Tall Trees HOA Update

Similar documents
Shadow Lake Woods HOA

Suncoast Parkway 2/SR Toll 589 FPID: & 3, -4

1.4 Analysis of Alignment Alternatives

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION. Project Commitment. Public Yes Design/ Permitting (Prior to Construction Beginning)

SR 50 PD&E Study

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017

NOISE REPORT ADDENDUM July 2003

The Main Street Bridge - Supporting Transportation Systems

I-20 East Transit Initiative

STAFF REPORT. About percent depending on how much is added in the outdoor storage area (max allowed where storm sewer exists is 90 percent).

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

City of San Juan Capistrano PROJECT UPDATE ORTEGA HIGHWAY (SR-74) CITY- SEGMENT WIDENING PROJECT (CIP 14107) December 15, 2015 FOR THE

NOISE STUDY REPORT DESIGN ADDENDUM

Reconstruction Project Update

LOCATION HYDRAULIC REPORT

State Road (S.R.) 12 (Florida Arts Trail PD&E)

NOISE STUDY REPORT. for the WEKIVA PARKWAY (SR 429)/SR 46 REALIGNMENT PD&E STUDY. Orange, Lake, and Seminole Counties, Florida

Route 7/15 Norwalk Project - Update Winter Route 7/15 Norwalk. Presentation to Silvermine January 30, 2017 CTDOT State Project #

Phase II: Proposed (regulated) Impervious in disturbed area (ac) Long Lake Existing Impervious in disturbed area (ac)

SECTION 9000 MAINTENANCE SERVICES

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Concept, Feasibility & Mobility Studies. Southport Connector Expressway

Alternatives Evaluation Methodology

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

County Road 61 (Shady Oak Road): CR 3 (Excelsior Boulevard) WELCOME. November 1, 2012

Engineering Design Services for Safety Improvements along CR 476 from the Hernando County Line to US 301 (SR 35) Sumter County, Florida

2018 ACEC OF FLORIDA OUTSTANDING PROJECT AWARDS (OPA) PROGRAM PROJECT NOMINATION FORM

Gordie Howe International Bridge Public Information Meeting. Detroit, Michigan July 19, 2017

DRAFT AIR QUALITY TECHNICAL MEMORANDUM

I-20 East Transit Initiative

Exposition Light Rail Transit Project

The Good, The Bad, and The Ugly

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM

BQE Atlantic to Sands Project Overview. 1. Project Background 2. Current Conditions & Findings 3. Upcoming Activities

Integrated Transportation Plan. TAC Meeting September 16, 2014

POLICY FOR CONSTRUCTION OF NOISE BARRIERS IN RESIDENTIAL AREAS

RESOLUTION NO:

Indiana ABC Experience

IM 0291(108)0 UNION COUNTY INDEX OF SHEETS. Index of Sheets. Estimate of Quantities. Table of Fence Quantities. Details for Right-of-Way Fence

FORT WORTH. Photo by Liam Frederick. November 17, 2015

<33 February OMF South Alternatives Evaluation Technical Memorandum

Final Air Quality Report

CENTRAL FLORIDA EXPRESSWAY AUTHORITY. SR 408 Eastern Extension PD&E Study

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

9.0 I-26 & I-526 Interchange Improvements

5.3 Noise Impact Analysis

POLK COUNTY TPO Polk County 2060 Transportation Vision Plan Final Report. ADOPTED June 18, 2009

WELCOME EAST LINK OVERLAKE MASTER PLANNED DEVELOPMENT

FTBA 2018 Construction Conference Major Projects Update

TRANSFORM 66 Outside the Beltway Project Update March 2018

NEPA and Design Public Hearings

MOUNTAIN HOUSE SPECIFIC PLAN II

Florida Department of Transportation District Four KICK-OFF MEETING. I-95 at Southern Boulevard (SR 80) Project Development and Environment Study

A PPEARANCE REVIEW BOARD

Conceptual Design Report

Noise Abatement Decision Report. Addendum. Supplemented by the August 2015 Noise Study Report Addendum

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions

Pensacola Bay Bridge Replacement Design Build. Industry Forum. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer

SECTION 5 Environmental Commitments

MID FLORIDA LOGISTICS PARK

TAMPA BAY NEXT MAJOR PROJECTS UPDATE

Curb and Gutter Replacement Project Phase I

Requests Conditional Use Permits (Craft Brewery & Open Air Market) Staff Recommendation Approval. Staff Planner Kristine Gay

I-229/26 th St/Southeastern Ave Reconstruction Project

ENV125. Basics of Noise and Policy. Date. Date. Footer Text

Municipal Class EA Process

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

Planning Commission November 20, 2013 URBAN FORESTRY LANDSCAPING CODE UPDATES

Barr Road Quarry (Site N) Frequently Asked Questions Last updated: November 19, 2007

CMNAA. Central Manatee Network Alternatives Analysis Alternatives Public Meeting CMNAA STUDY PROCESS. STUDY AREA 17th St. W

The rezoning application and proposed transportation facility warrants consideration.

Design-Build and Design-Bid-Build

Factor Potential Effects Mitigation Measures

a. Reevaluation Phase: Design Change (FM & ) b. Document Type and Date of Approval: Type 2 Categorical Exclusion approved 7/21/2010

4.10 LAND USE ENVIRONMENTAL SETTING

Harlem Avenue Interchange Design Discussion. August 24, 2015

Public Notice October 21, 2016 U.S. Army Corps of Engineers Charleston District

APPENDIX C NOISE STUDY TECHNICAL REPORT

Planning Commission Agenda Item

The Gateway Expressway FTBA Conference. February 2-3, 2017

County of Sonoma Agenda Item Summary Report

Beckett Bridge PD& E Study Elected Officials Kick-Off Meeting

FASTLANE Grant Project US-69 through Calera. Oklahoma Traffic Engineering Association 2017 Fall Meeting

Attachment No. 1 Council Report Attachment

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

Frequently Asked Questions Connecting Palo Alto

SEPA Modification Application

6 93 Corridor TUNNEL CROSS SECTION 42.0' 24.0' WITH 21.0' WITHOUT 1.5' 6.0' 12.0' 12.0' 6.0' 4.0' 0.5' CLEARANCE ENVELOPE (36' W x 16.

1. APPLICANT: RSA Architecture is the applicant for this request.

Ledges East Master Owners Association. Architectural Guidelines for the Community-Wide Areas

Final Air Quality Report

TH 100 Interchange & Auxiliary Lane from 36 th Street to Cedar Lake Road

Appendix H Mitigation Plan

T.H. 100 Reconstruction in St. Louis Park Environmental Assessment. Appendix C Traffic Noise Analysis Report

Organization. Project Management Institute, Olympia Chapter Date Nov. 20, 2012

Highway 417 Bridge Replacement

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

I-4 Beyond the Ultimate Project Development & Environment (PD&E) Reevaluation Study FROM WEST OF SR 528 (BEACHLINE EXPRESSWAY)

Transcription:

A Regional Transportation Solution Tall Trees HOA Update June 9, 2016

Meeting Agenda I. Brief Section Update II. List of Community Concerns Received III. Responses to Each Concern IV. Recap Action Items V. Remaining Questions & Discussion

Section 8 2.63 Miles Interchange Completes Beltway Construction Cost: $208 Million Aesthetic Walls 23 New, Replaced Bridges

Section 8 - Changes Since 2013 Design Update Eliminates Impact to Seminole Towne Center Eliminates Third & Fourth Level Flyover Bridges Keeps SR 417 Ramp Connection to International Parkway Adds New Pond Location South End of Atlantic & Metz Avenues

Section 8 - Change Since March 29, 2016 Public Workshop To Maintain a Consistent Border Width, FDOT has Adjusted the Right of Way (ROW) Line to Clip the Two Properties in the Corner of Tall Trees. FDOT ROW Acquisition Staff will be in Touch with these Home Owners.

Section 8 - Rendering at Tall Trees Wilson Road: 4 Bridges Height: 23 Ft. (Top of Barrier Wall) Landscaping: Future Project Safety Lighting: Bridge Underdecks & Interchanges

Section 8 Update Schedule Right-of-Way Acquisition: November 2016 March 2018 Some Advanced Acquisition (Total Takes) Has Occurred Advertise for Bids: January 2018 Construction Begins: October 2018 Open to Traffic: Late 2021 (Wekiva Parkway Complete)

We ve Heard You - List of Community Concerns Received 1. Move the bridges over Wilson Road at least 100 yards west of the community. Ideally, place the bridges directly between the edge of Tall Trees and Wilson Elementary. 2. Leave the trees and natural barrier to buffer the parkway noise. If a natural barrier is not permitted, a sound wall would be our second choice. 3. Concerns about neighborhood children walking and biking safely on Wilson Road to Wilson Elementary during construction and beyond. 4. Concerns about the lengthy process of pile driving during the construction phase. Request for sensors be used to ensure that there is no destruction to property. 5. Concerns about children in the back corner of the neighborhood that are on the autism spectrum and have medically documented issues with loud noises. 6. Concerns about the environmental impact to the adjacent property regarding the presence of indigo snakes, gopher tortoises and bears.

Responses to Individual Concerns 1. Move the bridges over Wilson Road at least 100 yards west of the community. Ideally, place the bridges directly between the edge of Tall Trees and Wilson Elementary. Response: The Wekiva Parkway alignment was approved by the Federal Highway Administration and the Seminole County Board of County Commissioners in 2012. The Section 8 alignment must connect with Section 7A and existing SR 417. If the alignment were shifted west, it would require taking more homes along Pacific, Atlantic and Metz Avenues. The alignment, therefore, cannot be shifted between Tall Trees and Wilson Elementary.

Responses to Individual Concerns 2. Leave the trees and natural barrier to buffer the parkway noise. If a natural barrier is not permitted, a sound wall would be our second choice. Response: Vegetation The parcel slated for floodplain compensation west of the community must be scraped down to avoid flooding. FDOT will try to save what trees we can. Once complete the pond s eastern boundary will be replanted with landscaping. The Department is prepared to work with the community in developing this landscaping plan. Landscaping is installed after the major project work is completed. Noise A noise study was done during the PD&E Study; the study determine noise abatement was not warranted in this location. In light of community concerns, and given some of the changes since the PD&E Study, the Department will conduct a noise study update. We will provide the noise study update results to the community.

Responses to Individual Concerns 3. Concerns about neighborhood children walking and biking safely on Wilson Road to Wilson Elementary during construction and beyond. Response: FDOT is very conscious of the need to protect pedestrians and bicyclists during construction. There are existing sidewalks along Wilson Road that will be maintained during construction. The contractor will have to devise a plan to maintain pedestrian access. Barriers could be used to channel and protect pedestrians during construction.

Responses to Individual Concerns 4. Concerns about the lengthy process of pile driving during the construction phase. Request for sensors be used to ensure that there is no destruction to property. Response: Property owners concerned about possible damage from vibration from future construction projects are encouraged to take pictures and video of the interior and exterior of their home to serve as baseline. FDOT can require the winning design-build team to conduct a pre-vibration assessment and monitoring in this location.

Responses to Individual Concerns 5. Concerns about children in the back corner of the neighborhood that are on the autism spectrum and have medically documented issues with loud noises. Response: Noise is an unavoidable impact of building these types of major transportation improvements. We will provide advanced notification prior to the beginning of pile driving. As noted, FDOT will conduct a noise study update.

Responses to Individual Concerns 6. Concerns about the environmental impact to the adjacent property regarding the presence of indigo snakes, gopher tortoises and bears. Response: Goal of Wekiva Parkway: Provide a mobility solution while helping to protect natural resources around the Wekiva River. Wildlife biologists will continue to be involved when we re building parkway sections. Black Bears: Contractors will be instructed to avoid leaving trash and food around the work site that would attract wildlife. Gopher Tortoises: Initial surveys indicate burrows in various locations in and adjacent to the project. Prior to construction, additional surveys will be conducted, a permit secured and the gopher tortoises will be relocated to a state-licensed recipient site. Silt fence will be installed afterwards to keep animals outside the right of way East Indigo Snake: Follow USFWS protection guidelines Educate construction staff of the potential presence of Indigos & their appearance Place instructional posters at the job site warning not to harass the snakes If crews find one, they are not to disturb the snake and allow it to move away on its own.

Section 8 Recap Action Items 1. The floodplain compensation pond will be landscaped after construction. 2. The Department is prepared to work with the community in developing this landscaping plan. 3. The Department will conduct a noise study update. We will provide the noise study update results to the community. 4. The Section 8 contractor will devise a plan to maintain pedestrian safety and access along Wilson Road. 5. Property owners concerned about vibration damage should take pictures and video of the interior/exterior of their home to serve as baseline. 6. FDOT can require the winning design-build team to conduct a pre-vibration assessment and monitoring in this location. 7. FDOT will provide advanced notification prior to the start of pile driving. 8. FDOT and the contractor will follow state and federal wildlife protection guidelines. This includes relocating gopher tortoises to a state-licensed recipient site.

Remaining Questions?

For More Information: Mary Brooks Public Information Officer C: 407-694-5505 E: Info@wekivaparkway.com W: www.wekivaparkway.com

THANK YOU!

Q&A Slides The following slides are for Q&A only.

Section 8 Tolls Toll-By-Plate collects tolls by taking a photo of a vehicle s license plate as it travels through an FDOT tolling location. It then mails a monthly bill for the tolls, plus a $2.50 administrative charge, to the registered owner of the vehicle.

Section 8 Projected Traffic Opening Year (2021) Design Year (2032) 43,000 82,500 (Vehicles Per Day) (Vehicles Per Day)

Section 8 Additional Preliminary Design Details I-4 Ultimate Connection: Accommodates I-4 Ultimate Typical Section Used Through Downtown Orlando (Corridor Consistency) I-4 Express Lanes Will Not be Constructed with this Project Provides Direct Connection from Future I-4 Express Lanes to SR 417 and SR 429

2020 2019 2021 2019 2018 2020-21 2021 2021 2017