Residential Construction Minimum Required Inspections

Similar documents
INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Inspection of New One- and Two- Family Dwellings

INSPECTION REQUIREMENTS Page 1 of 5. JOB SITE ADDRESS posted during entire construction process.

C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) Fax: (630)

Inspection Procedure Handout

BUILDING PERMIT APPLICATION CITY OF SIDNEY BUILDING INSPECTION DEPARTMENT

Boss Inspection Inc Wisconsin Uniform Dwelling Code Inspection and Code Enforcement

City of Westerville Guide to Commercial Inspections

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

Residential Building Plans

FIELD COPY ATTACHMENT

PERMIT SUBMITTAL GUIDE FOR COMMERCIAL PROJECTS

CITY OF OAK CREEK SINGLE FAMILY & TWO-FAMILY CONSTRUCTION/PERMIT REQUIREMENTS

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

RESIDENTIAL BUILDING PERMIT GUIDE FOR MULTI-FAMILY DWELLINGS

1 AND 2 FAMILY DWELLING REQUIREMENTS

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT

The Inspection Process. Waxhaw N.C.

Nassau County Building Department

BUILDING A NEW HOME. Construction Permit Tips For Home Owners

TOWN OF FRANCESTOWN BUILDING/CODE ENFORCEMENT 27 MAIN STREET P.O. BOX 5 FRANCESTOWN, NEW HAMPSHIRE Building Permit Application Guide

City Of Mendota Construction Procedures

City of Rohnert Park Building Department Inspection Descriptions

ARTICLE 12 INTERNATIONAL RESIDENTIAL CODE 2012 International Residential Code Modification Summary (Statutory Authority: 1976 Code Section )

Scale Drawing This drawing will need to show the full lot and location of the proposed

THE CONSTRUCTION SUPERVISOR

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage

Module number 3 provides an on-line, self-paced training seminar on chapter 4, foundations and chapter 5, floors from the residential code of ohio.

COMMERCIAL SUBMITTAL PACKET

CONSTRUCTION COST BREAKDOWN THIS IS FORM CCB

229 Rehoboth Avenue Telephone P.O. Box 1163 Fax

ACCESSORY BUILDING. Building Permit Requirements: (must be completed before submitting application)

UCC Permit Application Procedures

RESIDENTIAL CONSTRUCTION New Dwellings and Additions

Town of Fredonia. 25 N Main St. * PO Box 217 Fredonia AZ Fax: * Office

Residential Building Inspections

The following information is required when submitting a building permit application:

ROUTT COUNTY REGIONAL BUILDING DEPARTMENT 136 * P.O.

Citizens Guide to Residential Building Permits

One and Two Family Additions

FirstEnergy Program Overview

Borough of Doylestown Building and Zoning Department

BUILDING DIVISION 120 Malabar Road, S.E., Palm Bay, FL Phone: (321) Fax: (321)

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST

CITY OF LA MARQUE Gateway to the Gulf st St., La Marque, TX (409) Fax: (409)

BUILDING PERMIT INFORMATION GUIDE FOR THE HOMEOWNER

PERMITS REQUIRED BEFORE OBTAINING A PERMIT

Town of Kingsville. Building Department

Oregon Building Officials Association

Administrative Changes

MINIMUM PLAN INFORMATION REQUIRED FOR A BUILDING PERMIT

Town of Kingsville. Building Department

RESIDENTIAL GUIDELINES

COMMERCIAL BUILDING HANDBOOK 2015 International Building Code (IBC)

CITY OF GLASGOW BUILDING PERMIT APPLICATION 126 E. Public Square Glasgow, KY Phone: (270) Fax: (270)

Required Information for Permit Issuance

BUILDING DEPARTMENT GUIDE TO RESIDENTIAL BUILDING PERMITS

The Homeowner s Building Application Checklist for Constructing a Residential Addition

Training Certification Categories

TOWN OF HAGUE GUIDELINES FOR PERMIT APPLICATION

TOWN OF ROTTERDAM BUILDING DEPARTMENT RESIDENTIAL ACCESSORY BUILDINGS AND STRUCTURE PERMIT APPLICATION Ext 395

RESIDENTIAL BUILDING PERMIT APPLICATION ( MINIMUM Building Requirements-Page 6)

Elko County Building & Safety Division

CITY OF FATE SINGLE FAMILY BUILDING PERMIT PACKET. Adopted Codes:

HOMEOWNER S GUIDE Construction and Inspection Procedures for Single Family Dwelling Alterations/Additions/Decks

TOWNSHIP OF DRUMMOND/NORTH ELMSLEY. Deck/Porch Guide & Permit

PLEASE READ AND SIGN RESIDENTIAL ENERGY CODE AND EROSION CONTROL!

Greene County Department of Building Regulation Residential Permit, Plan Approval, & Inspection Process

BUILDING CODES & DESIGN CRITERIA

City of Jacksonville Development Guide Building Permits

General Installation Requirements ( )

Town of Falmouth FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage COSTS FOR SUBSTANTIAL IMPROVEMENTS / REPAIR OF SUBSTANTIAL DAMAGE:

Office use only 115 S. FRANKLIN AVE. Permit No. POLO, IL 61064

CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist

UNIFORM CONSTRUCTION CODE (UCC) BUILDING PERMIT APPLICATION RESIDENTIAL NEW CONSTRUCTION AND/OR IMPROVEMENTS

RESIDENTIAL BASEMENT ALTERATIONS GUIDE

Building Permit Application

BASEMENT FINISH CONSTRUCTION

UNIFORM CONSTRUCTION CODE (UCC) BUILDING PERMIT APPLICATION RESIDENTIAL NEW CONSTRUCTION AND/OR IMPROVEMENTS

GENERAL BUILDING CODE AND ZONING REQUIREMENTS: Post and spread footings shall be designed and constructed below the minimum frost depth of 42 inches

Alabama Home Inspections

CITY OF COOPER CITY BUILDING DEPARTMENT

City of Lorena 107-A S. Frontage Road Lorena, Texas Phone: (254) Fax: (254)

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE

ADDITIONS BUILDING AND ZONING REQUIREMENTS (REVISED 4/22/2008)

PENNSAFE BUILDING INSPECTION SERVICES LLC NEW COMMERCIAL BUILDING UCC PLAN REVIEW HANDOUT AND CHECKLIST

Basement Build-Out Guidelines

Applicant s Name Applicant s Address Phone # Year Built (verified) Property Owner s Name Address Phone # Site Phone # Description of Proposed Work:

* RESIDENTIAL PLAN REVIEW *

District of Barriere A GUIDE TO BUILDING PERMITS

RESIDENTIAL BUILDING PERMIT

TOWN OF GREENVILLE APPLICATION FOR PERMIT

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

CITY OF RICHMOND HEIGHTS DEPARTMENT OF BUILDING ZONING AND HOUSING STANDARDS AND REGULATIONS

Commercial and Residential Projects (after appropriate Board approvals have been made if necessary):

1. Complete Building Permit Application forms on page 2. Include septic system design approval from the Washington County Health Department.

TOWN OF LOUDON OFFICE OF THE BUILDING INSPECTOR P.O. BOX 7032 ~ 8 COOPER STREET LOUDON, NH 03307

Permit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2)

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

Transcription:

Residential Construction Minimum Required Inspections The permit which you have been issued gives authority for work to commence. The stamped, approved plans, returned with this permit, shall be retained at the job site and be available for inspectors on request. It shall be the applicant s responsibility to perform all work in accordance with the Virginia Uniform Statewide Building Code, and within the scope of what was authorized by the plans submitted and approved. Changes to these plans must be approved by this office. Please post your permit placard in a prominent location. Inspections at various stages of work are required by this office, under provisions of the Virginia Uniform Statewide Building Code. The required inspections for buildings are listed below. James City County, Division of Building Safety and Permits, operates an automated 24-hour a day, 7 days a week web-based inspection request system https://epermit.jamescitycountyva.gov to schedule inspections. You will need a Customer ID and Password number assigned when a permit is issued or obtained from our office by calling 757-253-6620. Instructions are available on our Building Safety and Permits web page under NEW epermit website. Omission of any of this information may result in the inspection not being conducted. Requested inspections are assigned daily at 6:30 a.m. Any inspection requested after that time will be done the following business day. If work is not complete and open for inspection, it may be subject to disapproval and require reinspection. When work is disapproved by an inspector, a $50.00 reinspection fee must be paid. Separate permits are required for building, mechanical, electrical, gas, gas fireplace, and residential sprinkler work. No requested inspection is performed unless a valid permit exists for that work. Work performed without a permit, when permit is required, is a violation of the law! If you have a question whether a permit is required, or if work is within the scope of any permit issued, call the Division of Building Safety and Permits. If you feel that it is necessary to speak directly to an inspector, their office hours are 7:00 8:00 a.m. and 3:00 3:30 p.m. only. Please do not call them to request an inspection. BUILDING INSPECTIONS REQUIRED: (ALL APPROVED PLANS MUST BE ON SITE FOR INSPECTIONS.) A. FOOTING INSPECTION To be made after basement or footing trenches are excavated and forms, where applicable, are erected. All reinforcement steel, when necessary, must be in place and anchored. This inspection must be made prior to pouring concrete. If slab on grade (monolithic pour) construction this inspection includes the foundation inspection. The inspector will also check for the required erosion control measures as shown on the approved site plan. If these items (e.g., silt fence, construction entrance, etc.) are not properly installed, this inspection may be disapproved. Structures with reinforcing steel that is ½ or larger and 20 or longer must have a grounding electrode system installed per National Electrical Code 250.50 (3). This will be inspected at the same time as the footing inspection. B. FOUNDATION 1. Masonry Foundation and Concrete Wall Inspection The foundation block must be completed to the level of the finish grade, and be continuous over any steps or grade changes. Piers must be complete to the level of finish grade and any brick or other veneer must also be in place. All bonding or other lateral support of intersection walls must be complete and visible. All form boards or step boards must be removed and the foundation trench ready for backfilling. The top of the footings must be clean and clearly visible. For Cast in Place concrete walls, all forms and reinforcing steel must be in place and ready for inspection prior to pouring concrete. If Foundation Survey Required is noted on your approved

Residential Construction Minimum Required Inspections Page 2 plans, this must be submitted to BuildingSafetyandPermits@jamescitycountyva.gov and approved before you request a floor joist inspection. Please allow three business days to review and process the survey. 2. Floor Joists Inspection To be made after load-bearing walls to the first floor sill height have been erected, beams and floor-joists have been installed, and grading within the perimeter walls has been completed. Sub-flooring shall not be installed before this inspection has been approved. In basements, the first floor system (box) shall have all approved (on plans) supports (posts, columns) for beams and girders in place and secured. NOTE: If you are in a flood zone, an FEMA flood elevation certificate must be submitted to our office prior to this inspection. The Building Under Construction box on line C1 of the Elevation Certificate must be checked. 3. Water/Damp-Proofing Inspection Basements must be inspected for water-proofing method, drains, gravel, and filter cloth before being backfilled. 4. Concrete Slab Inspection To be made prior to pouring a concrete slab. All reinforcing steel, vapor barriers, fill material if required, perimeter insulation, etc. must be in place and ready to inspect before scheduling this inspection. A compaction certification is required where fill material exceeds 24 inches in depth (including but not limited to garages, porches and stoops). Concrete material waiting to be installed on site will not be an excuse to allow incomplete slabs to be inspected. C. FIREPLACE INSPECTION Where there is to be a fireplace(s) installed in a building, this inspection must take place while combustible clearances can be inspected. This must be before the interior is insulated and sheetrocked, but may be after the fireplace is finished. This includes all types of fireplaces; masonry, prefab, and ventless. NOTE: A separate mechanical permit is required for gas fireplace appliances. D. FRAMING INSPECTION To be made after the roof, all framing firestopping, blocking and bracing is in place, and the sub-flooring has been installed. Do not install insulation before the framing inspection is approved. The building should be weathered in including windows, doors, and roof shingles for this inspection. The inspector will also check the condition of the required erosion control measures. If these items are not in good condition, this inspection may be disapproved. NOTE: Our current web-based inspection request system (https://epermit.jamescitycountyva.gov) will now automatically schedule all trade rough-in inspections upon requesting a residential framing inspection. As of September 1, 2013, we will no longer conduct residential trade inspections on new single-family homes and townhouses prior to the framing inspection. Trade inspections called in prior to the framing inspection on these dwellings will be cancelled. All required trade permits must be obtained prior to calling for framing inspections. We will continue to perform trade inspections on alterations, additions and homeowners permits as they are scheduled. Partial framing inspections may be done on a case-by-case basis on some commercial projects prior to trade rough-ins. In general all inspections should be requested in the proper sequence as work progresses. Please coordinate trades readiness for rough inspection with the framing inspection. Re-inspection fees will apply to work not ready for inspection.

Residential Construction Minimum Required Inspections Page 3 E. AIR BARRIER INSPECTION An air barrier visual inspection will be required on all new homes before concealing the air barrier unless a blower door test will be performed by a certified individual. The choice for the blower door testing option must be made at the time a permit is applied for. In either case, an insulation inspection will also be required. This may be done at the same time as the air barrier inspection or at a later date. It shall be the permit holder s responsibility to know what option was chosen and to call for the proper inspections. A certified test result for blower door testing must be supplied prior to a final building inspection. Failure to pass a blower door test when that option was selected will require air sealing measures be taken until a passing test result can be achieved. The air barrier inspection will include: An approved air barrier material or suitable film or solid material applied per manufacturer s installation instructions at all required locations and all penetrations of exterior walls sealed. F. INSULATION INSPECTION To be made when all required insulation and appropriate air sealing elements have been installed. In the event that the contractor intends to use blown insulation in the ceilings, that portion of this inspection may be delayed until and during the final inspection. Exception: Insulation between slabs and exterior walls will be inspected during the foundation inspection. G. FINAL INSPECTION To be made after the building has been completed and ready for occupancy. This inspection will not be made until all required electrical, plumbing, gas, fireplace, and mechanical final inspections have been made and the work approved. Disturbed yard, slope, and lawn areas on the lot must be properly stabilized*; or alternatively, properly installed and approved erosion and sediment control measures must be in place and functional to handle runoff associated with the land disturbing activity and be in satisfactory condition as determined by the VESCP/VSMP Authority. Site grading and drainage must match the approved site plan. *Properly stabilized means disturbed yard, slope, and lawn areas for the residential lot are stabilized with temporary or permanent vegetation that is uniform, mature enough to survive, and will inhibit erosion as determined by the VESCP/VSMP authority. This includes proper testing, preparation and treatment of the soil, the establishment of temporary or permanent seeding or cool/warm season turf grass by other allowable methods such as sprigs, plugs or sod, and mulching in accordance with Minimum Standards of the Virginia Erosion and Sediment Control Regulations, Minimum Standards & Specifications of the Virginia Erosion and Sediment Control Handbook (VESCH) and state/local Virginia Erosion and Sediment Control Program (VESCP), Virginia Stormwater Management Program (VSMP), VPDES construction general permit (VAR10), and County MS4 permit requirements, including special provisions surface waters identified as impaired or for which a TMDL wasteload allocation has been established. Seeding mixtures or sod types selected must be Virginia Crop Improvement Association (VCIA) certified and adaptable to the coastal plain region of Virginia and specific soil, climate and rainfall conditions of James City County. A Certificate of Use and Occupancy is issued only after the final inspection is approved and the yard has been stabilized. The structure may not be used or occupied in whole or part until issuance of a Certificate of Occupancy. NOTE: If you are in a flood zone, a FEMA flood elevation certificate must be submitted to our office prior to this inspection. The Finished Construction box on line C1 of the Elevation Certificate must be checked. PLUMBING INSPECTIONS REQUIRED: A. WATER AND SEWER To be made after all water and sewer lines are installed from the water and sewer mains (or wells and septic tanks) to the structure. Trench must be open and all lines accessible to the inspector. This includes Geothermal Piping System horizontal trenches.

Residential Construction Minimum Required Inspections Page 4 B. 1. ROUGH IN INSPECTION Under-slab inspection to be made prior to pouring concrete (under-slab). Rough-in inspection after all interior piping (water and sewer) has been installed and tested, and prior to concealment. The rough-in inspection will be conducted for residential work on the same day the general contractor requests the framing inspection for new single-family dwelling construction. 2. SHOWER PAN LINER INSPECTION To be performed if a ceramic tile or other field installed shower receptor covering is being used. This can be a separate inspection in addition to the regular plumbing rough in if necessary and must be scheduled and approved prior to the installation of tile or other materials. The inspection includes a leak test of the liner, and requires a minimum of two inches of water measured at the threshold. This inspection is also required for Schluter Systems. C. FINAL INSPECTION To be made after all plumbing work has been done and all appliances and fixtures involving water and/or sewer connections have been installed. Grinder pumps need to be operational ELECTRICAL INSPECTION: A. ROUGH-IN INSPECTION Under-slab inspection required prior to pouring concrete. Rough-in inspection to be made after all interior wiring and electrical equipment has been installed, but prior to covering or concealment and prior to installation of any insulation. The rough-in inspection will be conducted for residential work on the same day the general contractor requests the framing inspection for new single-family dwelling construction. All electrical contractors will have the option to have the electrical meter release inspection for one and two-family residences performed on the same day as the electrical rough-in inspection. The following requirements must be in place at this release/rough-in electrical inspection: 1. The service wiring and equipment, including the meter socket enclosure, shall be installed and the service wiring terminated. 2. The grounding electrode system shall be installed and terminated. 3. At least one receptacle outlet on a ground fault protected circuit shall be installed and the circuit wiring terminated. 4. Service equipment covers shall be installed. 5. The building roof covering shall be installed 6. Temporary electrical service equipment shall be suitable for wet locations unless the interior is dry and protected from the weather. If all of the above-listed items are not completed at the time of the electrical rough-in inspection, the rough-in may be approved but the meter will not be released until the electrical trim-out has been completed and inspected. B. FINAL INSPECTION To be made after electrical work is complete and power is turned on. JUST BECAUSE POWER IS ON, IT DOES NOT MEAN YOU CAN OCCUPY OR USE THE STRUCTURE. YOU MUST HAVE A C.O. FIRST! MECHANICAL INSPECTIONS REQUIRED: A. ROUGH-IN INSPECTION Under-slab inspection to be made prior to pouring concrete. Rough-in inspection to be made after the installation of all duct work, gas lines, fuel storage tanks, etc., and prior to covering or concealment. The rough-in inspection will be conducted for residential work on the same day the general contractor requests the framing inspection for new single-family dwelling construction.

Residential Construction Minimum Required Inspections Page 5 At the mechanical rough-in inspection of a new home either a visual inspection of the duct sealing method will be required or the permit holder will have elected on a separate form at the time a permit is applied for the intent to perform a duct blaster test. The results of this test must be supplied in writing to the building department prior to the final mechanical inspection. B. FINAL INSPECTION To be made after all heating, ventilating, and air conditioning installations have been completed and tested. C. GAS LINES Rough-in inspection required after installation of all lines and after pressure test is complete (but before concealment of any lines or fittings). The rough-in inspection will be conducted for residential work on the same day the general contractor requests the framing inspection for new single-family dwelling construction. Final inspection required after hookup of all gas appliances. Gas service will not be released to the utility company for connection until these inspections are approved. If service is interrupted, new pressure tests and inspections may be required prior to release to the utility company. In addition to these required inspections, the USBC states that structures may be inspected at any time during construction. Occasionally, inspectors will visit jobs unannounced and when not requested. It is the permit holder s responsibility to furnish a ladder if one is needed for a requested inspection. Nonresidential structures may have other inspection obligations. Fire separation walls, fire walls, and party walls in apartments, condominiums, town houses, and commercial structures may require separate inspections. Please consult the Building Safety and Permits Office if your permit(s) involve(s) such fire-rated walls. Drawings required to be submitted may vary depending on the complexity of the work and requirements of the Building ResMinReqInsp.doc Rev. 8-2016