Planning, Design and Estimation of a Check Dam B.H. Ramathilagam 1, S. Murugesan 2, M. Manikandan 3, A. Arumugaraja 4, Assistant professor 1 2, 3, 4

Similar documents
Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Inflow pipe. Drain. Drain

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

PART B. Irrigation Design Drawing

10(a) Bridge and culvert design information

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)

Figure Inlet protection (Source: Minnesota DOT)

Narora Weir A Historical Perspective of Piping Theory

STREAM CONDITION & EROSION CONCERNS IN CITY OF FORT WORTH. Ranjan S. Muttiah Stormwater Management City of Fort Worth

Temporary Watercourse Crossing: Culverts

Fabric Drop Inlet Protection

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

Hydraulics of Jinnah Barrage; Existing Structure and Rehabilitation Alternatives

Performance Assessment of Taunsa Barrage Subsidiary Weir for Long Term Rehabilitation Planning

Solution for Irrigation Engineering

Diversion Dikes. Fe=0.95

Asst.Prof.Dr. Jaafar S. Maatooq. 1 st Semester HYDRAULIC STRUCTUER, KINDS & FUNCTIONS 1 of 26

Types of Hydropower Facilities

Inlet Protection. Fe= (Depends on soil type)

Riprap must be placed uniformly and carefully to eliminate any weak area where erosion can get a start.

PART 1 GENERAL REQUIREMENTS

Block and gravel filters can be used where velocities are higher. Reduces the amount of sediment leaving the site.

Construction Inspection Checklists

[1] Level spreaders can release sheet flow down steep slopes, but the level spreader itself must be constructed across a level gradient.

Temporary Watercourse Crossing: Fords

SE-6 GRAVEL BAG BERM. Objectives. Potential Alternatives

LINED WATERWAY OR OUTLET (Feet) Code 468

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL

Irrigation Structures 2. Dr. M. R. Kabir

D EROSION AND SEDIMENT CONTROL. Table of Contents

Irrigation Structures 1

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Gabions. Introduction

Common Construction-Site BMPs Quick Reference Guide

EROSION CONTROL GENERAL NOTES EC JAN 2017 C.B.

SECTION EROSION AND SEDIMENTATION CONTROLS

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

COFFERDAM (no.) CODE 803

Pond Closure - Case Study[TP1]

Filter Tube Barriers (Instream)

PROJECT SCREENING MATRIX: A User s Guide

Sediment Basin. Fe= (Depends on soil type)

Chapter 2: Selecting Best Management Practices (BMPs)

These potential changes and their implications are outlined in Annex 1.

Drop Height For Channel Erosion Control

THE CONSTRUCTION PHASES OF THE NEW NAGA HAMMADI BARRAGE COFFERDAMS

LOW WATER CROSSINGS, fords, or drifts, as they

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT

4. Ponds and infiltration BMPs can achieve 60 to 100% removal efficiencies for sediment.

Modular Sediment Barriers (Instream)

Fig: Alignment of a ridge or watershed canal (Head reach of a main canal in plains)

Ministry of Forests, Lands and Natural Resource Operations

Feasibility of Pipe Distribution Network (PDN) over Canal Distribution Network (CDN) For Irrigation

Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

Suggested Stormwater Management Practices For Individual House Lots

Dam Safety and Low Cost Spillway Designs

Stormwater Local Design Manual For Houston County, Georgia

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Irrigation Design (1) IHD302

TD 603. Water Resources Milind Sohoni sohoni/ Lecture 10: Minor Structures for Ground and Surface Water. () March 23, / 31

Rock Sock (RS) Rock Sock height.

R I Freshwater Wetlands Buffer Zones

Methods of Streamflow Analysis

Erosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions)

Storm Drain Inlet Protection

CONSTRUCTION PLAN CHECKLIST

Table Storm Drain Inlet Protection. Applicable for Paved/ Earthen Surfaces

Afon Claerwen Hydropower Project. Flood Risk Assessment. February 2018

A CASE STUDY ON RAIN WATER HARVESTING TECHNOLOGIES FOR TRIBAL AREA OF MADHYA PRADESH, INDIA

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)

GRASS-LINED CHANNEL (acre) CODE 840

Index. outlet protection Rev. 12/93

IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY WATER MANAGEMENT OF CONSTRUCTION SITE Patil V.A*, Gawade S.

TENDER FOR EXPANSION OF ASH POND AT NALCO's ALUMINA REFINERY AT DAMANJODI

Flow Diversion Banks: On grassed slopes

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project

MODEL Stormwater Local Design Manual. City of Centerville

WQ-08 ENHANCED DRY SWALE

Our reference BGS-0003-c. Direct line +31(0)

ITEM 750 ROCK FILTER DAMS

4.2 Discharge measurement by Velocity Area Method (Chitale, 1974)

Conceptual-Level Cost Estimates Arkansas River Corridor Dam Improvement and River Bank Stabilization Projects

Flow Diversion Banks: General

footings are provided with a concrete grade of M20. The maximum axial load 1600 KN as arrived from design is taken for the design of the footing.

SC-01 Surface Outlet and Baffle Sediment Basin

WQ-06 SAND FILTER. 1.0 Sand Filter. Greenville County Technical Specification for: 1.1 Description

Temporary Stream Crossing

Temporary Stream Crossing

STREAMBANK RESTORATION DESIGN

404(b)(1) EVALUATION

2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS

Bill of Quantities. Bill 1: Site Preparatory Works. Page No. 1/7. Bill 1 Page 1/1. Contract No.

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

Buffer Zones. November 29, RIDEM Freshwater Wetlands

Water Resources. Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4

GRADING, FILL, EXCAVATION AND LANDSCAPING 2012 EDITION

DRAINAGE & DESIGN OF DRAINAGE SYSTEM

Transcription:

ISSN XXXX XXXX 2017 IJESC Research Article Volume 7 Issue No.4 Planning, Design and Estimation of a Check Dam B.H. Ramathilagam 1, S. Murugesan 2, M. Manikandan 3, A. Arumugaraja 4, Assistant professor 1 2, 3, 4, U. G. student Department of Civil Sethu institute of technology, Virudhunagar, India Abstract To overcome these issues on a global scale, water erosion is the most severe type of soil erosion. It occurs mostly in the form of running water. This study was to develop information from dam which check dam can be adopted for the purpose of ground water recharge. Dams are constructions built across a river or a stream and used to interrupt and store water for special purpose. Check dams are comparatively smaller and more temporary to other types of dams for the purpose of ground water recharge. The Study consisted of a site selection phase, a surveying phase, an planning phase, an design phase and estimation analysis..this Particular scheme lies in highly favourable zone for recharge as classified in the zonation map for Ground water recharge. By implementing this scheme, with in the zone of influence of about 1 km radius from the check dam site will be benefitted by way of percolation. Increase the Ground water level and increase the revenue through the ayacut. Totally 185.02.0 Ha Ayacut is benefitted through Seventy Eight No s of wells. Moreover, all the wells (both domestic and agricultural wells) within the zone of influence will be recharged. The length of the check dam is 106m. The design and Estimation of the structure is done using the software Ms-Excel. The total estimation amount of the project is Rs.248.57461 Lakhs. Keywords : Ground Water-Recharge, Water Erosion Control, Check Dams, Flow Velocity. I. INTRO DUCTION A dam is a barrier that impounds water or underground streams. Reservoirs created by dams not only suppress floods but also provide water for activities such as irrigation, human consumption, industrial use, aquaculture, and navigability. Hydropower is often used in conjunction with dams to generate electricity. A dam can also be used to collect water or for storage of water which can be evenly distributed between locations. Dams generally serve the primary purpose of retaining water, while other structures such as floodgates or leaves are used to manage or prevent water flow in to specific land regions. There are several types of check dams; each type of dam is constructed with different conditions. In general, some essential considerations of check dams need to be considered. First, the site of each check dam must be carefully inspected to assess dam settling. The slope of waterway should be no more than 50% and the depth to bedrock should be over 2 feet (Department of Environmental Quality, 2005). Second, check dams materials will vary depending on conditions and locations. Logs and rock are usually utilized in permanent or semi-permanent check dams for their stability, and sandbag is for short term purpose (Mississippi Department of Environmental Quality, 2011) This type of dam project can be widely utilized in small open channels and drainage ways, including temporary and permanent swales. Check dams flattens the gradient of channels and blocks streams from fluently flowing. As a consequence, not only the velocity of flow is mitigated, but also the path can be distributed toward vegetation. On another hand, check dams also trap sediments from streams which helps to reduce water erosion. II. S ITE S URVEYING Before starting surveying work to select the area where the check dam is constructed and some procedures should be consider for selecting a site the water demand and ground water is necessity for cultivate crops and increase revenue and standard of living afterwards opinion from public and grievance should be noted. leveling should be done in the proposed site with the use of surveying instrument like autolevel, tripod, tape, plump bob, thread. Surveying work of leveling is carried out from upstream to downstream of the river up to 50 M from the site then reduced level of each points should be calculated from height of collimation method. Site should be cleared from vegetable, leaves, un bushy level after foundation should be erected at where the soil is week depth up to 3m to 5 m. Figure 1 I. Plan of check dam The planning of check dam done should be in two views A) Half plan at top & half plan at foundation. b) cross -section of check dam A. Half plan at top & half plan at foundation Half plan from top view and half plan at foundation are shown in fig 2. From top view plan shows apron & of both U/S International Journal of Engineering Science and Computing, April 2017 6464 http://ijesc.org/

side and D/S side. from left to right half top plan shows figure 2. U/S Return wall then us bed level +328.280 to crest +329.480 and stilling basin is 6.40m wide afterwards cement concrete blocks in right side portion ends is apron in D/S bed level+328.280 and 8.00m wide. total discharge through scour vents and over weir = 17565.088cusecs Design discharge for the anicut = 17497 cusecs D. Stability calculation The stability of body wall of the anicut was checked for the following conditions: 1 Reservoir empty without eq 2. Reservoir at MWL,with tail water with uplift 3.Reservoir at FRL, no tail water with uplift 4.Upstream side fully silted up to crest, No silt/water at D/s side WT @Crest Figure:2 Half plan at top & half plan at foundation B. Cross-section of check dam Cross-section of check dam shows abutments, d/s wing at start,u/s wing & return, d/s wing at end, d/s wing at basin. cement concrete 1:3:6 using 40mm aggregate m15 graded aggregate with surface reinforcement details are shown in figure 3 1. Maximum stress= SV/b*(1+6e/b) = 3.5442T/m 2 Minimum stress = SV/b*(1+6e/b) = 1.0501T/m 2 2. Maximum stress= SV/b*(1+6e/b )=3.5442T/m 2 3. Maximum stress= SV/b*(1+6e/b) =3.5442T/m 2 4.Maximum stress= SV/b*(1+6e/b) =3.5442T/m 2 E. Surface flow Regime width Looseness factor = 4.83 sqrt (494.691) =107.5m = Existing overall length /Regime width = 107.5 M Figure 3 II. CROSS-SECTION DES IGN A. Design the check dam structure The check dam structure design in limit state method. Design should be followed by the rules of indian standard IS 6966-1973. B. Rear water calculation To find out the discharge in the rear water calculation by applying manning s formula (i) area (A)=183.478m 2 (ii) wetted perimeter (p) =107.054 m (iii)discharge=17497 cusecs. C. Front maximum water level The front maximum water level determines discharge the amount of water from anicut and back water length calculation : P/ H O 0.65 < 1.33 (velocity of approach should be taken) total discharge over the weir = 497.38m 3 /sec % of discharging passing = 100.39% Scour depth = 3.6 M Stilling basin level = 327.780 m Total horizontal floor length: Length of u/s floor = 3.00m Width of the body wall = 2.50m D/s floor length = 6.80m Total floor length required =12.30 m providing stilling basin length = 6.40m Hence total floor length = 12.30m F. Downstream protection work Length of downstream protection block = 1.5 D =5.7 m Hence provide 4 rows of CC block of size 1.5x1.5x0.9 m tk of pitching (Is 6966-1973) = 850mm International Journal of Engineering Science and Computing, April 2017 6465 http://ijesc.org/

slope of =2.00:1 Length of launching =8.560 m qty of stone reqd for tk = 0.85x 8.56 = 7.276 m 3 Inner tk reqd = 7.276/8 = 0.9095m Quantity of pitching provided = 10.4 m 3 Quantity of pitching required = 9.416 m 3 G. Ups tream wing wall &returns earth pressure: Vertical component =94.163 KN Horizontal component =90.806 KN Maximum stress = P/A(1+6e/b) =161.724 KN/m 2 Minimum stress =P/A (1-6e/b) =5.145 KN/m 2 J. Design of downstream wingwall at end portion Earth pressure: Vertical component = 70.189 KN/m 2 Horizontal component = 67.805 KN/m 2 Maximum stress = P/A(1+6e/b) =184.963 KN/m 2 Minimum stress =P/A (1-6e/b) =3.728 KN/m 2 H. Design of downstream wing wall at start earth pressure: Vertical component = 187.148 KN/M 2 Horizontal component =90.806 KN/M 2 Maximum.stress = P/A(1+6e/b) =73.277 KN/m 2 Minimum stress =P/A (1-6e/b) =73.277KN/m 2 K. Design of downstream wingwall at return portion earth pressure: Vertical component t= 70.189 KN/M Horizontal co mponent=67.805 KN/ m2 Maximum stress = P/A(1+6e/b) =187.148 KN/m 2 Minimum stress =P/A (1-6e/b) =2.468 KN/m 2 I. Design of downstream wingwall at basin portion Earth pressure: Vertical component = 91.676 KN/m 2 Horizontal component t=88.562 KN/m 2 Maximum.stress = P/A(1+6e/b) =139.242 KN/m 2 Minimum stress =P/A (1-6e/b) =7.309 KN/m 2 III.ES TIMATION The estimation of the total approximate cost of the project is calculated by the detailed estimated method are as in the below tabulation. International Journal of Engineering Science and Computing, April 2017 6466 http://ijesc.org/

SI.NO Qty Description of work Rate Per Amount 1 L.S Clearing the site L.S 50000 2 560 m 3 Earth work excavation for 123.50 m 3 69160 foundation 3 3640 m 3 Earth work excavation in all 55.60 m 3 202384 soils except medium rock 4 4200 m 3 Extra for every additional 6.90 m 3 28980 lead of 10m 5 4200 m 3 Extra for every additional lift of 1m 5.50 m 3 23100 6 C.C 1:4:8 using 40 mm Hard broken stone jelly A) 100 m 3 Up to 1.50 m depth below 3716.96 m 3 371696 7 C.C 1:3:6 using 40 mm hard broken stone jelly a) 1580 m 3 Upto 1.50 m 4.50 m depth below 4084.16 m 3 6452970 8 Cement concrete 1:2:4 using 20mm metal a) 266 m 3 Up to 1.5 m depth below 5179.46 m 3 1377736 b) 266 m 3 From 1.5 m depth -4.5 m below 5238.06 m 3 471425 9 Cement concrete 1:2:4 (Graded mix ) 60% of 40mm & 40% of 20mm a) 1580 m 3 Upto 1.5 m depth below 4991.00 m 3 7885777 b) 266 m 3 Upto 1.00m height above 4991.00 m 3 1327605 c) 49 m 3 From 1.00m height -4..5m 5050.40 m 3 247470 height above 10 175 m 3 Cement concrete 1:1, 5:3 using 20 mm metal with minimum Reinforcement 5913.86 m 3 1034925 11 3900 m 3 Supplying and erecting centering for soffits steel 537.00 M 2 2094300 sheets of size 90 x60 cm and 10 BG stiffened 12 70 Qtl Steel fabricating 5702.50 Qtl 399175 13 140 m 3 Forming sand filter of 1614.32 m 3 226005 course sand and fine sand 14 280 m 3 Graded filter using broken 1302.45 m 3 364686 stone 10 to 80mm 15 70 m 3 Gravel filling for protection 1077.11 m 3 75398 blocks 16 30 m 3 Rough stone dry packing for 1231.72 m 3 36951 revetment 17 1110 m 3 Jeddy stone dry packing for 1269.12 m 3 1408718 launching apron 18 L.S Provision for expansion joints on every 20m interval L.S L.S 300000 19 L.S Provision for bailing out of L.S L.S 250000 water fixing hydrology board, gaugeplates.marking stones etc. 20 L.S Provision for bank connection L.S L.S 159000 Total 24857461 IV. CO NCLUSION From this study, by observing the results the following conclusions were made the purpose of the project is increase the Ground Water recharge through the increase a yield of Crops. The site of check dam is surveyed in the area of Kadamalaikundu village of Andipatti thaluk in Theni District. In this study consist of Surveying, Planning, Designing and Estimation. The Surveying work carried with the instrument of Auto-Level. The designing and estimation work are done in Ms - excel software. All the Results of design and estimated are found to be safe The IS code of 6966 1973 Design is followed International Journal of Engineering Science and Computing, April 2017 6467 http://ijesc.org/

This method of design is considered to be better than the other methods available for design particularly for check dams From the design result it has been concluded that this design can be adopted for any check dams. The estimated cost of the check dam is found to be Total Rs.248.57461 Lakhs. This amount implies the material cost, labour cost and all other miscellaneous charges. REFERENCE [1] Hangxi Fan The Function of check dams and the effect of Check Dams on Water Erosion department of resource analysis, saint Marry s university of Minnesota, winona, MN55987. [2] IS 6966 1973 criteria for structural design of barriages and weirs. International Journal of Engineering Science and Computing, April 2017 6468 http://ijesc.org/