CONSTRUCTION SPECIFICATION FOR BORROW

Similar documents
CONSTRUCTION SPECIFICATION FOR BORROW

CONSTRUCTION SPECIFICATION FOR BORROW

CONSTRUCTION SPECIFICATION FOR BORROW

CONSTRUCTION SPECIFICATION FOR EARTH BORROW

CONSTRUCTION SPECIFICATION FOR COMPACTING

CONSTRUCTION SPECIFICATION FOR UNTREATED SUBBASE, BASE, SURFACE, SHOULDER, SELECTED SUBGRADE, AND STOCKPILING

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

CONSTRUCTION SPECIFICATION FOR CLEARING, CLOSE CUT CLEARING, GRUBBING, AND REMOVAL OF SURFACE AND PILED BOULDERS

CONSTRUCTION SPECIFICATION FOR PRIMING GRANULAR BASE

STANDARD SPECIFICATIONS JANUARY 2015 S-4 GRANULAR BASE and AGGREGATES TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

Construction Specification for General Excavation

CONSTRUCTION SPECIFICATION FOR EXCAVATING, BACKFILLING AND COMPACTING FOR MAINTENANCE HOLES, CATCH BASINS, DITCH INLETS AND VALVE CHAMBERS

CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR SUBBASE, BASE, SURFACE, SHOULDER, AND STOCKPILING

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR SINGLE AND DOUBLE SURFACE TREATMENT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR UNTREATED GRANULAR, SUBBASE, BASE, SURFACE SHOULDER AND STOCKPILING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING AND COMPACTING

CONSTRUCTION SPECIFICATION FOR PRIMING GRANULAR BASE

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR PRIMING GRANULAR BASE

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

Construction Specification for Trenching, Backfilling and Compacting

CONSTRUCTION SPECIFICATION FOR IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

CONSTRUCTION SPECIFICATION FOR STOCKPILING OF PATCHING MATERIALS AND PATCHING OF ASPHALT PAVEMENT

CONSTRUCTION SPECIFICATION FOR STOCKPILING OF PATCHING MATERIALS AND PATCHING OF ASPHALT PAVEMENT

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

MATERIAL SPECIFICATION FOR AGGREGATES - GENERAL

CONSTRUCTION SPECIFICATION FOR GRADING

MATERIAL SPECIFICATION FOR AGGREGATES - GENERAL

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

Special Provision No. 599S22 March 2001

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

CONSTRUCTION SPECIFICATION FOR WICK DRAIN INSTALLATION

CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX

CONSTRUCTION SPECIFICATION FOR COLD RECYCLED MIX

MATERIAL SPECIFICATION FOR AGGREGATES - GENERAL

MATERIAL SPECIFICATION FOR AGGREGATES - MISCELLANEOUS

Special Provision No. 599S22 March 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS)

CONSTRUCTION SPECIFICATION FOR WICK DRAIN INSTALLATION

CONSTRUCTION SPECIFICATION FOR IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

INDEX DESCRIPTION MATERIALS APPROVAL FOR BASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6

MATERIAL SPECIFICATION FOR AGGREGATES - MISCELLANEOUS

CONSTRUCTION SPECIFICATION FOR WICK DRAIN INSTALLATION

MATERIAL SPECIFICATION FOR AGGREGATES - MISCELLANEOUS

CONSTRUCTION SPECIFICATION FOR IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

CONSTRUCTION SPECIFICATION FOR GRANULAR SEALING

CONSTRUCTION SPECIFICATION FOR GRANULAR SEALING

CONSTRUCTION SPECIFICATION FOR WICK DRAIN INSTALLATION

INDEX GENERAL EQUIPMENT CONSTRUCTION SUBGRADE PROTECTION MEASUREMENT PAYMENT 5

Special Provision No. 421F01 April 2006

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

MATERIAL SPECIFICATION FOR SODIUM CHLORIDE SOLID AND SODIUM CHLORIDE SOLUTION

CONSTRUCTION SPECIFICATION FOR COLD IN-PLACE RECYCLING

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

CONSTRUCTION SPECIFICATION FOR STANDARD HIGHWAY FENCE

DIVISION 4100 SITEWORK

January 2008 No. 500 INDEX FOR SPECIFICATIONS FOR GRADING SCOPE...1

CONSTRUCTION SPECIFICATION FOR STANDARD HIGHWAY FENCE

GENERAL SPECIFICATION FOR WEIGHING OF MATERIALS

SECTION EROSION CONTROL DEVICES

CONSTRUCTION SPECIFICATION FOR SLURRY SEAL

CONSTRUCTION SPECIFICATION FOR GRANULAR SEALING

DIVISION 2 - EARTHWORKS

COMPACTED CLAY LINERS

MATERIAL SPECIFICATION FOR EXTRUDED EXPANDED POLYSTYRENE PAVEMENT INSULATION

CONSTRUCTION SPECIFICATION FOR RUBBLIZING CONCRETE PAVEMENT AND CONCRETE BASE

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

CONSTRUCTION SPECIFICATION FOR TUNNELLING

Special Provision No. 305S02 January 2016

CONSTRUCTION SPECIFICATION FOR NOISE BARRIER SYSTEMS

ONTARIO PROVINCIAL STANDARD SPECIFICATION

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

CONSTRUCTION SPECIFICATION FOR GRADING

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

Special Provision 206S03 November OPSS 206, Construction Specification for Grading is deleted in its entirety and replaced with the following:

CONSTRUCTION SPECIFICATION FOR TRAFFIC CONTROL SIGNING

CONSTRUCTION SPECIFICATION FOR SINGLE AND DOUBLE SURFACE TREATMENT

CONSTRUCTION SPECIFICATION FOR OPEN GRADED DRAINAGE LAYER

CONSTRUCTION SPECIFICATION FOR COMPACTING

CONSTRUCTION SPECIFICATION FOR GROUNDING

CONSTRUCTION SPECIFICATION FOR REMOVAL OF ELECTRICAL EQUIPMENT AND MATERIALS

CONSTRUCTION SPECIFICATION FOR CONCRETE FOOTINGS AND MAINTENANCE PLATFORMS FOR HIGH MAST LIGHTING POLES

Special Provision No. 335S03 April 2015

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

CONSTRUCTION SPECIFICATION FOR TRAFFIC CONTROL SIGNING

CONSTRUCTION SPECIFICATION FOR THE CLEANING AND FLUSHING OF PIPE SEWERS, CATCHBASINS, MAINTENANCE HOLES, DITCH INLETS, AND OIL-GRIT SEPARATORS

Select Subgrade Material, Compacted

CONSTRUCTION SPECIFICATION FOR SINGLE AND DOUBLE SURFACE TREATMENT

ONTARIO PROVINCIAL STANDARD SPECIFICATION

ADMINISTRATION OF AGGREGATE SOURCES INCLUDING EARTH AND ROCK BORROW SOURCES. Special Provision No. 199S38 March 2003

SECTION BUILDING EARTHWORK

MATERIAL SPECIFICATION FOR AGGREGATES - SURFACE TREATMENT

CONSTRUCTION SPECIFICATION FOR OPEN GRADED DRAINAGE LAYER

SECTION AGGREGATES

205 - EXCAVATION AND EMBANKMENT FOR HIGHWAYS SECTION 205 EXCAVATION AND EMBANKMENT FOR HIGHWAYS. Common Excavation (Contractor-Furnished)

Transcription:

ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 212 APRIL 1999 CONSTRUCTION SPECIFICATION FOR BORROW TABLE OF CONTENTS 212.01 SCOPE 212.02 REFERENCES 212.03 DEFINITIONS 212.04 SUBMISSION AND DESIGN REQUIREMENTS - Not Used 212.05 MATERIALS 212.06 EQUIPMENT - Not Used 212.07 CONSTRUCTION 212.08 QUALITY ASSURANCE 212.09 MEASUREMENT FOR PAYMENT 212.10 BASIS OF PAYMENT 212.01 SCOPE This specification covers the requirements for earth and rock borrow. 212.02 REFERENCES This specification makes reference to the following standards, specifications, and publications: Ontario Provincial Standard Specifications, General: OPSS 102 OPSS 180 Weighing of Materials Management and Disposal of Excess Material Ontario Provincial Standard Specifications, Construction: OPSS 206 Grading Page 1 Rev. Date: 04/1999 OPSS 212

Ministry of Transportation Publications: MTO Laboratory Testing Manual LS-623 LS-701 LS-702 LS-703/704 LS-706 LS-707 One Point Proctor Test (OPT) Determination of Moisture Content of Soils Determination of Particle Size Analysis of Soils Liquid Limit, Plastic Limit and Plasticity Index of Soils Moisture-Density Relationship of Soils Using 2.5 kg Rammer and 305 mm Drop Moisture-Density Relationship of Soils Using 4.5 kg Rammer and 457 mm Drop 212.03 DEFINITIONS For the purpose of this specification, the following definition applies: Borrow: means earth or rock material acquired from outside the right of way to complete the work. 212.05 MATERIALS 212.05.01 Earth Borrow Earth borrow shall consist of earth and shale as defined in OPSS 206 and shall be free from organic or foreign material. Earth borrow with more than 50% of the particles smaller than 75 μm, as determined by LS-702, shall not be used unless the field moisture content meets the requirements of Table 1. 212.05.02 Rock Borrow Rock borrow shall consist of rock as defined in OPSS 206. 212.07 CONSTRUCTION 212.07.01 General The work required for borrow shall include clearing, grubbing, stripping of borrow source; construction and maintenance of access roads and maintenance and restoration of haul roads; excavating, hauling, placing and compacting the borrow material and borrow source rehabilitation. 212.07.02 Right to Occupy and Operate Written proof, including appropriate permits, for the right to occupy and operate a borrow pit site shall be provided to the Contract Administrator. 212.07.03 Owner's Properties Unless otherwise specified, material will not be available from the Owner's properties. 212.07.04 Clearing, Grubbing and Stripping Borrow sources shall be cleared, grubbed and stripped of unsuitable materials. These operations shall be completed a minimum of three working days in advance of excavation where cross-sections are required. Page 2 Rev. Date: 04/1999 OPSS 212

Stripped material shall be piled sufficiently back from the face of the pit or quarry to prevent the contamination of the face material. The stripped material shall be piled such that the distance from the face being worked to the stripped material shall be: a) for pits: at least equal to the depth of the face or 5 m, whichever is the greater distance; and b) for quarries: at least 5 m. 212.07.05 Placement The construction of embankments and backfill areas with borrow material shall be according to OPSS 206. Earth borrow with 50% or more of the particles between 5 µm and 75 µm in size, as determined by LS-702, shall not be placed within the frost penetration depth. 212.07.06 Haul Roads All restoration work required shall be performed where haul roads are damaged due to hauling operations. Acceptable material shall be placed and work performed on the haul road to provide safe passage and control of traffic at all times. Acceptable material shall be placed and work shall be performed to repair the haul road to pre-contract condition, and to the satisfaction of the Contract Administrator and owner of the haul road upon completion of the hauling operations. 212.07.07 Quality Control 212.07.07.01 Earth Borrow Source The Contract Administrator shall be notified of the intended earth borrow source two weeks in advance of when the material will be used to allow time for sampling and testing. The Contractor shall designate a quality control laboratory, acceptable to the Owner, and be responsible for all costs associated with the testing for quality control requirements. Responsibilities shall include excavation of all test holes and sampling and delivery of all materials to the quality control laboratory. All test results shall be submitted to the Contract Administrator prior to placement of any material in the work. Test holes for earth borrow shall be excavated to the depth of intended excavation. The minimum number of test holes shall be one for every 20,000 m 3 of material or three per source, whichever is greater. The minimum sampling frequency is one sample per visually identified soil type per test hole. Where the earth borrow material is determined to be frost susceptible, it may be conditionally accepted provided a plan is submitted to the Contract Administrator for approval outlining its use outside the frost penetration depth. 212.07.07.02 Excavation and Placement of Earth Borrow Where the earth borrow material is not acceptable due to the moisture content, a plan shall be submitted to the Contract Administrator for approval outlining the excavation, placement and testing procedures. Page 3 Rev. Date: 04/1999 OPSS 212

212.07.07.03 Rock Borrow Rock borrow used in embankments shall meet the requirements of OPSS 206. 212.07.08 Borrow Source Rehabilitation The borrow source shall be rehabilitated to comply with the requirements of provincial regulations. 212.07.09 Management and Disposal of Excess Material The management and disposal of excess material shall be according to OPSS 180. 212.08 QUALITY ASSURANCE 212.08.01 Earth Borrow Source The earth borrow source shall be accepted provided the quality control test results submitted by the Contractor meet the requirements of this specification. The Contract Administrator will take and test a minimum of one sample per source to verify the material meets the requirements of this specification. Additional quality assurance samples may be taken at anytime. 212.08.02 Excavation and Placement of Earth Borrow The Contract Administrator reserves the right to identify on a visual basis, localized soft spots which result from excessive wet, silty or organic borrow materials. Removal and replacement of these areas shall be the responsibility of the Contractor at no additional cost to the Owner. 212.08.03 Rock Borrow The Contract Administrator reserves the right to visually inspect rock borrow to ensure the material conforms to the requirements of OPSS 206. 212.09 MEASUREMENT FOR PAYMENT 212.09.01 Earth Borrow Rock Borrow 212.09.01.01 Tonne Measurement The method of determining the mass of borrow material shall be according to OPSS 102. 212.09.01.02 Cubic Metre Measurement Measurement of payment by the cubic metre shall be as determined by the Contract Administrator according to one of the following methods. a) End Area Method, At Source The volume of material will be measured at the source in their original location and computed in cubic metres by the method of average end areas. Page 4 Rev. Date: 04/1999 OPSS 212

Cross sections will be taken after the source has been cleared, grubbed, and stripped of all unsuitable surface materials. The volume of boulders removed from borrow pits that cannot be accommodated in embankments will be deducted. b) End Area Method, In Place The measurement for payment will be made of borrow materials measured in place with no allowance for shrinkage and computed in cubic metres by the method of average end areas. c) Truck Box Method Materials will be measured in cubic metres, loose, by predetermined truck box capacities and an appropriate bulking factor as determined by the Contract Administrator. The predetermined capacity of each truck will be that computed from its box dimensions. Each truck shall be uniquely and readily identifiable. 212.10 BASIS OF PAYMENT 212.10.01 Earth Borrow - Item Rock Borrow - Item Payment at the contract price for the above items shall be full compensation for all labour, equipment and material required to do the work. 212.10.02 Haul Roads No separate payment will be made for the cost of haul roads. Payment for maintenance and restoration of haul roads will be made for the materials provided and the work performed as specified herein, at contract prices or, at negotiated unit prices. 212.10.03 Access Roads No separate payment will be made for the cost of construction and maintenance of access roads. PI FMC OMC Table 1 Field Moisture Content Acceptance Criteria For Earth Borrow With > 50% Passing the 75 μm Sieve - LS-702 PI 7% FMC OMC + 1% PI > 7% FMC OMC + 5% Plastiity Index, as determined by LS-703/704 Field Moisture Content, as determined by LS-701 Optimum Moisture Content, as determined by LS-623, LS-706 and LS-707 Page 5 Rev. Date: 04/1999 OPSS 212