Spent Nuclear Fuel, Low Level Radioactive Waste and Decommissioning

Similar documents
Spent Nuclear Fuel and Low Level Radioactive Waste: Current and Future Storage Options

U.S. NUCLEAR POWER PLANT DECOMMISSIONING

State of the Nuclear Industry Decontamination & Decommissioning Are We Ready. April 25, Presented by: Michael Frediani

Spent Power Reactor Fuel:

THE NUCLEAR FUEL CYCLE

The Electric Power Research Institute (EPRI) is the

ICFD Session 2, Cost Estimation Stockholm, Sweden - 21 September 2016 Michael Lackey P.E. Vice President - Nuclear Operations

Interim Storage of Used Nuclear Fuel. The Nuclear Energy Institute

S T A T E O F M I C H I G A N BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION DIRECT TESTIMONY THOMAS S. LAGUARDIA ON BEHALF OF CONSUMERS ENERGY COMPANY

Perspective of Decommissioning Worldwide in View of Metrological Needs

TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft)

Waste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report

THE NUCLEAR FUEL CYCLE

RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES UNITED STATES NATIONAL NUCLEAR ENERGY CONTEXT

Decommissioning Pilgrim What is Decommissioning, and What Should be Done to Protect our Communities?

Spent Power Reactor Fuel:

Power Reactor Decommissioning: U.S. Perspective on Regulatory Insights and Challenges

Radioactive Waste and the Future of Nuclear

CHARACTERISTICS AND COMMON VULNERABILITIES INFRASTRUCTURE CATEGORY: NUCLEAR SPENT FUEL STORAGE FACILITIES

TABLE OF ACRONYMS / ABBREVIATIONS

Part 2. EVPP 111 Lecture Dr. Largen

RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES UNITED STATES [2011]

Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste

NUCLEAR WASTE MANAGEMENT AND DECOMMISSIONING BACKGROUND INFORMATION

Current Status of Shutdown Sites Activities. San Onofre Nuclear Generating Station (SONGS) Site Visit

A PROPOSED WASTE ACCEPTANCE QUEUE FOR SHUTDOWN NUCLEAR POWER REACTORS. Steven P. Nesbit Lara S. Nichols

Near-term Options for Treatment and Recyle

Centralized Interim Storage and a National Interim Storage Strategy. Robert Petroski ANS WISE August 1, 2005

Acceptance and Disposition of Department of Energy Spent Nuclear Fuel

Lessons Learned from EPRI Decommissioning Program Decommissioning Pre-Planning Overview

Spent Fuel Storage: Defining the Problem. Commissioner Tim Echols Georgia Public Service Commission

Indian Point: An Ever Present Danger

Reprocessing and Spent Nuclear Fuel Management at the Savannah River Site

Community Engagement Panel ISFSI Location and Technology Option Update July 17, For internal use only

Department of Energy Spent Nuclear Fuel - Update. Outline

Activities of the NRC s Division of Spent Fuel Management: An Overview

Onsite dry cask storage of used nuclear fuel (Image taken from Wikimedia Commons)

WM2016 Conference, March 6 10, 2016, Phoenix, Arizona, USA. Preliminary Evaluation of Removing Used Nuclear Fuel from Shutdown Sites An Update 16057

WM2015 Conference, March 15 19, 2015, Phoenix, Arizona, USA

A Unified Spent Nuclear Fuel (SNF) Database and Analysis System

PLANNING FOR THE EARLY RETIREMENT OF THE OYSTER CREEK NUCLEAR GENERATING STATION ENGINEERING ISSUES

CGoEd. June 1, U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555

Report to the Legislature: Activities of the Midwest Interstate Low-Level Radioactive Waste Compact Commission

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576

Activities of the Midwest Interstate Low Level Radioactive Waste Compact Commission Biennial Report

Nuclear Energy Fundamentals

W R I T T E N S T A T E M E N T O F R U S S E L L A

The Social and Economic Impacts of Nuclear Power Plant Closures Jonathan Cooper & Jen Stromsten Institute for Nuclear Host Communities

Thermal Fission.

Appendix B. History of the Civilian Radioactive Waste Management Program. Early development of radioactive waste management policy

Going Underground: Safe Disposal of Nuclear Waste

Spent fuel Management The case for Hardened On-Site Storage (HOSS) Arjun Makhijani President, IEER

Testimony On 2016 SONGS 1 Decommissioning Cost Estimate

Risks of long term irradiated. on site at nuclear power plants

Solving the Nuclear Waste Storage Dilemma

Yucca Mountain. High-level Nuclear Waste Repository

Operational Challenges of Extended Dry Storage of Spent Nuclear Fuel 12550

Decommissioning Worldwide and NEA Activities

CONNECTICUT YANKEE ATOMIC POWER COMPANY

Nuclear Issues 5. Decline of Nuclear Power? Three Mile Island Chernobyl Waste Disposal

The Nuclear Fuel Cycle. by B. Rouben Manager, Reactor Core Physics Branch Atomic Energy of Canada, Ltd.

Questions regarding Tritium, Spent Nuclear Fuel and Security. 1. What are the standards for ground water contamination at the Vermont Yankee site?

DESIGNING DECOMMISSIONING INTO NEW REACTOR DESIGNS 1

S z5a MPC&D July 31, U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C

Storage and disposal of radioactive waste in Italy

Marc Bachman Amanda Lawing Amanda Toner

Analysis of Blending of Low-Level Radioactive Waste

The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402

2014 Decommissioning Cost Analysis of the San Onofre Nuclear Generating Station Units 2 & 3

The Question of Queue: Implications for Best Practice in Cross-country Transport of Commercial Spent Nuclear Fuel 9402

San Onofre Unit 1 Decommissioning

Useful applications of radioactivity and nuclear energy Power for good... and evil

Science of Nuclear Energy and Radiation

Science of Nuclear Energy and Radiation. Nuclear Reactor Concepts. by Dr. Jerry M. Cuttler, PEng

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA. Opportunities for the Multi Recycling of Used MOX Fuel in the US

Decommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment

WM 2010 Conference, March 7-11, 2010 Phoenix, AZ

Decommissioning of Nuclear Installations

Methodology to Manage Material and Waste from Nuclear Decommissioning. Waste Management & Decommissioning Working Group

UNIT-5 NUCLEAR POWER PLANT. Joining of light nuclei Is not a chain reaction. Cannot be controlled

Nuclear Energy. Nuclear power is a hell of a way to boil water. - Albert Einstein

Lecture (3) on. Nuclear Reactors. By Dr. Emad M. Saad. Mechanical Engineering Dept. Faculty of Engineering. Fayoum University

Zion Project Overview S. Chris Baker VP EH&S

FIG. 1. Fort St. Vrain Nuclear Generation Station.

So Now You Are The RSO Radiation Safety Programs. Norman W. Henry III, MS,CIH SHBP (Safety and Health By Protection) comcast.

Spent Fuel Storage Alternatives

IAEA CLASSIFICATION OF RADIOACTIVE WASTE

Radioactive Materials Released from Nuclear Power Plants

IMPACT OF LACK OF CONSISTENT FREE RELEASE STANDARDS ON DECOMMISSIONING PROJECTS AND COSTS

Nuclear Energy. Consolidated Interim Storage Facility Design Concepts In the United States. Nuclear Fuels Storage and Transportation Planning Project

STURGIS Barge Decommissioning Project

Nuclear Energy. Nuclear Fuels Storage and Transportation Planning Project Transportation System Development Overview. Matt Feldman

Nuclear Power Reactors. Kaleem Ahmad

SOLUTIONS. Role of Radioactive Waste Management in D&D. Colin Austin (Senior Vice President, International Business)

Announcements. Homework 9 due on Tuesday.

PROPOSAL OF A DRY STORAGE INSTALLATION IN ANGRA NPP FOR SPENT NUCLEAR FUEL

Robert Kilger (GRS) Criticality Safety in the Waste Management of Spent Fuel from NPPs

LOW-LEVEL RADIOACTIVE WASTE FORUM, INC. DISCUSSION OF ISSUES: Management of Commercial Low-Level Radioactive Waste

Considerations for Disposition of Dry Cask Storage System Materials at End of Storage System Life

Safety of Spent Fuel Transportation

Transcription:

Spent Nuclear Fuel, Low Level Radioactive Waste and Decommissioning Vermont Legislature January 29, 2009 - Revised Montpelier, Vermont Presented by Bruce Lacy 1

Topics Spent Nuclear Fuel Low Level Radioactive Waste Decommissioning Understanding key technical and policy issues will foster the best legislative decisions 2

Spent Nuclear Fuel ( SNF ) Isotopes What is nuclear fuel? How does nuclear fuel become spent Main Characteristics of SNF Storing and disposing of SNF US Commercial SNF history and policy Dry storage SNF Storage Capacity at the Vermont Yankee Vermont Yankee Dry Storage Technology and Site Vermont SNF Considerations 3

Isotopes Chemical reactions between elements are determined by electrons Nuclear reactions involve protons and neutrons in the nucleus Neutrons help keep the nucleus stuck together Examples Element Isotope Protons Neutrons Total Half life Decay Particle Helium He-4 2 2 4 Infinite / stable Carbon C-12 6 6 12 Infinite / stable Carbon C-14 6 8 14 5,600 years electron Nitrogen N-14 7 7 14 Infinite / stable Nitrogen N-15 7 8 15 7.4 seconds electron Cobalt Co-59 27 32 59 Infinite / stable Cobalt Co-60 27 33 60 5.3 years electron Uranium U-235 92 143 235 700,000,000 He++ Uranium U-238 92 146 238 4,500,000,000 He++ Uranium U-239 92 147 239 23.5 minutes electron Plutonium Pu-239 94 145 239 24,000 years He++ 4

Isotopes Continued Radioactivity: energy from the nucleus in the form of particles and rays Gamma rays (like powerful X-rays) require thick shielding Electrons (beta particles) are stopped by a thin layer of metal Helium atoms (alpha particles) are stopped by a sheet of paper All unstable isotopes decay over time into stable isotopes The half life and decay particle tell us a lot about the degree of radiation hazard General characteristics of unstable or radioactive isotopes Half life Decay rate Decay Particle Intensity of Radiation Short Fast Electron High Long Slow He++ Low 5

What is Nuclear Fuel? Uranium Oxide (UO2) in solid ceramic pellets The Uranium has been enriched in the U-235 isotope The pellets are in hollow steel rods or pins Pins are grouped into bundles or assemblies Reactors are designed for a specific number of assemblies, e.g. the Vermont Yankee reactor is designed for 368 bundles 6

How does nuclear fuel become spent? U-235 and Pu-239 fission of split, producing heat, fission products and 2-3 neutrons U-238 is converted into Pu-239 and other heavy isotopes Neutrons are the key to both the fission and conversion processes Depletion of U-235 and accumulation of fission products dampens the fission process 7

Main Characteristics of SNF Still in solid form, but internal composition has changed U-235 depleted U-238 about 10% converted Pu-239 being produced and fissioned Other heavy isotopes Fission products Fission products are the primary source of the radiation exposure hazard and residual heat production after SNF is taken out of the reactor Fission product half lives range from milliseconds to around 30 years There are over 750 fission product isotopes that over time decay into approximately 34 elements 8

Storing and Disposing of SNF Short term it needs shielding and cooling in the spent fuel pool After five years the residual heat production and radiation levels are low enough to allow it to move to dry storage Longer term is a question of national policy 9

US Commercial SNF History and Policy 1960 s 1970 s Anticipation of recycling (reprocessing) and geologic disposal of residues Uranium was a government monopoly, considered scarce and expensive Subsequent opening of the Uranium market showed it to be plentiful and cheap 1979 Carter executive order against commercial reprocessing 1982 Nuclear Waste Policy Act ( NWPA ) Regional interim storage Permanent repositories Standard contracts with utilities for SNF disposal, 1998 date Established Nuclear Waste Fund, $0.001/kwh payments 1987 NWPA Amended Response to DOE progress on site selection Federal effort on regional interim storage prohibited until a repository licensed Yucca Mountain, NV, selected by Congress If Yucca Mountain unsatisfactory, report back to Congress 1990 s advent of dry storage 2002 Yucca Mountain satisfactory 2008 Yucca Mountain license application submitted to and accepted by US NRC Dry storage is the default long term interim US policy 10

Dry Storage 55 Independent Spent Fuel Storage Installations (ISFSI) in 33 States All aspects of dry storage are regulated by the US NRC Two types of site licenses Site specific (15) General (40), including Vermont Yankee Primary siting criteria involve: Soil Stability Seismic Air temperature Flooding Canister and cask systems, including transportation, are certified by the US NRC Security is required for ISFSI s until the last SNF leaves the site 11

SNF Storage Capacity at Vermont Yankee All SNF produced at Vermont since startup in 1972 is stored at the site Until recently, all in in the spent fuel pool Dry storage added due to limits of spent fuel pool Current inventory 2819 (see note) bundles in the spent fuel pool 340 bundles in 5 dry storage canisters (68/canister) The existing ISFSI pad, which can accommodate up to 36 canisters, in combination with the spent fuel pool, can meet storage needs through 2032 Additional dry storage capacity will be needed to empty the spent fuel pool as part of decommissioning Note: Corrected from 1911 number used in January 29, 2009 legislative presentation 12

The Vermont Yankee Dry Storage Technology and Site Vermont Yankee uses A general license The Hi-Storm 100 System 260 The Hi-Storm system meets all Vermont Yankee site criteria The Hi-Storm system is certified for submergence up to 125 feet, however it is reasonable to assume that the ISFSI will never be flooded Preliminary independent geological evaluation of the site indicates it to be stable with no indication of flood hazard beyond that already evaluated Elevation (feet above mean sea level) 250 240 230 220 210 200 254 ISFSI pad surface 252 252.5 Reactor Building Floor Probable Maximum Flood 230.9 500-Year Flood 226.3 100-Year Flood 220 Approximate Normal River Site elevation and flood data from independent surveys, FEMA and reports to NRC 13

Vermont SNF Considerations The Vermont Yankee Dry Storage meets NRC requirements and should not be regarded as posing an imminent threat to public health and safety. The existing ISFSI pad provide in-place storage capability for fuel produced during the license renewal period. The key date for SNF storage at Vermont Yankee is when the last bundle leaves the site Success at the national level provides the only substantive resolution of long term interim storage at the site Given the history of Congress and Administrations over the past, it is reasonable to contemplate that SNF at Vermont Yankee, and other commercial nuclear plants in the US, will be at the reactor sites well past the end of plant operation and possibly after decommissioning of the power plant 14

Low Level Radioactive Waste ( LLW ) What is it? Class A: contaminated clothes, equipment, and some plant water resins Class B: concentrated water purification resins Class C: materials directly exposed to neutrons in the reactor core What do you do with it? Reduce volume by compaction, incineration and metal melting Burial in NRC approved sites Burial site options Class A, Envirocare in Utah Class B & C, pending in Texas 15

US Low Level Radioactive Waste History and Policy Barnwell, SC and Hanford, WA have historically provided the bulk of US LLW disposal capability In response to concerns, Congress passed the Low Level Radioactive Waste Policy Act in 1980 Objective was to motivate the development of additional disposal sites States were encouraged to join into Compacts where they would agree on development of a site within the compact Non-compact states could be excluded from burial sites A new site was developed and opened in Clive, Utah, accepting Class A LLW from all states Most Compacts have not been successful in agreeing on development of new sites Closure of Barnwell and Hanford to non-compact members has eliminated Class B and C disposal options Texas, Vermont s Compact partner, is making good progress on opening a facility that will accept Class B and C waste Economics has and will continue to play an important role in availability of and access to LLW waste disposal 16

Vermont LLW Considerations LLW disposal during plant operation is a relatively low profile activity that can weather some changes and disruptions in national or state policy Class A, B and C disposal capability is essential for decommissioning of Vermont Yankee The cost and availability of LLW burial is the major variable in the cost of decommissioning Vermont Yankee History suggests that access to disposal sites and cost of disposal can and does change over time and should not be taken for granted. 17

Decommissioning Decommissioning Options Experience To-date Key Decommissioning Requirements Vermont Yankee Decommissioning Cost Estimates Vermont Yankee Decommissioning Funding Vermont Decommissioning Considerations 18

Decommissioning Options DECON equipment, structures and portions of a facility and site containing radioactive contaminates are removed or decontaminated to allow for unrestricted use shortly after cessation of operations SAFSTOR essentially deferred DECON, decommissioning must be complete within 60 years, assumptions about the SAFSTOR period are commonly timed to correlated with assumptions about removal of SNF ENTOMB radioactive contaminates are encased in a long live material and the entombed structure is monitored and maintained until the radioactive material decays to a level permitting unrestricted release of the property Decommissioning focuses on removal of radioactive contamination. SNF storage and site restoration, while important, are separate issues. 19

Experience To-date DECON complete, 11 sites Pathfinder, Elk River, Saxton, Shippingport, Shoreham, Fort St. Vrain, Yankee Rowe, Trojan, Haddam Neck, Maine Yankee, Big Rock Point DECON in progress, 2 sites Rancho Seco, San Onofre 1 SAFSTOR, 11 sites GE VBWR, CVTR, Fermi 1, Indian Point 1, Peach Bottom 1, Humbolt Bay 3, Dresden 1, LaCrosse, Zion 1&2, Millstone 1 ENTOMB Hallam, Pique, Bonus License renewal is pushing most decommissioning thinking farther into the future 20

Key Decommissioning Requirements: Removal of the SNF from the spent fuel pool LLW burial access for Class A, B and C waste Money to cover the costs 21

Vermont Yankee Decommissioning Cost Estimates (January 2007 TLG Study, Millions of $2006) DECON Option SAFSTOR Option Low High Low High License Termination 469 469 License Termination 455 450 Spent Fuel Management 142 384 Spent Fuel Management 221 501 Site Restoration 44 40 Site Restoration 41 40 Total 655 893 Total 717 991 22

Vermont Yankee Decommissioning Funding The Vermont Yankee Decommissioning Trust Fund has declined due to turmoil in the financial markets, other companies are having similar experiences There is no indication yet as to how NRC will address declines in Fund balances due to recent declines in the financial markets September 30, 2007 June 30, 2008 December 31, 2008 Balance $440 M $414 M $ 372 M NRC will require that the Fund be first applied to completing License Termination Note: the December 32, 2008 fund balance of $372 M, provided by Entergy on January 29, 2009, will be independently verified 23

Vermont Decommissioning Considerations The January 2007 TLG study is the best available, but the precision of the numbers can lead users to a false sense of confidence. The underlying assumptions can vary significantly between now and when decommissioning takes place. Vermont is well position with LLW burial options given the progress of Texas in developing a new site. This option needs to be managed with an understanding that decommissioning could be many decades in the future Removal of SNF is dependent upon national policy success which is arguably very uncertain, the cost of SNF management is consequently similarly uncertain Given the uncertainties in final costs and that they may be far in the future with new evolutions in ownership compared to when Vermont Yankee is producing power, Vermont should consider strategies that motivate all parties (the state, customers and the plant owner) to support adequate fund collection. Erring on the side of what seems like over collection today could be of great benefit in the future While premature shutdown and owner bankruptcy at some point in the future are not anticipated outcomes, they are possible and should be examined, including how Vermont involvement in the economic aspects of Vermont Yankee could be interpreted as assumption of a decommissioning obligation by the state of Vermont 24