Grossmont-Cuyamaca Community College District Facilities Construction Update

Similar documents
Grossmont-Cuyamaca Community College District Facilities Construction Update

Governing Board Capital Construction Program Annual Workshop September 10, 2013 Agenda

BOARD OF TRUSTEES OCTOBER 13, 2014

July 1 September 30, 2008

Semi-Annual Report. January 1, 2012 June 30, 2012

MIRACOSTA COMMUNITY COLLEGE DISTRICT

EL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN

January 1, 2009 March 31, 2009

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING APRIL 17, 2018

October 1, 2008 December 31, 2008

QUARTERLY REPORT. (July 1, 2013 September 30, 2013) December 18, 2013

Facilities Planning & Management

HIGHER EDUCATION CENTER NATIONAL CITY BUILDING ADDITION

QUARTERLY REPORT. January 1, 2014 March 31, 2014

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by

QUARTERLY REPORT. October 1, 2013 December 31, 2013

Governing Board Presentation

Project Update Prop M Bond Series A & B

Ohlone Community College District

PROPOSITION R Citizen s Bond Oversight Committee

East Los Angeles College Project Priority List Occupancy Date

3 CUMULATIVE METHODS AND PROJECTS

Through. November Current Strong Schools Bond Capital Improvement Projects. Prepared by

DRAFT September 26th, 2003

PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016

UNIVERSITY OF HOUSTON Campus Facilities Planning Committee Request for Project Approval Form. 2. Project Name University Center Expansion/Renovation

Board Report. Bond Program Update:

GOING GREEN BIG TIME. Terence Williams Architect, Inc. 1

Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement

FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST

Orange Education Center Project Update. Board Of Trustees Meeting November 9, 2015

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

1.0 EXECUTIVE SUMMARY

Implementing Unifier at a Large Public K-12 School District

Independence Adult Center

ASPE LOCAL 18 & CSI LOS ANGELES CHAPTER LACCD CONSTRUCTION BOND PROGRAM

Santa Teresa High School

An Overview of Design-Build

ORANGE VISTA HIGH SCHOOL PHASE I

I. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards

Oconomowoc Area School District Facility Construction Update June 29, 2018

Facilities Modernization Program Funded by Measure B Project Report

Project Information. Nominations of Artists. University of Houston

DEL MAR COLLEGE Capital Improvement Program for Proposed Southside Campus. Prepared by;

Facilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

Repair & Replacement Study

MONTHLY PROGRESS REPORT

Boynton High School & Blackford Site

Berryessa Union School District Measure L Bond Construction Program

Capital Projects Report

FACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015

James Lick High School

SCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA

University of North Florida BOARD OF TRUSTEES. CAMPUS PLANNING, DESIGN & CONSTRUCTION CAPITAL PROJECTS UPDATE January 18, 2011

Ohlone Community College District

Program Update. Chino Health Science Parking Lot

Recessed Board Meeting March 20, 2018

ZERVAS SCHOOL BUILDING COMMITTEE and DESIGN REVIEW COMMITTEE MEETING Zervas Elementary School Newton, MA June 26, 2014

ORANGE VISTA HIGH SCHOOL PHASE I

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Perimeter Site Improvements

MARCH 23 FACILITIES MASTER PLANNING AND OVERSIGHT COMMITTEE Included Materials

Architectural Services Consultant Registration Form

Through. June Current Strong Schools Bond Capital Improvement Projects. Prepared by

ACBO Institute. Integrated Educational & Facilities Planning

PURPOSE: The purpose of this meeting was to review the scope and schedule with the Vocational Technology staff.

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Juanita High School Modernization vs. New-in-lieu of Modernization Report

Master Plan, January 16, 2012 Roesling Nakamura Terada Architects

Business Affairs Committee Dobo Recovery Update. February 7, 2019

Health Life Safety Survey and Master Facilities Plan

MIRACOSTA COLLEGE. [X] MiraCosta College Bid Opportunities Website /FAX

REVIEW OF SERVICES. Miramar College May 23, p.m.

October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL:

CONSTRUCTION UPDATE FEBRUARY 2016 THIS IS AUBURN.

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Project Delivery Method

SONOMA COUNTY JUNIOR COLLEGE DISTRICT. Governing Board of Trustees Presentation Measure H update. December 13, 2016

LOVEJOY Independent School District

Orange Education Center Project Update. Board of Trustees Meeting February 25, 2019

RATIONALE AND REASONING

Oconomowoc Area School District Facility Construction Update July 27, 2018

DISTRICT ADVISORY COMMITTEE MEETING MAY 2, 2018 HALF CENT SALES TAX PROGRESS REPORT

Bond Construction Program

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:

Projects Currently in Planning, Design and Construction. April 12, 2017

Governing Board Presentation

GROSSMONT COLLEGE ARTS & COMMUNICATION COMPLEX PHASE 1 TEACHING AND PERFORMANCE THEATER LIST OF PRE-QUALIFIED CONTRACTORS BY TRADE

GREENE COUNTY PUBLIC SCHOOLS ADDITIONS + RENOVATIONS

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

Completed projects. Projects in progress. Program developments

Peter Kirk Elementary School Modernization vs. New-in-lieu of Modernization Report

Cupertino Union School District

3D/International. Facility Condition Assessment Report. Coast Community College District

CONSENT CALENDAR 5 Agreement for Architectural Design Services for the COS Hanford Educational Center Student Quad

Report No F Meeting Date: June 22, 2017 REVISED ATTACHMENT BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA

PROJECT UPDATE August 28, 2014

Transcription:

Grossmont-Cuyamaca Community College District Facilities Construction Update April 17, 2018 Presented by Fred Parker Program Manager Gafcon, Inc.

Agenda Grossmont College Update Cuyamaca College Update Energy Conservation Measures Analysis of Construction Costs Cost Savings Update 2

Grossmont College Performing and Visual Arts Center Project Estimate : $42.7 M Removal of Buildings 22 A-C Construction of a new 38,680 square foot (SF), 390-seat teaching and performance theater The theater will include the new Hyde Gallery Footing layout and chilled water reroute work are ongoing First concrete pour of deep Orchestra pit poured on 4/9/18. Construction Duration: December 2017-October 2019 3

Grossmont College Science, Math and Career Tech Complex Building 31 Renovation Project Estimate: $14.3 M Remodel of Bldg. 31 including classrooms, labs, and offices Outdoor gathering area All tenants relocated to swing space over winter break Bids received and under review Construction start May 2018 4

Grossmont College Interim Swing Space-Phase 1-3 Project Estimate: $3.4 M Phase 1 provides Building 31 swing space in Parking Lot 5 South For phases two and three of this project, the interim space will house programs affected by construction from Buildings 21, 24, 27 & 36 Construction complete. Buildings occupied and functional. 5

Grossmont College Science, Math and Career Tech Complex Building 36 Project Estimate: $33.5 M Removal of Building 36 and construction of a new two (2) story 46,850 GSF building & Includes Veteran s Center Removal of buildings 32B, 37, 30B, 38C, 95 at the end of the project Schematic Design Underway DSA submission fall 2018 Construction start fall 2019 6

Cuyamaca College Building L Remodel Project Estimate: $1.4 M Remodel existing building to accommodate Water/Waste Water Technology program 2 classrooms, 2 labs and office space Renovation underway Construction duration: March 2018-July 2018 7

Cuyamaca College Student Center & Veterans Services Project Estimate: $4.2 M Expansion of Veteran Center Reconfiguration of space includes: Bookstore Food Services Student Affairs In design Construction duration: winter-summer 2019 8

Cuyamaca College Ornamental Horticulture Complex Project Estimate: $12.5 M New offices and retail building Remodel existing New greenhouses New storage Design Development Complete Construction Documents underway Submission to the Division of the State Architect anticipated May 2018 Construction duration: spring 2019-summer 2020 9

Cuyamaca College Student Services & Administration Building Project Estimate: $31 M New Student Services and Administration facility Veteran Support Center Schematic Design Bidding/Award: 2019 Construction start: 2020 10

Cuyamaca College Landscape Improvements-Central Park Project Estimate: $2 M Scope is being defined Designed in coordination with the upcoming Student Services and Administration Building Schematic Design Bidding/Award: Fall 2019 Construction start: 2020 11

Energy Conservation Measures Year 4: Energy Conservation Measures Project Budget: $685,327 State funding received Grossmont College Prop 39- Main Chiller Addition (Prop V & Prop 39) Cuyamaca College Building D Main Chiller water loop Monitor Based Commissioning Out to bid Building D Main Chiller Water Loop Anticipated construction start June 2018 12

Energy Conservation Measures Chiller Expansion & Year 5 Energy Conservation Measures Project Estimate: $9 M Expansion of central plant Modernization of aging chiller equipment and infrastructure In design Anticipated construction start fall 2019 Cuyamaca College Central Plant Grossmont College Main Chiller Addition 13

Analysis of Construction Costs Construction Trends & Escalation Outlook Typical escalation factor used in the construction industry has ranged from 3% to 4.5% through 2016 National total construction spending in 2017 was forecasted to finish at $1.263 billion, an increase of 6% over 2016 Escalation has shot up to an average of 22% in the greater San Diego market. Factors include: A rebounding economy Mega projects in Nevada and Arizona Construction start is up by 6% Contractors are busy and resources (labor pool) is at an all-time low Commodities are trending higher than normal Extensive amount of local school bonds passed in 2016 Materials: substantial increases in the costs of cement, copper pipe and lumber. 14

Analysis of Construction Costs Escalation Impacts in 2017 PROJECT BUDGET BID DAY RESULTS PERCENTAGE OVER 1 Performing Arts Center Sage Creek High School, Carlsbad, Ca. $11.5M $14.8M 30% 2 Orange Coast Community College Planetarium $14.1M $16.39M 16.24% 3 Sacramento Municipal Utilities District HQ $66M $97M 46% 4 Pinole Valley High School $97M $130M 56% 5 Anatolia Elementary School $20M $24.76M 23.8% 15

Cost Savings Update Cost Savings Update Campus Project Cost Savings Reason Grossmont College Performing and Visual Arts Center $93,000 Change order negotiations: CM at Risk Contract Sound blankets Wayfinding signage Grossmont College Performing and Visual Arts Center $852,000 Value engineering efforts: Reduced sun shades and increased mullion spacing Soil screening Site utilities reallocated Total $945,000 16

Bond Program Update Questions? 17