Thermal Pile Installation

Similar documents
Renewable Energy Solution Using building foundations It s a no brainer! Tony Amis GI Energy Business Development Director

Learning Legacy Document Duration of data recorded (approx.) 1

Review of Thermal (Energy) Piles

Research Seminar Current and Future Research Into Ground Source Energy Thursday - 21st January 2010, Energy Piles & Diaphragm Walls

Sample Specifications for Testing Foundations with the Thermal Integrity Profiler (TIP)

Geothermal Tunnel Linings. Principles of Geothermal Tunnel Linings

GSHPA Thermal Pile Standard

1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3

Crossrail Brief to INCOSE Chris Sexton Technical Director

GSHPA Thermal Pile Standard

Soil-Structure Interaction (SSI) Testing Facility and Capabilities at Lehigh University

Lesson 2 Substructure. Dr S.Sreenath BSc Engg, MSc Engg, MSc (ICM), MBA, PhD

Can sustainability win you more work? 10th April 2013

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

GSHPA Thermal Pile Standard Develop

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

SECTION DRILLED CONCRETE PIERS AND SHAFTS

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

ITEM 416 DRILLED SHAFT FOUNDATIONS Materials. All materials shall conform to the requirements of the pertinent items as follows:

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

03/12/2012. JSPS/CSIC international symposium on Smart Infrastructure and Construction. Business opportunities for Smart Infrastructure

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk

SPECIAL SPECIFICATION Thermal Integrity Profiler (TIP) Wire Cable Testing of Drilled Shafts

ITEM 432 TUNNEL CONSTRUCTION

GeoBIM Geospatial World Forum Crossrail: A case Study in Project Information Management. Malcolm Taylor 28 th May 2015

Diaphragm wall Construction

Company Profile. projects, with values in excess of 500K, and technically complex projects.

Design and Construction of Drilled Full Displacement Piles using the Penetration Resistance Method

Quality Control of Drilled Piles

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

SECANT PILE. Introduction:

SAFE SYSTEMS FOR PILING OPERATIONS

Eglinton Crosstown LRT Construction Liaison Committee

CROSSRAIL INFORMATION PAPER D24 TUNNELLING DURATION AND CONSTRUCTION STRATEGY

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN

SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015

Experts in tunneling with Tunnel Boring Machines

Lattice Plate Flooring

UNDERPINNING A CRANE FOUNDATION

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Fleet Elementary School

Schnabel Foundation Company

BUILDING THE MERSEY GATEWAY a step by step guide

RAUGEO GROUND-SOURCE SOLUTIONS RENEWABLE SOURCE OF HEATING AND COOLING

Introduction to Geothermal Comfort Systems in INDIA

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

Note: Although proprietary brand names are referred to in this document, the FPS does not recommend any particular method or system.

Crossrail Environmental Statement

Green Data Center CRYOGEL Ice Ball Thermal Storage

Misan University - College of Engineering Civil Engineering Department

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Construction Technology B (CON4313)

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

ASSEMBLY INSTRUCTIONS RESIDENTIAL SOLUTION CROSSRAIL GROUND MOUNT SYSTEM USA

Civil Engineering Construction I (CBE5031)

Drilled Shaft. Inspection. HQ Construction Office HQ Geotechnical Division

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP

Piling & Contaminated Land. Dr Derek Egan Technical Director Keller Ltd

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

INNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

GEOTECHNICAL SERVICES

Concrete Framing Systems - Walls and Columns

Lesson 4. Construction Techniques and Materials. Learning Outcomes. Basic Construction

The basic elements of the system include: Buried loops of piping (the ground loop); A biodegradable liquid antifreeze;

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE

A. This Section includes exterior piping for vertical, direct-buried, ground-loop, heat-pump systems that operate between 23 and 104 deg F.

Large-diameter bored piles and Large-hole drillings Applications

HIGH TENSION LOAD TRANSFER USING BORED PILES FOR SOUL APARTMENTS, Surfers Paradise

Lesson 7 REINFORCING CAGE. Version 1-1/

USING DESIGN-BUILD TO MITIGATE RISK TO A MAJOR WATER DELIVERY SYSTEM ROCKY MOUNTAIN DBIA PRESENTATION MAY 20, 2016

SECTION DRILLED CONCRETE PIERS AND SHAFTS

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

Ground Freezing for Tunnel, Shafts, and Adits

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment

METHOD STATEMENT for INSTALLATION OF MICROPILE

GEOTHERMAL HEAT PUMPS CONFIGURATIONS/INSTALLATION

London Crossrail Transport Stations Receive Superior Waterproofing Solution

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text.

TECHNOLOGY. Continuous Flight Auger

Ground Improvement Piling Piled Retaining Walls Enlarged Head Piles Innovations.

Dril ed Shaft Inspector CBT Lesson 5 Contractor and equipment Arrive On-Site Learning Objectives Inspector s Role

PILING PART-VI CONSTRUCTION AND INSTALLATION OF RCC BORED CAST IN-SITU PILES

John James Audubon Bridge

A brilliantly simple Foundation Method

Case examples for the construction of complex basement

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

Soil Services SCS Ferretti International Soil Services Soil Services Industrial Construction Infrastructures Real Estate Soil Services Soil Services

703 - DRILLED SHAFTS SECTION 703 DRILLED SHAFTS

Final Estimates Level 2

Direct Drilled New Micropile TITAN 127/111 for Underpinning Roman Bullring in Barcelona, Spain

WELCOME TO THE PILE DRIVING INSPECTOR COURSE

Performance Control Tests and Numerical Simulations for Concrete in Deep Foundations

DRILLED SHAFT LOG (REV ) Project Name Page 1 of 6

Drill Shaft Contractor and Equipment Arrive On-Site CBT Script

Basement & Waterproofing

geoexchange as an alternative energy source DESIGN APPROACHES

6 BIM FAILURES. The design is complete, contracts are written, the project team is assembled and ready to build. Optimism is at its peak!

Transcription:

Thermal Pile Installation Peter Smith Geothermal Manager Slide 1

Thermal Pile Standard Overview 1 Preamble (as BHS) 2 Regulatory & Government Agency Requirements (as BHS) 3 Contractual Responsibilities 4 Training Requirements 5 Design 6 Thermal Response Testing 7 Pipe Materials and Jointing Methods 8 Thermal Pile Concrete 9 Loops Installation 10 Pressure Testing 11 Indoor Piping / Values (as BHS) 12 Thermal Transfer Fluids (as BHS) 13 Design Drawings 14 Monitoring and Checking 15 Alterations Slide 2

Contents 1. The integration of the loops into various construction activities without loss of loop integrity Loop installation good practice Standard Rotary and CFA piles loop Loop Protection Testing during installation. 2. The integration of a thermal pile solution into the construction programme, with cause minimal delay and disruption Design Project performance Coordination 3. Thermal piles on Crossrail Station Boxes (Bond St) Slide 3

Potential defects Scratch or abrasion Creasing Puncture Misuse Lack of understanding Slide 4

Loop installation: Good practice Loops attached to reinforcement cage depends on the pile technique and depth of installation Plastic ties are recommended Optimum loop fixing on cages is between bars Fishtails must be straightened Loops filled with water and capped off Fusion welds can be used in the factory manufacture of loops but best avoided during pile installation Consider any methods to reduce loop abrasion / scratching Slide 5

Continuous Flight Auger (CFA) Sequence Loops on central bar Bore Pump concrete Withdraw auger Finish concrete Plunge loop then cage Slide 6

CFA Reinforced shoe Technique No surging Loop length restriction (circa 20m) Additional craneage and central steel bar Approx 30% cost uplift over normal piling rate (small dia) Loops Slide 7

Rotary Sequence Loops fixed on cage Bore Place Casing Bore to depth Place steel and loops Pour concrete, extract casing Slide 8

Rotary Loops positioned inside (preferable) or outside cage - depends on depth of pile Loops can extend beyond the cage base No depth limit 10 / 15% cost uplift over normal piling rate Protect loops from vertical impact of concrete using appropriate length of tremmie tube Technique Slide 9

Rotary Loops Loops fixed on inside and extend below the cage using a cage former Loops fixed on outside 52m deep on full depth cage Placed under bentonite Slide 10

Protection Foam around loop, encased in plastic as a standard Prevent ingress of materials likely to block fluid flow Protect from damage of follow on trades. Slide 11

Testing Test at every stage to confirm ongoing system integrity Use the test as a handover of responsibility between contractors Variety of tests depending on the construction stage Tests to be independently witnessed Slide 12

Recommended Testing and hold points GSHP Contractor (1) Piling contractor (2-5) Groundwork contractor (6) GSHP contractor(7-9) Slide 13

Observation Types of Test Bi directional Flush test Type A pressure test Pressure test on manufacture + docs Type B pressure test - 8 bar 10 mins, reduce to 4 bar 30 mins Type C pressure test same as type B but then held for 24 hrs Acceptance is no loss of pressure Slide 14

Integration of thermal pile projects Thermal piles are an integral part of the building structure A scheme implementation will impact on programme and several other trades This impact on programme and trades needs to be understood and managed Early engagement from the cross discipline project team Architect / Consulting Engineer Building Systems M & E Contractor Piling Contractor Main Contractor Ground worker M & E Engineer M & E Contractor Geothermal Geothermal Contractor Contractor Slide 15

Multi discipline Integration - Design Geotechnical, Structural and M&E designs must be integrated and compatible. Redundancy levels within each element should be mutually agreed between all parties. Redundancy arises from risk in: o Pile installation o Operational damage (ie trimming) o Geothermal design (thermal conductivity) Clash with headering and drainage Slide 16

Integration Project Performance The scope and responsibility of each package needs to be clearly and fully defined Procurement route needs careful consideration several different options are available Co-operation and Interface management is essential during construction for a smooth programme BIM techniques are useful Slide 17

Co-ordination Recommended as official role Most important during construction phase Ideally from the Main Contractor o Project management experience o Building development & HVAC experience Typical Concurrent activities: Excavation, Spoil removal, concreting, breaking down piles, geothermal headering Slide 18

Crossrail Philosophy Committed to the environment Required to have 10% renewable energy Decided to use the deep station boxes and foundations for thermal collectors (ie diaphragm wall and bearing piles) Cost of the collectors borne by Crossrail Benefit available for future over site developments Slide 19

Crossrail and Geothermal Slide 20

Crossrail Geothermal Capacity Contract No of Piles / Panels Total linear m of pipe (m) CO2 potential saving Heating peak power Cooling peak power (m) (T /annum) (kw) (kw) Paddington Integrated 41 25,000 200 420 240 Bond St WTH 43 2,449 28 186 186 Bond St ETH 57 8,559 49 340 340 TCR West 65 4,729 21 160 160 TCR East 34 1,710 9 75 75 Fisher St 18 2,900 10 60 60 Liverpool St Blomfield 62 15,000 11 150 80 Liverpool St Moorgate 18 7,200 14 70 25 Farringdon West 26 3,432 16 120 120 Farringdon East 21 3,182 12 90 90 Totals 385 74,161 370 1,671 1,376 Slide 21

Crossrail - Bond Street Station Eastern Ticket Hall Western Ticket Hall Slide 22

Bond St ETH Elevation Ground Level 30m Thermal piles Slide 23

Bond St ETH 57 Thermal pile 1.8m diameter 67m deep 6 loops per pile 30m Effective length due to deep cut off Slide 24

Bond St ETH Loop design Slide 25

Bond St ETH Access tunnels Thermal piles at base of shaft Slide 26

1.2m D-Wall 44m deep 29 panels 2 loops /panel Bond St WTH 14 Thermal piles 2.5m diameter 20m deep 6 loops per pile Slide 27

Crossrail WTH Loop fixing Diaphragm wall loops on outside of panel Thermal loops prefixed on inside of reinforcement Slide 28

WTH - Capping beams with loops Loops collecting up inside the capping beam Loops at central collection point Slide 29

The good practices outlined and illustrated in this presentation, are all included in the Thermal Pile Standard. So have a successful installation and Happy Reading! Thank You Slide 30