City of Dallas Drought Update. Dallas Water Utilities February 1, 2012

Similar documents
Dallas Water Utilities Drought Update and Impact. Dallas Water Utilities November 16, 2011

City of Dallas Water Utilities Drought Management Update. September 20, 2006

Water Utilities: Overview of Proposed FY11 Budget. August 23, 2010

Region C Water Planning Group Meeting. TRA Central Wastewater Treatment Plant April 25, 2005

ARTICLE DROUGHT CONTINGENCY AND WATER EMERGENCY RESPONSE PLAN

The Path to 2060: Dallas Water Plan Update Reuse Partnership with North Texas Municipal Water District

DALLAS WATER UTILITIES LONG RANGE PLANNING FOR SUSTAINABILITY

3. Analysis of Water Supply Currently Available to Region C

3. Analysis of Water Supply Currently Available to Region C

Drought Contingency Plan for Denton County Fresh Water Supply District 6

APPENDIX I WATER SUPPLY AVAILABLE TO REGION C

Public Hearing on. Region C Water Plan. May 25, 2010

APPENDIX I WATER SUPPLY AVAILABLE TO REGION C DRAFT

Water Conservation Program: Twice Weekly Watering

APPENDIX I WATER SUPPLY AVAILABLE TO REGION C

as it Affects North Texas and Water for Energy in North Texas

6.6 Drought and Emergency Response Stages

Water Conservation Plan

MODEL DROUGHT CONTINGENCY PLAN. Prepared by Upper Trinity Regional Water District for its Members and Customers

City of Rowlett. Water Management Plan

Texas Water Plan and Region C Water Plan. UTA Water Systems Design Class March 26, 2009

WATER TREATMENT PLANT TOUR

DROUGHT CONTINGENCY PLAN

Water Supply Corporation here by adopts the following regulations and restrictions on the delivery and consumption of water.

Region C Water Planning Group (RCWPG) Public Notice of Possible Amendments of the 2001 Region C Water Plan PUBLIC NOTICE

April 2014 Resolution No Adopted by BWA Board on 4/29/14 Print Date 4/30/14

APPENDIX M SELECTION OF KEY WATER QUALITY PARAMETERS AND BASELINE WATER QUALITY CONDITIONS

Region C Water Planning Group. 2 Population and Water Demand Projections. 2.1 Historical Perspective. 2.2 Population Projections

Honorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee

Water Supply in North Texas: Where Does (and Where Will) it Come From?

CONSERVATION PLAN April 2009

Region C Water Planning Group. 1 Description of Region C. 1.1 Economic Activity in Region C. 1.2 Water-Related Physical Features in Region C

WATER CONSERVATION AND DROUGHT CONTINGENCY AND WATER EMERGENCY RESPONSE PLAN FOR THE CITY OF ALLEN, TEXAS

7.1 Introduction. 7.2 Consistency with the Protection of Water Resources

APPENDIX W WATER SUPPLY STUDY FOR KAUFMAN COUNTY

APPENDIX B. LOWER COLORADO RIVER AUTHORITY DROUGHT CONTINGENCY PLAN RULES FOR WATER SALE CONTRACTS December 2013 TABLE OF CONTENTS

Drought Contingency and Emergency Management Plan

Public Notice of a Proposed Amendment of the 2001 Region C Water Plan

FORWARD. Questions regarding this water conservation plan should be addressed to the following:

DRAFT. TO: Stephanie Griffin, P.E. PROJECT: Region C Water Supply Plan Freese and Nichols, Inc.

DROUGHT CONTINGENCY PLAN FOR

MUNICIPAL WATER CONSERVATION PLAN FOR THE CITY OF CHANUTE JUNE 2010

City Council Work Session Handouts. July 21, I. Review and Discuss North Texas Municipal Water District Water Supply Plan and Projects

Frequently Asked Questions: Wholesale Water Rates and Water Supply Contract

Water Supply and Drought Update January 14, 2015

CITY OF MARION MUNICIPAL WATER DEPARTMENT WATER CONSERVATION PLAN

NTMWD WATER AND WASTEWATER PROJECTS, COST FORECASTS

NORTH TEXAS MUNICIPAL WATER DISTRICT WATER CONSERVATION AND DROUGHT CONTINGENCY AND WATER EMERGENCY RESPONSE PLAN MARCH 2008.

REGION C WATER PLANNING GROUP

A. The opportunity for the public to provide input into the preparation of the Plan was provided by District 1-A by means of:

MEMORANDUM TO: FROM: SUBJECT: DATE:

NTMWD ESSENTIAL SERVICES, PROJECTS

DROUGHT CONTINGENCY PLAN (Updated June 17, 2014)

SECTION G. East Central Special Utility District DROUGHT CONTINGENCY PLAN

11 Implementation and Comparison to Previous Regional Water Plan

NORTH TEXAS MUNICIPAL WATER DISTRICT EAST FORK RAW WATER SUPPLY PROJECT

NORTH TEXAS MUNICIPAL WATER DISTRICT

DROUGHT CONTINGENCY PLAN

ORDINANCE No

CHAPTER 10 Water Shortage Contingency Plan

DRAFT MEMORANDUM. Water Management Strategies for Tarrant Regional Water District

EL DORADO IRRIGATION DISTRICT DROUGHT PREPAREDNESS PLAN DROUGHT ACTION PLAN

DALLAS COUNTY PARK CITIES MUNICIPAL UTILITY DISTRICT DROUGHT CONTINGENCY PLAN ADOPTED: APRIL 9, 2019 PREPARED BY:

DROUGHT MANAGEMENT AND WATER CONSERVATION IN CHARLOTTESVILLE AND ALBEMARLE COUNTY

USER DROUGHT CONTINGENCY PLAN

DROUGHT CONTINGENCY PLAN

FOREWORD. Questions regarding this Model WREMP should be addressed to the following:

WATER CONSERVATION & DROUGHT CONTINGENCY PLAN. for WEST TRAVIS COUNTY PUBLIC UTILITY AGENCY FIRM WATER CONTRACT

The Drought of the Century to the Flood of the Century

The Path to 2060: Dallas Water Plan Update. The State s 16 Regional Planning areas are identified by the letters A to P. Dallas is in Region C.

Created in 1924 as a political subdivision of the State of Texas. Primary missions: water supply, flood control and recreation

City of Healdsburg 2010 Urban Water Management Plan Water Use Baseline and Water Use Targets. May 13, 2015 Public Workshop Meeting

DROUGHT CONTINGENCY PLAN SUMMARY

The Impact of Indirect Reuse on Water Supply Planning

Regional Service Through Unity Meeting our Region s Needs Today and Tomorrow BOIS D ARC RESERVOIR

Argyle Water Supply Corporation WATER CONSERVATION AND DROUGHT CONTINGENCY PLAN May 2007

Draft Environmental Impact Statement Lake Ralph Hall Regional Water Supply Reservoir Project Volume II

Water Conservation and Emergency Water Management Plan

Implementing EMS to Improve Operational Performance and Energy Management for Dallas Water Utilities. TACWA Meeting May 31, 2013

Water Conservation Plan Allen, Texas. Gail Donaldson Water Conservation Manager November 22, 2013

WATER CONSERVATION AND DROUGHT CONTINGENCY PLAN REVISED MAY 2014

Water Utilities: Overview and Recommended FY09 Budget. August 25, 2008

DRAFT MEMORANDUM TO FILE

UWMP Standardized Tables. Dominguez District Urban Water Management Plan Appendix H

Water Conservation Awareness and Education Programs May 12, 2016

ARTICLE 10 WATER SHORTAGE CONTINGENCY PLAN 90

UWMP Standardized Tables. King City District Urban Water Management Plan Appendix H

UWMP Standardized Tables. Livermore District Urban Water Management Plan Appendix H

UWMP Standardized Tables. City of Hawthorne District Urban Water Management Plan Appendix H

Region C Water Planning Group Meeting. TRA Central Wastewater Treatment Plant August 18, 2003

Region C Water Planning Group. April 9, 2018

Next Meeting: Monday, April 28, 2014 at 1:00 p.m., subject to change. Please monitor for updates.

Model Drought Contingency Plans

WATER SHORTAGE RESPONSE PLAN. Tacoma Water

Created in 1924 as a political subdivision of the State of Texas. Primary missions: water supply, flood control and recreation

UWMP Standardized Tables. Salinas District Urban Water Management Plan Appendix H

Model Drought Management Plan and Response Ordinance

UWMP Standardized Tables. Palos Verdes District Urban Water Management Plan Appendix H

Drought Contingency & Emergency Water Management Plan

ORDINANCE NO NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GARLAND, TEXAS: SECTION 1

Transcription:

City of Dallas Drought Update Dallas Water Utilities February 1, 2012

Purpose This briefing provides an overview of the ongoing drought weather conditions and its impact on Dallas water supply and other area water providers, and Recommends that Council extend drought Stage 1 by 120 days to June 8, 2012 White Rock Lake 1950 s 2

Outline Background Current Drought Conditions Dallas 2012 Water System Treatment Capacity Restrictions Interim Raw Water Sales Actions and Next Steps Appendix Trinity River 1994 3

Background June 2010 - Dallas Drought Contingency Plan adopted by the Council and submitted to the State August 2011 - Dallas called for customers to voluntary restrict outside watering December 12, 2011 - Dallas entered Stage 1 of its Drought Contingency Plan 4

Current Drought Conditions In August 2011 Briefing, lakes were 82 percent full (18 percent depleted) In November 2011 Briefing, lakes were 75 percent full (25 percent depleted) December 2011 and Jan 2012 rains have helped Lakes are currently 85 percent full (15 percent depleted) Lakes were 91 percent full on 2/1/11 Dallas will also face treatment plant related restrictions this summer due to ongoing infrastructure improvements Lake Tawakoni 2006 5

Current Drought Conditions - Drought Monitor January 24, 2012 Jan 18, 2011 April 5, 2011 June 28, 2011 Sept 13, 2011 Nov 22, 2011 6 Source: National Drought Mitigation Center 6

Current Drought Conditions - Status of Dallas Water Supply Reservoirs WISE COOKE DENTON Down 0 ft. 0% Depleted RAY ROBERTS LAKE LEWISVILLE LAKE GRAPEVINE LAKE Down 2.7 ft. 12% Depleted ELM FORK WTP Down 2.4 ft. 8% Depleted DALLAS BACHMAN WTP GRAYSON COLLIN NTMWD / IRVING PIPELINE Down 2.6 ft. 12% Depleted LAKE RAY HUBBARD ROCKWALL FORNEY PUMP STATION EASTSIDE WTP LAKE TAWAKONI Down 5.3 ft. 21% Depleted HUNT TAWAKONI BALANCING RESERVOIR FANNIN HUNT IRON BRIDGE PUMP STATION LAKE CHAPMAN HOPKINS RAINS INTAKE & PUMP STATION DELTA HOPKINS LAKE FORK RESERVOIR Down 6.3 ft. 24% Depleted TARRANT JOHNSON JOE POOL LAKE DALLAS ELLIS CEDAR CREEK RESERVOIR WOOD SMITH PROPOSED DWU / TRWD INTEGRATED PIPELINE KAUFMAN VAN ZANDT HENDERSON LAKE PALESTINE LEGEND DWU Water Sources Future Water Sources Other Reservoirs Existing Water Treatment Plant Future Water Treatment Plant Existing Facilities Future Facilities Existing Pipeline Future Pipeline INTAKE & PUMP STATION (FUTURE) Data as of 1/26/12 7

Dallas 2012 Water System Treatment Capacity Restrictions Ongoing construction at the East Side Water Treatment Plant will provide water quality improvements, rehabilitation and increased plant capacity for future demand This construction will result in a temporary water treatment capacity restriction of 680 MGD for Dallas treated water system during the Spring/Summer of 2012 Service restrictions to customers are anticipated as a result 8

Water Supply Benchmarks 75% capacity remaining after 18 months and 50% remaining after 3 ½ years 9

Interim Raw Water Sales

Interim Raw Water Sales - State Rules/Laws Surface water is owned and permitted by the State of Texas Texas Water Code 11.036, allows a water rights holder to supply water under contract terms that are just and reasonable and without discrimination, and that if the contract sets forth explicit expiration provisions, no continuation of the service obligation will be implied House Bill 2694, passed in 2011, allows the State to suspend or adjust water rights during drought or emergency water shortage In addition, Texas Water Code, 11.139 allows the commission to grant an emergency permit, order, or amendment to an existing permit, certified filing, or certificate of adjudication for a period of 120 days May be renewed for an additional 60 days For conditions which present an imminent threat to the public health and safety 11

Interim Raw Water Sales - Impacts Water sales from the Eastern system up to approximately 70 MGD would not impact Dallas drought planning Water sales from the Western system may accelerate Dallas drought plan needs by 9 months System Eastern (Lakes, Ray Hubbard, Tawakoni and Fork) Western (Lakes, Lewisville, Ray Roberts, Grapevine and Elm Fork Run of the River) Yield 335.5 MGD 177.7 MGD Connected Yield 264.8 MGD 177.7 MGD Available for Interim Sale 70.7 MGD 0.0 MGD 12

Interim Raw Water Sales Luminant - Received Luminant has requested additional water from Lake Fork for a two year term expiring December 31, 2013 No impact to Dallas drought plan Estimated revenue at $1.2M per year Contract agenda item to be scheduled for February 22, 2012 13

Interim Raw Water Sales Anticipated Requests Anticipated Requests North Texas Municipal Water District (NTMWD) up to 60 MGD City of Irving TBD Upper Trinity Regional Water District (UTRWD) TBD Water sales, assuming drought conditions continue as forecasted, may require Dallas to implement stronger drought measures, i.e., Stages 2-4 Terms and conditions will include length of contract, volume of water, conditions of service, pricing and other considerations 14

Interim Raw Water Sales NTMWD - Pending NTMWD is not currently a water customer of Dallas NTMWD water supply sources Lavon 36% depleted Chapman 57% depleted Texoma 0% available (due to Zebra mussels) Potential raw water purchase amounts from Dallas - 27 MGD to 60 MGD Contract requested by NTMWD to be completed in the Spring 2012 timeframe A request from NTMWD of up to 60 MGD from Dallas Eastern system would have no impact to Dallas drought plan 15

Interim Raw Water Sales City of Irving - Pending Irving has been a Dallas water customer since 1955 Irving purchases approximately 7 MGD through a wholesale treated water contract Irving has a treatment services contract with Dallas to treat 40 MGD of their Lake Chapman water Lake Chapman is 57% depleted Depending on future rain and weather conditions, Irving s water supply in Chapman may be at risk At Irving s request, Dallas staff has met to discuss possible water sales to Irving At this time, a formal water sale request has not been made to Dallas Request would be for Western system water May accelerate drought plan scheduling by 9 months depending upon amount of request 16

Interim Raw Water Sales Upper Trinity River Water District (UTRWD) - Pending UTRWD has been a Dallas water customer since 1992 UTRWD takes water from Lake Chapman which is 57% depleted Depending on future rain and weather conditions, UTRWD s water supply in Chapman may be at risk (14.3 MGD Chapman Water and 8.6 MGD Chapman Reuse) UTRWD s Harpool Water Treatment Plant s sole source of water is Lake Chapman UTRWD also purchases a small amount of raw water from Dallas (approx. 4MGD) May ask Dallas for a yet to be determined amount Request would be for Western system water May accelerate drought plan scheduling by 9 months depending upon amount of request 17

Actions and Next Steps

Actions and Next Steps City Manager recommends that the Council extend the drought restrictions 120 days From Feb 10, 2012 to June 8, 2012 Item is scheduled on the Feb 8, 2012 Council Agenda Luminant contract recommendation for approval on February 22, 2012 Council Agenda No impact to Dallas drought plan We will continue to monitor the drought situation and provide additional updates to the Council as needed 19

Appendix

Drought Triggers and Action Measures (City of Dallas Drought Contingency Plan adopted June 9, 2010) Stage 1 Stage 2 Stage 3 Stage 4 35% Depleted 45% Depleted 55% Depleted 70% Depleted Mandatory Mandatory Mandatory Mandatory Target 5% reduction in total Gallons Per Capita per Day (GPCD) Restrict operation of ornamental fountains and ponds to initial filling and to support aquatic life Encourage reduction in draining and refilling of swimming pools Prohibit recreation water use of faucets hoses and hydrants which use water in such a manner as to allow run-off Restrict washing of vehicles to hand held bucket (does not affect commercial car washes) Mandatory maximum 2 day a week landscape irrigation Target 15% reduction in total GPCD Prohibit hosing off paved areas, buildings, windows or other surfaces Restrict op of ornamental fountains/ponds to initial filling or support aquatic life Encourage further reduction in draining and refilling of swimming pools Prohibit recreation water use of faucets hoses and hydrants which use water to allow run-off Restrict washing of vehicles to hand held bucket (but not commercial car washes) Mandatory maximum 1 day a week landscape irrigation Foundations may be watered any day during allowed watering hours with soaker or hand held hoses Target 20% reduction in total GPCD No approval for new, additional, expanded, or increased-in-size water service connections, meters, service lines, pipeline extensions, mains, or water service facilities 10% rate increase for high water demand users (greater than 10,000 gallons per month) Prohibit the filling/refilling of swimming pools, wading pools and Jacuzzi pools, Existing pools may add water for proper operation; no permitting of new pools Prohibit washing of vehicles (does not affect commercial car washes between 6:00 a.m. and 10:00 a.m. or 6:00 p.m. to 10:00 p.m.) Mandatory maximum 1 day a week landscape irrigation with hand held hoses and hand held buckets only Foundations may be watered for a 2 hour period (off-peak) with soaker hose or hand held hose. Target 25% reduction in total GPCD Prohibit washing of vehicles Prohibit landscape irrigation Foundations may be watered for a 2 hour period (off-peak) with soaker hose or hand held hose. 21

Comparison of Drought and Conservation Measures Conservation measures are used to achieve more efficient use of water resources Conservation examples include: Water Wise landscaping (Xeriscape) Time of Day Watering Low Flow Showerheads Repairing leaking faucets Reducing the frequency of watering lawns Drought measures are restrictions used to ensure that water is available to meet public health, welfare, and safety needs Drought examples include Restricting lawn watering Prohibiting permitting or filling of swimming pools Prohibiting operation of ornamental fountains Prohibiting recreational water use 22

Process to Implement Contingency and Emergency Measures Utility Director responsible for ongoing monitoring of water system Director is responsible for recommending implementation of contingency and emergency procedures to City Manager City Manager may enact the measures for up to 60 days City Council may extend the measures beyond original 60 days for additional time periods, not to exceed 120 days each To be effective, measures must be published in a local newspaper within 24 hours of announcement 23

Water Use and 2012 Water System Restriction Water Consumption FY10 and FY11 750 650 MGD 550 450 350 250 10/1 10/15 10/29 11/12 11/26 12/10 12/24 1/7 1/21 2/4 2/18 3/3 3/17 3/31 4/14 4/28 5/12 5/26 6/9 6/23 7/7 7/21 8/4 8/18 9/1 9/15 9/29 FY10 FY11 85% Available Treatment Capacity Treatment Capacity During Construction Note: Graph shows that water restrictions would be needed in FY10 and FY11. FY10 was a relatively wet year; FY11 was hot and dry. 24

Major North Texas Water Providers 25

Drought Conditions for Other Area Water Providers and Irving Other area water providers are experiencing restrictions due to lack of rainfall, reservoir location, and other drought related factors Stage Dallas North Texas Municipal Water District (NTMWD) Tarrant Regional Water District (TRWD) Upper Trinity Regional Water District (UTRWD) City of Irving Stage 1 December 12, 2011 April 19, 2011 August 29, 2011 July 13, 2011 May 15, 2011 Stage 2 August 11, 2011 August 11, 2011 Stage 3 November 1, 2011 January 1, 2012 Stage 4 26

Drought Conditions for Other Area Water Providers and Irving Other area water providers are experiencing restrictions due to lack of rainfall, reservoir location, and other drought related factors Stage Dallas North Texas Municipal Water District (NTMWD) Tarrant Regional Water District (TRWD) Upper Trinity Regional Water District (UTRWD) City of Irving Date Response Date Response Date Response Date Response Date Response 1 12/12/11 Maximum twice per week watering 4/19/11 Voluntary water use reductions 8/29/11 Maximum twice per week watering 7/13/11 Voluntary water use reductions 5/15/11 Voluntary water use reductions 2 8/11/11 Maximum twice per week watering 8/11/11 Maximum twice per week watering 3 11/1/11 Maximum Once per every two weeks watering 1/1/12 Maximum once per week watering 4 27

Water Supply Depletion (as of 1/26/12) Dallas Combined Down 15% North Texas Municipal Water District Lavon Down 36% Chapman Down 57% Texoma 0% available Tarrant Regional Water District Combined Down 25% 28