Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Similar documents
POTOMAC ELECTRIC POWER COMPANY

NERC PLANNING STANDARDS

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

Standard MH-TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements

Standard TPL (i) System Performance Under Normal Conditions

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

Standard Development Timeline

Standard Development Timeline

FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Standard TPL System Performance Following Extreme BES Events

Platte River Power Authority. Ten-Year Transmission Plan ( )

Standards de planification du NERC

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Standard Development Timeline

Standard TPL-004-0a System Performance Following Extreme BES Events

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard Development Timeline

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

1.3 Planning Assumptions and Model Development

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Mapping Document for FAC-010-3

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

TPL 001 AB 0 System Performance Under Normal Conditions

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff

NYSRC RELIABILITY RULES For Planning And Operating the New York State Power System

DRAFT STUDY PLAN FOR 2018

Criteria. C~/v~ ~ ~ ~ G! " A1A "~"" T"""g"'~10N COr'P""''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria

PSE&G Assumptions Overview. November 2018

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon

Connection Study Requirements

B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

Standard TPL System Performance Under Normal Conditions

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

SPP RTO Compliance Forum TPL Jason Terhune

BULK ELECTRIC SYSTEM PLANNING CRITERIA

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions

Transmission Planning Procedures and Planning Criteria TDOG108

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

Feasibility Study Report

SRRTEP Meeting 2019 Annual Assumptions for Pepco

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

1.3 Planning Assumptions and Model Development

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

2012 NCTPC PJM Joint Interregional Reliability Study. PJM Interconnection. Duke Energy Carolinas. Progress Energy Carolinas

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

5.4 Post Contingency Local Load Relief Warning

Comparison of IV.A.M2 and IV.A.M3 to EOP-005-1

NERC Reliability Functional Model

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

Energy Management System (EMS) Model Updates and Quality Assurance (QA)

2015 Operational Practices Survey Questions

Project Single Points of Failure TPL-001 Cost Effectiveness

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE

Standard FAC System Operating Limits Methodology for the Planning Horizon

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects. System Protection Subgroup

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering

TABLE OF CONTENTS. UNCONTROLLED WHEN PRINTED 2 USA Operations

Transmission Expansion Advisory Committee. December 15, 2011

AEP Transmission Local Planning Assumptions, Models, and Criteria

NYSRC RELIABILITY RULE/NERC STANDARD CROSS-REFERENCE

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria

Standard BAL-502-RF-03

Ancillary Services Matrix

Outage Scheduling Manual

Standard TOP Monitoring System Conditions

Security Guideline for the Electricity Sector: Identifying Critical Assets

Reliability Analysis Update

Post SAR July day Formal Comment Period with Parallel Ballot July 2013

AEP Guidelines for Transmission Owner Identified Needs

Methodology PLG-METH-0002-V1

SSR STUDY REPORT FINAL

~2~ ~ i. Methodology """ '~"" T"""S""~' " ~ " """~ P LG -METH V7.2

Southwest Power Pool CRITERIA

Standard BAL-502-RFC-02

TSOs, taking into account the following: Whereas

MATL Requirements Facility Interconnection Requirements

Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015

Reliability Coordinator Area System Operating Limit Methodology

Transmission Interconnection Requirements. Table of Contents

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation

Transcription:

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017

Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2 2.2 Regional Reliability Planning Standards...4 2.3 2.3 PJM Planning Standards...4 3 3 RMU Transmission Planning Adequacy Criteria...5 3.1 3.1 Planning Principles and Standards / Adequacy...5 3.2 3.2 Detailed Adequacy Criteria...7 3.2.1 3.2.1 System Load Level...7 3.2.2 3.2.2 Multiple Contingencies / Common Mode Failures...7 3.2.3 3.2.3 Power Transfers...8 3.2.4 3.2.4 Equipment Ratings...8 3.2.5 3.2.5 Circuit Breaker Interrupting Capability...8 3.2.6 3.2.6 Reactive Power Planning...9 4 References...10 2

1 Background This document provides the local planning criteria which will determine the reinforcements and enhancements to the RMU transmission system. This RMU Transmission Planning Criteria ensure compliance with the transmission planning standards of the North American Electric Reliability Corporation (NERC) and those of ReliabilityFirst (RF), one of the eight Regional Entities (REs) of NERC. The RMU Planning Criteria also coordinates with the ComEd Transmission Planning Criteria as RMU is located within the ComEd transmission system. In this document, Transmission system refers to the networked facilities operated at a voltage level of 138 kv. Facilities operated at 100 kv and above are considered part of the Bulk Electric System (BES), except as modified by the Inclusions and Exclusions listed in the NERC BES definition. All of RMU s transmission facilities are BES facilities. 3

2 National and Regional Criteria and Guides 2.1 NERC Transmission Planning Standards The NERC was established to promote the reliability of the BES of North America and coordinates reliability standards for the power systems of the United States, the bordering provinces of Canada, and a portion of Mexico. NERC consists of eight Regional Entities; RMU is a member of the ReliabilityFirst RE. NERC has developed planning standards to ensure the reliable operation of the interconnected BES. These standards can be found on the NERC website. The RMU Transmission Planning Criteria describes how RMU performs analyses to determine the ability of the interconnected transmission system to withstand probable and extreme contingencies. The analyses are performed by simulated testing of the transmission system as prescribed by NERC. 2.2 RFC Regional Reliability Planning Standards As a member of ReliabilityFirst, RMU builds its BES facilities to meet the requirements of NERC and RFC. 2.3 PJM Planning Standards RMU is a member of the PJM Interconnection, LLC (PJM) Regional Transmission Organization (RTO). PJM manages a regional planning process for generation and transmission expansion to ensure the continued reliability of the electric system. PJM annually develops a Regional Transmission Expansion Plan (RTEP) to meet system enhancement requirements for firm transmission service, load growth, interconnection requests and other system enhancement drivers. The criteria PJM uses in developing the RTEP is set forth in PJM Manual 14B. 4

3 RMU Transmission Planning Adequacy Criteria 3.1 Planning Principles and Standards/Adequacy The transmission system must perform reliably for a wide range of conditions. Because system operators can exercise only limited direct control, it is essential that studies be performed in advance to identify the facilities necessary to assure a reliable transmission system in future years. The voltages and equipment loadings on the transmission system should be within acceptable limits, both during normal operation and for an appropriate range of potential system faults and equipment outages. The more probable contingency conditions should not result in voltages or equipment loadings beyond emergency limits. The emergency limits can vary based on equipment type and allowable time period. Table 1 specifies the conditions analyzed by RMU for the purpose of identifying any thermal or voltage violations. The 50/50 and 90/10 load forecasts are defined in section 3.2.1.1. Thermal capability is given with equipment ratings in Amps or MVA. Voltage limits are in reference to the nominal design voltage and shown in per unit (pu). Adherence to the criteria given in this table ensures that the RMU transmission system meets the applicable reliability requirements of NERC, RFC and PJM. System readjustment is allowed when attempting to reduce line loadings or improve a voltage profile. System readjustments considered in planning analysis include: Behind the Meter Generation Load tap changer adjustment Circuit breaker switching Loadings on facilities over their applicable ratings but below short-term emergency ratings, following a contingency, must be adjusted back down to the normal or long-term emergency rating, as indicated in Table 1, within the time frame of the short-term emergency ratings using the system readjustments listed above. If the criteria described in this document cannot be met, mitigation plans are developed. A valid mitigation plan will bring the system into compliance through the most judicious use of a variety of feasible options. These include the development of an operator action plan in conjunction with the use of short-term emergency ratings, behind the meter generation dispatch, or the installation of a physical reinforcement. In addition to those events and circumstances included in Table 1, more severe but less probable scenarios should also be considered for analysis to evaluate resulting consequences. As permitted in the NERC TPL Standard, judgment shall dictate whether and to what extent a mitigation plan would be appropriate. Such events are listed in the Steady State & Stability Performance Extreme Events section of Table 1 of TPL-001-4. 5

None (P0) Outage Event Table 1 RMU Adequacy Criteria Thermal 50/50 Load Forecast All Facilities Within Normal Ratings 1 Line (P1) All Facilities Within Short- Term Emergency Ratings (1) 1 Open Circuit Breaker All Facilities Within Short- Term Emergency Ratings (2) One Line, followed by another Line 2 Lines on a Common Tower (6) (simultaneous, all voltages) or 1 Faulted non-bus Tie Circuit Breaker (7) (138 kv) or 1 Faulted Bus Tie Circuit Breaker (7) (all voltages) or 1 Faulted Bus Section (138 kv) 1 st Contingency: All Facilities Within Short-Term Emergency Ratings (1) 2 nd Contingency: All Facilities Within Short-Term Emergency Ratings (2) All Facilities Within Cascading Levels (3) (5) Thermal 90/10 Load Forecast All Facilities Within Long- Term Emergency Ratings (4) All Facilities Within Short- Term Emergency Ratings (2) All Facilities Within Short- Term Emergency Ratings (2) Not required Not required Voltage (pu) 138 kv 0.95 min 1.03 max 0.92 min 1.05 max 0.92 min 1.05 max 0.92 min 1.05 max 0.92 min 1.05 max (1) Must return to normal ratings post contingency, load shed not allowed (2) Must return to long-term emergency ratings post contingency, load shed not allowed (3) Must return to long-term emergency ratings post contingency, planned/controlled load shed allowed (4) The 90/10 load forecast is higher than the expected 50/50 load forecast, thus equipment loading up to emergency ratings is acceptable for normal conditions (5) As a proxy for cascading, RMU uses the lower of the relay loadability rating or 115% of the load dump rating (6) Excludes lines that share a common structure for 1 mile or less. (7) For Planning Criteria purposes a bus tie circuit breaker connects two individual substation bus configurations, such as two straight busses or two rings. Breakers within a ring, breaker-and-a-half, or double bus double breaker configuration are not considered bus ties when applying the Planning Criteria Note: For contingency analysis, a synchronous condenser is treated the same as a line. Note: Wind Turbines are to meet the same voltage requirements as Transmission Substations. 6

3.2 Detailed Adequacy Criteria 3.2.1 System Load Level 3.2.1.1 Peak Period Studies The peak load period must be studied to determine future requirements for the transmission system. The basic references for system peak load to be used in studies for future years are the total corporate system load projection provided by the PJM Load Analysis Subcommittee and the substation load forecasts provided by the Capacity Planning Group. The actual peak load in any given future year is likely to be higher or lower than the forecast value. A 50/50 load forecast provides a peak load projection that has an equal probability of being higher or lower than the peak load that actually occurs in that year. A 90/10 forecast provides a peak load projection with a 10% probability that the actual peak will be higher than the level forecasted in that year. A system planned using the 90/10 forecast provides additional security, as the load estimate is usually about 7% higher than the 50/50 forecast. 3.2.1.2 Off-Peak Period Studies Studies should also be conducted for the purpose of determining risks and consequences at light load or shoulder peak conditions, and for any other period for which system adequacy cannot be evaluated from peak period study results. For these off-peak periods, it is assumed that the number of hours of occurrence is substantially higher than the number of hours at or near peak load levels. 3.2.2 Multiple Contingencies/Common Mode Failures Credible contingencies more severe than those included in Table 1 shall also be considered for analysis. The types of contingencies considered for this analysis are defined in the Steady State& Stability Performance Extreme Events section of Table 1 in TPL-001-4. The transmission system shall be evaluated for the risks and consequences of a number of each of these extreme contingencies, as listed below: Loss of a tower line with three or more circuits Loss of all transmission lines on a common right-of-way Loss of a switching station or substation (one voltage level plus transformers) Loss of a generating station Loss of a major load center Failure of a RAS to operate when required Mis-operation of a RAS Impact of severe power swings or oscillations from disturbances in another Regional Council Loss of the most critical transmission line followed by the loss of another critical transmission line in an adjacent system Single phase to ground fault with a failure of a protective device A multi-phase fault with delayed clearing 7

3.2.3 Power Transfers All studies should consider known firm power transfers affecting the RMU transmission system. This includes known firm transmission service reservations, including those with rollover rights, as well as parallel path power transfers through the system that may impact system reliability. RMU is part of a larger regional power system that must be capable of withstanding certain levels of power transfers between or through sub areas of the region. PJM conducts load and generator deliverability tests for specific sub areas as part of the RTEP process to determine whether the system can accommodate these transfers. The RMU system must reliably accommodate these transfers per the P J M Load and Generator Deliverability Procedures. A description of the deliverability testing procedures can be found on the PJM web site. ReliabilityFirst also performs transfer limit testing to trend the strength of the transmission system. PJM s resource reliability criterion is a loss of load expectation (LOLE) of.04 day per year for each zone in PJM and 0.1 day per year for the entire PJM footprint. 3.2.4 Equipment Ratings Allowable loading levels (ratings) for transmission facilities are available in an equipment ratings database and include ratings for normal and emergency conditions. RMU has defined three types of emergency ratings based on time duration: long-term, short-term, and load-dump emergency ratings. The long-term emergency rating is defined as lasting the duration of the contingency, taking into account the daily load cycle for the transmission facility. The short-term emergency rating is defined as lasting either 30 minutes or two hours. The load-dump emergency rating is defined as lasting for 15 minutes. The following durations and assumptions will be used to establish short-term emergency ratings on RMU s transmission system. For transmission facilities serving load in the RMU Area a two-hour duration should be used. The two- hour duration provides Transmission Operations sufficient time to perform the required post-contingency operating steps that normally involve the adjustment of one or more phase angle regulating transformers. For all other transmission facilities serving load outside of the Chicago Metro Area a 30-minute duration should be used as Transmission Operations can normally perform the required post-contingency operating steps such as opening or closing a circuit breaker within this time frame. The specific methodologies used for determining equipment ratings are outlined in the RMU Transmission Ratings Methodology technical reference document. These ratings are set to obtain a reasonable useful life (40 to 50 years) from the equipment throughout normal and emergency use. Equipment ratings are issued to all appropriate areas of the company and are used by both planning and operating personnel. 3.2.5 Circuit Breaker Interrupting Capability Under normal conditions, the current through a circuit breaker shall not exceed the maximum normal ratings of that breaker. Further, a circuit breaker shall have sufficient capability to interrupt a close-in single-phase or three-phase to ground fault. 8

3.2.6 Reactive Power Planning The objective of system reactive power planning is to efficiently coordinate the reactive requirements of the transmission and distribution systems to satisfy voltage criteria. Meeting this objective ensures voltage stability, provides generator auxiliary power systems and the distribution system with adequate voltage, and minimizes transmission losses and reactive interchange. System reactive requirements can be supplied by generating units, transmission, subtransmission, and distribution level static capacitors,synchronous condensers and by a variety of solid-state reactive compensation devices (SVCs, STATCOMS, etc.). The RMU system is planned so that transmission voltages will be maintained within an acceptable range for normal and emergency conditions as described in Table 1. Low transmission voltage levels will lead to undesirable effects in both the transmission and distribution systems, such as higher losses, reduced insulation life, and reduced effectiveness of capacitors. These effects would also increase the difficulty in recovering from low transmission voltage level situations. The outage events analyzed to assess voltage adequacy are the same as those listed in Table 1. 9

4 References NERC TPL Standard latest revision available on the NERC website: Standard TPL-001-4 Transmission System Planning Performance Requirements Load and Generator Deliverability Procedures latest revision available on the PJM website: Manual 14B: PJM Regional Planning Process Attachment C: PJM Deliverability Testing Method 10