methods differ is in the means of applying water to the junction between the brick and the insulation. A mode 1 style test involves building the wall into one face of a pressure box and applying water to the face of the wall simulating the outside of the building. An applied pressure difference is used to drive water through the wall into contact with the insulation material, which therefore simulates the water leakage process. Alternatively, in the mode 2 test, water is simply applied to the inner face of the wall and allowed to drain down the interface between the wall and insulation. New Zealand Building Code requirements for controlling external moisture were revised in 2005 in response to a systemic leaking building problem. The new Acceptable Solutions 3 in E2/AS1 stipulated the use of cavities more widely than before, and defined weathertightness performance expectations for cavity walls in Verification Method E2/VM1 2. The test sequence in E2/VM1 is significantly different to that proposed by Ballantyne. Firstly, it is designed to protect timber framing inside a wall from water, where the Ballantyne test applied to brick/block veneer walls with no timber (or other material likely to be damaged by water). Consequently, the failure criteria in the two test methods are different. In E2/VM1 the failure criteria is water reaching the building wrap where in the Ballantyne method it is water reaching the internal wall lining. The second important difference between the two methods is that the E2/VM1 test sequence calls for a drainage path on the back of the cladding that is independent of the weathertightness characteristics of the cladding. The test actually creates leakage paths through the cladding to ensure that water reaches the drainage path. The test applied in this report followed this approach by simply allowing water to drain down the back of the cladding. Brick veneer walls are known to be relatively porous and have been designed to include a water managed cavity throughout their history of application in New Zealand. Cladding water leakage studies at BRANZ 4 have measured leakage rates through brick veneer walls of 0.04 l/m 2.min. and this rate has been used to calculate a target water application rate of 0.26 l/min for application at the head of the test wall. The test brick wall measuring 2.4 m wide by 2.7 m high was built in the laboratory and fitted with a porous tube (see Figure 1) to feed water to the back of the cladding. The dosing rate was controlled by a peristaltic pump, which was later measured using a catch and weigh method. The wall wrap was replaced in this test wall with a sheet of transparent Perspex to ensure that any water leakage would be seen. It was noted that water tended to initially to flow down the wall in defined trails (see Figure 1) but that in time, the flow spread out as the full surface of the brick wall became wet.

Figure 1: Water applied through a porous tube (D4864) The following sequence of events was recorded after dosing was started at 10:37 am on Friday 9 th April 2010. Time Observation See Figure 10:37 am Start of test 10:39 am First signs of water at the wall wrap position Figure 2 10:43 am Second sign of water at wall wrap position Figure 3 11:20 am Significant leakage observed and test terminated Figure 4 Table 1: Observations during test The dosing flow rate was measured and found to be 0.174 l/min, somewhat less than the target rate of 0.26 l/min. Figure 2 to Figure 4 show water reaching the wall wrap position only minutes after the start of water leakage down the back of the cladding. This is evidence that the foam fill in the water managed cavity has provided drainage paths to the wall wrap position.

Figure 2: Leakage observed 2 minutes after start of test (D4864) Figure 3: Leakage observed 6 minutes after start of test (D4864)

Figure 4: Leakage well established 43 minutes after start of test (D4864) Masonry veneer walls have a record of satisfactory weathertight performance in New Zealand. They provide acceptable cladding solutions for high risk buildings (up to risk score 20) that could include a number of design features associated with rain water leaks. Filling the water managed cavity with insulation products potentially reduces the acceptable risk score to somewhere in the range 0 6, in line with many other direct fixed claddings. At this time, brick veneer without the traditional drained and ventilated cavity is not listed as an acceptable solution in E2/AS1 3. It falls into the category of specific design until further testing and an examination of field performance records can be used to recommend a risk score. The Airfoam insulation cavity fill was observed to have shrunk away from the brick veneer cladding, creating a potential drainage and ventilation passage down the back of the brick veneer. Because the cavity formed was rather less than the minimum 18 mm required for a full test to E2/VM1, 1 some adaption of the test sequence was needed to test for water bridging paths between the back of the cladding and the wall wrap. The measurements described in this report show that the small cavity formed between the brick veneer and insulation by shrinkage was insufficiently continuous to prevent water bridging across to the insulation where it was transported to the building wrap position. The drainage cavity in the test wall did not provide a reliable drainage path for water leakage on the back of the brick veneer cladding. 2.2 Effect of Airfoam on Humidity and Timber Moisture Content Two brick veneer walls were installed on both the north and south elevations of the weathertightness test building at BRANZ in 2003-2004 and used for moisture studies within various research programmes. The walls are fully instrumented and actively logged for temperature, humidity and timber moisture content. From December 2009 the two brick veneer walls have been used to investigate the effects of introducing UFF insulation into the stud cavities and the effect on timber moisture content levels within

the wall. The brick veneer test walls in the weathertightness test building at BRANZ were also installed with Airfoam during an initial visit in December 2009. Figure 5: Brick veneer cladding on BRANZ test building Figure 6: Thermal image of brick veneer test sample during drying stage after Airfoam installation The framing and instrumentation layout is shown in Figure 7. For the purposes of the current study the moisture content pins were all moved to the middle of their respective framing member, as shown in Figure 7. This was done in an attempt to look at the moisture distribution across the frame from the internal lining to the building wrap. The exposed ends of the moisture pins were coated with an adhesive in an attempt to

eliminate shorting of the pins through the wet foam. The humidity sensors were located in the stud space and were protected from liquid water by placing masking tape over the ends of their sheathing. Figure 7: Framing and instrumentation layout for test building sample Holes were drilled through the internal lining and the foam was pumped into each of the cavities formed by the framing. The holes were then left open to the indoor environment. The logging system recorded information from all of the channels every 15 minutes recording the moisture content and the humidity in the insulated cavity. Figure 8: Average Results from Brick Veneer Walls in Test Hut Figure 8 shows the results from both walls for the period from 1/12/09 to 13/2/10. The installation of the UFF insulation causes a rapid rise in both the relative humidity in the cavity and the moisture content of the framing.

The moisture content of the framing stayed roughly constant for about 2 weeks and then began to slowly dry out. In February 2010, several weeks after installation, the timber was still above the pre-uffi levels. The results for both walls are similar, but past work indicates that had the UFFI been installed in the winter, the south facing wall would take considerably longer to dry and would be likely to stay wet for the whole of the winter. The humidity measurements are representative of the moisture in the foam. The results show that the humidity is at 100% (free moisture) for 2-3 weeks before drying out. The foam in the north facing wall dried quicker (about 5 weeks) than its south facing counterpart (about 8 weeks), but in both cases the foam dried at a considerably quicker rate than the framing. Sustained high humidities have the potential to support mould growth and so should be avoided if possible. 3. LIMITATION The results reported here relate only to the item/s tested. Higher than expected moisture contents for bottom plates within brick veneer construction several months after UFFI installation have been observed during BRANZ site visits 5, and DBH investigations 6. Although these elevated moisture contents (up to 25% in some cases) appear to support the findings of this report, further research would be required to determine whether these elevated moisture contents were due to residual moisture from the installation process, or from external water being transported across the brick veneer. 4. REFERENCES 1. Department of Building and Housing. (2005). Compliance Document for New Zealand Building Code Clause 2 External Moisture, Verification Method E2/VM1. 2. Ballantyne, E.R., Dubout, D.R., GMI Masonry Cavity Insulation Project. 3. Department of Building and Housing. (2005). Compliance Document for New Zealand Building Code Clause 2 External Moisture, Acceptable Solution E2/AS1. 4. Bassett, M.R. and McNeil, S. (2009). Weathertight characteristics of weatherboard claddings. Proceedings of the 12 th Conference on Building science and Technology. Montreal. 5. BRANZ Study Report 233 6. Department of Building and Housing Report, Paul Probett, Injected Foam Insulation (Airfoam), August 2007.