GENERATION CURTAILMENT AS A MEANS TO INCREASE THE WIND POWER HOSTING CAPACITY OF A REAL REGIONAL DISTRIBUTION NETWORK

Similar documents
Network Interconnection Studies of Distributed Generation

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

OPTIMAL RECLOSER DEPLOYMENT TO LEVERAGE SELF-HEALING: A TECHNO-ECONOMIC ROBUSTNESS ASSESSMENT

A JOINT DSO-TSO REACTIVE POWER MANAGEMENT FOR AN HV SYSTEM CONSIDERING MV SYSTEMS SUPPORT

USING A BATTERY ENERGY STORAGE SYSTEM AND DEMAND RESPONSE CONTROL TO INCREASE WIND POWER PENETRATION IN AN ISLAND POWER SYSTEM

CIRED Workshop - Helsinki June 2016 Paper ABSTRACT PROPOSED APPROACH INTRODUCTION. N. Natale, F. Pilo, G. Pisano, G. G.

Modeling and Operation Analysis of Meshed Distribution Systems with Distributed Generation

Joint DSO TSO reactive power management for an HV system considering MV systems support

DISTRIBUTION FEEDER PROTECTION WITH AND WITHOUT PV SYSTEM

Microgrid impact on the development of electricity infrastructure

Prof. Jean-Louis Lilien & Huu-Minh Nguyen University of Liège Belgium

Effects of Renewable Distributed Generation on the Operational Characteristics of Meshed Power Distribution Systems

Electric Power Systems Research

Project RESPONSE on Improved Modelling of Electric Loads for Enabling Demand Response by Applying Physical and Data-Driven Models

THE IMPROVEMENTS TO PRESENT LOAD CURVE AND NETWORK CALCULATION

Challenges with high PV penetrations in distribution grids

Fault Current Limiters for the Smart Grid

Microgeneration and new end-use technologies in ADDRESS, INCA and SEESGEN-ICT

IMPACT OF WIND POWER PLANT OPERATION ON MV DISTRIBUTION GRIDS

REFORMING DISTRIBUTION TARIFFS OF SMALL CUSTOMERS TARGETS, CHALLENGES AND IMPACTS OF IMPLEMENTING NOVEL TARIFF STRUCTURES

Gas Natural Fenosa s Experiences on Renewable Energy Integration

MANAGING SITUATION AWARENESS IN POWER DISTRIBUTION GRID DISTURBANCES

POWER QUALITY IMPROVEMENT OF A GRID CONNECTED WIND ENERGY SYSTEM USING STATCOM-CONTROL

Smart Grid, Integration of Renewable Sources and Improvement of Power Quality

NORDAC 2014 Topic and no NORDAC 2014 http :// 3.1

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

The new role of DSO. David Trebolle Trebolle Manager, Active Networks and Network Analysis Applications Gas Natural Fenosa

DISTRIBUTION GRID PLANNING CONSIDERING SMART GRID TECHNOLOGIES

Case Studies on Using Load Models in Network Calculation

CASE STUDY : ASSESSMENT OF POWER QUALITY IN PRACTICE

VOLTAGE STABILITY LIMITS FOR WEAK POWER SYSTEMS WITH HIGH WIND PENETRATION ALA TAMIMI AN ABSTRACT OF A DISSERTATION

Capacity and Location Effects of Wind Turbine Energy Systems on Power Systems Stability

Load Shedding in Microgrids

AN ANALYTICAL METHOD TO ASSESS THE IMPACT OF DISTRIBUTED GENERATION AND ENERGY STORAGE ON RELIABILITY OF SUPPLY

INTERACTIVE CUSTOMER GATEWAY FOR ELECTRICITY DISTRIBUTION MANAGEMENT, ELECTRICITY MARKET, AND SERVICES FOR ENERGY EFFICIENCY

What makes a Wind Plant Grid Friendly?

CSIRO CLUSTER PROJECT #3

2007 Technology & Science Publishers. Reprinted with permission.

I. INTRODUCTION

Variable Renewable Energy Sources in Distribution Networks Martin Braun Fraunhofer IWES & Universität Kassel

MEASUREMENTS AND SIMULATION FOR POWER QUALITY OF A WIND FARM

Coordinated voltage support in distribution networks with distributed generation and microgrids

Assessing the impact of micro generation in radial low voltage distribution networks taking into consideration the uncertainty

EVALUATING INVESTMENT DEFERRAL BY INCORPORATING DISTRIBUTED GENERATION IN DISTRIBUTION NETWORK PLANNING

Economics of energy storage technology in active distribution networks

EXTRACTION OF 9,163 REAL LV NETWORK MODELS FROM DNO GIS DATABASE TO ASSESS OVERVOLTAGE FROM PV AND CONSEQUENT MITIGATION MEASURES

ISSN Vol.07,Issue.16, November-2015, Pages:

SMART GRID VENDÉE PROJECT: A DECISION-SUPPORT TOOL FOR THE MULTI- YEAR PLANNING OF ACTIVE DISTRIBUTION NETWORKS

Chronological Simulation of the Interaction between Intermittent Generation and Distribution Network. G.N. Taranto C.C.O. Hincapié

Analysis of Wind Power Integration for Power System Transient Stability

Schedule 2 TECHNICAL INFORMATION

Hierarchical Frequency Control Scheme for Islanded Multi-Microgrids Operation

Large-scale Integration of Distributed Energy Resources within Electric Power Systems. Danish Cell Controller Project Brief

Power System Operation Procedure Glossary Of Terms

Desenvolvimento da Microgeração e das Microredes

ADVANCED FAILURE RATE AND DISTRIBUTION NETWORK RELIABILITY MODELLING AS PART OF NETWORK PLANNING SOFTWARE

ENABLING EMBEDDED GENERATION

Maximum PV-penetration in low-voltage cable networks

THE IMPACT OF RESTRUCTURING URBAN AND SUBURBAN DISTRIBUTION GRIDS WITH SMART GRID APPROACHES ON SYSTEM RELIABILTY

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

ANALYSIS OF TRANSITION STEPS TOWARDS POWER-BASED DISTRIBUTION TARIFF OF SMALL CUSTOMERS

Improving the Reactive Power Balance between a German MV and HV Grid through Coordinated Reactive Power Provision by Wind Power Plants

Distributed Energy Resource Management System (DERMS)

THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks

WIND ENERGY INTEGRATION IMPACT ON POWER QUALITY IN ESTONIA

Distributed Generation Penetration Impact on Distribution Networks Loss

Costs and Benefits of DG Connections to Grid System

Smart Virtual Power Plants for the Future Electric Grid Realization and Benefits

CERTS Microgrids. Tom Jahns Professor, University of Wisconsin-Madison. LPPC Rates Roundtable May 21, 2013

Incentivising the connection of DG: Promoting efficient connection and appropriate benefit sharing

IMPACT OF THREE-PHASE PSEUDO-MEASUREMENT GENERATION FROM SMART METER DATA ON DISTRIBUTION GRID STATE ESTIMATION

Risks and challenges results from study

Voltage Stability Assessment of a Power System Incorporating Wind Turbine Using Power System Analysis Toolbox (Psat)

Facing the challenges of distribution systems operation with high wind power penetration

MORE MICROGRIDS Contract No: PL019864

Connection Study Requirements

Impacts of the Decentralized Wind Energy Resources on the Grid

IDE4L project overview and ANM concept. Distributed automation system

Transmission Topology Control for System Efficiency Simulations on PJM Real Time Markets

Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany

Control of a Microgrid in Islanded Mode

Study on the value of flexibility in the management and design basis of distribution networks in France

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

Mitigation of Voltage Fluctuations in Power System Using STATCOM

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

Methodological Application to Integrate Renewable Energy Resource into Kuwait s Electrical Grid

Critical Load Serving Capability by Microgrid using 100% Renewable Energy

POWER SYSTEM AND ASSET MODELS

AORC Technical meeting 2014

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008

A. Behaviour of the Wind

PREVENTING BLACKOUTS IN A CORSICAN VILLAGE THANKS TO LOCAL BIOMASS GENERATOR

Contribution of PV Power Plants to Flicker Severity in Power Distribution Grids

Harnessing Renewables in Power System Restoration

ENGINEERING RECOMMENDATION P2/6 SECURITY OF SUPPLY JULY Energy Networks Association Engineering Directorate

POTENTIAL TECHNICAL IMPACTS OF ROOFTOP SOLAR GENERATION ON LOW VOLTAGE DISTRIBUTION NETWORKS

Variation of Reliability Indices with Generation Techniques Applied.

Transcription:

GENERATION CURTAILMENT AS A MEANS TO INCREASE THE WIND POWER HOSTING CAPACITY OF A REAL REGIONAL DISTRIBUTION NETWORK Anna KULMALA Sami REPO Jouni PYLVÄNÄINEN VTT Finland Tampere University of Techlogy Finland Elenia Oy - Finland anna.kulmala@vtt.fi sami.repo@tut.fi jouni.pylvänäinen@elenia.fi ABSTRACT This paper represents how generation curtailment can be utilized to increase the wind power hosting capacity of an existing distribution network. The paper proposes a control algorithm that implements the curtailment and can be easily implemented as a part of the existing network management tools of the distribution system operator. The paper also presents how the amount of annual curtailment can be evaluated prior to wind farm construction. INTRODUCTION The amount of generation connected to distribution networks is constantly increasing. Depending on the type and size of the distributed generation (DG) units, they can be connected to any of the voltage levels operated by distribution networks operators (DSOs). Small DG units such as rooftop PV plants are connected to LV networks (4 V), medium-sized DG units such as larger PV plants or single wind turbines are connected to MV networks (in Finland usually 2 kv) and large units such as wind farms are connected to HV distribution networks (in Finland 11 kv) or directly to transmission system. Connecting generation to any of the above mentioned DSO networks can cause problems related to voltage quality, overloading of network components and protection [1]. The factor limiting the network s DG hosting capacity depends on the voltage level and the type of network (weak/strong). In weak MV and LV networks, voltage rise is usually the factor limiting the amount of DG that can be connected to the network. In stronger networks, overloading of feeders/transformers or increased fault levels are usually the limiting factors. The measures that can be used to mitigate the DG caused problems are different depending on the limiting factor and also on the voltage level. This paper concentrates on mitigating overloading problems. The work has been demonstrated as a case study considering a real Finnish 11 kv HV distribution network to which a large amount of wind power is to be connected but the proposed methodology is applicable also to other networks and generation types. Overloading problems caused by wind power plants can be mitigated either by reinforcing the network or moving towards an active network management scheme. The cost of network reinforcement is, in many cases, very high and can make otherwise profitable wind power projects too expensive. Active network management methods can decrease the total costs significantly. [2] In this paper, generation curtailment as a means to increase the wind power hosting capacity of an existing 11 kv HV distribution network is studied. The study network is a real network operated by a Finnish DSO Elenia. The study network is located at the coast and has, therefore, good wind conditions. A large amount of wind farms is planned to be built on the area. If the current passive network management method is maintained, some of the planned wind farms cant be connected to the existing network because the feeders would be overloaded if all the connected units would be generating their minal power. However, due to the intermittent nature of wind power, the frequency of occurrence of these kind of network conditions can be rare. Moreover, the feeder current limits are dependent also on the ambient temperature and wind speed and, hence, during the winter time more power can be transferred than during the summer time. The average wind conditions are better during the winter time than during the summer time [3]. Utilizing generation curtailment when overloading would otherwise occur can, therefore, be a profitable option. The aim of this paper is to study the implementation and profitability of generation curtailment in the study network. The proposed control algorithm is described in detail and also its integration as a part of the existing DSO systems is discussed. The paper will also present estimates on the amount of generation that would be annually curtailed if the control algorithm would be taken into use and all the planned wind farms would be connected to the existing network. This information is vital to wind power producers when making the investment decisions and the network connection agreement. STUDY NETWORK The study network consists of a 11 kv main feeder and branches. The main feeder has transmission system connection points at both ends but is radially operated. At the moment, the network feeds load s and one wind farm. There is, however, significant interest in building new wind farms to the area. Some of the planned wind farms already have finalized connection agreements and with some negotiations are still ongoing. The network structure is depicted in Figure 1. Only the main feeder can be overloaded since the minal powers of the wind farms connected on the branches are CIRED 217 1/5

17,25 MW Transmission network connection point 2 6 1 Load Load 3 8 4 27,6 MW 59,5 MW 16 MW 18 48,3 MW 16 5 Open 36,3 + 42 MW Load 17 5 + 3 MW 15 3 + 9 MW Transmission network 14 46,2 MW 12 11 connection 13 Load point 25 MW Figure 1. The example network structure. 7 25 + 29,7 MW relatively low. The current limit for the whole main feeder is 1155 A. Current and voltage measurements are available from load s, wind farms and transmission network connection points. Also real and reactive power measurements are available from load s and wind farms. PROPOSED CONTROL ALGORITHM The proposed algorithm has been designed such that implementing it as a part of the existing DSO SCADA would be as easy as possible. The algorithm utilizes measurement data that is already available and sends the control signals through standard communication channels that are available to all generation plants connected to HV distribution networks. Also contractual issues have been taken into account when defining the control principles. Operational principle The control algorithm curtails wind power generation when any part of the network is overloaded. At first, the algorithm utilizes measurement data and network static data to determine currents at each network section. If the current limit is exceeded at any of the network sections, the algorithm determines the amount of needed generation curtailment, selects the wind farms to be curtailed using a predefined order and sends new real power set points to the wind farms to be curtailed. The algorithm includes also a restoring part which cancels the generation curtailment commands in case they are t needed anymore. The Measurement data Generation curtailment Current calculation Overloaded branches? Static network data New set points to relevant resources Figure 2. The functional diagram of the control algorithm. Restoring control functional diagram of the algorithm is represented in Figure 2. Current calculation There is both load and production in the network and, therefore, the maximum current can be located also elsewhere than at the transmission system connection point. Control decisions cant be made based only on direct measurement data but currents in all network sections have to be calculated. In a radial network, currents can be easily calculated utilizing the network static data and the measured current magnitudes and angles at load and production sites. Moving averages of the current measurements should be used as input to the current calculation function instead of instantaneous values. The thermal time constants of feeders are quite long and, therefore, current transients do t require control actions to be conducted. Generation curtailment Generation curtailment is implemented using the last-infirst-out (LIFO) principle. From the contractual point of view, this is the simplest approach because modifying the already existing connection agreements is t a feasible option. It is the best choice also from the wind power producers point of view because an estimate on the annual curtailed energy can be given during connection negotiations and the situation does t change even if new units connect to the network later. Moreover, in case of overloading mitigation, all units whose power is transmitted through the overloaded branch are equally effective in reducing the overloading whereas if the main problem would be voltage rise, different units would have different voltage sensitivities and, therefore, LIFO would t necessarily lead to a very efficient outcome. Other selection methods are discussed in [4]. The flow chart of the algorithm part that determines the amount of curtailment for each of the generating units is depicted in Figure 3. To minimize the amount of generation curtailment, the algorithm starts from the branch that is most distant from the and proceeds through all the branches. At first, the algorithm checks if the studied branch is overloaded and determines CIRED 217 2/5

the needed current reduction. If ambient temperature measurement is available, the current limit is changed based on the measurement. The effect of ambient temperature to the feeder capacity is significant [5]. It would be possible to take also wind conditions into account when determining the current limit but the DSO operating the example network preferred t to include it because major part of the feeder is located in the middle of forest where the impact of wind speed for the cooling of feeder is unkwn and is expected to vary a lot in each specific feeder section. The algorithm utilizes a LIFO table in deciding which units to curtail. The table includes information on the order in which the units have been connected to the network but also information on which branch currents the unit can affect. The algorithm curtails as many units as necessary to obtain the current reduction target for the branch under study, saves the new calculated real power set points and moves to the preceding branch. When all the branches have been gone through, the new set points are sent to the units. If the network switching state changes, the LIFO table has to be updated. If network topology data is available in the distribution management system, this update can be done automatically. Also other principles than LIFO can be used without changing the algorithm implementation. Since the controlled units are selected from the LIFO table, the order in which the units are controlled can be changed by simply modifying the table. Calculated currents at each branch Select furthest branch from the transmission system connection point Branch overloaded? i = 1 Restoring control Restoring control is invoked if there are overloaded branches in the network. At first, it checks if the maximum current in the network differs from the feeder current limit more than a predefined margin. If it does, the algorithm determines new higher real power set points using a similar operational principle as the one presented in Figure 3. The units whose real power has been curtailed are gone through in a reverse LIFO order and the set points are increased until the maximum current reaches its limiting value (feeder current limit - margin). Restoring control is needed to prevent situations where generation is curtailed although there is need for it anymore. Practical implementation The control algorithm is implemented as a part of the existing DSO SCADA. The control algorithm is executed with a predefined interval. The interval cant be too long to prevent overheating of the feeder. On the other hand, the algorithm should t be executed again before new measurement data is available and the previous control actions have been finalized. The feeder thermal time constant is in the study network approximately 2 minutes. New measurement data is available in the study network at least two times a minute and the rate of change of wind farm real power can be set between 1 to 1 % per minute [6]. Execution interval of 5 minutes is selected. Since the proposed algorithm was planned to be as simple as possible, implementing it as a part of the existing SCADA is relatively easy. Also, it does t require a lot of calculation capacity and, therefore, does t slow down other SCADA processes. The algorithm utilizes measurement data that is already available in the SCADA with the exception of the ambient temperature measurement which is, however, t mandatory for the algorithm implementation but just improves its performance. The new set points are sent to the wind farms through existing communication channels. Find from the LIFO table the ith unit that can decrease the current at the overloaded branch Meas. current of the ith unit > required current reduction? Calculate new P set,ith so that the current reduction target is fulfilled i = i + 1 Set P set,ith to. MW Calculate new value for the required current reduction The algorithm has to be able to prevent feeder overloading also in exceptional situations. In the example network, branch currents can be accurately determined also in case measurements from one de are missing because there is a current measurement also at the transmission system connection point. If measurements are missing from more than one wind farm, the algorithm assumes the powers of these units to be minal and uses them as the primary curtailment resource. Select preceding branch All branches checked? New set points ready Figure 3. Flow chart of the algorithm that determines the new set points for each of the wind farms. AMOUNT OF NEEDED CURTAILMENT It is important to the wind power producer to kw an approximate value for the annual curtailment when making the investment decision. In this paper, statistical planning method [7] is used to calculate the amount of curtailed generation. In statistical planning, load flow calculations are conducted for the whole year using CIRED 217 3/5

available load and production data. If measurement data is t available, load and production profiles can be used. In the study network, hourly load measurements are available from all the load s. Wind speed measurement data is available from one of the wind farm sites with 1 minute interval. The production profiles for the wind farms are calculated from this measurement data by utilizing typical wind turbine power curves and by assuming that the wind speed does t differ between sites. The assumption is conservative and the real curtailment need will be somewhat smaller than the calculated one. The functional diagram of the statistical planning method is represented in Figure 4. t = t + t_step Figure 4. Operational principle of statistical planning algorithm. In this paper, calculations are conducted with a 1 minute interval for the whole year i.e. t_start = 1 min, t_stop = 5256 min and t_step = 1 min. In total 5256 calculations are conducted per study case. Statistical planning method could be relatively easily included as a part of the network information system (NIS) that is used as the DSO network planning tool [7]. However, the functionality is t yet available in any commercial NIS. The DSO can utilize also a separate tool similar to the one used in this paper for curtailment calculations. SIMULATION RESULTS Calculate load flow with the load and production values at time t t = t_start Calculate amount of curtailment at time t t < t_end The operation of the control algorithm has been simulated in this paper using Matlab PST toolbox. Load flow simulations are adequate since the execution time of the algorithm is negligible compared to the feeder thermal time constant. The study network depicted in Figure 1 has been modelled using the real feeder data (lengths, impedances) so that also reactive power production or consumption by the line and the real power losses are taken into account in the calculations. The connection order of the units is t yet kwn but for the calculations the order shown in Table 1 was defined. Calculations were conducted for two different wind tower heights (1 m and 12 m) and for two different transmission system voltages (11 kv and 118 kv). The Annual curtailment need for each wind park Table 1. The order in which the units are curtailed for both of the radial feeders. The uppermost is connected last to the network and will be, therefore, curtailed first. Connection de Nominal power Connection de Nominal power 7 29.7 17 3 5 16 16 42 7 25 16 36.3 8 59.5 13 46.2 4 27.6 17 9 6 17.25 18 48.3 15 3 15 5 14 25 annual total curtailment is presented for these four cases in Figure 5. The wind farms operated with a unity power factor although in reality they would be operating in voltage control mode which would affect the currents also somewhat. The results shown in Figure 5 give some general idea on the network operation if all the planned wind farms would be built. For the wind power producers, however, the information is t adequate but the amount of curtailment for each wind farm is needed. Figure 6 shows the wind farm production data when the tower height has been assumed to be 12 m and the transmission system voltage 118 kv which is the typical value. MWh 25 2 15 1 5 11.8 % 8.3 % 121 m 122 m 13 m 14 m 11 kv 118 kv 11 kv 118 kv Annual production Annual curtailment Figure 5. Total curtailment in the studied cases. 1 % 9 % 8 % 7 % 6 % 5 % 4 % 3 % 2 % 1 % % 44638 5494 Node 7 29.7 MW 42345 49395 Node 5 16 MW Annual production 45884 54666 Node 17 3 MW 8.3 % 5.7 % 44793 95977 Node 16 42 MW Annual curtailment 121659,9 Figure 6. Production data for the wind farms that have been curtailed (tower height 12 m and transmission system voltage 118 kv).,1 Node 16 36.3 MW CIRED 217 4/5

It should be ticed that the results above assume a certain connection order of the units and the curtailed units will be different if the LIFO table is modified. However, the amount of curtailed energy will remain similar since the maximum current is for both radial feeders at the beginning of the feeder. The results show that for some of the wind farms the amount of curtailment is so high that probably they will t be built, at least with the planned minal power. However, the real amount of curtailment would be lower since it was assumed that the wind speed is the same in all the sites and also the temperatures were t taken into account. Especially the latter increases the amount of calculated curtailment significantly compared to the real situation. The effect of temperature could be added to the calculations by using a typical yearly temperature curve as an input. From the DSO point of view, the algorithm operated in each situation as desired. The current remained below its limit in all loading and production situations. Figure 7 shows the operation of the algorithm in one example case. CONCLUSIONS Generation curtailment can be an attractive alternative to network reinforcement in cases where the amount of annual curtailed generation is moderate. This paper presents a control algorithm that utilizes generation curtailment to increase the wind power hosting capacity of an HV distribution network. The paper also presents a method to evaluate the amount of annual curtailment prior to wind farm construction. Although the paper concentrates on an example network, the proposed control algorithm can be applied also to other radial networks. The statistical planning method is applicable to all kinds of distribution networks. REFERENCES [1] N. Jenkins, R. Allan, P. Crossley, D. Kirchen and G. Strbac, 2, Embedded Generation, The Institution of Electrical Engineers, London, UK, p. 273. [2] A. Kulmala, 214, "Active voltage control in distribution networks including distributed energy resources", Doctoral Dissertation, Department of Electrical Engineering, Tampere University of Techlogy. [3] VTT, "Wind energy statistics in Finland", available: http://www.vttresearch.com/services/low-carbonenergy/wind-energy/wind-energy-statistics-infinland [4] R. Currie, B. O'Neill, C. Foote, A. Gooding, R. Ferris and J. Douglas, 211, "Commercial arrangements to facilitate active network management", Proc. 21st Int. Conference on Electricity Distribution, Frankfurt, Germany. [5] C. J. Wallnerström, Y. Huang and L. Söder, 215, "Impact from dynamic line rating on wind power integration", IEEE Trans. Smart Grid, vol. 6,. 1, pp. 343-35. [6] Fingrid, 213, "Specifications for the operational performance of power generating facilities", available: http://www.fingrid.fi/en/customers/connection/speci fications. [7] A. Kulmala, S. Repo and P. Järventausta, 211, "Using statistical distribution network planning for voltage control method selection", Proceedings IET Conference on Renewable Power Generation, Edinburgh, UK. 2 15 Feeder current limit 1 5 No control 1-2 2-3 3-4 4-5 2-6 3-7 4-8 1 2 3 4 5 6 7 8 9 1 Feeder current limit 12 1 8 6 4 2 Generating curtailment algorithm operating 1-2 2-3 3-4 4-5 2-6 3-7 4-8 1 2 3 4 5 6 7 8 9 1 4 3 Node 7 29.7 MW Node 5 16 MW 2 1 1 2 3 4 5 6 7 8 9 1 t [1 min] Figure 7. The operation of the proposed control algorithm in the radial feeder fed from transmission system connection point 1 for 1 first time steps (tower height 12 m and transmission system voltage 118 kv). CIRED 217 5/5