Operability & Maintainability Analysis Technique Overview

Similar documents
ISOGATE A GLOBAL ISOLATION RISK MANAGEMENT DECISION SUPPORT PORTAL

TYREgate a Causal Factors Database and Risk Management Decision Making Support Tool for Earthmover Tyres and Rims

QAL 5 Year Environmental Improvement Program

EMESRT a Safety by Design initiative operated by the global mining industry 2006 to date

Building Effective Health and Safety Committees. C. Denise Bland Bowles, MOSE, CET Health and Safety Specialist AFSCME International

PROCEDURE FOR IDENTIFICATION OF ENVIRONMENTAL ASPECTS, HAZARDS, EVALUATION OF IMPACTS, RISKS AND DETERMINATION OF CONTROL MEASURES

APPENDIX 5 ENVIRONMENTAL IMPACT ASSESSMENT METHODOLOGY

HAZARD IDENTIFICATION AND ASSESSMENT

Using RISKGATE to shift industry s focus to control effectiveness

6 Risk assessment methodology

Asset Integrity Solutions. All-of-facility care for complete field life

Evaluation of Occupational Health & Safety Management System

At Revolution IT, one goal sets the tone for all our portfolio and project management: achieving strong investment returns for clients.

Vehicle Interaction Systems

The following steps are used to manage occupational health and safety risks.

Mine Health and Safety Council

TRANSPORT SAFETY. BUSINESS SWEDEN THE SWEDISH TRADE & INVEST COUNCIL 26 September 2013 UNCLASSIFIED

SAFE WORK METHOD STATEMENT/JSA WORKSHEET

Auckland Transport HS08-01 Safety In Design

NC Sturgeon Safety Management System

HAZARD IDENTIFICATION AND ASSESSMENT

Safe Work Method Statement. 14/4/16 Approved by (Snr Management Rep):

MANUFACTURING MODULE

ANNUAL NOISE MONITORING REPORT. Environmental Protection (Fimiston Gold Mine Noise Emissions) Approval 2016

LOADING UNLOADING OPERATIONS

Management of Risk Assessment

Fatality Prevention/Risk Management

HEALTH AND SAFETY POLICY AND PROCEDURES

1 AIM 2 4 REASON FOR INCLUSION 2 6 PLANT AND EQUIPMENT REQUIREMENTS 3 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6

Progress on the Industry-wide Buy and Maintain Quiet Initiative

Critical Elements from the Arrium Codes of Practice (Including Arrium Mining Codes of Practice)

Mobile Application Based Heavy Vehicle Fatigue Compliance in Australian Operations

Getting TPM & Lean / CI to Sustain using CTPM s Australasian approach

JOB SAFETY ANALYSIS (JSA) FOR. <Insert Organization Name> Adopted <Insert Date Policy Is Adopted> LC-442 Rev. 3/11

The Landmark Longwall Automation Project

SECTION II.3 DESIGNING USING VALUE MANAGEMENT

CS ENERGY PROCEDURE FOR A JOB SAFETY AND ENVIRONMENTAL ANALYSIS CS-OHS-11

Digital Value Chain Strategy Participant Input Summary

Comprehensive Regional Goods Movement Plan and Implementation Strategy Study Introduction and Overview

Pothole Patching / Edge Repair Work Instruction

Safety in the Matrix. Siemens AG All rights reserved.

C Manufacture of basic pharmaceutical products and pharmaceutical preparations (NACE II)

Operational Risk Management Policy

For personal use only

The OHS Body of Knowledge and Learning Outcomes

SAFETY CULTURE RESEARCH IN THE CONSTRUCTION SECTOR

JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) CS-OHS-11

Manufacturing Domain Health and Safety Manual

WORKGROUP-LEVEL OVERVIEW. What You Will Learn. What You Will Apply To Your Workgroup

MANUAL TASK RISK ASSESSMENTS

PS 02 PLANT AND EQUIPMENT

CPCCCM2010A Work safely at heights

OELG Event Categories

DOCUMENT CONTROL INFORMATION

OPITO DESKTOP AUDIT APPROVAL - GUIDANCE MATRIX FOR COMPETENCE MANAGEMENT SYSTEMS TO BE SUBMIITED WITH APPLICATION FORM

Version Date Author Change Description

Applying a quality systems approach to improve supply chain management

12. Environmental management

National Health and Safety Function, Workplace Health and Wellbeing Unit, National HR Division. Guideline Document

How to Develop a Safe Operating Procedure

SAFETY INTEGRITY LEVELS CONSIDERATIONS FOR NEW AND EXISTING ASSESSMENTS

SAFE WORK METHOD STATEMENT/JSA WORKSHEET

Asset Management Culture Change for Effective and Efficient Sewerage Service Delivery

Overview of Technical Skills and Competencies (TSC)

Evolution of International Paper s LIFE Initiative. John Williams Global Director, Occupational Heath & Safety

EMF Safety.

Employee Injured Back While Unloading Cylinders

EVALUATION FRAMEWORK 2017

TASC Training. Developed by Safety Partnership TASC SME Team

OPITO DESKTOP AUDIT APPROVAL - GUIDANCE MATRIX FOR COMPETENCE MANAGEMENT SYSTEMS TO BE SUBMIITED WITH APPLICATION FORM

Backhoe Boom Collapses Endangering Workers

Forklift Disposal Truck Near Collision

Facility Management Solutions

RAM MODELING AND ANALYSIS

Omron meets Pharma Milan, January 29 th Container Closure Integrity Testing (CCIT): a Risk Management Application

Electrical Junction Box Damaged by Clamp Truck

Safe Work Method Statement Perimeter and Balcony Fallguard (0003)

Risk Assessment (RA) in Maintenance Activities - A specialized methodology through a simplified approach GEORGE SCROUBELOS

ONRSR Guideline. Investigation Reports by Rail Transport Operators

Module 3 Assessing Climate Change Risk

Crushing and Screening Management Procedure Environment

Cristal Australia Pty Ltd

2 ConocoPhillips Health, Safety and Environmental Management System

Selective WIRTGEN Surface Mining in Australia. Changing of the guard in the coal mine

COPYRIGHTED MATERIAL 1 MANAGING THE STRATEGIC PLANNING PROCESS PURPOSE. Chapter Content

Implementing an Effective Personal Protective Equipment (PPE) Programme

Design and Analysis of Experiments

Optimizing asset management: Four key questions to help mining organizations align asset maintenance strategies with business objectives.

1. What is a key difference between an Affinity Diagram and other tools?

Hazard & Risk Assessment Procedure

FEBRUARY 2018 Human health and CSG development: a framework to investigate possible health effects

Apply for Working at Heights Permit

Gunlake Quarry. Air Quality Management Plan

RECENT REVIEW ON STANDARDS RELATED TO RISK ASSESSMENT FOR CONFINED SPACES

Section 32 Evaluation Report Business Mixed Use Zone (formerly the Business Zone) Contents

SECTION 1 - INTRODUCTION 2 PURPOSE 2 SCOPE 2 DEFINITIONS 2 LEGISLATIVE CONTEXT 4 RESPONSIBILITIES 4

Project Planning & Scheduling

2014 Mine Occupational and Safety Summit

Contents of the Failure Mode Effects Analysis the Plant Wellness Way Distance Education Course FMEA Training Online

Significant Service Contracts Framework

Transcription:

Operability & Maintainability Analysis Technique Overview October, 2009

Preface This document is intended to familiarise Original Equipment Manufacturers (OEMs) and Mine Site Users with the objectives and concepts of the Operability and Maintainability Analysis Technique (OMAT). It is not intended to provide detailed directions for the facilitation and implementation of OMAT. OMAT was developed by the Minerals Industry Safety and Health Centre (MISHC). This risk assessment technique was developed in alignment with the Earth Moving Equipment Safety Round Table (EMESRT) vision, specifically by providing processes for User Engagement and the application of the Design Philosophies. Trials involving Mine Site Users and OEMs were undertaken to refine and finalise the technique as part of a 2008 Australian Coal Association Research Program (ACARP) study entitled Identification of Priority Operability and Maintainability Issues and Potential Solutions Related to Large Surface Haul Trucks. Subsequently, the tool has been refined and implemented at various mine sites. 1

OMAT Introduction OMAT is a risk assessment technique, ideally performed by OEMs with the assistance of Mine Site Users. OMAT is a task-oriented process which systematically examines the health and safety risks imposed on operators and maintainers of mining and exploration equipment. This qualitative risk assessment technique distinguishes relative levels of risk to highlight the priority design concerns. Risk management practices are most effective when incorporated early in the equipment design life cycle. OMAT is a 6-step process that aligns with, and spans across, the OEM design milestones and ideally begins at the concept phase of the design process. A modified version of the OMAT can also be used at a mine site during operation or modification phases of existing equipment or to address any residual risks or site specific risks of newly purchased equipment. 2

Step 1: Critical Task Identification The first step of the OMAT process is the Critical Task Identification. This step should be completed early in the Design Phase, ideally in a joint OEM and User workshop. The User is defined as the operator, maintainer or other mine personnel with extensive experience with the equipment at a mine site. The OEM should include both factory engineers and field personnel. Critical Task Identification exposes the priority operability and maintainability tasks that warrant further investigation. This process begins by detailing all operation and maintenance tasks specific to the equipment being analysed. For each of these tasks, a Priority Score is determined by considering the impact of a less than adequate design using a list of key hazards/risks relevant to the scope of the OMAT. The EMESRT DPs were used to select the key hazards/risks for OMAT. The complete list of suggested OMAT key hazards/risks is below: EMESRT Design Philosophies Equipment Access and Egress Working at Heights Noise Whole-body Vibration Fire Dust, DPM, and other Airborne Hazards Isolation of Energy, inlcuding Parking Visibility, Collision Detection & Avoidance Machine Stability / Slope Indication Guarding Controls & Displays Tires & Rims Manual Handling Operator Workstation Confined Spaces OMAT Key Hazards & Risks 1. Slips / trips 2. Falls 3. Posture 4. Manual Handling 5. Moving Parts 6. Pressure Release 7. De-energising 8. Noise 9. Vibration 10. Dust 11. Confined Spaces 12. Contol / Display Error 13. Collision 14. Roll-over 15.Fire 3

The Priority Score is determined from a frequency-consequence matrix and the Total Priority Score is tallied for each task. The highest scored tasks should be further analysed in the OMAT. Ideally, all Catastrophic (5), Severe (4) and Serious (3) consequence tasks should be resolved. 4

Step 2: Task Flow Chart The second step involves the development of a task flow chart for each priority task flagged during the Critical Task Identification. This step should be completed early in the design life cycle, ideally in a joint OEM and User workshop. When constructing the task flow chart, each task should be divided into its individual discrete steps, as there may be different risks associated with each step. Important notes and observations should be documented as part of the risk assessment. In this step and subsequent steps, improved realism of task performance and equipment design enhances the risk assessment. 5

Step 3: Risk Identification Risk Identification is the third step of the OMAT process. This step should also be completed during the joint OEM and User workshop. The purpose of the Risk Identification is to uncover the possible risks in every step of the Task Flow Chart. The User s input is vital at this point to effectively identify all risks. The risks to be mitigated, which are outlined in the EMESRT design philosophies, can be reviewed to help identify the potential risks for each task step. For each unwanted event identified, the appropriate consequence and frequency is determined. The frequencies are broad enough to cover both operation and maintenance tasks. If the actual frequency falls between these preset frequency 6

values the assessor should be consistent in selecting either the closer value or the more conservative value. A score for the particular event will be generated from a frequency-consequence matrix to identify the highest priority task steps. This approach allows designers to systematically consider these risks in their design concepts. Using a brainstorming approach, the workshop team should now propose potential design solutions. The purpose is not to stipulate specific solutions, but rather to provide potential options for consideration by the OEM design engineers. These options may stimulate their thinking to create other innovative solutions or fundamental design changes. Next, the team should determine where on the Hierarchy of Controls the Suggested Solutions fit. The Hierarchy of Controls, sometimes called the Safety Precedence Sequence, considers hazards in terms of energy. There are many types of energies present on a mine site including chemical, electrical, mechanical, pressure, noise, gravity, thermal, and biomechanical. The best way to ensure the risk has been controlled is to design to eliminate the energy source. In order of effectiveness, the levels of the hierarchy used in OMAT are: Eliminate the energy source Substitute or minimise the energy source Implement a passive engineering control that does not require human involvement (example, kickboards) Implement an active engineering control that does require human involvement (example, tie off point for safety harness) Install a warning or alarm system Implement procedural controls, including personal protective equipment; and lastly and least effectively Awareness and competency controls 7

Step 4: Solution Options Step 4, Solution Options, also takes place early in the Design Phase. In addition to the User s Suggested Solutions from Step 3, further solutions to mitigate the risk can be provided by the OEM. Risks of the highest priority, as determined in step 3, will require more robust controls or a greater number of controls. When selecting appropriate controls it may be helpful to consider the EMESRT design philosophies section entitled industry attempts to mitigate risks. This section provides some examples of industry designs and mine site retrofits that have been implemented to eliminate or mitigate human factors risks associated with mining and exploration equipment. Another tool that can assist with selection of appropriate controls is the Minerals Industry Risk Management Gateway, known as MIRMgate (www.mirmgate.com/emesrt.asp). 8

Step 5: Feedback & Action Plan Step 5 is the Feedback & Action Plan. By means of a workshop, this step provides an opportunity for the Users to provide the OEMs with crucial feedback on the practical nature of the solutions. After solutions have been agreed by the OEM and Users, personal responsibility and an implementation date can be assigned. Additional controls may be identified as the design evolves and existing verification practices are applied. Any new controls should be added and tracked on the Action Plan. 9

Step 6: Equipment Risk Register Step 6, the final step, is the Equipment Risk Register. This step should be completed by the OEM in preparation for the hand-over before commissioning the equipment. The Equipment Risk Register compiles and summarizes all relevant information collected during the OMAT. It collates the results of the OMAT into a risk management document that outlines all the prioritised unwanted events/problems and the associated risks and controls for that particular piece of mining and exploration equipment. For OEMs the most useful information in the Equipment Risk Register is the detailed record of risk controls that have been investigated using the OMAT process. These controls may also be used as a reference for the development of future equipment models. Individual mine sites can also benefit from the information contained in the Equipment Risk Register, from both the implemented controls and identified residual risks. Ultimately, this comprehensive risk assessment process is intended to deliver mining and exploration equipment that will ensure the safety and well being of all operators and maintainers. 10