Title Requirements for Work Using Cranes and Plant. Reference Number PMP 04 - (RIC Standard: EP SI)

Similar documents
Title Overview of the Australian Rail Track Corporation Electric Power System Safe Operation Manual

Title Public Electrical Safety Awareness Plan. Reference Number PSP 02 - (RIC Standard: EP SP)

Status Date Prepared Reviewed Endorsed Approved

Title Transmission Line Base Safety and Operating Standards. Reference Number POS 01 - (RIC Standard: EP SP)

Title Transmission Line Maintenance Standards. Reference Number PMP 17 - (RIC Standard: EP SP)

Reference Number PCS 03 - (RIC Standard: EP SP)

Title Cables for Railway Signalling Applications - Traction Return Bonding and Track Connection Cables

Leasing of Railway Land

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Field Instruction. Any part of a person (body). Any conducting object, tool or equipment being held or carried.

Automatic Equipment Identification (AEI) WOS 01.H

Civil Engineering Technical Requirement CIVIL-SR-008 PROTECTION SCREENS. Revision: 3 Updated: 13/01/2017

Performance Measures for Track and Civil Infrastructure

Working of Passenger Trains over Non- Passenger Lines

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 22 kv, SINGLE CORE, 95mm 2 COPPER

Persons Working On or Near to AC Electrified Lines

Microgeneration Installation Standard MIS 3006

L1-CHE-SPE-171 TECHNICAL SPECIFICATION FOR ELECTRIC CABLE

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED WITH METALLIC SCREEN

Engineering Recommendation G39 Issue

Microgeneration Installation Standard MIS 3006

ARCHITECTUS FEBRUARY 2010

Electricity Safety (Electric Line Clearance) Regulations 2010

ALO (Any line open) Knowledge Briefing OTPS LNE&EM

L1-CHE-SPE-294 CONNECTORS FOR SIGNALLING INTERFACE

Microgeneration Installation Standard: MIS 3003

L1-CHE-SPE-302 GENERAL REQUIREMENTS FOR LABELLING OF SIGNALLING EQUIPMENT

MTM REQUIREMENTS SPARES FOR NEW ASSETS

Engineering Instruction

Infrastructure Based Train Detection Interface Requirements

Pilot Staff Notice (PSN)

Title Power Supply Units for Signalling Equipment - General Requirements. Reference Number SPS 22 - (RIC Standard: SC SP)

Cranes and Derricks Standard Summary. April, 2010

Testing Railway Safety Critical Workers for Drugs and Alcohol

Memorandum of Understanding

TruckSafe Operator Business Rules and Code of Conduct

Assessment of Compatibility of Rolling Stock and Infrastructure Gauging and Stepping Distances

L1-CHE-SPE-272 TWISTED 6 PAIR COPPER SIGNALLING CABLE 7/0.50 MM

香港電燈有限公司 THE HONGKONG ELECTRIC CO., LTD. ************************************

L1-CHE-SPE-300 BATTERIES FOR RAILWAY SIGNALLING APPLICATIONS

Basic ALO knowledge Briefing. RRV Safety Improvement Programme

Critical Elements from the Arrium Codes of Practice (Including Arrium Mining Codes of Practice)

Applying for Signals Competency

A GUIDE TO WRITING GOOD GOVERNANCE RULES

Air Quality and Lighting Environment for Traincrew Inside Railway Vehicles

Services for professional procurement. Be better informed, make better decisions. RISQS Audit Questions Network Rail On-Track Plant Operations

Microgeneration Installation Standard

HYDRO AND ELECTRIC ENERGY REGULATION

General Accreditation Criteria Equipment assurance, in-house calibration and equipment verification

L1-CHE-SPE-304 AC SHELF RELAYS

IMAS First Edition 01 October 2001 Incorporating amendment number(s) 1

DIVISION 9 TRAM TECHNICAL

Safety: Role of a. Safety Observer. 30 th March th MARCH 2011 ISSUE 3 UNCLASSIFIED UNCONTROLLED COPY IF PRINTED

ISO INTERNATIONAL STANDARD. Cranes Safe use Part 3: Tower cranes

Provision of information and signs for access on the railway

Rail Safety Management Procedure General Engineering and Operational Systems Railway Track Signals - Detonators

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

22.1 ISSUES OBJECTIVES POLICIES RULES PERFORMANCE STANDARDS 10

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Electrical Networks Principles and Performance

4. GENERAL REQUIREMENTS

IDENTIFICATION AND MANAGEMENT OF HAZARDS

Safe tree working in proximity to overhead electric lines

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash

RIBA Overhead Line Structures Competition Questions and Answers

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 70mm 2 FLEXIBLE TINNED COPPER CONDUCTOR 3.3kV EPR INSULATED WITHOUT METALLIC SCREEN

Project Management Rail Safety Worker Competence

Microgeneration Installation Standard: MIS 3002

Terminal Tracks - Managing the Risk

DESIGN OF ROAD OVERBRIDGES

RISQS Audit Protocol. Plant Operations Scheme. Document no.: RISQS-AP-004. Plant Operations Scheme

Transmission Substation Field Instructions

Signals Staff Competency Assessment

RIS RIS-1800-ENE. Rail Industry Standard for Network and Depot Interface Management Isolation Documentation. Rail Industry Standard

4. GENERAL REQUIREMENTS

General Terms and Conditions of Alfons W. Gentner Verlag GmbH und Co. KG for Advertising in Online Media

Inspection and Testing of Signalling Plans, Programs, Documentation and Packages

WMTS-051:2016 Bidet douche seats

Construction Safety Education Forum. 6 March Scaffolding. Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT

Document Revision Change Table Revision Number

Document B252TM 2007

Palmerston North City Council District Plan May 2018 NETWORK UTILITIES Introduction Resource Management Issues 2

SAFE WORKPLACE PROCEDURE No. 222 WORKING NEAR OVERHEAD & UNDERGROUND SERVICES

Plant within the Rail Corridor

Skills and Training Guideline

MATERIAL STANDARD FOR GANTRY AND OVERHEAD CRANES ORIGINAL EDITION MAY. 1997

PROJECT: SUPPLY TO BERRY ROAD APARTMENT - SUVA SCHEME: G43-13

Specifications for Top Running & Under Running Single Girder Electric Traveling Cranes Utilizing Under Running Trolley Hoist

CONTROL OF ON-SITE WASTEWATER DISPOSAL SYSTEMS

Re: Appointment as Independent Director.

Operate a dozer (wheeled and tracked)

Assessment of Route Compatibility of Vehicles and Infrastructure

Incident Response Planning & Management

Procedure: Safety Management System Procedure - My Safety

Version # Date Reviewed Prepared by Reviewed by Endorsed Approved. Description of Amendment

Health and safety representatives

MTSP MANUFACTURE AND SUPPLY OF INSULATED RAIL JOINTS

Concrete Sleepers - Design

Schedule 3 MEMORANDUM of UNDERSTANDING SafeWork NSW INSPECTORS

Service Suppliers Performing Tightness Testing of Hatches With Ultrasonic Equipment on Ships, High Speed and Light Craft and Mobile Offshore Units

Transcription:

Discipline Engineering Standard - NSW Category Electrical Title Reference Number PMP 04 - (RIC Standard: EP 95 00 00 03 SI) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards and Systems Refer to Reference Number Signalling Standards Engineer T Moore GM Infrastructure Strategy & Performance M Owens Safety Committee Refer to minutes of meeting 24/01/05

Disclaimer Australian Rail Track Corporation has used its best endeavors to ensure that the content, layout and text of this document is accurate, complete and suitable for its stated purpose. It makes no warranties, express or implied, that compliance with the contents of this document shall be sufficient to ensure safe systems of work or operation. Australian Rail Track Corporation will not be liable to pay compensation in respect of the content or subsequent use of this document for any other purpose than its stated purpose or for any purpose other than that for which it was prepared except where it can be shown to have acted in bad faith or there has been willful default. Document Approval The technical content of this document has been approved by the relevant ARTC engineering authority and has also been endorsed by the ARTC Safety Committee. Document Supply and Control The Primary Version of this document is the electronic version that is available and accessible on the Australian Rail Track Corporation Internet and Intranet website. It is the document user s sole responsibility to ensure that copies are checked for curency against the Primary Version prior to its use. Copyright The information in this document is Copyright protected. Apart from the reproduction without alteration of this document for personal use, non-profit purposes or for any fair dealing as permitted under the Copyright Act 1968, no part of this document may be reproduced, altered, stored or transmitted by any person without the prior written consent of ARTC. March 2005 Page 2 of 10

About This Standard The working of cranes and plant near overhead lines, whether exposed or insulated, or near other exposed electrical equipment, is regulated by the Construction Safety Regulation 133A. As a Network Operator, ARTC and its contractors are able to utilize an exemption certificate issued by WorkCover. This exemption permits approach to closer distances when additional controls are put in place. March 2005 Page 3 of 10

Document History Primary Source RIC Standard EP 95 00 00 03 SI Version 1.1 List of Amendments ISSUE DATE CLAUSE DESCRIPTION 1.1 11/03/2005 Disclaimer Minor editorial change March 2005 Page 4 of 10

Contents About This Standard...3 Document History...4 1. Safe Working Distances...6 2. Where Approach is not Closer than Prescribed Safe Working Distances...7 2.1. General...7 2.2. Working to Regulation 133A without exemption certificate...7 2.3. Measures To Be Taken...7 3. Where Approach is within the Prescribed Safe Working Distances...8 3.1. Permit Requirements...8 3.2. Persons to Sign Onto Permits...8 3.3. Travelling...8 3.4. On Rail Plant...8 4. Exemption Certificate 5099...9 4.1. General...9 4.2. Application...9 4.3. Compliance...9 4.4. Minimum Approach Distances of Cranes, Plant and Loads...10 March 2005 Page 5 of 10

1. Safe Working Distances Special electrical Safe Working Distances apply to cranes and plant and these are set out in Table 1. These distances are generally larger than the normal electrical Safe Working Distances for personnel and must be applied in accordance with the conditions described in sections 2, 3, and 4. If the crane or plant is operated in accordance with exemption certificate 5099 then the electrical Safe Working Distance required to exposed electrical equipment is reduced to that shown in Column D, E, F, or G of Table 1 as appropriate. A summary of the requirements of exemption certificate 5099 is set out in section 4. MINIMUM APPROACH DISTANCES OF CRANES AND PLANT TO LIVE ELECTRICAL APPARATUS A B C D E F G NOMINAL VOLTAGE PACKED UP FOR TRAVELLING MINIMUM APPROACH DISTANCE IN METRES WORKING UNDER REGULATION 133 A WORKING UNDER EXEMPTION 5099 USING AN OBSERVER OR LIMITING DEVICE WORKING UNDER EXEMPTION 5099 WITHOUT AN OBSERVER ELECTRICAL WORK NON- ELECTRICAL WORK ELECTRICAL WORK NON- ELECTRICAL WORK Up to 650V 1.1 3.0 0.5 1.0 1.0 No reduction 1500V dc only ** 1.0 3.0 0.7 1.0 1.4 from Above 650V but not exceeding 11kV ** Above 11 kv but not exceeding 66kV Above 66kV but not exceeding 132kV Above 132kV but not exceeding 220kV Above 220kV but not exceeding 330kV 2.3 3.0 0.7 1.2 1.4 requirement of 2.3 3.0 1.0 1.5 2.0 Regulation 2.3 3.0 1.5 2.0 3.0 133A 3.6 6.0 2.5 3.0 5.0-3.6 6.0 3.0 3.5 6.0 Refer Above 330kV 4.6 8.0 4.0 4.5 8.0 Column C ** 1500V dc is treated as a separate case. WARNING: Table 1 Table 1 does not imply that it is always safe to work up to these distances of exposed electrical equipment. An additional distance should be added if indicated by the terrain, prevailing weather or functional behaviour of the appliance. March 2005 Page 6 of 10

2. Where Approach is not Closer than Prescribed Safe Working Distances 2.1. General Clauses 2.2 and 2.3 are a summary of the requirements of Regulation 133A. For further details refer to the full text of the Regulation. 2.2. Working to Regulation 133A without exemption certificate When working without any exemption, Regulation 133A under the Construction Safety Act requires that no part of any crane or plant be permitted to come within the electrical Safe Working Distances in Column C of Table 1 from exposed electrical equipment. 2.3. Measures To Be Taken If it is reasonably foreseeable that the crane or plant may approach to the prescribed Safe Working Distance of exposed electrical equipment, appropriate measures must be taken to prevent any part of the crane or plant coming within that distance, and a person other than the driver or operator of the crane or plant must: observe the position of the crane or plant in relation to the exposed equipment, and warn the driver of the crane or plant of the proximity of the crane or plant to the exposed equipment in sufficient time to enable the driver to prevent the crane or plant coming near the exposed equipment. March 2005 Page 7 of 10

3. Where Approach is within the Prescribed Safe Working Distances 3.1. Permit Requirements A Permit must be obtained when it is foreseeable that a crane or an item of plant will be required to, or might inadvertently, come within the prescribed safe working distances of exposed electrical equipment. 3.2. Persons to Sign Onto Permits Where a Permit is required for the work, each crane or plant operator must sign onto the Permit. In the case of a crane, each dogman and/or chaser must also sign onto the Permit. 3.3. Travelling When correctly packed up for travelling, a crane or plant may approach to the distances in column B of Table 1 from exposed electrical equipment for the purpose of travelling under overhead lines. When correctly packed up for travelling on rail, cranes or plant must be within the rolling stock gauge. Other electrical clearance provisions do not apply. 3.4. On Rail Plant Where a plant item is: rail mounted, and does not include any component that can be positioned such that it would infringe the rolling stock gauge above the plant, the electrical Safe Working Distance required to exposed electrical equipment above the plant is that clearance distance provided by the rolling stock gauge. March 2005 Page 8 of 10

4. Exemption Certificate 5099 4.1. General Exemption Certificate 5099 permits work to be carried out closer to exposed electrical equipment than the distances prescribed in Regulation 133A. The following Clauses are a summary of the requirements of Exemption Certificate No 5099. For further details refer to the full text of the Exemption Certificate. 4.2. Application The Exemption applies to work carried out by or on behalf of an organisation listed in Schedule 1 of the Exemption, when the work comprises: Electrical work Work on or connected with the construction, erection, maintenance, adjustment or dismantling of electrical installations, Railway Signalling Electric Systems, public lighting, electric substations, high voltage areas, switchyards, electrical transmission, distribution or railway traction systems and includes trimming of trees near electrical apparatus (Refer Column D of Table 1). Non-electrical work Work not directly connected with electrical systems or apparatus such as building work, landscaping, landfill work, excavations, road work and includes the construction, maintenance, adjustment or dismantling of railway track systems and drainage, sewerage and water supply systems (Refer Column E of Table 1). 4.3. Compliance Any crane, load or plant which is at rest, travelling or in motion in accordance with the exemption certificate must comply with the conditions of the exemption certificate and in particular:- The owner of the crane or plant and the person having immediate control of the operation of the crane or plant, must ensure that the relevant provisions of the certificate are complied with and in any case must not hinder, obstruct or attempt to prevent the provisions of the certificate being complied with. The safety observer and the operator of the crane or plant must exercise due diligence to ensure that the relevant provisions of the certificate are complied with. A person or an organisation requesting or approving work under contract, by agreement or otherwise shall as far as is practicable ensure that the relevant provisions of the certificate are complied with and in any case shall not hinder, obstruct or attempt to prevent the provisions of the certificate being complied with. March 2005 Page 9 of 10

4.4. Minimum Approach Distances of Cranes, Plant and Loads Except where effective insulation is provided in accordance with the certificate, and where required under Clause 3 of the certificate approval has been granted, cranes, loads, plant and component parts shall not approach closer to live electrical apparatus than the minimum approach distances appropriate to the voltage provided in Columns D or E of Table 1. A safety observer required under Clause 7 of the certificate must be appointed at any time the crane, plant or load is in motion and is likely to move within the distances provided in Column C, F or G of Table 1. A safety observer is no longer required after an effective limiting device has been set to prevent any component part of a crane, plant or load approaching closer than the minimum approach distances in Columns B, D or E of Table 1 provided that the limiting device is effective under stress conditions and the limiting device is inspected and tested at regular intervals. Where, by virtue of the design of the crane or plant, no component part of the crane or plant, or the load, can approach closer than the minimum approach distances in Columns B, D or E of Table 1, the crane or plant may be operated on the same basis as a crane or plant fitted with a limiting device. Clause 3 of the certificate provides for closer approach. This facility shall not be utilised unless a written waiver to this document is obtained. March 2005 Page 10 of 10