CONSISTENCY MEETING DEPARTMENTAL GOALS: % 1 DAY TURN AROUND % CONTRACTOR PASS RATE QUALITY INSPECTIONS! EXCELLENT CUSTOMER SERVICE!

Similar documents
MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 11/10/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 7/14/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 5/12/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

(Condensed from National Electric Code)

EFFECTIVE DATE: November 1, 2011, unless a later date is cited at the end of a section. [ NMAC - Rp,

Sections through of Chapter 5 of the Victoria City Code are amended to read as follows: ARTICLE IX. NATIONAL ELECTRICAL CODE

Inspection Guide for PV Systems in One- and Two- Family Dwellings (For Rooftop Photovoltaic Systems meeting the Standard Plan)

Click here to get back to 2011 NEC Code Updates Part 1

New Jersey Chapters July NEC updates. The Association of Electrical and Medical Imaging Equipment Manufacturers

Basic Requirements for Residential Electrical Installations

2. Article (A) Delete the measurement of 6 feet 7 inches and insert: 66 inches (5 feet 6 inches).

FOR ALL STAKEHOLDERS TO HAVE A SUCCESSFUL PROJECT

EFFECTIVE DATE: July 1, 2008, unless a later date is cited at the end of a section. [ NMAC - Rp,

SERVICES CHAPTER 35. wire. For all other installations, the rating of the ungrounded conductors shall be not less than 60 amperes.

Replace 210.8(a)(7) with: Sinks. Where receptacles are installed within 6 feet of the outside edge of a sink. Page 1 of 5

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

Temporary Wiring Practices And Guidelines For NECA. National Electrical Contractors Association Omaha, Nebraska

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL).

WIRING METHODS CHAPTER 38

2015 Code Rollout Meeting Q & A

TABLE OF CONTENTS CHAPTER 2 WIRING AND PROTECTION CHAPTER 1 GENERAL RULES... 19

MUSCO ENGINEERING ASSOCIATES Consulting Engineers

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL

ELECTRICAL BULLETIN

DEPARTMENT OF PLANNING SERVICES BUILDING INSPECTION DIVISION 1555 N 17 TH AVENUE, GREELEY, CO (970)

2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING

St. Clair County Electrical Code Regulations

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

Wyoming Division IAEI Annual Meeting/Seminar 2003 Code Panel Questions Answers in BOLD, using 2002 NEC

Temporary Wiring. Low-Voltage Electrical Safety Orders

NEC 2014 Code Changes

POWER AND LIGHTING DISTRIBUTION

IMPORTANT CODE UPDATE ENFORCEMENT DATE FOR NEW NATIONAL ELECTRIC CODE IS SET FOR MAY 1, 2013

2011 National Electrical Code Update Training. Henrico County Department of Building Construction and Inspections

2011 National Electrical Code Update Training

SECTION GROUNDING

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

About This Textbook... xvii About the National Electrical Code...xxi About the Author... xxv About the Illustrator... xxvi About the Team...

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

POWER AND LIGHTING DISTRIBUTION

DESIGN GUIDELINES WIRING AND CONDUITS PAGE 1 of 7

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

Article 10 - ADMINISTRATIVE SECTION

Appendix C - International NEC Electric Code Amendments

GENERAL NOTES PEDERNALES ELECTRIC COOPERATIVE, INC. RESIDENTIAL AND COMMERCIAL AMP METER LOOP SPECIFICATIONS

ELECTRICAL SAFETY Information Bulletin

BULLETIN SUBJECT: GENERAL BULLETIN, 2015 SASK INTERPRETATIONS CORRECTIONS, AND ELECTRIC SERVICE REQUIREMENT CHANGES OR ADDITIONS

Design Standard Conduit for Electrical Systems

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

ELECTRICAL BULLETIN

BULLETIN LICENSED ELECTRICAL CONTRACTORS. SaskPower Electrical Inspections. June 13, Item #1 Arc-Fault Receptacles, CEC Rule (f)

SECTION PART 1 GENERAL

Homeowner electrical wiring guide. Including the 2015 Canadian Electrical Code amendments

UNDERGROUND SERVICES SECONDARY

SOUTHERN NEVADA AMENDMENTS TO THE 2018 NATIONAL ELECTRICAL CODE

OVERHEAD SERVICES - RESIDENTIAL & GENERAL SERVICE. See Chapter 3, Section 3.01 for more information about point of entrance (POE).

B. Provide a complete conduit system with associated couplings, connectors, and fittings.

POWER AND LIGHTING DISTRIBUTION Reserved

MECKLENBURG COUNTY Land Use & Environmental Services Agency Code Enforcement 10/7/09 ELECTRICAL CONSISTENCY MEETING

Manitoba Electrical Code

ELECTRICAL DEFINITIONS

CHAPTER LOCAL AMENDMENTS TO THE NATIONAL ELECTRICAL CODE 2011 EDITION

CONTENTS. B. System Design and Performance Requirements

Reference Information:

SOUTHERN NEVADA AMENDMENTS TO THE 2017 NATIONAL ELECTRICAL CODE

DEVICES AND LUMINAIRES

SOUTHERN NEVADA AMENDMENTS TO THE 2017 NATIONAL ELECTRICAL CODE AS AMENDMEND BY THE CITY OF NORTH LAS VEGAS

ORDINANCE NO NOW, THEREFORE, BE IT ENACTED BY THE CITY COUNCIL OF THE CITY OF FAIRBANKS, ALASKA, as follows:

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL

SOUTHERN NEVADA AMENDMENTS TO THE 2017 NATIONAL ELECTRICAL CODE AS AMENDMEND BY THE CITY OF NORTH LAS VEGAS

Continuing Education Credits. Learning Objectives. Jim Dollard. OSHA Fine Structure. Reasons to get it right! 5/27/2014

HOMEOWNER PERMITS AND ELECTRICAL WIRING GUIDE

2008 ELECTRICAL CODE RULES Part 8

SECTION INSULATED WIRE AND CABLE

Youngstown State University

BASIC CONCEPTS IN ELECTRICAL DESIGN. Prepared by Engr. John Paul Timola

City of Santa Monica Building and Safety Division

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL

CONSULTATION MEETING: Adoption of the 2015 edition of the Canadian Electrical Code

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

PORT OF SAN FRANCISCO ELECTRICAL CODE. Based on the 2016 California Electrical Code

Article Requirements for Electrical Installations (A) and (B) - Available Fault Current (New)

CONTINUING EDUCATION FOR FLORIDA ELECTRICIANS NEC Code Change Part 1 8 Hours

a) Line and load compartments must be separated by a stable barrier.

ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION CODE

This product specification is written according to the Construction Specifications Institute MasterFormat, 2014 Update.

TEMPORARY METER POLE INSTALLATION

Top Changes 2014 NEC

Please check with your local inspection authority for any additional requirements before installation.

Service Entrance Cable Fittings

Table of Contents. Preface

2008 Port of San Francisco Electrical Code February 2010 edition. February 2010 edition of the 2008 Port of San Francisco Building Code

UNDERGROUND SERVICES (RESIDENTIAL) SINGLE FAMILY RESIDENTIAL, DUPLEXES, OR TOWNHOUSES

SECTION GROUNDING AND BONDING

3. Intermediate metal conduit (IMC). 4. Electric metallic tubing (EMT). 5. Flexible metal conduit (FLEX). 6. Polyvinyl chloride conduit (PVC).

Revisions for the 2015 Edition of the "Specifications and Requirements for Electric Installations (Bluebook)"

SERVICES - SERVICE EQUIPMENT- PANELBOARDS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT

Transcription:

CONSISTENCY MEETING Date: 3/12/2014 DEPARTMENTAL GOALS: 85-90 % 1 DAY TURN AROUND 80-85 % CONTRACTOR PASS RATE QUALITY INSPECTIONS! EXCELLENT CUSTOMER SERVICE! SAFETY ISSUES: REMEMBER COUNTY CELL PHONE POLICY, USE ALL APPROVED SAFETY EQUIPMENT ISSUED TO YOU. (i.e. HARDHAT, SAFETY GLASSES, SAFETY SHOES, PPE) Q: WHY ARE WE HERE? A: TO SERVE THE CUSTOMER Consistency Questions 1. Is it permissible to sleeve SER cable in PVC from an outdoor panel into a crawl space? (Chris Dellinger) Yes, the key word here is sleeve. See 338.10(B)(4) SERVICE-ENTRANCE CABLE (TYLZ)

GENERAL This category covers service-entrance cable designated Type SE and Type USE for use in accordance with Article 338 of ANSI/NFPA 70, "National Electrical Code" (NEC). Service-entrance cable, rated 600 V, is certified in sizes 14 AWG and larger for copper, and 12 AWG and larger for aluminum or copper-clad aluminum. The cable is designated as follows: Type SE Indicates cable for aboveground installation. Both the individual insulated conductors and the outer jacket or finish of Type SE are suitable for use where exposed to sun. Type SE cable contains Type RHW, RHW-2, XHHW, XHHW-2, THWN or THWN-2 conductors. Maximum size is 4/0 AWG copper or 300 kcmil aluminum or copper-clad aluminum. Types USE and USE-2 Indicates cable for underground installation including direct burial in the earth. Maximum size is 2000 kcmil. Cable in sizes 4/0 AWG copper, aluminum or copper-clad aluminum and smaller and having all conductors insulated is suitable for all of the underground uses for which Type UF cable is permitted by the NEC. Multiconductor Type USE cable contains conductors with insulation equivalent to RHW or XHHW. Multiconductor Type USE-2 contains insulation equivalent to RHW-2 or XHHW-2 and is rated 90ºC wet or dry. Single- and multiconductor Types USE and USE-2 are not suitable for use in premises. Single- and multiconductor Types USE and USE-2 are not suitable aboveground except to terminate at the service equipment or metering equipment. Both the insulation and the outer covering, when used, on single- and multiconductor Types USE and USE-2, are suitable for use where exposed to sun. 2. How do you ground Service Equipment in more than 1 enclosure-or Subpanel (Gerald Barnes) 3. In a dwelling, do the receptacles installed in an appliance garage have to be GFCI protected? (David Rains)

Yes see 210.8. While these receptacles don t count as the required countertop receptacles, they still serve the countertop space none the less. 4. I have an outdoor floodlight controlled by a switch located in the living room. Since the lighting outlet is located outside the living room, would this have to be on an AFCI circuit? (Matt King) (A) Dwelling Units. All 120-volt, single phase, 15- and 20-ampere branch circuits supplying outlets installed in No there are no requirement for AFCI protection on outdoor OUTLETS Outlet. A point on the wiring system at which current is taken to supply utilization equipment. 5. Is a Butler s Pantry required to be on small appliance circuit, GFCI, and/or AFCI? (Craig Sloop) In the Interpretations White Book pg 7.5 is being changed as follows: Per 210.8(A)(6) & (7), 210.11(C)(1), 210.12, and 210.210.52 (B) (1) & (C) of the code, if the butler s pantry is located in the kitchen it is required that all spacing and GFCI protection be met, the same as all other kitchen countertops. If the butler pantry is located outside of the kitchen (i.e. dining room or hallway) it will be required to be on AFCI as well as small appliance branch circuit. 6. Please clarify GFCI protected circuitry for Temporary Utilities installations (Joe Weathers) 10.8 Temporary Power 10.8.1 Scope. The provisions of this section apply to the utilization of portions of the wiring system within a building to facilitate construction. 10.8.2 Provisions for Temporary Power. The Code enforcement official shall give permission and issue a permit to energize the electrical service when the provisions of 10.8 and the following requirements have been met: 1) The service wiring and equipment, including the meter socket enclosure, shall be installed, the service wiring terminated, and the service equipment covers installed.

2) The portions of the electrical system that are to be energized shall be complete and physically protected. 3) The grounding electrode system shall be complete. 4) The grounding and the grounded conductors shall be terminated in the service equipment. 5) At least one receptacle outlet with ground fault circuit interrupter protection for personnel shall be installed with the circuit wiring terminated. 6) The applicable requirements of the North Carolina Electrical Code apply. 10.8.3 Uses Prohibited. In no case shall any portion of the permanent wiring be energized until the portions have been inspected and approved by an electrical Code Enforcement Official. Failure to comply with this section may result in disconnection of power or revocation of permit. 590.6 Ground-Fault Protection for Personnel. Ground fault protection for personnel for all temporary wiring installations shall be provided to comply with 590.6(A) and (B). This section shall apply only to temporary wiring installations used to supply temporary power to equipment repair, or demolition of buildings, structures, equipment, or similar activities. This section shall apply to power derived from an electric utility company or from an on-site-generated power source. (A) Receptacle Outlets. Temporary receptacle installations used to supply temporary power to equipment used by personnel during construction, remodeling, maintenance, repair, or demolition of buildings, structures, equipment, or similar activities shall comply with the requirements of 590.6(A)(1) through (A)(3), as applicable. Exception: In industrial establishments only, where conditions of maintenance and supervision ensure that only qualified personnel are involved, an assured equipment grounding conductor program as specified in 590.6(B)(2) shall be permitted for only those receptacle outlets used to supply equipment that would create a greater hazard if power were interrupted or having a design that is not compatible with GFCI protection. (1) Receptacle Outlets Not Part of Permanent Wiring. All 125-volt, single-phase, 15-, 20-, and 30-ampere receptacle outlets that are not a part of the permanent wiring of the building or structure and that are in use by personnel shall have groundfault circuit-interrupter protection for personnel. (2) Receptacle Outlets Existing or Installed as Permanent Wiring. Ground-fault circuit-interrupter protection for personnel shall be provided for all 125-volt, singlephase, 15-, 20-, and 30-ampere receptacle outlets installed or existing as part of the permanent wiring of the building or structure and used for temporary electric power. Listed cord sets or devices incorporating listed ground-fault circuit interrupter protection for personnel identified for portable use shall be permitted. 7. Is it permissible to use compression fittings on EMT in wet locations or do they have to be listed as rain tight? (Chris Dellinger)

It is permissible and they do have to be listed rain tight. See (FKAV) pg 151 in the 2013 UL White Book: ELECTRICAL METALLIC TUBING FITTINGS (FKAV) GENERAL This category covers electrical metallic tubing fittings such as connectors, couplings and expansion fittings, from 1/2 to 4 (metric designators 16 to 103) inclusive trade sizes, intended for installation and use in accordance with the following information and the limitations specified in Electrical Metallic Tubing (FJMX ). All male threaded fittings have only been investigated for use with locknuts. Indentor Fittings Indentor-type fittings are for use with metallic-coated electrical metallic tubing only and require a special tool supplied by the manufacturer for proper installation. Diametrically opposed indentor-type tools require two sets of indentations nominally 90º apart. Triple-indent tools require one set of indentations. Grounding These fittings are considered suitable for grounding for use in circuits over and under 250 V and where installed in accordance with ANSI/NFPA 70, "National Electrical Code." Reusability Fittings have not been investigated for reusability. Reusability should be determined by the installer and the Authority Having Jurisdiction. PRODUCT MARKINGS Fittings suitable for use in poured concrete or where exposed to rain are so indicated on the device or carton. The term "rain tight," "wet location" or the equivalent on the carton indicates suitability for use where directly exposed to rain. The term "concrete tight" or equivalent on the carton indicates suitability for use in poured concrete. Fittings have been tested for use only with steel tubing unless marked on the device or carton to indicate suitability for use with aluminum or other material. CARTON MARKINGS A fitting that is taped completely (from the raceway to the box, or raceway to raceway) is concrete-tight when the product carton is marked "CONCRETE-TIGHT WHEN TAPED." ADDITIONAL INFORMATION For additional information, see Electrical Metallic Tubing (FJMX ) and Electrical Equipment for Use in Ordinary Locations (AALZ ). REQUIREMENTS

The basic standard used to investigate products in this category is ANSI/UL 514B, "Conduit, Tubing, and Cable Fittings." UL MARK The UL symbol on the product and the Listing Mark of UL on the smallest unit container in which the product is packaged is the only method provided by UL to identify products manufactured under its Listing and Follow-Up Service. The Listing Mark for these products includes the UL symbol (as illustrated in the Introduction of this Directory) together with the word "LISTED," a control number, and the product name "Electrical Metallic Tubing Fitting" (or "EMT Fitting" ), "Connector" or "Coupling," or other appropriate product name as shown in the individual Listings. * * * * * * * * * * * * * * * * * * * * * * * * * UL, in performing its functions in accordance with its objectives, does not assume or undertake to discharge any responsibility of the manufacturer or any other party. UL shall not incur any obligation or liability for any loss, expense or damages, including incidental or consequential damages, arising out of or in connection with the use, interpretation of, or reliance upon this Guide Information. 8. I have been turned down several times lately for my conduits to LED pool lights being covered before inspection. The pools are 1 piece fiberglass pools and must be backfilled and filled with water immediately after setting in place. Is it really necessary to see these conduits since they only contain a 12V low voltage cable? (Matt King) Yes this is necessary. There is nothing in articles 300 or 411 or 680 that say this underground installation does not have to be inspected. 9. We are replacing the kitchenette cabinets and countertops in the guest suites in a hotel. Will we have to bring it up to the current code like we would in a house? It does have a cooktop. (Chris Dellinger)

Yes. 210.60 Guest Rooms, Guest Suites, Dormitories, and Similar Occupancies. (A) General. Guest rooms or guest suites in hotels, motels, sleeping rooms in dormitories, and similar occupancies shall have receptacle outlets installed in accordance with 210.52(A) and (D). Guest rooms or guest suites provided with permanent provisions for cooking shall have receptacle outlets installed in accordance with all of the applicable rules in 210.52. 10. When replacing the existing receptacles in a hotel guest suite, do they have to be Tamper Resistant? (Craig Sloop) Yes 406.4(D)(5); 406.13 406.4(D)(5) Tamper-Resistant Receptacles. Listed tamper-resistant receptacles shall be provided where replacements are made at receptacle outlets that are required to be tamper-resistant elsewhere in this Code. 406.13 Tamper-Resistant Receptacles in Guest Rooms and Guest Suites. All nonlocking-type, 125-volt, 15- and 20-ampere receptacles located in guest rooms and guest suites shall be listed tamper-resistant receptacles. ****************NOTICE************** 406.4(D)(4) (4) Arc-Fault Circuit-Interrupter Protection. Where a receptacle outlet is supplied by a branch circuit that requires arc-fault circuit interrupter protection as specified elsewhere in this Code, a replacement receptacle at this outlet shall be one of the following: (1) A listed outlet branch circuit type arc-fault circuit interrupter receptacle (2) A receptacle protected by a listed outlet branch circuit type arc-fault circuit interrupter type receptacle (3) A receptacle protected by a listed combination type arc-fault circuit interrupter type circuit breaker This requirement becomes effective January 1, 2014. 11. I have EMT coming from a trough to a disconnect. I cut my own hole in the trough and the disconnect has concentric knockouts. It is a 480 volt circuit and I pulled an equipment grounding conductor. Do I have to install a bonding bushing at the disconnect? (David Rains)

Maybe 250.97 Bonding for Over 250 Volts. For circuits of over 250 volts to ground, the electrical continuity of metal raceways and cables with metal sheaths that contain any conductor other than service conductors shall be ensured by one or more of the methods specified for services in 250.92(B), except for (B)(1). Exception: Where oversized, concentric, or eccentric knockouts are not encountered, or where a box or enclosure with concentric or eccentric knockouts is listed to provide a reliable bonding connection, the following methods shall be permitted: (1) Threadless couplings and connectors for cables with metal sheaths (2) Two locknuts, on rigid metal conduit or intermediate metal conduit, one inside and one outside of boxes and cabinets (3) Fittings with shoulders that seat firmly against the box or cabinet, such as electrical metallic tubing connectors, flexible metal conduit connectors, and cable connectors, with one locknut on the inside of boxes and cabinets (4) Listed fittings 517.19(D) Equipment Grounding and Bonding. Where a grounded electrical distribution system is used and metal feeder raceway or Type MC or MI cable that qualifies as an equipment grounding conductor in accordance with 250.118 is installed, grounding of enclosures and equipment, such as panelboards and switchboards, shall be ensured by one of the following bonding means at each termination or junction point of the metal raceway or Type MC or MI cable: (1) A grounding bushing and a continuous copper bonding jumper, sized in accordance with 250.122, with the bonding jumper connected to the junction enclosure or the ground bus of the panel (2) Connection of feeder raceways or Type MC or MI cable to threaded hubs or bosses on terminating enclosures (3) Other approved devices such as bonding-type locknuts or bushings 12. I was thinking perhaps we could use our code consistency team to come up with an SOP for PV inspections. When we came up with it there was only one type of system being installed residentially and now there are several. (Gerald Barnes) Guidelines for Residential PV Inspections

ectrical permit along with the building permit exceeding $30,000 will require a NC Licensed General contractor on the building permit. fall protection. multiple trade complexities and continuity critical follow through. The initial inspection will require the following: a) Plans to be onsite for inspector use. Plans shall include all wire sizes and types, all applicable voltages, amperages and volt-amperes in relation to maximum PV source and output currents, inverter output currents, disconnect locations and grounding details. b) Structural engineering report to be given to inspector on first inspection trip. c) All manufacturers installation requirements are required to be on project at inspection times. Generating Facility no larger than 10kw document or similar document will need to obtain a project Certificate of Completion available through the Mecklenburg County website or Documents and Inspections at (704) 336-3830 as inspectors have been instructed not to sign any outside vendor / customer documentation. ***ANY PITCHED ROOF INSPECTION REQUIRES FALL PROTECTION TRAINING AND GEAR. *** 13. I was turned down for not installing an isolated ground to an isolated grounding type receptacle. Was the inspector correct? (Matt King) Yes. 406.3(D)(1) (D) Isolated Ground Receptacles. Receptacles incorporating an isolated grounding conductor connection intended for the reduction of electrical noise (electromagnetic interference) as permitted in 250.146(D) shall be identified by an orange triangle located on the face of the receptacle. (1) Isolated Equipment Grounding Conductor Required. Receptacles so identified shall be used only with equipment grounding conductors that are isolated in accordance with 250.146(D). 14. The available fault current coming into the trough from Duke Power is 33K.The electrical contractor has installed a 3 phase 200amp meter box. Inside the meter box the label states that

the meter box is approved for up to 600 volts at 10K.Would this be a code violation or would this fall back onto the utility co.? The voltage is 120/208 3 phase and the load serving the unit is 145 amps. (Gary Mullis) It is a code violation and would have to be rated equal to or greater than the fault current coming from the utility. 230.66 Marking. Service equipment rated at 600 volts or less shall be marked to identify it as being suitable for use as service equipment. All service equipment shall be listed. Individual meter socket enclosures shall not be considered service equipment. 110.9 Interrupting Rating. Equipment intended to interrupt current at fault levels shall have an interrupting rating not less than the nominal circuit voltage and the current that is available at the line terminals of the equipment. Equipment intended to interrupt current at other than fault levels shall have an interrupting rating at nominal circuit voltage not less than the current that must be interrupted. 110.10 Circuit Impedance, Short-Circuit Current Ratings, and Other Characteristics. The overcurrent protective devices, the total impedance, the equipment short circuit current ratings, and other characteristics of the circuit to be protected shall be selected and coordinated to permit the circuit protective devices used to clear a fault to do so without extensive damage to the electrical equipment of the circuit. This fault shall be assumed to be either between two or more of the circuit conductors or between any circuit conductor and the equipment grounding conductor(s) permitted in 250.118. Listed equipment applied in accordance with their listing shall be considered to meet the requirements of this section. 15. Duke energy Talks (Joe Weathers) 16. CE classes (Joe Weathers) NEXT MEETING: Contractors Wednesday June 11, 2014 Inspectors Wednesday April 11, 2013