SUMMARY SHEETS OF GROUTED DUCT CONNECTIONS

Similar documents
SUMMARY SHEETS OF HYBRID CONNECTIONS

SUMMARY SHEETS OF INTEGRAL CONNECTIONS

A precast Concrete Bridge Bent for Seismic Regions: Achieving both Performance and Constructability

NCHRP Project Michael Culmo, PE CME Associates, Inc.

Accelerated Bridge Construction Developments on the Earthquake Frontier

APPENDIX G SUMMARY SHEETS OF EMERGING TECHNOLOGY AND DEFORMABLE ELEMENT CONNECTIONS

Rapidly Constructible Large-Bar Precast Bridge-Bent Seismic Connection

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

ACCELERATED BRIDGE CONSTRUCTION IN WASHINGTON STATE FROM RESEARCH TO PRACTICE

HIGHWAYS FOR LIFE PROJECTS AND ACCELERATED BRIDGE CONSTRUCTION IN WASHINGTON STATE

Quasi-static cyclic tests of Emulative Precast Segmental Bridge Piers (E-PSBP)

Seismic Performance of Precast Concrete Bents used for Accelerated Bridge Construction. Bijan Khaleghi 1

20. Security Classif. (of this page) Unclassified

ABC-UTC. Research Progress Report (Feasibility Study) Title: Alternative ABC Connections Utilizing UHPC. March, 2017

Quasi-static cyclic testing of half-scale fully precast bridge substructure system in high seismicity

Bijan Khaleghi, Ph, D. P.E., S.E.

PRECAST CONCRETE CONNECTIONS - US PRACTICE

Special Requirements for Precast Bent Cap Connections C General

SEISMIC PERFORMANCE AND RETROFIT OF BRIDGE FOOTINGS. David I. McLean 1

Accelerated Bridge Construction in USA

SUITABILITY OF BRIDGE MADE WITH PRECAST COMPONENTS IN AREAS OF HIGH OR MODERATE SEISMISITY. Bijan Khaleghi 1

Chapter 2 Notation and Terminology

PRECAST CONCRETE CONNECTIONS FOR ACCELERATED BRIDGE CONSTRUCTION IN REGIONS OF HIGH SEISMICITY

QUASI-STATIC CYCLIC TESTS OF HALF-SCALE FULLY PRECAST BRIDGE BENTS INCORPORATING EMULATIVE AND POST- TENSIONED LOW DAMAGE SOLUTIONS

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

Connections between precast girders and cap beam

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

Title. Author(s)KIM, D. W.; SHIM, C. S. Issue Date Doc URL. Type. Note. File Information

Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

EXPERIMENTAL TESTING OF EMULATIVE FULLY PRECAST CONCRETE BRIDGE BENT IN SEISMIC REGIONS

In-plane testing of precast concrete wall panels with grouted sleeve

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:

Florida DOT efforts toward improving Post Tension Durability

Disaster Risk Management, National Institute for Land and Infrastructure Management (NILIM)

New Development in Accelerated Bridge Design and Construction in WA

MPC-545 November 15, 2017

Precast Bent Cap Systems: Non Non--Integral Integral GSC Bolted GP/CP

Why high seismic zone matters?

FEBRUARY 2019 LRFD BRIDGE DESIGN 5-1

Concrete Framing Systems - Walls and Columns

A PRE-TENSIONED, ROCKING BRIDGE BENT FOR ABC IN SEISMIC REGIONS.

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

PRECAST PIERS WITH GROUTED SPLICE SLEEVE CONNECTIONS FOR ACCELERATED BRIDGE CONSTRUCTION IN SEISMIC ZONES

DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY

The following excerpt are pages from the Hilti North America Post- Installed Reinforcing Bar Guide.

SEISMIC RETROFIT OF BEAMS IN BUILDINGS FOR FLEXURE USING CONCRETE JACKETING

Bridge reinforced concrete column limit state definition

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

PACIFIC EARTHQUAKE ENGINEERING RESEARCH CENTER

Self-Centering Bridge Piers with Structural Fuses

ANCHORAGE OF LARGE-DIAMETER REINFORCING BARS GROUTED INTO DUCTS

Revise Sections through of Part 1 of the 2009 Provisions as follows:

4.6 Procedures for Connections

CHAPTER 10: GENERAL STRUCTURAL DETAILS

ACI MANUAL OF CONCRETE PRACTICE-2009

Bridge PBEE Overview & Pilot Next Generation Bridge Studies

JULY 2014 LRFD BRIDGE DESIGN 5-1

PARTIAL-DEPTH PRECAST DECK PANEL DESIGN AND CONSTRUCTION IN TEXAS

TRANSPORTATION RESEARCH BOARD. Seismic Design and Accelerated Bridge Construction. Wednesday, July 11, :00-4:00 PM ET

Joint Design of Precast Concrete Moment Frame using Hollow Precast Concrete Column Soo-Yeon Seo, Tae-Wan Kim, Jong-Wook Lim, Jae-Yup Kim

SECTION REINFORCING STEEL

Ductility of Welded Steel Column to Cap Beam Connections Phase 2

SECTION TILT-UP PRECAST CONCRETE. A. Work includes, but is not limited to, the following:

MPC-405 January 1, 2012 December 31,2012

Two integral girder connections for precast concrete bridges in seismic regions utilizing extended prestressing strands

Sabah Shawkat Cabinet of Structural Engineering 2017

DESIGN AND CONSTRUCTION OF HEAVY INDUSTRIAL ANCHORAGE FOR POWER-PLANTS

Unbonded Prestressed Columns for Earthquake Resistance

Section REINFORCING STEEL

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1

BS EN :2004 EN :2004 (E)

SECTION 415 REINFORCING FOR CONCRETE

LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE. Mark S. Mahan 1

CSU GUIDELINES. April 27, 2018 FOR POST-TENSIONED CONCRETE STRUCTURES.

The fib state-of-the-art report on the seismic design of precast concrete building structures

SECTION H COLUMNS SUBJECTED TO FLEXURE AND AXIAL

EXECUTIVE SUMMARY POST-TENSIONING TENDON PROTECTION STRATEGIES FOR PRECAST ELEMENTS

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

Ironton Russell Bridge Project

Large-scale Cyclic Loading Test on a Multi-Spiral Stirrup Bridge Pier Constructed by Automated Method

Seven Wonders of the Ancient World

Post-EQK Damage Assessment of Bridges

ISU Spring Transportation Seminar Series April 1, Mark Mahan, PhD, P.E. Ron Bromenschenkel, P.E. California Department of Transportation

CONTINUITY OF PRECAST BRIDGE U-GIRDERS CONNECTED TO A CAST-IN-PLACE SUBSTRUCTURE SUBJECTED TO SEISMIC LOADS

Ductile Detailing for Earthquake Resistant R C Structures. Dr. S. K. PRASAD Professor of Civil Engineering S.J. College of Engineering Mysore

A Precast Concrete Bridge Bent Designed to Re-Center After an Earthquake

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

SEISMIC RETROFITTING OF REINFORCED CONCRETE COLUMNS USING CARBON FIBER REINFORCED POLYMER (CFRP)

CHAPTER 16 - GANTRIES

Lecture 13 CONCRETE WORKS

MPC-526 December 20, 2016

SUNSHINE SKYWAY BRIDGE

PACIFIC EARTHQUAKE ENGINEERING RESEARCH CENTER

Seismic Design and Retrofit. Reginald DesRoches Professor and Associate Chair Georgia Institute of Technology

Boeing North Bridge in Washington State

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

SEISMIC PERFORMANCE OF BRIDGE SLAB-COLUMN JOINTS WITH HEADED REINFORCEMENT

Pacific Earthquake Engineering Research Center

Transcription:

APPENDIX B SUMMARY SHEETS OF GROUTED DUCT CONNECTIONS

NCHRP 12-88 Connection Evaluations Appendix B B-1 APPENDIX B SUMMARY SHEETS OF GROUTED DUCT CONNECTIONS

NCHRP 12-88 Connection Evaluations Appendix B B-2 Location: Column to cap beam Type: Grouted Ducts: Column to precast Cap, ED Title: Connection GD-1 FHWA Connection Manual 3.1.1.1.B TRL: Maximum TRL: 3 Source: Texas DOT TRL Gaps: None

NCHRP 12-88 Connection Evaluations Appendix B B-3 BACKGROUND Title: Connection GD-1 (FHWA Connection Manual 3.1.1.1.B) History / Description: Vertical bars project from the columns. A pier cap with corrugated metal ducts aligned with the column bars is lowered over the columns. The ducts are grouted using cementitious grout. The ducts stop short of the top reinforcing steel in the bent cap. Connection built many times since 2003. A similar, but not identical, grouted duct connection was tested monotonically to failure under eccentric axial and small lateral load by Matsumoto et al. (2001). References: FHWA Connection Manual 3.1.1.1.B (Culmo 2009) Matsumoto et al. (2001) ; Brenes et al (2006) Contact Information: Lloyd M. Wolf, PE (Texas DOT) lwolf@dot.state.tx.us EVALUATION Constructability: Risk Value: -1 Seismic Performance: Inspectability: Value: -1 Durability: Time Saving Potential: Value: +2 TRL Comments: Additional Comments: Projecting bars need to be placed and aligned accurately. Here they are in the interior of the column, not tied to the spiral and need an alignment device. Difficult to align a large number of rebar in ducts, especially for multiple columns. Column capital requires separate concrete pour with joints above and below. Difficult to form and pressure grout the bedding layer above column. Effectiveness of the grouting vent system and bedding layer is questionable. Needs spirals around internal bars and ducts. Short load path. Critical joint shear issue. Deformation is concentrated at beam-column interface. Shows promise for low seismic zone use. Needs to be tested for cyclic lateral loading. Need to determine whether the bar splice in the plastic hinge zone performs adequately. Capital flare at top of column could spall off. Damage assessment post-earthquake will require dismantling a portion of the connection. With good quality grouting, durability is similar to that of CIP concrete. Precast cap beam saves considerable time over CIP cap beam.

NCHRP 12-88 Connection Evaluations Appendix B B-4 Location: Column to cap beam Type: Grouted Ducts: Precast column to precast cap, ED Title: Connection GD-2 Large Bars in Large Ducts TRL: Maximum TRL: 8 Source: University of Washington TRL Gaps: None

NCHRP 12-88 Connection Evaluations Appendix B B-5 BACKGROUND Title: Connection GD-2 (Large Bars in Large Ducts) History / Description: A small number of large diameter bars project from the column. The precast pier cap beam contains corrugated metal ducts that align with the column bars as it is lowered onto shim stacks in the bedding layer. The bedding layer and ducts are then grouted using cementitious grout poured from above the cap beam. The ducts extend through the full depth of the bent cap and the column bars extend into the CIP diaphragm above. The connection was developed in cooperation with the WSDOT, which used it to construct a freeway overpass in the autumn of 2010. Seismic performance tested at University of Washington. References: Pang et al.(2008,2010) Contact Information: Prof. John Stanton (University of Washington) stanton@u.washington.edu EVALUATION Constructability: Risk Small number of large bars in large ducts allows for easier alignment and generous tolerances, and facilitates erection and inspection of the grouting process. Seismic Performance: Anchorage of large bars in a short length demonstrated by Steuck et al. (2009). Deformations were concentrated at a single crack at the column-beam interface promoted by the additional column bars that stopped at the interface. The CIP reference specimen exhibited more distributed cracking over the column height. Design procedures should be developed to aid designers. Seismic response from tests emulative of CIP construction and performance. Inspectability: Durability: Time Saving Potential: Value: +2 TRL Comments: Inspectability post-earthquake is the same as for CIP construction. With good quality grouting, durability is similar to that of CIP concrete. Add a drip detail under the cap beam to provide protection against water ingress. Precast cap beam saves considerable time over CIP cap beam. Additional Comments: Steel congestion in the diaphragm, as shown in the San Mateo-Hayward Bridge Widening Project photograph, prevents the use of T-heads or hooks on the column bars. However, J bars could be lap spliced to column bars after the cap beam is placed.

NCHRP 12-88 Connection Evaluations Appendix B B-6 Location: Column to column Type: Grouted Ducts: Precast column to precast column, CP Title: Connection GD-3 Large Bars in Large Ducts TRL: Maximum TRL: 8 Source: University of Washington TRL Gaps: None

NCHRP 12-88 Connection Evaluations Appendix B B-7 BACKGROUND Title: Connection GD-3 (Large Bars in Large Ducts) History / Description: Large diameter bars in the lower portion of the column are anchored into grouted ducts in the upper portion of the column. The upper column contains a larger number of smaller diameter bars, which overlap with the grouted ducts. Seismic performance tested at University of Washington. First bridge is contracted to be constructed by the WSDOT in 2011, as a Highways for Life project. References: Haraldsson et al. (2010 Draft) Contact Information: Prof. John Stanton (University of Washington) stanton@u.washington.edu EVALUATION Constructability: Risk Small splice bars can be tied to ducts and spiral during fabrication. Interface and ducts were grouted separately in the lab. Experience with flowable grout suggested that they could be grouted in one operation. Complete grouting of grout layer and ducts is essential. Bleed holes allow inspection. Seismic Performance: Intended for use in capacity protected locations, not plastic hinge regions. Splice designed to transmit the yield strength of the column. Depends on lap splice of bars to ducts. Proprietary splice sleeves use butt-splice inside sleeve. Seismic response from tests emulative of CIP construction and performance. Inspectability: Inspectability post-earthquake is the same as for CIP construction. Durability: With good quality grouting, durability is similar to that of CIP concrete. Time Saving Potential: Time to construct precast column segments and connect with grouted splice is similar to forming, pouring and curing CIP column. TRL Comments: Additional Comments: Inspectability and durability similar to those of proprietary splice sleeves. Grout key in center of column may be unnecessary.

NCHRP 12-88 Connection Evaluations Appendix B B-8 Location: Column to cap beam Type: Grouted Ducts: Column to precast Cap, ED Title: Connection GD-4 FHWA Connection Manual 3.1.1.1.C TRL: Maximum TRL: 3 Source: Texas DOT TRL Gaps: None

NCHRP 12-88 Connection Evaluations Appendix B B-9 BACKGROUND Title: Connection GD-4 (FHWA Connection Manual 3.1.1.1.C) History / Description: Holes are drilled into the columns. Vertical bars are grouted into the holes and project upwards. Pier cap with ducts is lowered over the column. The ducts are grouted. Note that the ducts extend the full height of the bent cap. Lake Ray Hubbard Bridge article was written in 2002 A similar, but not identical, grouted duct connection was tested monotonically to failure under eccentric axial and small lateral load by Matsumoto, et al. (2001) References: FHWA Connection Manual 3.1.1.1.C (Culmo 2009) Matsumoto et al. (2001) ; Brenes et al. (2006) Contact Information: Lloyd M. Wolf, PE (Texas DOT) lwolf@dot.state.tx.us EVALUATION Constructability: Risk Value: -1 Drilling holes for embedding steel in columns allows bars to be aligned with ducts in cap beam and facilitates Inspectability, but adds an additional step on site. Need to roughen and clean out holes in column prior to grouting dowels. Need to form and pour or pressure grout the bedding layer grout pad. Grouting of dowels in the pier cap beam can be performed from the top. Seismic Performance: Inspectability: Value: -1 Durability: Time Saving Potential: Value: +2 Shows promise for seismic use. Needs to be tested for large cyclic lateral loading. Need to determine if the bar splice in the plastic hinge zone performs adequately. Deformation is concentrated in plastic hinge zone. Damage assessment post-earthquake will require dismantling a portion of the connection. With good quality grouting and site drilling, durability is similar to that of CIP concrete, assuming that tops of ducts are protected from water infiltration. Precast cap beam saves considerable time over CIP cap beam. TRL Comments: Additional Comments:

NCHRP 12-88 Connection Evaluations Appendix B B-10 Location: Column to foundation Type: Grouted Ducts: Aluminum PT ducts in precast column to connect bars Title: Connection GD-5 in footing, ED Ducts in Column TRL: Maximum TRL: 6 Source: University of Bergamo TRL Gaps: None

NCHRP 12-88 Connection Evaluations Appendix B B-11 BACKGROUND Title: Connection GD-5 (Ducts in Column) History / Description: Corrugated aluminum PT ducts are cast into the column. Reinforcing bars with hooked or straight anchorage are cast into the foundation and project from the top face. The column is placed onto the projecting bars. The bedding layer is formed and the ducts are filled with grout. This type of connection has been used in Italy to connect building columns to mat foundations. Seismic performance was tested at the University of Brescia, Italy. References: Riva (2006) Contact Information: Paolo Riva paolo.riva@unibg.it EVALUATION Constructability: Risk Value: -1 Seismic Performance: Inspectability: Foundation projecting bars need to be aligned accurately. Complete grouting of grout layer and ducts is essential. Bleed holes allow inspection. Difficult to assure that the grout layer is fully filled. Use of aluminum PT ducts is questionable due to corrosion in contact with concrete. Not clear if connection has been constructed in moderate to high seismic regions. Inspectability post-earthquake is the same as for CIP construction. Durability: Durability is similar to that of CIP concrete. Time Saving Potential: Value: +1 Time to form the bedding layer, set the column, and grout the ducts with cure time is similar to forming, pouring and curing CIP column. TRL Comments: Additional Comments: Research related to buildings with smaller scale columns, tested approximately 16 square columns with 7/8 or 1 diameter bars

NCHRP 12-88 Connection Evaluations Appendix B B-12 Location: Column to cap beam Type: Grouted Ducts: Corrugated steel ducts in cap beam anchoring bars Title: Connection GD-6 from column, ED All Column Bars in Ducts TRL: Maximum TRL: 7 Source: NCHRP 12-74 TRL Gaps: None

NCHRP 12-88 Connection Evaluations Appendix B B-13 BACKGROUND Title: Connection GD-6 (All Column Bars in Ducts) History / Description: The cap beam is cast with 1.75 diameter corrugated galvanized steel ducts. All of the vertical column reinforcing bars extend from the top of the column and are inserted into the ducts. A grout bed form is attached and the grout is pumped in from the bottom of the bedding layer, flowing upwards to fill the ducts. An air vent system in the top of the bedding layer assisted with prevention of air entrapment. Seismic performance was tested at CSU-Sacramento as part of NCHRP 12-74. References: Matsumoto (GD 2009), Restrepo et al. (2010 Draft) Contact Information: ematsumoto@csus.edu EVALUATION Constructability: Risk Value: -1 Seismic Performance: Inspectability: The large number of bars extending from the column into moderately sized ducts could be difficult to locate correctly and simultaneously align. A template is likely necessary. Need to form and pressure grout the bedding layer and ducts from the bottom. Inspection of grouting can be performed from the top of ducts. Seismic response from tests emulative of CIP construction and performance. Inspectability post-earthquake is the same as for CIP construction. Durability: Durability is similar to that of CIP concrete, assuming that tops of ducts are protected from water infiltration. Time Saving Potential: Value: +2 TRL Comments: Precast cap beam saves considerable time over CIP cap beam. Additional Comments: Spiral bars are required in the bedding layer to eliminate buckling of vertical bars. A similar connection was used in the SR 520 / SR 202 Bridge in Redmond, WA.

NCHRP 12-88 Connection Evaluations Appendix B B-14 Location: Pile to pile cap Type: Grouted Ducts: Precast pile cap connected to pile with adhesive Title: Connection GD-7 anchored bars in drilled holes, ED FHWA Connection Manual 3.1.1.4.D TRL: Maximum TRL: 3 Source: South Carolina DOT TRL Gaps: None

NCHRP 12-88 Connection Evaluations Appendix B B-15 BACKGROUND Title: Connection GD-7 (FHWA Connection Manual 3.1.1.4.D) History / Description: After pile driving, holes are drilled in a precast pile to align with bars projecting from a precast pile cap. The holes are filled with adhesive and the dowels are inserted. Foam board is provided around the perimeter of the recess in the pile cap. References: Culmo (2009) Contact Information: Barry Bowers (SCDOT) bowersbw@scdot.org EVALUATION Constructability: Risk Value: -1 Pile cap projecting bars need to be aligned accurately. Difficult to align multiple pile tops to match alignment of pile cap projecting bars. Difficult to inspect the adhesive bonding effectiveness. Seismic Performance: Value: -1 Inspectability: Value: -1 The unpredictability of final pile locations might require the holes for connection bars to be drilled eccentrically in the cross-section. This could adversely affect connection performance by non-uniformly loading the pile or having little cover over the drilled holes. Spirals should be present as close as possible to the drilled holes with inserted bars. A rotohammer should be used so that internal bars are not damaged. Determine if the bar splice in the plastic hinge zone performs adequately. Potential for use may be limited to low seismic regions. Damage assessment post-earthquake will require dismantling a portion of the connection. Durability: Durability is similar to that of CIP concrete. Time Saving Potential: Value: +1 Precast pile cap saves considerable time over CIP pile cap, assuming that very few adjustments in alignment of piles to pile cap bar projections are required. TRL Comments: Additional Comments: