Jet Grouting for Seepage Control at Lac Des Iles (LDI) Water Management Facility

Similar documents
SPECIFICATION FOR JET GROUTING

JET GROUTING AT THE WEST TORONTO DIAMOND GRADE SEPARATION PROJECT

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment

Wassara Jet grouting hammer. - Enabling single fluid jet grouting in difficult formations!

Jet Grout Soilcrete Stabilization Version 2006

Brochure E. The Soilcrete Jet Grouting Process

Compaction and Jet Grouting

Bauer Jet Grouting. Process

Soil Improvement by Compaction Grouting

Jet Grouting to Increase Lateral Resistance of Pile Group in Soft Clay

Figure (12.1) Foundation Grouting

JET GROUTING Implenia Spezialtiefbau GmbH

Section WATER LINE IN TUNNELS

Proofing Concept of Thermoinsulating Enclosure for Underground Heat Storage Systems

Shoring of Long Beach Main Pump Station utilizing Ground Improvement Methods, Long Beach, CA

June i TABLE OF CONTENTS

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

Ground Improvement. Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting

SUSTAINABLE FOUNDATION ENGINEERING MIXED-IN- PLACE TECHNIQUES FOR DURABLE CUT-OFF WALLS

NICO Tailings and Mine Rock Co-disposal Facility (CDF) Design Concept

Impact of Jet Grouting on the Lateral Strength of Soil Surrounding Driven Pile Foundations

SECTION GEOTECHNICAL INSTRUMENTATION

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-CE Washington, DC Regulation No March 2006

ITEM 416 DRILLED SHAFT FOUNDATIONS Materials. All materials shall conform to the requirements of the pertinent items as follows:

Wastewater Capital Projects Management Standard Construction Specification

New Development -Sonic Drilling with Sampling

APPLICATIONS SOILFRAC SOILCRETE PERMEATION COMPACTION INFILL. Underpinning. Settlement Control. Settlement Reversal. Void Grouting.

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA)

3. FIELD INVESTIGATION PROGRAM

LIMITED MOBILITY GROUTING -- PRACTICE IN NORTH AMERICA. Michael Byle, D.GE, F.ASCE,

EMBANKMENT DAM SEEPAGE MODIFICATIONS CHOICES AND CONSIDERATIONS. John W. France, PE, D.WRE 1 ABSTRACT INTRODUCTION

WATER LINE IN TUNNELS

GROUND ENGINEERING. Vibro Ground Improvement

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

SITE INVESTIGATION. Foundation Engineering

Grouting for Freezing

June 30, 2015 Project No.: C Mr. Kent Christensen, P.Eng. General Manager Huckleberry Mines Limited PO Box 3000 Houston BC, V0J 1Z0

SHAFT CONSTRUCTION SECANT PILE

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

Remedial grouting works to two dams in Hong Kong

CUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

Construction Technology B (CON4313)

Foundation Innovations Ensure Successful Bridge Replacement

piezometer installations

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CBC Aids WVDEP with Fresh Water Reservoir - Chief Logan State Park

11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE

Technical Bulletin No. MK3176. PREPARED: July, 2010

COMPACTED CLAY LINERS

ITEM NN17 - DRILLED SHAFTS ITEM NN17 - DRILLED SHAFTS (LOW OVERHEAD CLEARANCE) ITEM TRIAL SHAFTS

Grouting Bilfinger Spezialtiefbau GmbH

Trenchless Technology

TECHNICAL SPECIFICATIONS DEEP SOIL MIXING (CUTOFF WALL, RETAINING WALL, IN-SITU TREATMENT, IN-SITU FIXATION)

Jet Grouting Experience at Posey Webster Street Tubes Seismic Retrofit Project

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

Brief of evidence Tunnelling construction

Combined Pile Foundation System for a Residential Complex

POWER-INSTALLED FOUNDATIONS, GUY-ANCHORS AND INSTALLING EQUIPMENT

INFLUENCE OF GROUND IMPROVEMENT AND CONSTRUCTION MANAGEMENT ON SHIELD TUNNEL EXCAVATION: A CASE STUDY OF KAOHSIUNG MASS RAPID TRANSIT SYSTEM

Keywords: Jet Grouting, Deep Soil Mixing, Controlled Modulus Columns ABSTRACT

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

8Re: Northern Access 2016 Project. Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation

Appendix 5.3.5B Tailings Storage Facility Seepage Sensitivity Analysis

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Application of Vibro Techniques for Infrastructure Projects in India

TECHNICAL SPECIFICATIONS SHALLOW SOIL MIXING CONSTRUCTION. (In-Place Wall, In-Situ Stabilization, In-Situ Fixation, ph Adjustment of Soil)

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Geoprobe SDT45 Sonic Dual Tube Sampling System

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Forensics by Freezing

Project report on a deep well construction

Category 1 Waste Rock Stockpile Groundwater Containment System

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

water-powered drilling in ground engineering

Wet Speed-Mixing WSM - Soil Mixing Procedure in Twinmix Design

Deep Foundation Testing, Analysis and Consulting Services

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

The Soilcrete Jet Grouting Process

MODIFIED DRY MIXING (MDM) A NEW POSSIBILITY IN DEEP MIXING

Misan University - College of Engineering Civil Engineering Department

SOIL IMPROVEMENT WITH JET-GROUT COLUMNS: A CASE STUDY FROM THE 1999 KOCAELI EARTHQUAKE

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Civil Engineering Construction I (CBE5031)

Water Well Decommissioning Guidelines

San Antonio Water System Standard Specifications for Construction ITEM NO SANITARY SEWER LATERAL STUB OUTS OR RECONNECTIONS

Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization

Tunnelling and Underground. Construction Technology

Appendix I-2.4 Sub-cell 3 Monitoring Well Details

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

Using Thermal Integrity Profiling to Confirm the Structural Integrity of foundation applications

Practical Application and Design Considerations for Fully Grouted Vibrating Wire Piezometers in Mine Water Investigations.

CHAPTER 32 - WELL ABANDONMENT ORDINANCE OF DUBUQUE COUNTY, IOWA. Adopted September 5, Part 1 Introduction...2

Transcription:

Jet Grouting for Seepage Control at Lac Des Iles (LDI) Water Management Facility Naresh Gurpersaud, P.Eng., M.ASCE, 1 Daniel Lees, P.Eng., 2 and Frank Hu, P.Eng. 3 1 Geo-Foundations Contractors, 302 Main Street North, Acton, ON, Canada, L7J 1W9; e-mail: ngurpersaud@geo-foundations.com 2 Geo-Foundations Contractors, 302 Main Street North, Acton, ON, Canada, L7J 1W9; e-mail: drlees@geo-foundations.com 3 Geo-Foundations Contractors, 302 Main Street North, Acton, ON, Canada, L7J 1W9; e-mail: frankhu@geo-foundations.com ABSTRACT Three low-permeability cut-off walls were required for seepage control along the upstream toe of two new dams as part of the Lac des IIes (LDI) Water Management Facility Works. The LDI palladium mine is located 135 km North of Thunder Bay, Ontario, Canada. Jet grouting was used to create the low permeability cut-off walls by installing overlapping soil-cement columns. Jet grout columns were constructed using the double-fluid process. A comprehensive quality control program was implemented to ensure that specified geometric properties and performance requirements of the cut-off wall were achieved. An Acoustic Column Inspector (ACI) tool was used to verify the diameters of the pre-production test columns. All jet grout locations were predrilled to prevent difficulties resulting from geological conditions and to ensure adequate penetration into bedrock. A three-dimensional profile of each jet grout column installed was generated and updated daily based on the results of pre-drill hole alignment measurements completed at every hole. In-situ permeability testing was also conducted during the pre-production test program and during the installation of the production columns. Permeability testing was performed in-situ and on cast cylinders of soil-cement samples. The low permeability cut-off walls were successfully installed and satisfied the specified performance criteria. Jet grouting was performed between the months of February and May under challenging winter conditions. This paper focusses on the quality management program (QMP) that was implemented to successfully complete this project. INTRODUCTION The Lac des Iles Mine (LDI) is located in northern Ontario, Canada, approximately 135 kilometers northwest of Thunder Bay, Ontario. There are three Tailings Management Facilities (TMF) at the LDI site. A new Water Management Facility was proposed as part of the long-term tailings 1

management plan at the LDI mine. Three low permeability cut-off walls were installed by Geo- Foundations Contractors as part of the Lac Des Iles Water Management Facility upgrades. The cut-off walls were required along the upstream toe of the proposed main and saddle dams. In areas where the depth to rock exceeded 6 metres, jet grouting was used to install the seepage control cutoff wall; conventional excavation and an earth/rock-filled dam with a geomembrane liner was used wherever the rock was present within 6 m from surface. The jet grouting scope of work consisted of 3 no. walls with lengths of 58, 83 and 136 metres. The cut-off wall was keyed into sound bedrock. The specified criterion with respect to permeability of the cut-off wall was 10-6 cm/s and was to be verified by in-situ testing. GEOLOGICAL SETTING The surficial geology at the LDI site consists of a blanket of till deposits overlying bedrock. The till blanket is extensive and bedrock outcrops at less than 10% of the total site area (Hatch, 2015). Till at this site is typically less than 3 m thick with sections exceeding 6 m in the lee-sides of bedrock and in valleys between outcrops. Peat deposits with thickness varying from 1.4 to 2.3 m also cover approximately 50% of the site. The subsurface condition within the footprint of the work zone consists of organic peat overlying glacial till. The till at this site comprises of sandy silt to sand and gravel with traces of clay and occasion to numerous cobbles and boulders. A partial view of the subsurface conditions after the peat layer was removed is shown in Figure 1. In some localized areas, the till is overlain by discontinuous silt, fill or glacio-fluvial layers. Bedrock is present within 10 m of the existing ground surface, except for the valley located along the proposed Saddle Dam, where bedrock was encountered at 14 m below ground surface. Bedrock at this site is classified as slightly weathered to fresh granite. All jet grout columns were socketed at least 1 m into rock. 2 Figure 1. Partial subsurface view within a proposed jet grout segment

SPECIFIED REQUIREMENTS The entire site was subdivided into three segments: Main Dam East, Main Dam West and Saddle Dam; each of these three segments required at least some jet grouting. The specified cut-off wall stipulated a single row of overlapping jet grout columns. The specified requirements were as follows: A minimum jet grouted soil thickness of 1.0 m Embedment depth into bedrock 1.0 m In-situ permeability 10-6 cm/s Unconfined compressive strength (UCS) after 28 days 1.2 MPa. A pre-production test program consisting of a minimum of one sacrificial jet grout column for each segment. In-situ permeability proof testing over the full depth of the wall at each segment. OVERVIEW OF THE JET GROUTING PROCESS Jet grouting is a ground modification technique used for in situ mixing of soils with a stabilizer (usually cementitious grout). The stabilizer (grout) is injected at high pressures (typically 300-400 bars) through a small diameter nozzle. Grout is injected at high velocity, which enables the jet grouting process to hydrodynamically destroy the natural matrix of the soil and results in a mixing of the stabilizer with the disintegrated soil particles. The result of this energetic mixing is a homogenous and continuous structural soil-cement element (also know as soilcrete) with predetermined characteristics. Jet grouting can be applied to a wide range of soils from noncohesive, poorly granular soils to cohesive plastic clays. Jet grout columns at the LDI site were constructed using the double fluid process. Grout slurry and air were conveyed through separate chambers in the drill string (see Figure 2). Upon reaching the intended design depth, jet grouting was initiated with high-velocity air and grout slurry. Grout slurry was used for eroding and mixing the soil. The addition of compressed air shrouded the grout slurry jet, which increased its erosive erosion. This process employed specially built nozzles designed to focus the grout laterally, thus creating the soilcrete column. 3

PRE-PRODUCTION TEST PROGRAM Figure 2. Typical double-fluid jet grouting profile The objectives of the pre-production test program were to obtain appropriate jet grout parameters necessary for production jet grouting, to create columns 1.5 metres diameter, and to demonstrate an in-situ soilcrete permeability of 10-6 cm/s. A target column diameter of 1.5 m was selected to provide a minimum wall thickness of 1.0 m, including at column overlap. A total of three preproduction test programs were undertaken - one for each of the three jet grout segments. The following jet grout parameters were used in the pre-production test programs: Grout flow rate = 250 L/min Grout pressure = 400 bars Lift rate = 0.25 m/min Rotation rate = 10 rpm Nozzle configuration = 2 no. x 3.5mm diameter The following jet grout mix design was used: W:C ratio (by weight): 1.2 Cement: Type GU Portland Cement Bentonite: Extra High Yield Bentonite (1.5% by weight of water) Superplasticizer: BASF - Rheobuild 1000 (0.75% by weight of cement) Acoustic column inspector (ACI) and Shape Accel Array (SAA) Measurements The column diameter and profile were confirmed by using an Acoustic Column Inspector (ACI) and permeability was determined by in-situ falling head testing. Jet grout spoil (backflow) samples were collected to conduct laboratory testing (UCS and permeability). One of the sacrificial test columns was also exhumed to visually inspect the column diameter over the uppermost 1 m. 4

The diameter and profile of the pre-production test columns were verified using Keller`s proprietary acoustic column inspector (ACI). The ACI is an acoustic inspection device for checking the diameter of a jet grout column while the subject column is being constructed. Two small diameter holes are drilled at a target distance from the centre of the planned test column and steel feeler rods are installed. Two acoustic sensors are connected on the top of steel rods previously inserted in cement-bentonite backfilled hole (Figure 3). A signal collection system is used to record acoustic data during the jetting process. When jetting the test column, the steel rods and the acoustic collection system detects if the jet stream is penetrating as far away as the steel rods. The signal was displayed on a real-time basis and recorded for post-processing. Interpreting this data can yield the minimum achieved radius of the jet grout column. A Shape Accel Array (SAA) measuring system was used to check the alignment of each 178 mm diameter pre-drilled hole prior to jet grouting. The SAA, manufactured by Measurand, is a flexible, non-magnetic, calibrated hole alignment measuring system designed for repeated use inside boreholes or drill rods. The SAA is a watertight system with robust joints made from hydraulic hose, stainless steel segment tubes, and stainless-steel fittings. For the LDI project, the SAA string of segments was lowered into the bottom of the pre-drilled hole via the inside of the drill rods. Each segment, 0.5m long x 22 mm diameter, contains sensors to measure acceleration, tilt, and temperature. Special software was used to collect and conduct post-processing of the information to verify the as-built hole alignments and orientations. An evolving set of 3-D profiles was generated for the LDI Project s overlapping jet grout columns. The data from the ACI collection system were combined with the geometry taken from the SAA tests to verify minimum column diameters along the entire depth of the test column at every tested location. 5 Figure 3. ACI sensor mounted atop of steel rod in cement-bentonite backfilled hole Results from the pre-production test program The pre-production test columns at the Main Dam West and the Saddle Dam achieved a minimum diameter of 1.6 m based on data acquired from the ACI and SAA. This finding was verified by exhumation of the pre-production jet grout test columns.

At the Main Dam East, drilling of the test column resulted in deviation due to a significant amount of cobbles and boulders that were encountered during drilling. As a result of the ground conditions that were encountered, the spacing between ACI rods and the jet grout test column was not ideal to clearly verify the as-built column diameter. Two additional steps were taken: (1) the test columns were exhumed to verify the diameter; (2) A second ACI test was performed on a production column JG #57. Figure 4 shows the exhumed overlapping test columns at the main dam east with a minimum observed diameter of 1.6 m. The ACI test on production column JG #57 also showed that a minimum diameter of 1.6 m was achieved. Figure 4. Exhumed sacrificial jet test grout columns at the Main Dam East Falling head tests Immediately after installation of the jet grout test columns a 75 mm outside-diameter (OD) steel pipe was inserted into the centre of the freshly installed column. A second pipe with an interior diameter of 38 mm (with bottom end capped) was inserted inside the 75 mm OD steel pipe to 2.0 m beyond the tip of the exterior pipe. Wherever this forming process was foiled by one circumstance or another, the permeability testing hole was advanced via diamond coring of the cured jet grout column. In order to form the hole necessary for performing the falling head test, the interior pipe was periodically rotated in the fresh soilcrete prior to initial set. After 3 days of curing time, the interior pipe was retracted, leaving a 2.0 m uncased formed hole below the exterior pipe which was left in place to act as a conductor to the permeability test zone. The falling head test procedure consisted of the following steps: The test hole was flooded with water and the water head was brought to the top of the exterior pipe. 6

A downhole pressure transducer (Level Troll 700) was lowered into the test hole to continuously record evolving changes in hydrostatic head. The Level Troll was extracted and the data were downloaded. Hvorslev`s method was used to calculate the permeability. Falling head test results are summarized in Table 1. All test results confirmed in-situ permeabilities on the order of 10-6 to 10-7 cm/s. Table 1. Summary of pre-production falling head test results Location/Segment Results Remarks Main Dam East 7.2 x 10-6 and 3.3 4 days and 8 days curing time, respectively; x 10-6 cm/s formed test hole Saddle Dam 8.2 x 10-6 cm/s 13 days curing time; formed test hole. JET GROUT CUT-OFF WALLS Installation of jet grout cut-off walls at all three segments employed the same jetting parameters and grout mix design that were verified during pre-production testing. All production columns were pre-drilled with a separate drill rig prior to jet grouting, on a split spacing sequence so that every interlock was constructed using wet-on-dry jet grouting. Each 178 mm diameter pre-drilled hole was temporarily cased to its full depth and the alignment of each pre-drilled hole was measured with the SAA device. After the hole alignment was measured each pre-drilled hole was backfilled with bentonite slurry and the casing removed. Jet grouting was then performed after lowering the jet grout tooling into the bentonite-filled hole. Typically, one row of overlapped jet grout columns was constructed along the cut-off wall centre alignment, extending 1.0 m into bedrock. The spacing of columns was 1.1m center-tocenter and the minimum constructed diameter was 1.6 m, as confirmed during the pre-production test programmes. Jet grout backflow (spoil) samples were routinely collected at the collar of the jet grout holes for laboratory testing. These samples were provided to the General Contractor for unconfined compressive strength (UCS) and laboratory permeability testing. Compressive strength test results indicated strengths in excess of the minimum specified strength. In total, 251 no. jet grout columns were constructed from March 1 to May 14, 2016, as shown in Table 2. Table 2. Breakdown of production work Location Date Total Columns Installed Drilling Depth (m) Total Jetting Length (m) Main Dam East March 1~30, 2016 127 5.3~12.04 644 Main Dam West April 1~27, 2016 72 1.9~10.6 392 Saddle Dam April 28~May 14, 2016 52 4.6~13.6 434 7

Real-time design adjustments based on QC data The minimum jet grout interlock and wall thickness were achieved throughout the entire wall using a center-to-center jet grout column spacing of 1.1 metres (at the collar) using 1.6 m diameter columns. Wherever the evolving as-built 3-D profiles indicated that the minimum 1.0 m wall thickness was not achieved, supplemental columns were installed. Main dam east One additional column was constructed between columns JG042 and JG043 to fill a section where the jet grout columns were inferred to have deviated. The wall was inferred to be only 0.85 m thick near the bottom of those particular columns. Figure 5 illustrates a 3D view of the as-built jet grout wall at the main dam east based on the data inferred from SAA measurements. Main Dam West One additional column was constructed to repair a potential window resulting from the inferred deviation between columns JG072 and JG073 to fill a section where the jet grout columns were inferred to have deviated at their respective bottoms and the expected wall thickness was only 0.91m, based on SAA data. Saddle Dam In conformance with the stipulated design all 52 no. columns along the alignment were constructed with each column extending a minimum of 1.0 metre into rock and meeting the minimum specified overlap. The minimum specified wall thickness was achieved as inferred from the combined data resulting from quality control and quality assurance measures. Figure 5. As-built overlapping jet grout columns at Main Dam East Post-production falling head testing As a quality assurance measure, in-situ permeability testing was performed at 3 no. locations along the as-constructed cut-off wall. 8

At Main Dam East, 2 no. falling head tests were performed in pre-formed holes, using the method mentioned used during the pre-production test program. A third falling head test was performed in a cored hole at JG #64 as follows: JG064 was allowed to cure for 2 weeks. A 178 mm diameter open hole was drilled to a depth of 4.9 m. A 152 mm diameter PVC pipe was installed and the annular space between the borehole and the outside of the PVC pipe was grouted. Triple tube (HQ3) coring was performed to a depth extending 4 m beyond the bottom of the PVC pipe. A falling head test was performed using the cored section of the hole as the tested medium. At Main Dam West, one falling head test was carried out using a formed hole and a second test using a cored hole on a production column. The third falling head test was foiled by the presence of large granular materials that were encountered in the soilcrete resulting in the PVC pipe not being able to be advanced into the fresh jet grout column; no results could be obtained. At the Saddle Dam two falling head tests were performed in the formed holes and one test in a cored hole, as specified. The triple tube (HQ3) coring process was employed for drilling the test hole in one production column at each of the three work segments. The recovered material was delivered to the General Contractor for further inspection and testing. The results of the in-situ falling head proof tests results are listed in Table 3. All results were on the order of 10-6 ~ 10-7 cm/s and thereby satisfied the specified criterion for permeability. Table 3. Summary of falling head proof test results Location/Segment Results Remarks Main Dam East - JG 090 9.9 x 10-6 cm/s 6 days curing time; formed test hole Main Dam East - JG 113 5.7 x 10-7 cm/s 8 days curing time; formed hole Main Dam West - JG 48 7 x 10-7 cm/s 22 days curing time; formed test hole Main Dam West -JG 71 1.1 x 10-6 cm/s 9 days curing time; cored hole Main Dam West N.A. Could not install pipes due to a significant amount of cobbles/boulders. Saddle Dam - JG 043 1.2 x 10-6 cm/s 10 days curing time; cored hole Saddle Dam -JG 017 4.3 x 10-6 cm/s 7 days curing time; formed hole QUALITY CONTROL PROGRAM The quality control program included the following elements: All jet grouting holes were predrilled and the deviation, if any, of each hole, was measured using the SAA to verify its verticality prior to it becoming a jet grout column and to verify, by inference, that the minimum overlap was achieved. Consequently, the jet grout column 9

locations were adjusted where necessary, or supplemental columns were added. Figure 6 shows a typical borehole deviation plan view from the SAA data. Grout and backflow samples were collected daily for laboratory permeability testing and unconfined compressive strength (UCS) testing. All tested samples exceeded the specified requirements for unconfined compressive strength (1.2 MPa). Table 4 provides a summary of the test results. Three falling head tests were performed in each segment. A data acquisition (DAQ) system was used to record the jet grout parameters, including the pressure, grout flow rate, rotation rate and lift rate. Figure 6. Typical deviation plan view from SAA data Table 4. Grout and backflow test results Location Backflow Grout Grout Backflow UCS (MPa) specific gravity (g/cm 3 ) specific gravity (g/cm 3 ) Marsh Time (sec) Main Dam East 1.70 ~1.98 1.42~1.48 36~46 3.1 to 3.7 MPa after 7 days Main Dam West 1.72~1.92 1.45~1.48 40~46 3.3 to 4.4 MPa after 7 days Saddle Dam 1.70~1.87 1.45~1.49 39~46 3.8 to 4.4 MPa after 7 days 10

LESSONS LEARNED AND CONCLUSIONS The geological conditions at the LDI site presented numerous challenges for the construction of the jet grout cut-off wall. A comprehensive review of the site conditions and experience gained from similar projects allowed Geo-Foundations Contractors to tailor the execution of the work in order to mitigate delays, address the performance requirements and allow for contingency planning. There are several key aspects of this project that can be adopted for work required in similar geological settings and weather conditions: Alignment readings at all pre-drilled holes were taken without negatively influencing the jet grout production rates and the risk of plugging jet grout nozzles. Pre-drilling improved productivity of jet grouting and reduced wear of jet grout drill string and tooling. The alignment of each jet grout hole was improved by tailoring the pre-drilling method to suit the subsurface conditions. The use of the SAA combined with ACI was a very effective process of verifying minimum column diameter and wall thickness. Forming a hole in the fresh jet grout column can be an effective, non-destructive method to check in-situ permeability of production jet grout columns. High concentrations of cobbles, boulders, and gravel in the jet grout treatment zone can complicate in-situ permeability testing efforts. Hole alignment checks at every hole using the SAA is a very effective method of confirming as-built wall geometry and allows for design adjustments, as necessary, in the field in a timely manner. ACKNOWLEDGEMENTS The authors would like to acknowledge the contributions from the jet grouting team from Geo- Foundations who contributed towards the safety and success of this project. REFERENCES GI-ASCE. (2009). Jet Grouting Guideline. Geo Institute of ASCE, Grouting Committee- Jet Grouting Task Force, American Society of Civil Engineers. Hatch. (2015). Specification of Jet grouting for Ground Seepage Control, Section 31 56 00. Hatch. (2015). Geotechnical Investigation for WMF1, H 348749-6400-229-066-0001, dated August 21, 2015. 11