This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations and the Ontario Building code.

Similar documents
The Six-Inch Layer Compaction Method

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations.

SECTION TRENCHING

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

Ontario ENGINEERING STANDARD SPECIFICATION 1.0 PURPOSE 2.0 MATERIALS

SECTION BUILDING EARTHWORK

DIVISION 4100 SITEWORK

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

SECTION EXCAVATION, BACKFILLING AND COMPACTING

SECTION 14 EMBANKMENT

C. Foundation stabilization for pipe and utility structures.

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

Union County Vocational - Technical Schools Scotch Plains, New Jersey

SECTION 10 - TRENCHING AND BACKFILLING

CITY OF LETHBRIDGE SECTION Construction Specifications Page 1 of 7 BACKFILL REGULATIONS FOR PUBLIC RIGHT-OF-WAYS

SECTION TRENCHING & BACKFILLING

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

SECTION EARTHWORK

SECTION SOILS REPORT

Section Fill Placement Tender No. [ ] Page 1

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

SECTION STRUCTURAL EXCAVATION FOR STRUCTURES

SECTION FILL AND BACKFILL

SECTION EROSION CONTROLS

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

SECTION EARTHWORK

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

SECTION EXCAVATION AND FILL

SECTION EROSION CONTROL DEVICES

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

SECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

SECTION RIPRAP, BOULDERS, AND BEDDING

A. Excavation consists of the removal of material encountered to subgrade elevations and the reuse or disposal of materials removed.

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

Special Provision No. 421F01 April 2006

SECTION ASPHALT CONCRETE

SECTION 02215BP TRENCHING AND BACKFILLING

378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

This specification describes the minimum requirements for Vale's standard practice for Concrete drawings.

ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES

MagnumStone Specifications Gravity

EXCAVATION AND BACKF1LL

SECTION EARTHWORK. B. Removal of subsoil and excavating all classes of material encountered.

Section SITE CLEARING. B. Description of Work: 1. The extent of site clearing is shown on the drawings.

SECTION A1 EXCAVATION AND BACKFILL GENERAL

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

CITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

SECTION TRENCI-JING PART 1 GENERAL

CONSTRUCTION SPECIFICATION FOR GRADING

SECTION EMBANKMENT

CONSTRUCTION SPECIFICATION FOR UNTREATED SUBBASE, BASE, SURFACE, SHOULDER, SELECTED SUBGRADE, AND STOCKPILING

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

Construction Specification 28 Lime Treated Earthfill

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.

1.2 REFERENCES.1 American Society for Testing and Materials International (ASTM)

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

SECTION EXCAVATION AND FILL

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION EXCAVATION AND BACKFILL, GENERAL

EARTHWORK. C. Handling, storage, transportation, and disposal of excavated material

SECTION BITUMINOUS CONCRETE PAVING

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

SECTION STRUCTURE EXCAVATION AND EARTHWORK

Appendix D General Earthwork and Grading Specifications for Rough Grading

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

SPECIFICATIONS - DETAILED PROVISIONS Section Grouted Rip-Rap C O N T E N T S

SECTION AGGREGATES

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION

TRENCH EXCAVATION AND BACKFILL

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

SECTION ASPHALT PAVING

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PORTLAND CEMENT. Section PORTLAND CEMENT STABILIZED SUBGRADE

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING TOOLS AND STRUCTURES

MSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

Special Provision No. 799F01 March 2012 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

SECTION TRENCHING, BACKFILL AND COMPACTION

SECTION EXCAVATION, TRENCHING AND BACKFILL

A. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):

TOWN OF LAFAYETTE SPECIFICATIONS FOR HIGHWAY CONSTRUCTION. June 1984

Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.

LANDSCAPE RETAINING WALLS

Transcription:

1/6 1.0 PURPOSE This specification describes the minimum requirements for filling depressions and for backfilling excavations for structural footings, slabs, floors, buildings, trestles, and the like.. This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations and the Building code. 2.0 DEFINITIONS "The Six-Inch Layer Compaction Method" means the spreading of backfill material in uniform full width layers not more than 6 inches in depth after compaction. "Backfilling Operation" means the activity required to fill surface depressions or to backfill excavations. "Sound" or "suitable" as applied to fill materials means free from deleterious matter, having a reasonably uniform gradation which permits compaction to a stable mass, and having the characteristics specified for the particular materials, all after handling, re-handling, processing and reprocessing where necessary. "Unstable" or "unsuitable" as applied to fill material means too wet, too dry, frozen or containing ice, snow, organic or other deleterious matter, or having poor characteristics for grading and compaction, or having other characteristics which may result in undesirable settlement or movement of the fill or within the fill, or otherwise not meeting the requirements of the specifications. However, this definition permits drying, dewatering, watering, thawing and any other processing or reprocessing to make the material stable and suitable prior to incorporating it into the fill. "Fill" and "backfill" are deemed to have the same meaning. Overexcavation means excavation beyond the authorized zone or the zone required to build the structure as specified..0 GENERAL.1 STOCKPILING OF MATERIAL The Slopes of stockpiled materials and bermes where the height is in excess of 4 feet (1.22 meter) must possess their own technical report or plans produced by a qualified professional, including the following items: Physical characteristics of the mound/slope; Total height; Elevations of base and crest;

2/6 Overall slope angle; Height of earth banks; Width of periodic horizontal strips; Height of slopes between periodic horizontal strips; Slope angles between periodic horizontal strips; Operational lifespan; Area occupied; Degree of risk; Vegetation or synthetic protection measures on earth slopes exposed to the weather; Possible obstructions to the operation of machinery/equipment that may be positioned in areas close to slopes or other earthworks, in terms of the dynamic effects that their operation may have on the mounds; Earth banks used as access routes must meet traffic safety criteria. Stockpile backfill material within designated areas. Stockpile granular material so as to prevent segregation and change in moisture content. Should any material become segregated, remix the material to provide uniform gradation. Remove excess backfill material not required for other purposes and dispose of at a designated location. Rough grade those materials in the disposal areas to promote drainage and to give a tidy appearance to the satisfaction of the Vale Representative. Exercise due care at all times to prevent earthfill materials from becoming contaminated by clay or other types of deleterious materials. 4.0 BACKFILL 4.1 BACKFILL MATERIALS Backfill materials and compaction are as specified on the project drawings. Conform to the requirements of Vale Specification SPEC-11004 entitled "Earthfill Materials". 4.2 GENERAL Do not place backfill on frozen, snow-covered, ice-covered, or wet ground. Maintain minimum overburden cover as specified on the project drawings. Co-ordinate fill operations with other work. Do not place fill until subgrade has been compacted to the required density determined by ASTM D698 (Standard Proctor Test) or ASTM D1557 (Modified Proctor Test). Do not cover any subgrade or work until authorized by the Vale Representative but otherwise place in the fill as soon as possible.

/6 Prevent damage and disturbance to subgrade, other work and existing buildings and installations. Keep heavy equipment at a safe distance, clear of structures and other installations. Within the safe distance, place fill by hand or other suitable means and compact it by means of hand guided power rollers or tampers operated to avoid damage to the structures and installations. Eliminate boulders and rock fragments larger than 6 inches, when earth or fragmented rock fill is permitted within 2 feet of structure on the top of piping, electric ducts and cable. Fill uniformly on all sides around structures and other installations not designed as retaining walls, and prevent unbalanced loadings. For earth and granular fill, deposit the fill material as near as practical to its final location and spread it in accordance with the six inch layer compaction method. Make each layer the full width of the fill required at its elevation, with the layer horizontal except for a slight slope of approximately 2% to promote surface drainage in the event of rain while the layer is exposed and except as required to suit the required elevations of the completed fill. Where earth fill material contains boulders or rock fragments, place and work the materials so that all such solid pieces are well distributed and all interspaces are completely filled. Eliminate such solid pieces; over 6 inches in their greatest dimension, from fill placed within 1 foot of the surfaces of earth fill. For earth and granular fill, compact each layer to the required density before placing further material on it. Adjust and control the moisture content to within plus or minus 1 percent of the optimum, adding water or drying the fill material as and when necessary. Add water and dry the fill material by means of suitable equipment capable of producing uniform results throughout the fill material. For concrete fill other than concrete bedding, place and cure the concrete in accordance with CSA- A2.1. Produce a dense surface but do not trowel or otherwise make the surface smooth. Backfill overexcavated zones by Lean concrete having 15 MPa strength unless otherwise approved by Vale representative. 4. SHEETING, BRACING AND SHORING Do not leave sheeting, bracing and shoring in place without the Vale Representative's prior approval. Submit a written request for approval, to the Vale Representative. If the Vale Representative gives approval, sheeting, bracing and shoring may be left in place. Where sheeting, bracing or shoring are left in place, cut off and remove to a depth of feet minimum below finished surface, unless otherwise instructed. If instructed, remove installed sheeting, bracing and shoring by withdrawing it in stages consistent with the progress in placing and compacting fill such that no movement occurs in the sides of the

4/6 excavation. Completely and promptly fill voids formed during the withdrawal, compacting the fill using rammers suitable for working in the confined spaces. Co-ordinate the activities to ensure adequate support is always in place. 4.4 SUBSTATIONS Slag shall not be used as backfill material within electrical substations. 4.5 FOOTINGS Cast concrete footings in place on undisturbed dry natural soil, or soil compacted to 100% density. Do not cast concrete footings on loose soil or on wet ground. 4.6 FOUNDATIONS Do not place backfill material against fresh concrete structures until the concrete obtains 75 percent of its design strength as determined by site test cylinders unless otherwise directed by Vale Representative. Carry out backfill operations for burial of service pipelines, cables, ducts, and the like which are located in foundation excavations, under the supervision and direction of the particular service trades involved. Provide bedding and backfill materials as specified. 4.7 FLOORS Do not use slag as backfill under floors having buried metallic services, exposed steel, or under floors and foundations supporting electrolytic processes. 5.0 SUBMITTALS Submit to the Vale Representative when requested: 5.1 SAMPLES A sample not less than 100 pounds, typical of each type of fill material from each proposed source. With each sample, submit results of testing proving the material complies with the gradation and physical requirements specified. The Vale Representative approval of any sample will not mean approval of the entire source. All materials from any source are subject to further sampling, testing and approval/rejection, whether Vale incorporated into the work or not.

5/6 5.2 TEST REPORTS AND CERTIFICATES Test reports showing the results of gradation, moisture content, compaction, physical requirements and other test. 6.0 INSPECTION AND TESTING Inspect and test the subgrade and fill materials to determine suitability of materials, moisture content and density of materials in place. 7.0 REFERENCE DOCUMENTATION The following documents are related to this specification and shall be used to their latest revision: CSA A2.1 ASTM D698 ASTM D1557 ASTM D698 SPEC-11004 SPEC-1101 Concrete Materials and Methods of Concrete Construction Standard Test methods for laboratory compaction characteristics of soil using standard effort (12,400 Ft-LbF/FT (600 KN-m/m ). (Standard Proctor Test) Standard Test Methods for Laboratory compaction characteristics of soil using modified effort (56,000 Ft-LbF/FT )) (Modified Proctor Test) Standard Test Method for in-place density and water content of soil and soilaggregate by nuclear method (shallow depth). Earthfill Materials Bedding Materials

6/6 8.0 REVISION AND TRANSITION NOTES Revision notes describe: what was changed, and if applicable, why it was changed, and the plan to implement the change, including whether changes are retroactive. Note: The revision notes are a summary of the changes and may not necessarily be a complete list. Rev 1 Description Document format and number changed due to Vale Engineering Document Program changes in 2011. Previous Standard number was 1106-01.01.611 Rev 5. Revision by Approved by Issue Date YYYY/MM/DD K.Clausen A.Alaeddine 2012/04/0 2 Approved for use in Thompson No Changes K.Clausen A.Alaeddine 2012/08/09 Document Reviewed Format updated Regional approvals removed K.Clausen A.Alaeddine