Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation

Similar documents
Fiber Reinforced Cured-in-Place Rehabilitation Under an Interstate

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore

Rehabilitation of Forced Sewer Mains with CIPP

Inland Pipe Rehabilitation. August 17 OAWWA Canton, OH

SPECIFICATIONS FOR PREMIER-PIPE USA CURED-IN-PLACE TECH LINER

Pipe User Group. Tuesday March 14, Walnut Creek, CA. Matt Wassam

Infrastructure Solutions Pressure Pipe Overview

CIPP Cured-in-Place Pipeline CIPP. cured-in-place pipe. trenchless pipe rehabilitation

Michelle D. Beason, PE National Plant Services, Inc.

Structural Lining of Water Mains. City of St. John s, Water and Wastewater Division

SPECIAL SPECIFICATION 4631 Cured-In-Place Pipe (CIPP)

TECHNICAL SPECIFICATIONS FIBERGLASS/ULTRAVIOLET LIGHT CURED-IN-PLACE PIPE (CIPP) FOR MAINLINE RENEWAL

SPECIAL SPECIFICATION 4411 Cured-In-Place Pipe (CIPP) (Drainage Structures)

The point of this briefing.

SECTION IRRIGATION PIPELINE LINING (CURED-IN-PLACE PIPE)

Special Specification SS1- INTERNAL CIPP POINT REPAIR OF PIPELINES. A. General. 1. Scope

International Aramoon Corp. Pipe Inspection and Rehabilitation By: Faiz Al-Elweet. SAWEA Al-Khobar KSA February 24, 2010

SPECIFICATIONS. Cured-in-Place Pipe Liner (CIPP Liner). Shall comply with Subsection

CIPMH (Cured-in-Place Manhole) Lining System

Table 1 Description of Work Pipe Size (mm) 1 Sunshine Way A/C No. A/C Yes

Lateral Thinking The Key To Meeting Sewer Infiltration Reduction Targets & Lowering Operating Costs

Fold & Form PVC Liners Sewer & Culvert Rehabilitation

PIPE REHABILITATION. Comply with Division 1 - General Provisions and Covenants, as well as the following:

Lessons Learned from a 60 CIPP Storm Sewer Liner Installation. Robert Stolt, PE Christopher Beranek, PE

r.tec GmbH The technology provider of the Rabmer Group

Product Information. Polyester Felt Cured-In-Place Pipe (CIPP) Lining Tube

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Installation Practice InnerSeal

INLINER LAY_InLiner Brochure_FA_ indd 1

San Antonio Water System Standard Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

TECHNICAL SPECIFICATION FOR CURED-IN-PLACE MANHOLE REHABILITATION LINER SYSTEM

Specifying Trenchless Sewer Rehabilitation Projects. Presented by: Todd Stelmacher Visu-Sewer, Inc.

San Antonio Water System Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

CIPP Lateral Renewal Connection System

ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

Infrastructure Point Repair System Technical Specifications

INTERFIT LATERAL SEALING SYSTEM INSTALLATION GUIDELINE SPECIFICATION

Method One: Liner/Bladder Assembly-Inversion Method.

SECTION 809 CURED-IN-PLACE PIPE (CIPP) LATERALS

EVALUATION SUBJECT: HAMMERHEAD CURED-IN- PLACE PIPE (CIPP) LINING SYSTEM DIVISION: PLUMBING SECTION: SANITARY WASTE AND VENT PIPING

SPECIAL SPECIFICATION 5256 Cured-In-Place Pipe (Sanitary Sewer)

STIFPIPE : INTRODUCING A NEW HONEYCOMB-FRP PIPE

CIPP REFERENCE SPECIFICATION

I&I Mitigation: Rehabilitation of Sewer Laterals and Sealing the Collection System

STANDARD SPECIFICATIONS FOR CONSTRUCTING SANITARY SEWER FACILITIES DIVISION III - CONSTRUCTION SPECIFICATIONS

ITEM NO SLIPLINING SANITARY SEWERS

Trenchless Technology

Technical Information: Standard Inverted and Pull-In CIPP

Project Specifications

Pipe Bursting Services. pipe bursting. services

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

ADDENDUM No. 2. City of Joliet, 2017 Spring Creek Interceptor Sewer Lining at CN Railyard

Overview of Lateral and Main/Lateral Connection Lining and Sealing Technologies

Overview of Lateral and Main/Lateral Connection Lining and Sealing Technologies

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction

Protective Coatings for Underground Utility Concrete Structures. By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc.

Assessing Salem s Oldest Transmission Main for Seismic Resiliency

CITY OF TAMPA ADDENDUM NO. 1. DATE: September 15, Contract 11-C-00001; Wastewater Sewer Rehabilitation by Cured-in-Place Pipe (C.I.P.P.

SECTION 808 CURED-IN-PLACE-PIPE (CIPP)

SPECIAL SPECIFICATIONS UV CURED IN-PLACE SPIRAL WOUND FIBERGLASSS PIPE LINING

17/03/2017 CONTENTS. Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation. Introduction CONTENTS. Introduction / Cont.

GENERAL SPECIFICATION FOR THE REHABILITATION OF SEWERS

Service Lateral Rehabilitation

CEDAR RAPIDS METROPOLITAN AREA STANDARD SPECIFICATIONS FOR PUBLIC IMPROVEMENTS May 2014 SECTION SEWER LINERS

EVALUATION SUBJECT: PERMA-LATERAL PULLED- IN-PLACE CURED-IN-PLACE PIPE LINING SYSTEM

Press Release. Rehabilitation of oil pipelines with flexible high pressure pipes

CONSTRUCTION PRODUCT MARKETING

Cured-In-Place-Pipe (CIPP) LATERAL SEALS

The Rehabilitation of Existing Building Drains and Building Sewers by the

KEEP IT FLOWING BYPASS STATION INSTALLATION ON A 35- YEAR OLD FORCE MAIN

THE COSTS FOR ACCESSING THE SEWER SHALL BE INCLUDED IN THE VARIOUS UNIT PRICES BID. THE UNIT COSTS SHALL INCLUDE ANY AND ALL ACCESS TO THE SEWER.

CITY OF ODESSA SPECIAL SPECIFICATIONS ITEM 1000 GLASS-FIBER REINFORCED POLYESTER (FRP) REHAB/REPLACEMENT MANHOLE

Process Specification. Structural Rehabilitation & Corrosion Protection for Circular Structures in Wastewater Collection and Potable Water Systems

FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS

ENGINEERING DESIGN GUIDE FOR REHABILITATION WITH CURED-IN-PLACE PIPE Second Edition

Service Lateral Rehabilitation Using Cured-In-Place-Pipe (CIPP)

Repair of Metal Culverts Using ECC Bendable Concrete. Celik Ozyildirim, Ph.D., PE., Virginia Transportation Research Council

Styrene Free Structural Liner for Sewers and Culverts

Contractor Cases for Using Temperature Monitoring All Along the Pipeline in CIPP Mid-Sized Pipe Installations. Gary Rapp VP, Operations

I&I Mitigation: Reconstruction of Sewer Laterals and Sealing the Connections to the Main Rick Gage

LATEST ADVANCES IN PIPELINE RENOVATION WITH FIBER REINFORCED POLYMER (FRP)

STANDARD SPECIFICATIONS SECTION SEWER MAINS AND LATERAL REHABILITATION BY LINING

A COMPREHENSIVE UNDERSTANDING

CONSTRUCTION PRODUCT MARKETING

TECHNIQUES, MATERIALS AND DESIGN CONSIDERATIONS: REHABILITATION & STRENGTHENING OF WATER AND WASTEWATER PIPELINES. Solutions & Case Studies

OTEC 2017 Spray Applied Pipe Liner Supplemental Specifications 833 Calculations for the Resin Based Liner Presented by Peter Blais, PE

THE SPECIALIST FOR NO DIG REHABILITATION

C) Poly-Triplex Liner System-4400: Custom fabricated liner composed of 20- ounce non-porous inner membrane with two (2) 12-ounce layers of structural

With over 40 years experience, SDI-unistride

HIGH CHEMICAL RESISTANCE LINER (EPOXY RESIN FORMAPOX 301)

SECTION WASTEWATER FORCE MAINS

Rehabilitation of the Coral Gables Wastewater Collection System

Rowlett Cottonwood Transfer Sewer: 60" RCP Sanitary Sewer Rehabilitation Project. TACWA Meeting

Numerical analysis of stresses for cured-in-place-pipe linings

Condition Assessment and Rehabilitation/ Renewal of Wastewater Rising Mains

PERFORMANCE SPECIFICATION GUIDELINE

Structural Testing of Geopolymer Pipe & Culvert Mortar Lining System

GENERAL INFORMATION AND REQUIREMENTS

GAS UTILITY TECHNOLOGY UPDATE

Transcription:

Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation Presented by Mike York, Insituform Technologies, Inc.

Trenchless v. Dig and Replace

What is CIPP? Developed in 1971, cured-in-place pipe (CIPP) is a trenchless technology developed by Insituform The end product is a jointless, seamless, pipe-within a pipe that protects against spills, breaks and pipeline leakage Insituform has installed over 90 million feet of CIPP and has been the industry leader for over 35 years

Benefits Eliminate infiltration and exfiltration Restore structural integrity Eliminate joints, root intrusion and leaks Prevent sinkholes and surface settlement Suitable for irregularly shaped pipes and changes in pipe diameter Increase flow capacity Protect pipes from corrosion Reduce maintenance Minimal traffic disruption Fewer social costs to open-cut

Materials Felt material: Custom made to hold resin in place until cure has been achieved Ensures proper pipe thickness Exterior coating allows for serial vacuum impregnation and prevents resin loss during installation and cure. Thermosetting resin retains its shape with no residual memory. Epoxy Vinyl ester Polyester

Water-Inversion Water-Cure Tubes are inverted using water pressure Water is heated to cure the inverted tube Final product is a brand new, jointless, pipewithin-a-pipe Tried and true method used for over 35 years

Air-Inversion Steam-Cure High quality end product Short installation cycle Specialized installation equipment minimize footprint Specially engineered resin and coatings used for AISC Diameters 6 to 96 inches 15,000 separate AISC installations in 2008 alone almost 3.5 million feet Uses 95% to 98% less water 50% reduction in energy usage Virtually eliminates discharge of process water into sewers No grade limitations Shorter cool-down allows lateral reinstatement to take place sooner

Insituform Tube

CIPP Installation Thermosetting resin is injected into a felt tube The tube is inserted into an existing host pipeline by either pull-in or inversion (water/air) The tube is inflated to the size of the host pipe The CIPP tube is cured using hot water or steam Ends are cut and the final product is a fully-functional pipewithin-a-pipe

Installation Animation

CIPP Technical Envelope Diameter Range 6 to 96 inches ph Range.5 to 10.5 Effluent Temperature Up to 140 Fully Deteriorated Pipe Condition Yes Partially Deteriorated Pipe Condition Yes Bends Yes Offset Joints Yes Diameter Changes Yes, without manhole access Thickness Changes Yes, without manhole access Typical Shot Length 200 ft. to 1,000 ft. Host Pipe Shape All Shapes Host Pipe Material All Materials

Mokapu Case Study Deteriorated with a chance of collapse, the pipe runs along Kalaheo Avenue and Mokapu Road in the Aikahi Loop area. A 3400-foot section of reinforced concrete pipe was rehabilitated as part of Honolulu s ongoing capital improvement program. As groundwater infiltration and a high water table around the job site made controlling water during any open cut work extremely challenging, cured-in-place pipe (CIPP) was chose as the best option.

Project Setup

Project Setup

Special project characteristics Bypass pumps were operated 24 hours/day Wooded boxes were constructed and placed over 4 trash pumps to reduce the operating noise levels. The boxes were constructed of ¼ plywood and had cut-outs to facilitate hose connections and fueling requirements. Similar methodology was used on a project in Maui, which received no any noise complaints.

Mokapu Case Study

Innovations in CIPP Pull-in installation iplus Infusion Fiber-reinforced CIPP iplus Composite CIPP for potable water and pressure pipes InsituMain

Pull-in Steam-Cure Small installation footprint minimizes disruption Boiler truck can be located 250 ft from MH Ideal for small backyard easements Minimal traffic disruption Reduced equipment on street 700+ ft installations Shorter installation time Shorter sewer outage

Tube Construction Protects tube during installation Allows for better resin impregnation Minimizes resin washout Reduces occurrence of resin slugs in lateral

Pull-in Installation Tubes wet-out using specialized controlled resin impregnation system Resin-saturated tube is pulled into damaged pipe Air is used to inflate the tube and steam is used to cure the resin Service laterals are restored internally

Reduced Equipment Requirements Smallest jobsite footprint of any CIPP process Portable equipment Ideal for off-road installations Minimal traffic disruption Reduces stress on tube Shot lengths up to 700 feet Meets or exceeds the physical properties set forth in ASTM F1743

Technical Envelope Diameter Range 6 12 in. ph Range.5 10.5 Effluent Temperature Up to 140 F Fully Deteriorated Yes Partially Deteriorated Yes Bends No Offset Joints Yes Shot Length Up to 700 ft Host Pipe Material All, except truss

iplus Composite High-strength, fiber-reinforced composite CIPP for rehabilitation of medium- to large-diameter pipes. Fiber reinforcement provides maximum stiffness which results in thinner tube walls Carbon Glass Composite sandwich technology

iplus Composite

iplus Composite sewn-seam coating (PP) PVC

iplus Composite Benefits Design flexibility thickness is no longer the only variable High strength and modulus thinner walls Larger finished pipe inside diameter Better flow capacity Less weight to transport Fewer on-site wet outs Easier to handle and install Expedites jobsite activities Reduces project risk

Technical Envelope Diameter Range 24 to 96 inches ph Range.5 to 10.5 Pipe Condition Fully Deteriorated Pipe Condition Partially Deteriorated Bends Offset Joints Host Pipe Shape Host Pipe Material Yes Yes Yes Yes All Shapes All Materials

Completed iplus Composite 30-inch iplus Composite installation at a service location. Service connection opened using diamond or carbide cutter.

CIPP for Pressurized Lines AWWA Class III or Class IV rating Can be a structural solution Corrosion-resistant Small jobsite footprint Typically reinforced with materials such as fiberglass

What is Cured-In-Place Pipe? Developed in 1971 by Insituform, curedin-place pipe (CIPP) is a trenchless technology Initially used in sewers Modified properties made it suitable for the drinking water market End product is a jointless, pipe-within-apipe that protects against spills, breaks and pipe leakage Over 25,000 miles of CIPP have been installed in the last 38 years by CIPP contractors

Product Development The InsituMain system Recently-introduced CIPP product for pressure pipelines Utilizes proven CIPP technology Extension of existing pressure pipe lining products available since 1995

InsituMain Product Characteristics Designed as fully structural, independent of host pipe Jointless, continuous pipe lining Tight fit maximizes flow capacity Materials inhibit further corrosion or internal buildup Bond to host pipe eliminates need for specialty fittings Certified to ANSI/NSF Standard 61 Manufactured and installed under ISO:9000 certified quality management system

InsituMain Technical Envelope Diameter Range Effluent Temperature Internal Pressure Capability 6 to 36 inches Up to 120 F 150 psi Bends Up to 22.5 Host Pipe Material Mechanical Properties All Materials Exceeds ASTM F1216 and ASTM F1743

InsituMain Applications The system is suitable for the following applications: Distribution and transmission mains Cooling water lines Fire water mains Industrial pressure applications Sewage force mains

InsituMain Composite Structure Epoxy/fiberglass structure Provides high tensile strength Number of layers vary depending on diameter and internal pressure Epoxy/polyester felt structure Provides for external load capacity Layer thickness can be varied depending on loading conditions PE coating Water contact surface Coating also provides water barrier for installation processes

InsituMain Design Internal pressure standalone design of 150 psi Hydrostatic burst tested up to 1300 psi Custom designs possible External loading design accounts for: Soil Groundwater loads Traffic Other live loads

InsituMain Manufacturing Custom manufactured glass reinforced tube Tube impregnated with epoxy resin regional facility or near jobsite Typically transported to job site in refrigerated trucks

Installation Process Bypass and Pipeline Access Bypass is set up preinstallation for potable water pipelines and for non-potable pipelines as needed Disinfection per AWWA/owner standards ensures continuous supply of safe drinking water Pits are dug to access lines

Pre-Installation Cleaning Pipeline is cleaned using drag scrapers, high pressure water jetting, pigs or other similar equipment, as needed

Plugging of Services Pipeline is inspected by CCTV before lining Any service connections are temporarily plugged using CCTV and robotics Plugs prevent resin migration into the service connection

InsituMain Installation InsituMain is installed utilizing the inversion or pull-in process Liner is formed under pressure utilizing hot water or air/steam Lengths of 500 ft to 750 ft typical Longer lengths possible depending on site conditions Hydrostatic pressure testing follows lining, as required ASTM F1216 or F1743

Service Connection Reinstatement Using a robotic cutting device and CCTV, operator enters the lined pipe and cuts out each service connection Process allows services to be abandoned and/or replaced externally, as required

Restoring Service Lined pipe disinfected per AWWA/owner requirements prior to reconnecting to system Standard fittings (MJ, etc.) are installed to reconnect the lined pipe section with existing system

Future Connections Typical maintenance equipment can be used on InsituMain Any time after lining, the Owner can add fittings (valves, tees, ARV s, repair spool pieces, etc.) with standard equipment Capability to perform hot taps using standard off-the-shelf equipment Eliminates the need for specialty fittings

Potable Water Case Study Water main renewal 600 linear feet 8-inch diameter 80-year-old steel host pipe Depth of pipe: 15 feet deep Three installations

Non-Potable Case Study Sewage Treatment Plant 6-inch diameter Cement-mortar lined DIP Three pipes connecting two main clarifiers 90 psi operating pressure Deteriorating due to wear and abrasion

InsituMain Product Benefits Utilizes proven CIPP technology Provides a fully structural, independent pipe lining system Handles both internal and external load requirements Small footprint and excavations minimize social costs Eliminates the need for specialized fittings

Questions? Thank you. Mike York myork@insituform.com 602-300-8160