Boston Society of Architects Building Envelope Committee 52 Broad Street Boston, MA 02109

Similar documents
Boston Society of Architects Building Envelope Committee 52 Broad Street Boston, MA 02109

Boston Society of Architects Building Envelope Committee 52 Broad Street Boston, MA 02109

Boston Society of Architects Building Envelope Committee 52 Broad Street Boston, MA 02109

Insulation manufacturer to submit dew point analysis free of charge for typical wall section. Analysis by:

Incorporating Insulating Sheathing into the Design of the Thermal and Moisture Management System of the Building Enclosure

Compliance for Continuous Insulation, Water Resistive Barriers & NFPA-285 What you need to Know

How-to: Commissioning Design Reviews for the Building Envelope

Doorways to the Future

Continuous Insulation and Air Barriers for High Performance Walls

New Air and Vapor Barrier Technologies

Building Enclosure Concept Design Checklist

A. Section includes fluid applied, vapor permeable membrane air barriers.

Henri Fennell, CSI/CDT ABX 2015

Managing Condensation and Thermal Performance with Continuous Insulation

Thermal Control Layers: Insulation Materials and Systems

SECTION FLUID-APPLIED VAPOR PERMEABLE MEMBRANE AIR BARRIER SYSTEM ASSEMBLY (August 2013)

Impact of NFPA 285 on Air Barrier Specification and Design

FirstEnergy Program Overview

The Disclaimer located on the reverse side of the title page of the OAA Rain Penetration Practice Guide applies to each section of the Guide.

BUILDING ENCLOSURE AIR TIGHTNESS TESTING Course Number: BCLUNA018-01P

SECTION FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE

Boundaries and Barriers

SECTION REFLECTIVE-FACED, MASONRY CAVITY WALL INSULATION

Insulating Exterior Assemblies : Batt, Blown / Spray, Board and Beyond

Thermasheath -3. Insulation for the Building Envelope ROOF WALL SPECIALTY

Advanced technologies for enhancing the building envelope. 3M Building and Construction Market

Introduction. Introduction. Designing Building Envelopes to Meet Sustainable and Aesthetic Goals Part 1

Building Envelope Solutions, Inc. Identifying solutions for better building performance

Ultra Wall System. CAD Detail Sets

Installation Procedures for the Ultra Air Barrier Wall System

Recommended Design Considerations. and. Guide Specifications For. Commercial Building Insulation

Guide Specification for the OSI QUAD Window and Door Flashing System

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION

SECTION FLUID-APPLIED VAPOR PERMEABLE MEMBRANE AIR BARRIER SYSTEM ASSEMBLY (August 2013)

SECTION SUPERGREEN LAM (LIQUID-APPLIED MEMBRANE AIR/VAPOR BARRIER SYSTEM)

WeatherSmart Air Barrier Installation Guide

An Introduction to Spray Foam Insulation

JOHNS MANVILLE CONTINUOUS INSULATION WALL SYSTEM MASTER SPECIFICATION June 2014 CSI FORMAT SECTION FOIL-FACED RIGID INSULATION

SECTION PRE-ENGINEERED BUILDING INSULATION

UNDERSTANDING DIFFICULT CRITICAL TRANSITIONS OF AVB SYSTEMS

SECTION MODIFIED BITUMINOUS MEMBRANE ROOFING Peel & Roof

Quality Control of Air Barriers During Construction

Building Science Control Layer Glossary. Façade Visible exterior face of a building, usually vertical or nearly so, but imprecisely used.

Building Enclosure Design Fundamentals, Components, and Assemblies

Building Construction and Water Intrusion

Why Control Heat flow? How to Control Heat Flow? Thermal Performance. Modes of heat transfer: Thermal Control: Insulation & Thermal Bridges

GAF EnergyGuard Polyiso Wall Sheathing

Avoiding Air Barrier Pitfalls When sub-trade activities are not in sync with air barrier requirements, installation can go poorly.

Insulated Composite Panels Designed for Brick Back-up

In addition to performing as an interior vapor retarder, MemBrain the Smart Vapor Retarder may be installed as a continuous, interior

THERMAL AND AIR BARRIER WALL SYSTEM

Insulation. First Revison October DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS

TECH SOLUTIONS A Prescriptive Solution to Meet Air Barrier Energy Code Requirements in Metal Buildings

EE13-3 Improving Building Enclosures Thermal Performance as a Goal of Energy Efficiency. Paul E. Totten, PE Marcin Pazera, Ph. D.

WATERPROOFING TAMKOWATERPROOFING.COM

Today s Trends in Air Barriers. Building Envelopes Today

A. Source Limitations: Obtain each type of building insulation through one source.

PART 6 - INSULATED WALL SYSTEMS

WATERPROOFING TAMKOWATERPROOFING.COM

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING

BREATHABLE MEMBRANES. Canada Inc. Water Vapour Permeable, Air Barriers for Sloped Roofs & Rain Screen Wall Systems

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:

8/14/2015. Course Description. Course Objectives AIR, WATER, AND MOISTURE MANAGEMENT IN LIGHT COMMERCIAL BUILDING ENVELOPES

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance

Thermasheath -3. Insulation for the Building Envelope ROOF WALL SPECIALTY

Installation Guidelines

WATERPROOFING TAMKOWATERPROOFING.COM

Thermasheath -3. Insulation for the Building Envelope ROOF WALL SPECIALTY

Professional Educational Series BSP716 USGBC # Commercial Building Science Thermal Control in Building Envelopes

SECTION AIR AND VAPOR BARRIERS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

NFPA 285 Assemblies. Table of Contents

Insulated Metal Panel (IMP) Systems

NFPA 285 Assemblies. Table of Contents

2015 IEC Code Compliance

COPYRIGHTED MATERIAL. Contents. 1 Making Buildings 3. 3 Wood Foundations and. Preface to the Sixth Edition xi. Sitework 31

CSI Boston Technical Paper No. 1: Specifying Air Barriers Air Barriers

MCCARTY ARCHITECTS, P.A. POST OFFICE BOX 440 / 533 WEST MAIN STREET TUPELO, MS / FOR ANSWERS TO QUESTIONS CONTACT: JUSTIN HARRINGTON

SECTION FLEXIBLE FLASHING SYSTEM FOR MASONRY VENEER

WALLTITE ECO Air Barrier System. Welcome

Tender No Section St. James - Assiniboia Centennial Pool Fitness Facility Addition Page 1

2006 INTERNATIONAL ENERGY CONSERVATION CODE

SECTION FLUID APPLIED VAPOR PERMEABLE AIR BARRIER MEMBRANE

1 Exam Prep Prov Module: Thermal and Moisture Protection Questions and Answers

HIGH PERFORMANCE SEALANT SOLUTIONS ARCHITECTURAL GLAZING SYSTEMS

EXTERIOR WALLS. exterior wall systems, cladding w/ masonry. chapters SUBJECT

Accellent Cardiology Expansion Brooklyn Park, Minnesota EXTERIOR ENCLOSURE - PART Exterior Wall Construction

R-Matte Plus-3: Insulation for the Building Envelope

G October 2018

SRP-AirOutshield UV Issued:

Moisture Considerations for Insulated Building Assemblies

Perm-A-Barrier NPS (Non Permeable Sheet)

How to Meet Code and Manage Moisture in an Environment of Increasing Air Tightness Requirements. Ted Winslow

Design No. HI/BP PERIMETER FIRE BARRIER SYSTEM Hilti, Inc. ASTM E 2307 Table 1

Smart Vapor Retarders

A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants.

Fundamentals of Building Construction: Materials and Methods

3/24/2017. Kohta Ueno. Building Science of Walls. March 24, Background Rhode Island AIA Presentation 2

SECTION SELF-ADHERING SHEET FLASHING

DIVISION 07 SECTION 2100 Short Form Guide Specification THERMAL, AIR BARRIER AND WATER BARRIER WALL SYSTEM

NOVAWRAP ASPIRE Q & A

Transcription:

Boston Society of Architects Building Envelope Committee 52 Broad Street Boston, MA 02109 Building Envelope Designs meeting the requirements of the new Massachusetts Energy Code 780 CMR 13 For Educational Purposes Only Acknowledgments: Process: The BSA Building Envelope Committee was approached by the Board of Building Regulations and Standards to develop building envelope details demonstrating compliance with the new energy code. Richard Keleher AIA, chairman and founder of the BSA building envelope committee appointed a task force to develop a narrative and details to demonstrate compliance with the new energy code. The task force developed the details and narrative below, which were then reviewed by the building envelope committee members. The BSA was under contract with the Peregrine Energy Group, a contractor to the Board of Building Regulations and Standards to deliver pdf format drawings and a narrative of the system alternatives. Shepley Bulfinch Richardson and Abbott, Architects, Boston, acted as prime consultant to the BSA to develop the deliverables. The task force decided to select, review, verify and edit some of the designs from the Architects Guide to The New Energy Code, by Mark Kalin, available in hard copy and in electronic form as publication No. 263 from the BSA. The following task force members contributed their time and knowledge in the development of these designs: Wagdy Anis AIA Mark Kalin FAIA, FCSI Jeff Wade AIA, CSI Lance Robson AIA Steven Rigione Shepley Bulfinch Richardson and Abbott, Task force chair. Kalin Associates Inc. ADD Inc Building Envelope Technologies Inc. HKT Architects Inc.

In addition to reviews by the subcommittee members, the following members of the BSA's Building Envelope Committee performed very helpful reviews of the details before publishing: Len Anastasi, CSI Vince Camalleri AIA Ken Crocco AIA Richard Keleher AIA, CSI Don Klema AIA Joseph Lstiburek, PhD. P. Eng. Ned Lyon P.E. Fred Nashed AIA Oscar Padjen AIA Allan Schmaltz Lennel Specialties Simpson Gumpertz and Heger ArchiTech Consulting Inc., Chicago Chapter AIA Shepley Bulfinch Richardson and Abbott Kallmann McKinnell and Wood Architects Building Science Corporation Simpson Gumpertz and Heger Architectural Consulting Services Padjen Architects, Inc. Unerectors Inc. The designs must be reviewed by a design professional before applying them for applicability to a specific project, including the limitations imposed by the interior and exterior environment of a building. Some designs are more durable than others, and cost is also a variable. The designs are based on a maximum of 35% interior relative humidity in the winter and normal exterior conditions in Massachusetts. Some of the designs fail if the interior RH is higher, and should be modified. Any misapplication or misinterpretation of these designs is the sole responsibility of the user. In all of the designs below, continuity of the air barrier from foundations to roof is a focus, including closure of all penetrations. None of the designs have been reviewed by a structural engineer. The structural support of the air barrier is taken into consideration to withstand positive and negative air pressures, but should be reviewed by a structural engineer for transfer to the backup wall and structure. The systems and anchorages normally designed by specialty engineers such as light-gage steel studs, stone and precast concrete connections have also not been engineered. Alternatives within each design are discussed below. Roof: No attempts to vary the low-slope roofing design were made. Remember that the new energy code establishes a relationship of 10 times less permeable for the roof membrane than the vapor barrier in the roof assembly. Roof membranes vary from 2 to 0.03 perms, therefore the vapor barrier should be from 0.1 to 0.003, based on the roof membrane permeability.

Design A shows a pitched shingle roof and a metal roof. The concept of tying the roof air barrier to the wall air barrier is demonstrated. The shingle roof is ventilated due to the shingle manufacturer's warranty requirements. If the metal roofing standing seams are sealed, then it too should be ventilated. Otherwise the metal roof assembly is nonventilated roof and takes advantage of the code roof ventilation exception for air-tight roof assemblies. Design A also shows a penetration conceptually. The concept of air-tightening all penetrations should carry through all the designs. Also in design A is an enlarged detail of a window connection, as an example of connecting a window-frame to the wall air-barrier. This is applicable to all the designs. Window crack perimeter sealants should be used that are compatible with polyethylene, such as low or ultra-low-modulus silicone. For small windows up to 5 or 6, one-part spray polyurethane foam may be used. A membrane, properly connected with compatible sealants and termination bars to window and membrane may also be used. The same tie-in location is true of louvers, metal door frames and store fronts. Curtain wall is tied in at the tube face of the glazing pocket. Design D Description: Brick veneer, cavity, rigid insulation, air and vapor barrier, concrete block back-up, gypsum board. Advantages & Disadvantages: This design is very similar to design A, except that less insulation (R-5) is required by code. All the other choices are identical. This wall type has a layer of continuous insulation, making it energy efficient. It is easy to build, because the air and vapor barrier and the insulation are continuous. The concrete block back-up wall has "thermal mass" which saves energy. The back-up wall is always kept above the dew-point of the winter indoor air, which promotes durability. The air and vapor barrier on the warm side of the insulation also works as the drainage plane, handling liquid water, water vapor in the winter and reverse vapor drive, keeping the back-up wall always dry. The year-round stable temperature of the air & vapor barrier promotes its durability. It is also well structurally supported, especially if the

insulation is mechanically fastened rigid insulation and/or if the membrane is a peel-andstick. With closed cell board insulation, this wall can function without a vapor barrier. A less expensive version can use an extruded polystyrene insulation with spun-bonded polyolefin air barrier and no vapor barrier. Other kinds of insulation need a vapor barrier. Insulation choices: extruded polystyrene polyisocyanurate expanded polystyrene spray polyurethane foam semi-rigid rockwool semi-rigid fiber-glass Air and Vapor Barrier Alternatives: In the case of spray polyurethane foam insulation, all it needs is membrane transition sheets and taping the sheathing joints. Peel-and stick modified asphalt/polyethylene membrane. Liquid-applied spray-on or trowel-on air/vapor barrier. (caution that asphalt damp-proofing is not considered to be flexible enough to be durable). Liquidapplied air and vapor barrier membrane may double as an insulation adhesive. If this kind of air and Vapor Barrier is used, trim-work at windows, and transitions needs to be made with a compatible sheet membrane, usually an asphalt peel-and-stick. Thermofusable modified asphalt membrane. Reinforced polyethylene sheet. Tape all joints with a compatible durable tape such as peel-and stick, and trim all openings and transitions with membrane. Reinforced aluminum foil air/vapor barrier, with taped joints and membrane transitions. Commercial grade spun-bonded polyolefin (not a vapor barrier), with membrane transitions and trim.