Singapore Safety Day. Keller civil works team for a large petrochemical project, Malaysia

Similar documents
FOUNDATION & SHORING. Whatever it takes... We build your vision! WORLDWIDE EXPANSION

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors

Soil Services SCS Ferretti International Soil Services Soil Services Industrial Construction Infrastructures Real Estate Soil Services Soil Services

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

SECANT PILE. Introduction:

Civil Engineering Construction I (CBE5031)

Construction Technology B (CON4313)

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN

KIEWIT FOUNDATIONS CO.

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP

GEO ENGINEERING COMPANY PRIVATE LIMITED FOR STRONG FOUNDATIONS AND STABLE STRUCTURES

KIEWIT FOUNDATIONS GROUP

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

Grouting Bilfinger Spezialtiefbau GmbH

1. Introduction Selection of Pile Type Soil Report / Boreholes Obstructions Design and Installation of Piling Mat 3

VIBRO REPLACEMENT COLUMNS FOR SHIPYARD INFRASTRUCTURE AT PIPAVAV, GUJARAT, INDIA

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

[Kouravand Bardpareh* et al., 5(6): July, 2016] ISSN: IC Value: 3.00 Impact Factor: 4.116

Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road Section between Scenic Hill and Hong Kong Boundary Crossing Facilities

Geotechnical and civil engineering contractors

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

Overcoming geotechnical challenges in rail and metro projects using ground improvement

DBM Contractors, Inc. Donald B. Murphy Contractors, Inc. 60 Years of Innovation and Customer Satisfaction

Topic: Site Formation

SHAFT CONSTRUCTION SECANT PILE

DIGEST. Issue 6 : July December In this Issue:

Company Profile 1300 SHOTCRETE

Ground Freezing for Tunnel, Shafts, and Adits

Diaphragm wall Construction

Misan University - College of Engineering Civil Engineering Department

Ground Modification Applications for Bio-Fuel Plants Raymond J. Franz, P.E. Roselle, IL

Ground Engineering. Headquaters. Main Offices. South Asia VSL Singapore Pte Ltd. Tel: Fax:

Earth Retaining System

Aveng Ground Engineering Profile

the ground improvement specialist Design Construct Perform

Geotechnical Engineering

Ching Guan Kee ABSTRACT

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

BAUER. Diaphragm and Cut-off Walls

The Aizhai Suspension Bridge is

Microtunneling Drive for Mixed Layers in Singapore / Japan

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad CIVIL ENGINEERING

Earth Retention Systems For Transportation Projects

GEOTECH YEAR Development in Geotechnical Engineering. Practical installation of stanchions for top-down construction in Bangkok subsoil

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

The HKIE Structural Examination Written Examination

Soil Mechanics Lateral Earth Pressures page Lateral Earth Pressures in case of inclined ground surface or friction at wall-ground interface

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

COMPANY PROFILE hssg.com

Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization

Design and performance of a 15m deep excavation for a wagon tippler

Modules for Graduate Certificate in Geotechnical Engineering

Foundation Works for a Sewage Treatment Plant using Ground Improvement Methods in Malaysia Y.W. Yee, C.G. Chua and

IGC. 50 th INDIAN GEOTECHNICAL CONFERENCE CONSTRUCTION PRACTICES OF DEEP BASEMENTS ANIL JOSEPH 1, A MURALIKRISHNA 2 ABSTRACT

FINITE ELEMENT ANALYSIS OF DEEP BASEMENT CONSTRUCTION OF BANK OF THAILAND ALONG CHAO PHRAYA RIVER CLOSED TO HISTORICAL PALACES

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

Basement Construction in Ho Chi Minh Pitfalls and Collected Stories

Large-diameter bored piles and Large-hole drillings Applications

Tunnel. Immersed Tunnels

CE 6012 Ground Improvement Techniques Question Bank

Excavation and Retaining Wall Solutions in the Alves Redol Car Park

Natalia Maca. TITAN POLSKA Sp. z o.o Kraków, Miłkowskiego 3/801 Tel Fax

The construction of deep excavation ditch in weak soil in St. Petersburg

WESTPRO PORTUS Use of RD Piles for Marine Construction

KIEWIT FOUNDATIONS GROUP

AMERDRAIN. Prefabricated Vertical Soil Drainage Systems ICK. Soil drainage method for accelerating settlement through vertical drainage

RETAINING WALL SYSTEMS

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Expert Solution in BUILD ON US GEOTECHNICAL AND CIVIL ENGINEERING CONTRACTORS

MODERN GEOTECHNICAL PRACTICES

Construction of a Semi-Buried Building A Super-sized Shopping Mall : The Festival Walk

Development Island Vehicle Access

Geo24h. Buiding Service

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know?

Overview. O-Pile Attributes

SCREW PILES INFORMATION SHEET

Construction of Access Shafts for Tunnels and Deep Pipelines in Urban New Zealand

Slope Stabilisation and the Beauty Of Shotcrete AN OVERVIEW

Geotechnical Investigation Reports and Foundation Recommendations -Present status in India -Examples

EFFECT OF DEEP EXCAVATION SUPPORTED BY CONCRETE SOLIDER PILE WITH STEEL SHEET PILE LAGGING WALL ON ADJACENT EXISTING BUILDINGS

Specialising in Ground Engineering & Slope Stabilisation

Ground Improvement. Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting

UNDERPINNING A CRANE FOUNDATION

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

Lesson Learned. Collapse of Diaphragm Wall Trench. Case study. Suez Canal Syphon Project

Sabah Shawkat Cabinet of Structural Engineering 2017

Long-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT. Steven Bartlett, University of Utah

Anchorplex retaining wall construction guide

Earth Retention Systems

Performance of high capacity jack-in pile for high-rise building with preboring in weathered sedimentary rock formation

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

FOUNDATIONS. Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1

Building. Anchorplex. Retaining Wall Systems

1. ORIGINAL CONSTRUCTION SEQUENCE PRESENTED IN THE APPROVED EIA REPORT

Transcription:

Singapore Safety Day Keller civil works team for a large petrochemical project, Malaysia

Bored Piling Bored Pile Pile Piles Piles Diaphragm Walls (D Walls) D Walls are constructed using grabs or cutters to create a narrow trench excavation into the ground. The trench is supported by an engineered slurry. Many D Walls use reinforced concrete, though unreinforced walls are also used. Joints in adjacent panels are formed using either an over-cut technique or via temporary stop-ends. Deep Vibro Techniques Vibro Compaction

Vibro Stone Columns Vibro Concrete Columns Compaction Grouting The Jet Grouting Permeation Grouting Rock Grouting Deep Soil Mixing

Dynamic Compaction and Dynamic Replacement are ground improvement techniques that involve

Coal-Fired Power Plant, Malaysia Deep Soil Mixing, Vibro Stone Columns, Jet Grouting, Driven Piling Ship Hull Block, Singapore Vibro Compaction, Prefabricated Vertical Drain Business Park, Singapore Piling, Ground Anchors, Soil Nailing, Shotcrete At Port Dickson, Malaysia, a 2x1000MW coal-fired power plant is being developed to increase the power supply in Malaysia by 2020. Keller, in collaboration with Ansah Asia, delivered a range of geotechnical solutions- Driven Piling, Deep Soil Mixing, Jet Grouting and Vibro Stone Columns to support various structures of the power plant. Working directly for the owner, Keller designed and executed a ground improvement scheme for a hull block workshop in Tuas, Singapore. Vibro Compaction was carried out and Prefabricated Vertical Drains were installed to improve the subsoil for a 126,000 square meter ship hull block fabrication facility. Keller, working together with Resource Piling, installed Foundation Bored Piles, Secant Bored Piles and Ground Anchors and carried out Soil Nailing and Shotcrete works for the foundations of an 11-storey commercial building in Singapore. Close collaboration and communication with our client enabled us to respond quickly to different site challenges and complete the work ahead of project schedule. Land Preparation for Airport Expansion, Singapore Vibro Compaction Retaining System for Mass Rapid Transit Station, Malaysia Deep Soil Mixing, Curtain Grouting, Secant Bored Pile Petrochemical Complex, Malaysia Driven Piling, Civil Works Keller is involved in the expansion project of Singapore Changi Airport Terminal Five, compacting 33 million cubic meters of sand. A telescopic Vibro compaction rig was used in areas with air height restriction. This project once again proves Keller s strength in innovative technologies and our extensive experience working in an active airport environment. Keller is involved in the development of an underground Mass Rapid Transit Station at Chan Sow Lin, Malaysia. We provided a Geotechnical solution package for a retaining system consisting of Deep Soil Mixing, Curtain Grouting and Secant Bored Piles. In spite of the complexity of the job, our skillful project management enabled us to deliver the work efficiently and safely. Keller, in collaboration with Ansah Asia installed over 36,700 pre cast Spun Piles of various diameters and performed various foundation civil works for the development of a large petrochemical project in South East Johor, Malaysia. This was also Keller s largest Civil Works contract by far. We brought together a multi-national and a multi-skilled team, to deliver the project to the satisfaction of the customer and the owner.

Ground Improvement for Expressway, Malaysia Vibro Stone Columns Intervention Shaft 2, Malaysia Deep Soil Mixing, Rock Fissure Grouting Gardens by the Bay, Singapore Piling On a very deep, soft alluvium soil, Keller installed Vibro Stone Columns for a road embankment in Klang, Malaysia. In spite of challenging ground condition, our team completed the work with an excellent safety performance. For Malaysia s Klang Valley Mass Rapid Transit 2 project, Keller provided a more efficient alternative solution using Deep Soil Mixing for the retaining wall of intervention shaft 2. Rock Fissure Grouting work was also carried out in this project. A one of a kind attraction in Singapore, Gardens by the Bay is made up of 50m tall illuminated supertrees, skywalks, water features, and conservatory domes. Resource Piling, installed over 1,500 piles with diameters up to 1,800mm for various structures of this attraction. These include the supertrees, the conservatories and the watrefront promenade. Link Road, Hong Kong Vibro Stone Columns Petrochemical Refinery Complex, Vietnam Vibro Stone Columns Commercial Building, Indonesia Piling The Hong Kong Link Road project comprises of sea viaducts in the Western waters of Hong Kong, tunnels through scenic hills and underneath the Aiport Road and Airport Express Line, and at-grade roads on reclamation along the East-coast of airport island. 200,000 linear meters of Vibro Stone Columns were installed in this project, some under air height restrictions because of the nearby airport. Nghi Son petrochemical refinery complex situated in Thanh Hoa province is the country s second refinery and the largest project so far. Keller constructed Stone Columns to treat the area approximately 50,000 square meters. Using Keller s bottom-feed method, over 100,000 linear meters of Vibro Stone Columns were installed to depths of 18m, supporting 12 tanks up to 90m in diameter and 19.9m in height. Strategically located at the new central business district in Surabaya, Indonesia, Ciputra World Surabaya is a premier workplace and a lifestyle centre. Frankipile Indonesia installed Foundation Bored Piles and Secant Pile Walls at the 1 hectare site.

Diaphragm Wall for the intervention shaft and the crossover of Mass Rapid Transit 2 project, Malaysia Vibro Compaction works for an airfield development, Singapore