Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

Similar documents
Special Provision No. 799F01 March 2012 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR NOISE BARRIER SYSTEMS

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS

CONSTRUCTION SPECIFICATION FOR CONCRETE FOOTINGS AND MAINTENANCE PLATFORMS FOR HIGH MAST LIGHTING POLES

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

CONSTRUCTION SPECIFICATION FOR CHAIN LINK FENCE

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

Special Provision No. 541S01 October OPSS 541, Construction Specifications for Chain Link Fence, is deleted and replaced with the following:

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations.

Special Provision No. 405F03 March 2005

AMENDMENTS TO OPSS 408 (OCT 89) CONSTRUCTION SPECIFICATION FOR ADJUSTING OR REBUILDING MANHOLES, CATCH BASINS, DITCH INLETS AND VALVE CHAMBERS

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

Special Provision No. 599S22 March 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS)

B760 - NOISE BARRIER SYSTEMS OPSS 760

Construction Specification for Utility Adjustments

CONSTRUCTION SPECIFICATION FOR ERECTION OF POLES

CONSTRUCTION SPECIFICATION FOR POLE ERECTION

CONSTRUCTION SPECIFICATION FOR ERECTION OF POLES

CONSTRUCTION SPECIFICATION FOR STANDARD HIGHWAY FENCE

Special Provision No. 599S22 March 2001

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3

CONSTRUCTION SPECIFICATION FOR POLE ERECTION

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS

CONSTRUCTION SPECIFICATION FOR STANDARD HIGHWAY FENCE

CONSTRUCTION SPECIFICATION FOR STANDARD HIGHWAY FENCE

Special Provision No. 109S17 June 2017

Special Provision No. 915S03 December References, Materials, Construction, and Quality Assurance for Sign Support Structures

CONSTRUCTION SPECIFICATION FOR STEEL BEAM GUIDE RAIL AND CABLE GUIDE RAIL

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING

Special Provision No. 999S28 June 2010 CONSTRUCTION SPECIFICATION FOR PRECAST PANELS FOR USE AS STAY-IN-PLACE DECK FORMS

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOR UNDERGROUND UTILITIES

CONSTRUCTION SPECIFICATION FOR STANDARD HIGHWAY FENCE

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POLES

CONSTRUCTION SPECIFICATION FOR PERMANENT SMALL SIGNS AND SUPPORT SYSTEMS

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

Construction Specification for Concrete Curb and Concrete Curb and Gutter

CONSTRUCTION SPECIFICATION FOR TUNNELLING

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS

Special Provision No. 421F01 April 2006

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOLLOWING INSTALLATION OF PIPELINES, UTILITIES, AND ASSOCIATED STRUCTURES

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3

CONSTRUCTION SPECIFICATION FOR STEEL BEAM GUIDE RAIL AND CABLE GUIDE RAIL

CONSTRUCTION SPECIFICATION FOR ADJUSTING OR REBUILDING MAINTENANCE HOLES, CATCH BASINS, DITCH INLETS, AND VALVE CHAMBERS

SECTION 2831 ITEM F-162 CHAIN-LINK FENCES

Amendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility Installation by Jacking and Boring

CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS

CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS

Special Provision No. 799S15 December 2016

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

CONSTRUCTION SPECIFICATION FOR PIPE SUBDRAINS

CONSTRUCTION SPECIFICATION FOR PIPE SUBDRAINS

CONSTRUCTION SPECIFICATION FOR EXPANDED METAL ANTI-GLARE SCREEN

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR GROUNDING

Special Provision No. 421S01 November 2006

CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS

Sport Systems Canada Inc. Section Angle Framed Bleachers Page 1

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

CONSTRUCTION SPECIFICATION FOR CONCRETE UNIT PAVERS

CONSTRUCTION SPECIFICATION FOR FULL DEPTH REPAIR OF CONCRETE PAVEMENT OR CONCRETE BASE

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

MATERIAL SPECIFICATION FOR STEEL POLES, BASE MOUNTED

CONSTRUCTION SPECIFICATION FOR EXCAVATING, BACKFILLING AND COMPACTING FOR MAINTENANCE HOLES, CATCH BASINS, DITCH INLETS AND VALVE CHAMBERS

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION

CONSTRUCTION SPECIFICATION FOR NEW MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION

CONCRETE FORMWORK. .2 CSA , Supplement No.1 to CAN/CSA , Engineering Design in Wood. .4 CSA O151, Canadian Softwood Plywood.

CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE

CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE

METAL FABRICATION..1 General Conditions and Division 1 shall govern Work of this section.

DIVISION 4100 SITEWORK

CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS

MagnumStone Specifications Gravity

CONSTRUCTION SPECIFICATION FOR GUIDE RAIL ENERGY ABSORBING TERMINALS

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

.2 Section Waste Management and Disposal.

CONSTRUCTION SPECIFICATION FOR METAL TRAFFIC BARRIERS AND METAL RAILINGS FOR STRUCTURES

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

MATERIAL SPECIFICATION FOR SECTIONAL STEEL HIGH MAST LIGHTING POLES

CONSTRUCTION SPECIFICATION FOR EMBEDDED WORK IN STRUCTURES FOR ELECTRICAL SYSTEMS

MATERIAL SPECIFICATION FOR STEEL TRUSS BRACKETS

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

Special Provision No. 540S01 March OPSS 540, Construction Specification for Highway Fence, is deleted and replaced with the following:

(SIZE) MANHOLES CATCH BASINS AND DITCH INLETS -Item No. ADJUSTING AND REBUILDING MANHOLES, CATCH BASINS AND DITCH INLETS - Item No.

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING AND COMPACTING

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.

Section 2 Supplemental Specification 2.11 High Tension Cable Barrier

Special Provision No. 911F04 March 1997

***************************************************************************************************************

Construction Specification for Concrete Unit Pavers

Transcription:

... m NOISE BARRIER - Item No.... m NOISE BARRIER INCLUDING PRECAST NOISE/TRAFFIC BARRIER - Item No.... m NOISE BARRIER ON STRUCTURES - Item No.... m SALVAGEABLE NOISE BARRIER - Item No.... m SALVAGEABLE NOISE BARRIER INCLUDING PRECAST NOISE/TRAFFIC BARRIER - Item No. PRECAST NOISE/TRAFFIC BARRIER - Item No. Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER 1.0 SCOPE 2.0 REFERENCES 3.0 Not Used TABLE OF CONTENTS 4.0 SUBMISSION AND DESIGN REQUIREMENTS 5.0 MATERIALS 6.0 Not Used 7.0 CONSTRUCTION 8.0 QUALITY ASSURANCE 9.0 MEASUREMENT FOR PAYMENT 10.0 BASIS OF PAYMENT 1.0 SCOPE This special provision covers the requirements for the installation of noise barriers. 2.0 REFERENCES This special provision refers to the following standards and specifications: Ontario Provincial Standard Specifications, Construction: OPSS 206, December 1993, Grading OPSS 501, February 1996, Compacting OPSS 609, November 2001, Grounding May 2004 Pg. 1 of 8 SSP599F01

Ontario Provincial Standard Specifications, Material: OPSS 1350, January 1995, Concrete (Materials and Production) OPSS 1352, November 1989, Precast Concrete Barriers Canadian General Standards Board: SGSB 1-GP-181-M1977 & March 1978 Amendment Coating; Zinc Rich, Organic, Ready Mix Canadian Standards Association: CSA Z107.9-00 Standard for Certification of Noise Barriers February 2000 CAN/CSA-S6-00 Canadian Highway Bridge Design Code CSA G164-M1981 Hot Dip Galvanizing of Irregularly Shaped Articles CSA W 47.1-1983 Certification of Companies for Fusion Welding of Steel Structures CSA W 59.1-1982 Welded Steel Construction (Metal-Arc Welding) CAN3-A23.2-M77 Method of Test for Concrete CAN3-A5-M 1983 Portland Cement/Masonry Cement/Blended Hydraulic Cement 4.0 SUBMISSION AND DESIGN REQUIREMENTS 4.01 Submissions 4.01.01 Shop Drawings The Contractor shall submit to the Contract Administrator six (6) copies of all shop drawings for noise barriers at least four (4) weeks prior to the commencement of construction. The shop drawings shall show full details of noise barrier related items, erection procedures and if applicable, connections to structures. All shop drawings shall bear the seal and signature of an Engineer. 4.01.02 Certificates of Conformance 4.01.02.01 Constructed Footings Prior to shipment of the noise barrier from the fabrication facility, the Contractor shall submit to the Contract Administrator a Certificate of Conformance sealed and signed by a Quality Verification Engineer. The Certificate shall state, that the footings have been constructed in general conformance with the contract documents including requirements for the location, top of footing elevation and finish to the specific tolerances. 4.01.02.02 Noise Barrier Installation Upon completion of the installation of the noise barrier, the Contractor shall submit to the Contract Administrator a Certificate of Conformance sealed and signed by a Quality Verification Engineer. The Certificate shall state that the installation has been carried out in general conformance with the contract documents and shop drawings. May 2004 Pg. 2 of 8 SSP599F01

4.02 Design Requirements The Contractor shall construct a noise barrier with the following minimum design features. 4.02.01 Reference Wind Pressure Reference wind pressure: *. 4.02.02 Acoustics The minimum acoustical characteristic of the noise barrier shall be such that the noise barrier is **. 4.02.03 Aesthetics The exact colour and pattern for the barrier will be specified following award of the contract but will be within the following parameters: Number of colours adjacent to highway ***. in the proportion of Number of textures in the proportion of Number of colours adjacent to residential property ***. in the proportion of Number of textures in the proportion of Final colour selections will be determined by the Contract Administrator at the point of manufacture from samples prepared by the Manufacturer. 5.0 MATERIALS The Contractor shall only use one type of barrier except on those contracts where additional barrier types are specified for use on structures or for differing sound absorption requirements. 5.01 Noise Barrier Noise barriers shall be supplied in accordance with OPSS 128. 5.02 Welds All welds shall conform to CSA W59.1 and CSA W47.1. May 2004 Pg. 3 of 8 SSP599F01

Steel posts to which special attachments are welded shall be hot dip galvanized after fabrication according to the requirements of CSA Standard G164-M. 5.03 Silicone Sealant Silicone sealant shall be CGE SILPRUF 2000 Series. 5.04 Post Footings Concrete in post footings shall be 20 MPa according to the requirements of OPSS 1350. 5.05 Granular Materials Granular material shall be as specified elsewhere in the Contract. 7.0 CONSTRUCTION 7.01 Site Grading and Preparation Grading and berm construction, which is associated with the barrier installation, shall be completed to within 25 mm below the bottom of the barrier prior to constructing the barrier footings. All grading shall be in accordance with OPSS 206. Excavated material not designated to be incorporated as backfill shall be managed as specified elsewhere in the Contract. Earth and granular materials shall be compacted according to the requirements of OPSS 501. There shall be no visible gaps between any barrier panels nor beneath the bottom panels after completion of the barrier. Tree pruning and removal shall be kept to a minimum. 7.02 Highway Signs Existing highway signs shall be maintained. If necessary, these signs may be placed on temporary stands during construction. 7.03 Footings The depth of the footings shall be determined by the Contractor in accordance with CAN/CSA-S6-00 Canadian Highway Bridge Design Code Clause 12.6.2 based on the following soil design parameters. Sta. to Sta. Soil Design Parameter **** May 2004 Pg. 4 of 8 SSP599F01

7.03.01 Footings in Earth Where footings are to be installed on or within 1 m from a downward slope of 3:1 or steeper, the shop drawings shall reflect this and shall note an increase in embedment depth of a minimum of 0.5 m greater than the requirements of the Canadian Highway Bridge Design Code. Concrete for drilled footings shall be cast entirely against undisturbed soil. If other than drilled footings are necessary, the footing shall be formed and the excavation shall be backfilled with granular materials and compacted to at least 95% Proctor. For concrete posts, the concrete working slab below the construction joint in the footing shall be placed a minimum of 4 hours prior to installing the post. Where required, the tops of all footings are to be shaped to provide for full horizontal seating of panels, the remaining surface area is to be sloped away from the post so as to shed water. Stepped footings are to be constructed to suit grade changes. The concrete in the footings shall be cured for a minimum period of 5 days before the noise panels can be installed. 7.03.02 Footings in Rock When rock is encountered within the specified excavation depth for footings in earth, the footing shall be constructed in accordance with the "Footings in Earth" design down to a minimum of 300 mm into the solid rock or 1.5 m below the top of footing grade, whichever is the greater depth. All excavations into rock shall be backfilled entirely with concrete. The excavation above the top of rock may be formed to the required dimensions and the remainder of the excavation backfilled with granular material. 7.04 Posts The barrier shall be constructed to the line and grades specified with a tolerance of ±10 mm. The posts shall be plumb within a tolerance of ±10 mm in 5 m. Galvanized surfaces which are abraded shall be cleaned and painted with a zinc-rich paint conforming with CGSB 1-GP-181M. Changes in horizontal direction shall be made using special arrangements of the posts as specified by the manufacturer. 7.05 Panels The profile of the barrier shall be installed to match the ground profile up to the maximum grade specified on the drawings. To accommodate ground profiles greater than the maximum grade, the barrier shall be stepped in accordance with manufacturers recommendations. All panels and posts shall be cleaned of any oils, dirt and debris. 7.06 Noise Barriers on Structures Noise barriers shall be attached to the structure as specified in the contract. May 2004 Pg. 5 of 8 SSP599F01

Flashing shall be installed according to the details in the contract and in such a manner that water will not pond on the structure. Upon completion of the flashing installation the Contractor shall apply silicone sealant according to the manufacturers recommendations and as follows: (a) (b) (c) all surfaces to receive sealant shall be clean and dry; the flashing surface is to be wiped with Naphtha to remove oils and dirt; and deleterious material is to be removed from the concrete surface by light wire brushing. 7.07 Precast Noise/Traffic Barriers The precast noise/traffic barrier units shall be constructed to the line and grades specified in the contract with a tolerance of ±10 mm. All related posts shall be plumb within a tolerance of ±10 mm in 5 m. When changes in horizontal alignment greater than 2 degrees or when changes in vertical alignment greater than 2% between adjacent units occur, the ends of the units shall be manufactured with the appropriate skewed end detail. Units required to match ground profiles with grades in excess of 2% shall be manufactured with skewed ends to match vertical post detail. The space between each unit on the traffic side surface shall not exceed 25 mm at the base of the traffic barrier. The difference in elevation between adjacent units shall not exceed 25 mm. Any levelling or plumbing of units shall be done solely by the use of mortar bedding on the post footings. The granular base for the precast noise/traffic barrier units shall be placed in such a manner as to ensure that there are no voids between the bottom surface of units and the granular material and that the units are set to the correct line and grades. The precast noise/traffic barrier units shall be set into a bed of fresh mortar at the post footings. The top of footings shall be clear of foreign material, ice, snow or water. The precast noise/traffic barrier units shall be positioned so as to have complete contact with the post flange along the traffic side of the units. The top of the noise/traffic barrier units shall be cleared of any foreign or loose material, ice, snow, or water prior to installing the noise barrier panels. The point of contact between the top of the precast noise/traffic unit and the bottom of the noise barrier panels shall be sealed with either mortar, neoprene or silicone sealant on both sides of the noise barrier panels along the entire length. 7.08 Salvageable Noise Barriers Salvageable noise barriers when specified are to be installed in accordance with the manufacturer's instructions. 7.09 Connection to Existing Chain Link Fence Where sections of an existing chain link fence are to be removed and/or replaced with a noise barrier, the Contractor shall ensure that a sufficient length of existing chain link security fence is maintained in good condition to adequately allow for connection to a new post at locations shown in the Contract. May 2004 Pg. 6 of 8 SSP599F01

7.10 Underground Utility and Drainage Crossings Shortened post spacing will be allowed to avoid placing posts on top of utilities and drainage facilities that interfere with the originally proposed barrier footing location. 7.11 Existing Overhead High Voltage Lines Where the potential of arcing exists due to the close proximity of existing overhead high voltage lines, metal noise barrier panels and girts must be grounded in accordance with the requirements of OPSS 609. 7.12 Personnel The Contractor shall engage the services of an Engineer who will act as the Quality Verification Engineer. 7.13 Quality Control The Contractor shall destructively test a minimum of one in 500 concrete noise barrier panels to verify: - depth of concrete cover to the reinforcing steel - position of the reinforcing steel - thickness of concrete and sound absorptive layers Where noise barrier includes concrete panels without the sound absorptive layers, the Contractor shall carry out compressive strength according to CAN3-A23.2-M and CAN3-A5-M and salt scaling resistance tests according to OPSS 1352. The Contractor shall submit to the Contract Administrator the destructive test results, compressive strength test results and salt scaling resistance test results at least 7 days prior to the installation of the panels. The compressive strength and salt scaling test results shall not be more than 12 months old at the time of submission. 8.0 QUALITY ASSURANCE The Contractor shall install noise barrier materials, which are visually uniform in appearance in terms of colour, pattern and texture. Uniformity of appearance is subject to approval of the Contract Administrator. Noise barrier panels must visually match adjacent panels. Inspection will occur during construction after installation at a distance of approximately 15 metres from the noise barrier. 9.0 MEASUREMENT FOR PAYMENT Measurement for the above items is by Plan Quantity as may be revised by Adjusted Plan Quantity, for the horizontal length in metres, of the specified height of noise barrier. Transitions between barrier heights will form part of the higher barrier, and terminations will form part of the adjoining barrier. At the discretion of the Contract Administrator, if unidentified difficult soil conditions, i.e. rock, shale or unstable earth is encountered above the design footing depths, work necessary to complete the design requirements such as caissons, dewatering, additional concrete or different augering equipment, will be paid for as extra work. May 2004 Pg. 7 of 8 SSP599F01

10.0 BASIS OF PAYMENT Payment at the contract price(s) for the above tender item(s) shall be full compensation for all labour, equipment and material necessary to construct the noise barrier(s) and for providing test samples. Grading of up to a depth of 300 mm shall be included as part of the noise barrier item. For earth grading requirements greater than 300 mm in depth, the full depth of grading is provided under the earth excavation item. May 2004 Pg. 8 of 8 SSP599F01