SECTION EXCAVATION, BACKFILLING AND COMPACTING

Similar documents
B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

A. Excavation consists of the removal of material encountered to subgrade elevations and the reuse or disposal of materials removed.

SECTION EXCAVATION AND FILL

Section SITE CLEARING. B. Description of Work: 1. The extent of site clearing is shown on the drawings.

SECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING

SECTION TRENCHING & BACKFILLING

Design and Construction Standards SECTION EARTHWORK

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

A. Work of this Section is affected by unit prices for earth moving specified in Section "Unit Prices."

SECTION 10 - TRENCHING AND BACKFILLING

SECTION FINISH GRADING

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

A. Backfill: Soil material or controlled low-strength material used to fill an excavation.

.1 Furnish all labor, material and equipment necessary to complete all Site Work as shown on the Drawings and Specifications.

SECTION EARTH MOVING

SECTION BUILDING EARTHWORK

SECTION EXCAVATION AND FILL

SECTION TRENCHING

EXCAVATION AND BACKF1LL

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.

C. Foundation stabilization for pipe and utility structures.

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

TECHNOLOGY CENTER WAREHOUSE ADDITION ADMINISTRATIVE SERVICE CENTER MOORE PUBLIC SCHOOLS 1500 S.E. 4 th Street Moore, Oklahoma

SECTION DRILLED CONCRETE PIERS AND SHAFTS

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

SECTION ASPHALT CONCRETE

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION GENERAL EXCAVATION

SECTION BUILDING EARTHWORK

SECTION EARTHWORK

SECTION 14 EMBANKMENT

SECTION EMBANKMENT

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

1.1 RELATED DOCUMENTS A. The provisions of the Contract Documents apply to the work of this Section.

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

SECTION STRUCTURAL EXCAVATION FOR STRUCTURES

SITE CLEARING OF 3

SECTION 18 - EARTHWORK TABLE OF CONTENTS

Standard Test Method for Minimum Index Density and Unit. Weight of Soils Using a Vibratory Table

1.1 RELATED DOCUMENTS

Union County Vocational - Technical Schools Scotch Plains, New Jersey

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

SECTION EARTHWORK. B. Removal of subsoil and excavating all classes of material encountered.

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

SECTION SOILS REPORT

A. Section includes temporary excavation support and protection systems.

Construction Specification for General Excavation

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

DIVISION 4100 SITEWORK

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL

SECTION 18 - EARTHWORK TABLE OF CONTENTS

A. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms.

SECTION EXCAVATING, BACKFILLING AND COMPACTING

SECTION FILL AND BACKFILL

SECTION FLEXIBLE PAVING

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations and the Ontario Building code.

The Six-Inch Layer Compaction Method

SECTION 18 - EARTHWORK TABLE OF CONTENTS

ABNER CLAY PARK RENOVATIONS RICHMOND, VIRGINIA SECTION GENERAL SITEWORK REQUIREMENTS PART 1 - GENERAL

EXCAVATION & BACKFILL SPECIFICATION

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

B. Subsurface data is available from the *Owner. Contractor is urged to carefully analyze the site conditions.

SECTION TRENCHING AND BACKFILLING. A. Earth excavation and backfilling for construction of pipe and appurtenances, and for required removals.

SECTION SUBSURFACE INVESTIGATION

TABLE OF CONTENTS (ISSUE FOR BID) MISCELLANEOUS CAST-IN-PLACE CONCRETE (OTHER THAN PAVEMENT)

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION EXCAVATION AND BACKFILL, GENERAL

Michigan State University Construction Standards EARTHWORK PAGE SECTION EARTHWORK PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

SECTION STRUCTURE EXCAVATION AND EARTHWORK

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION PORTLAND CEMENT CONCRETE

Section Fill Placement Tender No. [ ] Page 1

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION EARTHWORK AND GRADING

SPECIFICATIONS - DETAILED PROVISIONS Section Site Grading C O N T E N T S

378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE

SECTION 02215BP TRENCHING AND BACKFILLING

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION DRILLED CONCRETE PIERS AND SHAFTS

1.2 REFERENCES.1 American Society for Testing and Materials International (ASTM)

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SECTION EARTH MOVING

STANDARD SPECIFICATIONS SECTION 16 STORM SEWER SYSTEMS

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

Transcription:

PART 1 GENERAL 1.01 SCOPE Work of this Section shall include all labor, materials, equipment, plant and incidentals required to complete all excavation, backfilling and compacting as indicated on the Drawings and specified herein. 1.02 QUALITY ASSURANCE A. Codes and Standards: Perform excavation work in strict compliance with applicable requirements of Federal, State and Local authorities having jurisdiction. B. Owner shall utilize the soil testing and inspection services of an independent agency Material Testing Laboratory for quality control testing during earthwork operations. The name of the testing laboratory shall be submitted to the Engineer for approval prior to their use. 1.03 JOB CONDITIONS A. Site Information: Data on indicated subsurface conditions are not intended as representations or warranties of accuracy or continuity between soil borings. It is expressly understood that owner will not be responsible for interpretations or conclusions drawn therefrom by contractor. Data are made available for convenience of contractor. Additional test borings and other exploratory operations may be made by contractor at no cost to owner. B. Existing Utilities: Locate existing underground utilities in areas of work. If utilities are to remain in place, provide adequate means of protection during earthwork operations. Should uncharted, or incorrectly charted, piping or other utilities be encountered during excavation, consult utility owner immediately for directions. Cooperate with Owner and utility companies in keeping respective services and facilities in operation. Repair damaged utilities to satisfaction of utility Owner. Do not interrupt existing utilities serving facilities occupied and used by Owner or others, except when permitted in writing by Engineer and then only after acceptable temporary utility services have been provided. Demolish and completely remove from site existing underground utilities indicated to be removed. Coordinate with utility companies for shut off of services if lines are active. C. Use of Explosives: The use of explosives is not permitted. TALL OAKS STP 02200-1

D. Protection of Persons and Property: Barricade open excavations occurring as part of this work and post with warning lights. Operate warning lights as recommended by authorities having jurisdiction. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout and other hazards created by earthwork operations. PART 2 PRODUCTS 2.01 SOIL MATERIALS A. Definitions 1. Satisfactory soil materials are defined as those complying with American Association of State Highway and Transportation Officials (AASHTO) M145, soil classification Groups A-1, A-2-4, A-2-5, and A-3. 2. Unsatisfactory soil materials are those defined in AASHTO 145 soil classification Groups A-2-6, A-2-7, A-4, A-6 and A-7; also peat and other highly organic soils. 3. Subbase material: Naturally or artificially a mixture of natural or crushed gravel, crushed stone, crushed slag, natural or crushed sand. 4. Drainage fill: Crushed, evenly graded mixture of crushed stone, or crushed or regular gravel, with 100% passing a 1-1/2 sieve and not more than 5% passing a No. 4 sieve. 5. Backfill and fill materials: Satisfactory soil materials free of clay, rock or gravel larger than 2 in any dimension, debris, waste frozen materials, vegetable and other deleterious matter. 2.02 GEOTEXTILES Vegetative reinforcement and erosion control matting shall be a non-woven vinyl composition type such as: Greenstreak PEC-MAT, by Greenstreak Plastic Products Co. Miramat 2400, by Mirafi, Inc. Enkamat 7020, by Akzo Industrial Systems Inc. TALL OAKS STP 02200-2

PART 3 EXECUTION 3.01 EXCAVATION A. Excavation consists of removal and disposal of material encountered when establishing required finish grade elevations. B. Earth excavation includes removal and disposal of pavements and other obstructions visible on ground surface, underground structures and utilities indicated to be demolished and removed, material of any classification indicated in data on subsurface conditions, and other materials encountered that are not classified as unauthorized excavation. C. Unauthorized excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without specific direction of Engineer. Unauthorized excavation, as well as remedial work directed by Engineer, shall be at Contractor s expense. Under footings, foundation bases, or retaining walls, fill unauthorized excavation by extending indicated bottom elevation of footing or base to excavation bottom, without altering required top elevation. Lean concrete fill may be used to bring elevations to proper position, when acceptable to Engineer. Elsewhere, backfill and compact unauthorized excavations as specified for authorized excavations of same class classification, unless otherwise directed by Engineer. D. Additional Excavation: When excavation has reached required subgrade elevations, notify Engineer who will make an inspection of conditions. If unsuitable bearing materials are encountered at the required subgrade elevations, carry excavations deeper and replace excavated material as directed. Excavation and replacement of unsuitable materials will be paid for in accordance with the contract provisions of Extra Work. E. Stability of Excavations: Slope sides of excavations to comply with local codes and ordinances having jurisdiction. Shore and brace where sloping is not possible because of space restrictions or stability of material excavated. Maintain sides and slopes of excavations in safe condition until completion of backfilling. F. Shoring and Bracing: Provide materials for shoring and bracing, such as sheet piling uprights, stringers and cross braces, in good serviceable condition. Establish requirements for trench shoring and bracing to comply with local codes and authorities having jurisdiction. Maintain shoring and bracing in excavations regardless of time period abbreviations will be open. Carry down shoring and bracing as excavation progresses. TALL OAKS STP 02200-3

G. Dewatering: Prevent surface water and subsurface or groundwater from flowing into excavations and from flooding the project site and surrounding area. Do not allow water to accumulate in excavations. Remove water to prevent softening of foundation bottoms, undercutting footings, and soil changes detrimental to stability of subgrades and foundations. Provide and maintain pumps, well points, sumps suction and discharge lines, and other dewatering system components necessary to convey water away from excavations. Convey water removed from excavations and rain water to collecting or run-off areas. Establish and maintain temporary drainage ditches and other diversions outside excavation limits for each structure. Do not use trench excavations as temporary drainage ditches. H. Material Storage: Stockpile satisfactory excavated materials where directed, until required for backfill or fill. Place, grade and shape stockpiles for proper drainage. Locate and retain soil materials away from edge of excavations. Dispose of excess soil material and waste materials as herein specified. I. Excavation for structures: Conform to elevations and dimensions shown within a tolerance of plus or minus 0.10, and extending a sufficient distance from footings and foundations to permit placing and removal of concrete formwork, installation of services, other construction, and for inspection. In excavating for footings and foundations, take care not to disturb bottom of excavation. Excavate by hand to final grade just before concrete reinforcement is placed. Trim bottoms to required lines and grades to leave solid base to receive other work. For pile foundations, stop excavations from 6 to 12 above bottom of footing before piles are placed. After piles have been driven, remove loose and displaced material, and excavate to final grade, leaving solid base to receive concrete pile caps. J. Excavation for pavements: Cut surface under pavements to comply with cross-sections, elevations and grades as shown. K. Excavation for trenches: Dig trenches to the uniform width required for the particular item to be installed, sufficiently wide enough to provide simple working room. Excavate trenches to depth indicated or required. Carry depth of trenches for piping to establish indicated flow lines and invert elevations. Beyond building perimeter, keep bottoms of trenches sufficiently below finish grade to avoid freeze-ups. Grade bottoms of trenches as indicated, notching under pipe bells to provide solid bearing for entire body of pipe, backfill trenches with concrete where trench excavations pass within 18 of column or wall footings and which are carried below bottom of such footings, or which pass under wall footings. Place concrete to level of bottom of adjacent footing. TALL OAKS STP 02200-4

Concrete is specified in Division 3. Do not backfill trenches until tests and inspections have been made and backfilling authorized by engineer. Use care in backfilling to avoid damage or displacement of pipe systems. L. Cold Weather Protection: Protect excavation bottoms against freezing when atmospheric temperature is less than 35 degrees F (1 degree C). M. Steel Sheeting Left in Place: The sheeting shall be interlocked and driven plumb the full depth before excavation. The toe of the sheeting shall extend at least twelve (12 ) inches below the proposed subgrade elevation. The sheeting shall be of ample weight and cross section for the service intended and shall be adequately braced. Shop drawings indicating proposed methods and materials shall be submitted to the engineer for information prior to the start of the installation. Upon completion of the structure, the sheeting shall be left in place. 3.02 COMPACTION A. General: Control soil compaction during construction providing minimum percentage of density specified for each area classification. B. Percentage of Maximum Density Requirements: Compact soil to not less than the following percentages of maximum dry density for soils which exhibit a well defined moisture density relationship determine in accordance with ASTM D1557; and not less than the following percentages of relative density, determined in accordance with ASTM D2049 for soils which will not exhibit a well defined moisture density relationship. 1. Structures: Compact top 12 of subgrade and each layer of backfill or fill material at 95% maximum dry density. 2. Building Slabs and Steps: Compact top 12 of subgrade and each layer of backfill or fill material at 95% maximum dry density or 90% relative dry density. 3. Lawn or Unpaved Areas: Compact top 6 of subgrade and each layer of backfill or fill material at 90% maximum dry density. 4. Walkways: Compact top 6 of subgrade and each layer backfill or fill material at 90% maximum dry density or 90% relative dry density. 5. Pavements: Compact top 12 of subgrade and each layer of backfill or fill material at 90% maximum dry density or 90% relative dry density for cohesive soil material. C. Moisture Control: Where subgrade or layer of soil must be moisture conditioned before compaction, uniformly apply water to surface of subgrade, or layer of soil material, to prevent free water appearing on surface during or subsequent to compaction operations. TALL OAKS STP 02200-5

Remove and replace, or scarify and air dry, soil material that is too wet to permit compaction to specified density. Soil material that has been removed because it is too wet to permit compaction may be stockpiled or spread and allowed to dry. Assist drying by discing, harrowing or pulverizing until moisture content is reduced to a satisfactory value. 3.03 BACKFILL AND FILL A. General: Place acceptable soil material in layers to required subgrade elevations, for each area classification listed below. 1. In excavations, use satisfactory excavated or borrowed material. 2. Under grassed areas, use satisfactory or excavated or borrow material. 3. Under walks and pavements, use subbase material or satisfactory excavated or borrowed material, or combination of both. 4. Under steps, use subbase material. 5. Under building slabs, use drainage fill material. B. After satisfactorily completing testing watertight structures, the Contractor shall backfill around the structures, in accordance with this section, to the invert elevation of the lowest wall casting installed. C. Backfill excavations as promptly as work permits, but not until completion of the following: Acceptance of construction below finished grade including, where applicable, dampproofing, waterproofing, and perimeter insulation. Inspection, testing, approval, and recording locations of underground utilities. Removal of concrete formwork. Removal of shoring and bracing, backfilling of voids with satisfactory materials. Cut off temporary sheet piling driven below bottom of structures and remove in manner to prevent settlement of the structure or utilities, or leave in pace if required. Removal of trash and debris. Permanent or temporary horizontal bracing is in place on horizontally supported walls. D. Ground Surface Preparation: Remove vegetation, debris, unsatisfactory soil materials, obstructions, and deleterious materials from ground surface prior to placement of fills. Plow, strip, or break-up sloped surfaces steeper than 1 vertical to 4 horizontal so that fill material will bond with existing surface. TALL OAKS STP 02200-6

When existing ground surface has a density less than that specified under Compaction for particular area classification, break up ground surface, pulverize, moisture condition to optimum moisture content, and compact to required depth and percentage of maximum density. E. Placement and Compaction: Place backfill and fill materials in layers not more than 8 in loose depth for material compacted by heavy compaction equipment, and not more than 4 in loose depth for material compacted by hand-operated tampers. Before compaction, moisten or aerate each layer as necessary to provide optimum moisture content. Compact each layer to required percentage of maximum dry density or relative dry density for each area classification. Do not place backfill or fill material on surfaces that are muddy, frozen or contain frost or ice. Place backfill and fill materials evenly adjacent to structures, to required elevations. Take care to prevent wedging action of backfill against structures by carrying materials uniformly around structure to approximately same elevation in each lift 3.04 GRADING A. General: Uniformly grade areas within limits of grading under this Section, including adjacent transition areas. Smooth finished surface within specified tolerances, compact with uniform levels or slopes between points where elevations are shown, or between such points and existing grades. B. Grading Outside Building Lines: Grade areas adjacent to building lines to drain away from structures and to prevent ponding. Finish surfaces free from irregular surface changes, and as follows: 1. Lawn or Unpaved Areas: Finish areas to receive topsoil to within not more than 0.10 above or below required subgrade elevations. 2. Walks: Shape surface of areas under walks to line, grade and cross-section, with finish surface not more than 0.10 above or below required subgrade elevation. 3. Pavements: Shape surface of areas under pavement to line, grade and cross-section, with finish surface not more than ½ above or below required subgrade elevation. C. Grading Surface of Fill Under Building Slabs: Grade smooth and even, free of voids, compacted as specified, and to required elevation. Provide final grades within a tolerance of ½ when tested with a 10 straightedge. D. Compaction: After grading, compact subgrade surfaces to the depth and percentage of maximum density for each area classification. TALL OAKS STP 02200-7

3.05 PAVEMENT SUBBASE COURSE A. General: Subbase course consists of placing subbase material, in layers of specified thickness, over subgrade surface to support a pavement base course. B. Grade Control: During construction, maintain lines and grades including crown and crossslope of subbase course. C. Shoulders: Place shoulders along edges of subbase course to prevent lateral movement. Construct shoulders of acceptable soil materials, placed in such quantity to compact to thickness of each subbase course layer. Compact and roll at least a 12 width of shoulder simultaneously with compacting and rolling of each layer of subbase course. D. Placing: Place subbase course material on prepared subgrade in layers of uniform thickness, conforming to indicated cross-section and thickness. Maintain optimum moisture content for compacting subbase material during placement operations. When a compacted subbase course is shown to be 6 thick or less, place material in a single layer. When shown to be more than 6 thick, place material in equal layers, except no single layer more than 6 or less than 3 in thickness when compacted. 3.06 BUILDING SLAB DRAINAGE COURSE A. General: Drainage course consists of placement of drainage fill material, in layers of indicated thickness, over subgrade surface to support concrete building slabs. B. Placing: Place drainage fill material on prepared subgrade in layers of uniform thickness, conforming to indicated cross-section and thickness. Maintain optimum moisture content for compacting material during placement operations. When a compacted drainage course is shown to be 6 thick or less, place material in a single layer. When shown to be more than 6 thick, place material in equal layers, except no single layer more than 6 or less than 3 in thickness when compacted. 3.07 FIELD QUALITY CONTROL A. Quality Control Testing During Construction: Allow testing service to inspect and approve subgrades and fill layers before further construction work is performed. Perform field density tests in accordance with ASTM D 1556 (sand cone method) or nuclear density method, as applicable. 1. Footing Subgrade: For each strata of soil on which footings will be placed, conduct at least one test to verify required design bearing capacities. Subsequent verification and TALL OAKS STP 02200-8

approval of each footing subgrade may be based on a visual comparison of each subgrade with related tested strata, when acceptable to Engineer. 2. Paved Areas and Building Slab Subgrade: Make at least one field density test of subgrade for every 2000 square feet of paved area or building slab, but in no case less than 3 tests. In each compacted fill layer, make one field density test for every 2000 square feet of overlaying building slab or paved area, but in no case less than 3 tests. 3. Foundation Wall Backfill: Take at least 2 field density tests, at locations and elevations as directed. If in the opinion of the Engineer, based on testing service reports and inspection, subgrade or fills which have been placed are below specified density, provide additional compaction and testing at no additional expense. 3.08 MAINTENANCE A. Protection of Graded Areas: Protect newly graded areas from traffic and erosion. Keep free of trash and debris. B. Reconditioning Compacted Areas: Where completed compacted areas are disturbed by subsequent construction operations or adverse weather, scarify surface, reshape, and compact to required density prior to further construction at no additional expense. 3.09 DISPOSAL OF EXCESS AND WASTE MATERIALS A. Removal from Owner s Property: Remove waste materials, including unacceptable excavated material, trash and debris, and dispose of it off Owner s property. END OF SECTION TALL OAKS STP 02200-9

THIS PAGE INTENTIONALLY LEFT BLANK TALL OAKS STP 02200-10