Aluminothermic Weld Defects

Similar documents
TGN-RT-01. Post Weld Fatigue Improvement. Techniques Ultrasonic Impact Treatment

Composite Repairs for Pipelines

Tack Welding of Reinforcement Bar

GN01 DEAERATOR CRACKING

TGN-PE-04. Weld Repair of Creep Damaged Steel

Ontario ENGINEERING STANDARD GUIDELINE 1.0 PURPOSE 2.0 THERMITE WELDING 2.1 WELD PROCEDURE

TGN-BC-03 Rev: 0 Date: 1 March 2006 Pages: 19

Welding Inspection Defects/Repairs Course Reference WIS 5

Welding Defects, Causes and Prevention

INSPECTION OF FIELD WELDING

Specification for the Fabrication of Tower Structures

& STRUCTURES TECHNICAL SESSION T6

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Rail Repair using Wire Feed Welding

TESTING OF MANUAL ARC WELDERS Issue No 5 Date Issued 1/9/69

TN Weld Australia Technical Note 15: Welding and Fabrication of Quenched and Tempered Steels

NAME 345 Welding Technology Lecture 12 Welding Defects & Discontinuities

PILE WELDING QUALITY CONTROL PLAN

Sub-surface inspection of welds No. 6.03

Weld Imperfections and Preventive Measures

Casting Defects - Sand Mold, Metal Casting

Saggistica Aracne 266

INSTALLATION PROCEDURES

Specification for Fabrication of Steelwork for Pole Structures

Welding Efficiency & Learning Defects (W.E.L.D) Cards A

ISO INTERNATIONAL STANDARD. Non-destructive testing of welds Visual testing of fusion-welded joints

AN OVERVIEW ON SHIELDED METAL ARC WELDING (SMAW) OF STAINLESS STEEL (SS)

ME E5 - Welding Metallurgy

NAME 345 Welding Technology Lecture 03 (Welding Joint Design)

SECTION SHEET PILES. A. This section covers the contract item Sheet Piles. This work includes:

EXOTHERMIC WELDING APLIWELD

TECHNICAL GUIDE CUTTING

TECHNICAL GUIDE CUTTING

MasterSeal 940. Centrally and externally placed PVC Waterstops

GN06 POST WELD HEAT TREATMENT OF WELDED STRUCTURES

Lawrence, Chen, Cyre and Barkan 1. F. V. Lawrence. Y-R. Chen. J. P. Cyre. C. P. L. Barkan. Department of Civil and Environmental Engineering

Preparing and using manual TIG or plasma-arc welding equipment

TS 2 SOUTH AUSTRALIAN WATER CORPORATION

North Atlantic ENGINEERING STANDARD SPECIFICATION 1/7 REV. QUALITY SLAG BOWL WELDING AND QUALITY REQUIREMENTS. Approved by.

Porosity The good, the Bad and the Ugly of Radiographic Testing

IMPROVEMENT OF ALUMINOTHERMIC WELDING CYCLE LIFE

welding equipment Prepare and use manual TIG or plasma-arc Performance evidence required You must be able to:

Rerailing and Anchoring

Installation Instructions/Operation and Maintenance Manual. Models PLG-60 PLG-72. PS DOORS Contact Information. Website psdoors.

Preparing and using manual metal arc welding equipment

Discontinuities and Defects

GEOSYNTHETICS AND WELDED GAS RESISTANT MEMBRANE INSTALLATION QUALITY PLAN

Procedure for Visual and Optical Inspection

Defects and Discontinuities. Tim Turner Elizabethtown Technical College

Defect. Discontinuity. Defects and Discontinuities. Weld Joint Discontinuities

STEEL SURFACE PREPARATION

INSPECTION. Disk seat worm Mold parting. Replacement Good Required

MUELLER GAS. Line Stopper Fittings for. Reliable Connections. Preparation Procedures 2. Installation / Welding 3-5. Side-Out Fitting Installation 6

Subpart E Welding of Steel in Pipelines

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL PLAN FOR WELDING FOUNDATION PILING SPLICES

Item 448 Structural Field Welding

1. Cast-in-place concrete is specified in Section

Section Fluid Applied Waterproofing

Chemistry and Chemical Sampling Updated 2012

TECH TIPS. Booms/Scissors. Service Call: Platform repair instructions of steel guard rails on Terex/Genie Aerial Work Platforms and Scissors

TROUBLE SHOOTING TIPS

Guidelines To Gas Metal Arc Welding (GMAW)

INVESTIGATING SEALING ISSUES IN FLEXIBLE PACKAGING PRODUCTS

Cast Steel Propellers W27. (May 2000) (Rev.1 May 2004)

Fundamentals of Casting

Evaluation Report CCMC R NUDURA Waterproofing Membrane

Welding. What is Welding?

Manufacturing Process - I Dr. D. K. Dwivedi Department of Mechanical and Industrial Engineering Indian Institute of Technology, Roorkee

Evaluation Report CCMC R Colphene ICF, ICF Foundation Membrane, Membrane de Fondation ICF (for dampproofing)

GASTEC AND DENSITEC. Reduced Pressure Test and Density Index. Process Control for Porosity

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

Extended stickout guides are used to maintain a consistent CTWD (see Contact Tip to Work Distance section for more details).

Wire Feed Welding Manual RTS 3734

DISTRICT OF SUMMERLAND APPENDIX 7 UNIT PRICE APPENDIX 7 UNIT PRICE FOR IMPORTED MATERIALS CONTRACT 2018

OIL TECH SERVICES, INC.

7. Design for Castability

SECTION METAL FABRICATIONS FOR STEAM UTILITY DISTRIBUTION

PART 5 WELDING. 5.1 General 5.2 Preparation 5.3 Dimensions of welds 5.4 Materials 5.5 Aluminium alloys 5.6 Welding details 5.

EFFECTS OF COOLING MEDIA ON THE MECHANICAL PROPERTIES AND MICROSTRUCTURE OF SAND AND DIE CASTING ALUMINIUM ALLOYS

WELDER S. Visual Inspection HANDBOOK. May 2013

FCAW vertical welding of "V" butt plate in AC UHV transmission line construction

Construction. SikaProof A. Fully bonded FPO sheet waterproofing membrane system for basement and other below ground structures. Product Description

DIE SURFACE TEMPERATURE MONITORING

ITEM 448 STRUCTURAL FIELD WELDING

Planning Advisory Notice

JRC IMPROVING CASTING INTEGRITY THROUGH THE USE OF SIMULATION SOFTWARE AND ADVANCED INSPECTION METHODS

Florock Seamless Flooring Systems

WELDING PROCEDURE SPECIFICATION. Shielded Metal Arc Welding-SMAW

Engineering Guide For Zircoa s Foundry Crucibles

Pallet Gate Installation Instructions and Operators Manual

CHAPTER 3: TYPES OF WELDING PROCESS, WELD DEFECTS AND RADIOGRAPHIC IMAGES. Welding is the process of coalescing more than one material part at

By Authority Of THE UNITED STATES OF AMERICA Legally Binding Document

SECTION FLAT WALK-ON TYPE ALGAE CONTROL/LAUNDER COVERS

PIPELINE WELDING PROCEDURE SPECIFICATION

Introduction: NAV 30 - FORGING PROCESS. State, Zip: Type of company ownership: Business ownership/relationship with other organizations:

BONDING, POTTING, WELDING

TECHNICAL REQUIREMENTS FOR PRECIPITATION HARDENING (SS 17-4 PH and PH 13-8 MO) STAINLESS STEEL BARS

SAMPLE. MEM05026C Apply welding principles. Learner Guide. MEM05 Metal and Engineering Training Package. Version 1. Product Code: 5672

Transcription:

ABN 69 003 696 526 Aluminothermic Weld Defects TGN-R-04 Rev: 0 Date: 30 May 2006 Pages: 6 1.0 Introduction Aluminothermic welding has been applied for a century for the joining of rails, however defects do still occur in aluminothermic welds. These are generally due to poor set up and preparation and also due to inadequate attention to detail. The following list of defects in aluminothermic welds with causes of the defect and hints on avoiding the defects has been compiled to assist the personnel involved in performing aluminothermic welds to have a better understanding of the causes of defects in an effort to reduce or hopefully eliminate aluminothermic weld defects and increase the integrity of rail welds. 2.0 Welding procedures Rigorous adherence to the qualified welding procedure by welding personnel which are qualified to that procedure when executing aluminothermic welds is essential to ensure weld defects are not randomly introduced. The necessary care needs to be taken in each of the following areas: Rail end preparation; Mould fitting and alignment; Luting; Preheater alignment; Preheating; Crucible cleaning and preheating for multi-use crucibles; Correct portion selection. 3.0 Aluminothermic weld defect types causes and rectification 3.1 Black holes An isolated gas pore in the riser of a weld is known as a black hole. The name originated from its characteristic appearance as shown in figure 1 Figure 1. Typical black hole Black holes have been a major cause for rejection of welds, however there are very few recorded cases of failure initiating from a black hole as the isolated hole is generally fairly shallow and rounded. The defect is caused by gas passing through the weld during solidification. Gas source is from steam from the sealing material under the rail foot. Using narrower than normal weld widths increases risk of getting black holes Page 1 of 5

To minimise the occurrence of black holes: Use a railhead gap > 24 mm, adjusting the weld gap if required; Ensure that the luting material is not too wet; Observe all checks and procedures to control porosity; Ensure that preheating is performed correctly. 3.2 Slag inclusions Slag inclusions are caused by; Not cleaning or inadequate cleaning of the crucible where multi-use crucibles are used; Poor flame cut surfaces with incorrect cutting parameters producing gouges or with inadequate removal of slag and oxide can case slag inclusions on the weld fusion zone or cause slag to be taken up in the weld metal; Inadequate preheat can promote the formation of slag inclusions in that slag gets trapped in the weld; Incorrect joint gaps affect the flow of the metal in the mould and can also promote slag inclusions; Cold pour or early pour of the aluminothermic portion can also cause slag inclusions 3.3 Weld shrinkage or tearing Weld shrinkage or tearing are the same type of defect and generally occurs in the weld foot area as this is the last portion of the weld to solidify as shown in figure 2 Figure 2 Weld shrinkage/tearing The causes of shrinkage /tearing are due to one or more of the following: Insufficient pre heat prior to welding; Slip on the tensor jaws; Not using tensors or poor set up of the tensors; Other work on track causing undue stresses on cooling welds; Change in temperature can cause stress on solidifying welds; Unclamping of the aluminothermic weld before solidification is complete; Passing of traffic while the weld is still too hot. The weld should be allowed to cool down to below 350 o C to allow it to develop sufficient strength before any loads are applied. Hot tensile tests have shown that approximately 80 % of the strength is developed at 350 o C. Thermocouple measurements have shown that for welds to cool down to below 350 o C takes approximately 24 minutes. Page 2 of 5

3.4 Sand Burns Sand burns occur on the rail surface where luting sand has come in contact with the preheating flame or the pouring steel. The sand is heated to temperature where vitrification of the luting material takes place and marks are burned into the surface of the rail. These defects are normally removed during the grinding operation. Figure 3 shows sand burns remaining after the weld has been ground. In some cases repair welding may be required Figure 3 Sand burns on ground rail surface 3.5 Lack of Fusion Lack of fusion occurs when the weld fails to fuse into one side or part of the rail as shown in figure 4 LOF defect Figure 4 Lack of fusion in the rail foot Page 3 of 5

Lack of fusion defects can result from any one or a combination of the following causes: Mould misalignment; Cold pour or late pour; Inadequate preheat of the joint; Poor burner alignment causing uneven preheating of the two rail ends; Incorrect gas pressures on the pre heater; Incorrect weld gap; Incorrect portion size for the size of rail; Incorrect mould size being used on the joint. 3.6 Mould misalignment Mould misalignment can case the weld to not fuse in one or more areas of the rail and figure 5 shows an area where the rail foot has not been incorporated into the weld (the original flame cut surface can still be seen) Figure 5. Total lack of fusion at rail foot due to mould misalignment Mould misalignment is due to poor set up, location and fitting of the moulds on the joint. It is essential that the moulds are aligned vertically and are centered on the weld centre line. 3.7 Flashing or finning of the welds Flashing or finning of aluminothermic welds is where molten metal flows between the mould and the rail and forms a fin or flash as shown in figure 6. It is often not considered as a serious defect, however latest experience has shown that particularly on heavy haul track with high axle loads, a large number of rapid failures have resulted from these defects. Finning Figure 6. Flashing/finning at the weld edges on the rail foot Page 4 of 5

3.8 Porosity Porosity is mainly located within the weld and is often not visible on the outer surface of the weld. Particularly when a large number of pores are present (as shown in figure 7), the strength of the weld can be significantly reduced. Figure 7. Gross porosity in the weld Porosity in aluminothermic welds is caused by any one or more of the following factors: Inadequate or no preheating of the crucible in multi use crucibles; Wet luting material; Insufficient preheat of the joint; Wrong portion size for the rail size; Wet or contaminated moulds; Welding in the rain. 4.0 Conclusion If aluminothermic welders are properly trained and qualified, and the necessary care and attention is followed with welds being done rigorously to the procedure, weld defects can be eliminated. This will significantly increase the reliability of aluminothermic welding and can reduce the need for subsequent non-destructive testing. Avoidance of weld defects provides numerous advantages: Elimination of costly field repairs; Increased integrity of track; Reduced incidences of track failures. DISCLAIMER: While every effort has been made and all reasonable care taken to ensure the accuracy of the material contained herein, the authors, editors and publishers of this publication shall not be held to be liable or responsible in any way whatsoever and expressly disclaim any liability or responsibility for any injury or loss of life, any loss or damage costs or expenses, howsoever incurred by any person whether the reader of this work or otherwise including but without in any way limiting any loss or damage costs or expenses incurred as a result of or in connection with the reliance whether whole or partial by any person as aforesaid upon any part of the contents of this publication. Should expert assistance be required, the services of a competent professional person should be sought. PO Box 6165, Silverwater NSW 1811 Unit 50, 8 The Avenue of the Americas, Newington NSW 2127 Ph: +61 (0) 2 9748 4443 Fx: +61 (0) 2 9748 2858 Email: info@wtia.com.au Webpage: www.wtia.com.au Page 5 of 5

NDNP TECHNOLOGY DIFFUSION ACTIVITY # 27 ABN 69 003 696 526 NATIONAL DIFFUSION NETWORKS PROJECT TECHNOLOGY QUESTIONNAIRE Rail Group Aluminothermic Weld Defects Document No: 9.4.1 Revision No: Rev 0 Page 1 of 2 Date: 30 may 2005 1 As part of the WTIA National Diffusion Networks Project the Rail Industry Sector has identified the need for reducing aluminothermic weld defects. The WTIA has prepared a Technical Guidance Note Aluminothermic Weld Defects that explains how to produce sound welds and eliminate weld repairs. As a valued technology expert in this area we would like you to be part of the Technology Expert Group to review this note. Please complete this questionnaire so that we can gauge the success of meeting this need. Objective 1: Identify the need for quality cutting of rail. Aluminothermic welding is a standard method for joining rail. Weld defects do occur from time to time and this guidance note is intended to provide the Rail Industry with information on producing sound aluminothermic welds without defects. How well does the document achieve these aims? poor average good very good Comments: Objective 2: Identify appropriate technology receptors This document was written for Maintenance Engineers, Maintenance Contractors and Welding Coordinators in the Rail Industry. Are these people the appropriate individuals we should be targeting? yes no What other types of companies and/or personnel do you suggest we target? Objective 3: Identify current best practice for cutting rail The document was written to reflect current best practice for avoiding defects in aluminothermic welds. Do you envisage opportunities for the use of this practice in industry? yes no If yes, what and where, if no why not? Objective 4: Is the information provided clear, concise and accurate? yes no If not, why? Objective 5: Broad dissemination of technology to the Rail Industry Please indicate how best to disseminate this Technical Guidance Note to the appropriate Industry Recipients Free Website Download Poster Pocket Guide Pamphlet If poster, what size? A1 A2 A3 Laminated What selling price? $ If a pocket guide, what selling price? $ Other format? G:\USERS\guidance-notes\Questionnaires\R04 Aluminothermic weld defects Questionnaire.doc

NDNP TECHNOLOGY DIFFUSION ACTIVITY # 27 ABN 69 003 696 526 NATIONAL DIFFUSION NETWORKS PROJECT TECHNOLOGY QUESTIONNAIRE Rail Group Aluminothermic Weld Defects Document No: 9.4.1 Revision No: Rev 0 Page 2 of 2 Date: 30 may 2005 2 Objective 6: Continuous Improvement Please Identify areas where the document can be improved or return the document with your recommended additions/amendments. Alternatively, please use the area below to provide any additional comments. Respondents Name: Company: Phone: Fax: Email: Date: Please Fax (02 9748 2858) or E-mail (info@wtia.com.au) with your response. The WTIA has joined forces with industry and government to create a 3.5 million dollar Technology Support Centres Network. This network will assist industry to identify and exploit world s best technology and manufacturing methods to establish a vibrant Australian industry beyond 2006. Together we will be implementing a step by step process which will lead to ongoing viability and greater profitability for all concerned: (1) Determine your technological and manufacturing needs; (2) Identify world s best practice; (3) Draw upon the network to implement world s best practice at your site G:\USERS\guidance-notes\Questionnaires\R04 Aluminothermic weld defects Questionnaire.doc