Minutes of the Third Meeting of the State Advisory Committee held 17 th June 2002 at hours.

Similar documents
Minutes of the Second Meeting of the State Advisory Committee held 18 th February 2002 at hours.

COMMERCIAL CIRCULAR NO.: 194.

NEW POLICY FOR POWER GENERATION FROM NON-CONVENTIONAL SOURCES OF ENERGY -2008

CASE No. 39 of Shri P. Subrahmanyam, Chairman Shri Jayant Deo, Member Dr Pramod Deo, Member O R D E R

(Draft Captive and Renewable Energy Generating Plants) Regulations

MADHU SHARMA University of Petroleum and Energy Studies, Dehradun, India

GOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No 1 Order Energy Deptt. letter no. F.

Chhattisgarh State Electricity Regulatory Commission

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

Case No. 89 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member

GOVERNMENT OF RAJASTHAN

Approach Paper on Methodology for computation of Cross-Subsidy Surcharge for Open Access transactions

Solar Power Policy Uttar Pradesh 2013

Comm/CP/NCE/Tariff/28362 Date: COMMERCIAL CIRCULAR No. 228

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR

Case No. 52 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member CLARIFICATORY ORDER

CASE Nos. 8/9/10/15/17/18/19/20/21 of In the matter of Purchase of power from Bagasse based Co-generation Projects, etc.

Jammu and Kashmir State Electricity Regulatory Commission

PROCEDURE FOR GRANT OF DISTRIBUTION OPEN ACCESS PERMISSION AS PER MERC (DISTRIBUTION OPEN ACCESS) REGULATIONS, 2014

Transmission Policy and Wind Energy

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR-34 A, CHANDIGARH

CE/Comm/CP/NCE/Tariff/6699 Date: COMMERCIAL CIRCULAR No. 260

Paper Presented on Renewable Energy Sources Policies of India. Author- Rucha Korhale

RE Tariff Setting Approach

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

G.O. Ms. No.48. i) Tariff determination ii) Allotment of Potential Sites iii) Wheeling Charges and allied issues

UTTARAKHAND STATE GOVT. POLICY FOR HARNESSING RENEWABLE ENERGY SOURCES

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

M.P. Electricity Regulatory Commission

Government of Gujarat Energy and Petrochemicals Department G.R. No.EDA B Sachivalaya, Gandhinagar. Dated the 25 July, 2013.

CASE No. 328 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM. PRESENT: Shri. C. Abdulla, Member Shri. M.P.Aiyappan, Member.

Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

GOVERNMENT OF ANDHRA PRADESH ABSTRACT

Case No. 35 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member

Discussion Paper On Harnessing Captive Power Generation in Karnataka

SMALL HYDRO PROGRAMME IN INDIA. Bhuwanesh Kumar Bhatt Ministry of New and Renewable Energy

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR ***** NOTIFICATION Dated the 30 th September, 2010

TAMIL NADU ELECTRICITY REGULATORY COMMISSION Comprehensive Tariff Order for Bagasse

Case No. 81 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member

Case No. 308 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member

ACCELERATED POWER DEVELOPMENT AND REFORM PROGRAMME IN INDIA

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO No , SECTOR 34-A, CHANDIGARH

Prasad Modak, Corporate Consultant (Environment and Infrastructure) Infrastructure Leasing and Financial Services Ltd.

Case No. 111 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member ORDER

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Order No.4 of 2015 dated

November Explanatory memorandum for CERC Regulations for implementation of REC mechanism in India

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

Renewable Energy Programmes in India

CENTRAL ELECTRICITY REGULATORY COMMISSION. New Delhi In exercise of powers conferred under Section 178 of the Electricity Act,

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR *********

ZAMBIA REFIT POLICY 2015 GENERAL OVERVIEW

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW. Petition no.493/07. IN THE MATTER OF: Tariff for supply of electricity and payment of bills.

ADDRESS BY MINISTER FOR ENERGY, DR. JOE OTENG-ADJEI

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Comprehensive Tariff Order for Biomass based Power Plants

Request for MNRE assistance for Biomass sector. Presented by: Indian Biomass Power Association

CASE No. 120 of And. Miscellaneous Application No. 16 of 2016

Biomass Power Generation: Prospects and Issues

Gujarat Electricity Regulatory Commission

Discussion Paper. Development of Renewable Energy Framework for Maharashtra For New Control Period (FY to FY )

IMPERATIVE FOR RENEWABLE ENERGY SOURCES AN INSIGHT INTO THE REGULATORY AND POLICY FRAMEWORK

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

Regulatory Framework PPAs and IPPs

National Stakeholders Workshop on Accessible and Affordable Sustainable Energy. Brief Report

Welcome to Presentation on Integration of RES to the WR grid. 02 nd Sept, 2015 Taj Lands End, Mumbai

Bihar Electricity Regulatory Commission Vidyut Bhawan-II, J.L. Nehru Marg, Patna

Emerging issues relating to RE grid integration beyond F&S regulations

No. CEjPPjNCEj RE Tariff jCommentsj18224 Date:

PRAYAS Initiatives in Health, Energy, Learning and Parenthood

State wise analysis of RPO Regulation for Captive users

Madhya Pradesh Electricity Regulatory Commission (Power Purchase and Procurement Process) Regulations, 2004, Revision 1, 2006 (RG-19(I) of 2006)

No. UPERC/Secy/VCA/ Dated: Public Notice

Uttar Pradesh Electricity Regulatory Commission. No. UPERC/Secy/Regulation/ Dated: 23 March, 2006

Uttar Pradesh Electricity Regulatory Commission

Overview of Indian Power Sector & Opportunities for for promoting Social Inclusion in Indian power sector

APPROACH PAPER DISTRIBUTED GENERATION BASED FRANCHISEE FOR ELECTRICITY DISTRIBUTION

PUBLISHED IN THE KOLKATA GAZETTE, EXTRA ORDINARY, PT.I DATED AUGUST 10, 2010 VIDE NO. WB (Part-I)/2010/SAR-460

Sanjay Upadhyay Advocate Supreme Court of India Enviro Legal Defence Firm April 2012

Comprehensive Tariff Order on WIND ENERGY

Amendment to Wind Power Policy Wind Power Policy

ISLAMIC REPUBLIC OF PAKISTAN

Sub: Comments on Draft National Renewable Energy Act", 2015

Report of the. Inter-Ministerial Task Force. Draft Port Regulatory Authority Bill

SUPPORT EXISTING FOR AND

Doncaster Council Home Energy Conservation Act (1995) 2013 Report

Grid connected Renewable Generators and Net-metering Amendment Policy

Published byauthority EXTRAORDINARY ISSUE TRIPURA ELECTRICITY REGULATORY COMMISSION NOTIFICATION OF

ASSAM ELECTRICITY REGULATORY COMMISSION

SMALL HYDRO PROGRAMME IN INDIA

Outline of the Revised Renewable Energy Act

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION

Streamlining and simplification of the administrative procedures for renewable energy projects

The British Hydropower Association (BHA) fundamentally disagrees with the ending of both the generation and export tariffs.

Malini V Shankar. Principal Secretary, Water Supply and Sanitation Department, Mumbai

ASIA CLEAN ENERGY FORUM

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

TERMS OF REFERENCE TOOLKIT FOR DEVELOPING POWER PURCHASE AGREEMENTS FOR RENEWABLE ENERGY GRID INTEGRATION FOR TRINIDAD AND TOBAGO

Transcription:

Minutes of the Third Meeting of the State Advisory Committee held 17 th June 2002 at 11.00 hours. The Chairman, MERC, welcomed all the distinguished Members of the SAC and requested them to initiate discussion on the Agenda items already circulated. 2. The Commission informed the SAC members about the present status of the bagasse based PPAs, which are undergoing scrutiny of the Commission. A public hearing was held on 11 th June 2002, and, after taking into consideration the views expressed by the co-generators, objectors, consumer representatives, GoM / MNES /MEDA, etc., the Commission desires to send its recommendations to the Government of Maharashtra for its consideration while framing the policy guidelines. Keeping this in mind, the Members of the SAC may contribute their valuable suggestions in the matter. 3. M/s ICRA, consultant of the MERC, made a detailed presentation [copy enclosed] covering the aspects of policy parameters, GoM policy directives and issues involved. The proposed PPAs can be divided into two groups (i) Existing: six projects whose PPAs are already in existence and as per the present policy, the purchase price, as on January 2002, would be Rs.2.60/kWh, and (ii) Advanced: nine projects where either substantial investment has been made or are in advanced stage of clearances for initiation. However, for these nine projects no PPA has been entered into. The rate is to be decided by the Commission, while approving the draft PPAs (six out of nine) surviving before the Commission at present. 4. Besides above 15 projects, the third category is of new projects (for which clearance u/s 44 by the MSEB is given) where PPAs would be entered into as per modified policy of the GoM, which is under reference to the Commission for comments and suggestions. 5. Copy of the presentation gives an overview of various issues. 6. On request of the Chairman, MERC to comment about any specific issue, which may not have been addressed in the presentation and present their views, the SAC Members continued with their opinion and comments. Response from the Government of Maharashtra (GoM) 7. The Principal Secretary (Energy), GoM stated that the draft policy guidelines has already been discussed and approved by the Cabinet and submitted before the Commission for its approval and, therefore, the Commission may take its own views in the matter. He further added that if any changes are to be made in the draft policy, the Commission may make its suggestion which will be placed for the Cabinet s approval later on. C:\Users\pravin.ganvir\Desktop\SAC\Minutes-Third Meeting (17.6.2002).doc - 1 -

Maharashtra Energy Development Agency (MEDA) 8. The Director General of Maharashtra Energy Development Agency (MEDA), the nodal agency for the non-conventional energy sources in the State of Maharashtra, also expressed his views on similar lines as that of the PS (Energy). However, after hearing other members' views/suggestions, he may like to react. BSES Limited. 9. Shri S.S. Dua, CMD of BSES Limited stated that he may be permitted to submit his comments in writing at a later date. He further suggested that it would be better if the utilities, either individually or collectively, adopt a taluka for distribution network on a pilot basis, which can be replicated to other areas subsequently. Vidarbha Industries Association (VIA). 10. Shri Goenka of Vidarbha Industries Association [consumer representative u/s 26 of the ERC Act 1998] stated that: The GoM policy should not be limited only to Bagasse based Co-generation Projects, but should also include other NRSE projects, including Industrial Co-generation (Waste Heat Recovery) projects. It should be made applicable to the entire State and all the licensees. There should not be differentiation between the old projects and the new projects in terms of application of Tariff. As far as the Evacuation Arrangement is concerned, the cost should be borne by the utility itself (as provided under IE Rule 27). However, he further clarified that as per the Condition No.5(a) of Model Conditions of Supply (Rule 27 of IE Rules 1956), the Board can collect certain refundable advance from the developer. Charging the entire amount to the consumer is totally incorrect. Regarding the 15% Supervision Charges, Shri Goenka opined that since the developer is actually financing and executing the project upto the point of grid synchronization, only labour portion may be charged instead of charging the entire cost. He further added that Conventional Pass-through should be allowed after detailed deliberations. The Transmission charges in case of third party sale should be computed on the basis of the actual transmission losses while the wheeling charges should be a singular number not as proposed by the MSEB on slab basis. There should not be any unreasonable penalty for Reactive Power (RkVH) and it should be frozen at 32% (equivalent to 0.95 power factor). If the Board is unable to accept delivery of electricity from the generators due to any problem in its network, then the Board should pay deemed generation charges. With regard to terms of payment, he was of the opinion that the Board should pay within a period of 30 days and for any delay thereafter, interest at Bank Advancing Rate may be made applicable. 11. Another important issue he pointed out was that the Board is not empowered to issue Conditional NOC under Section 44 of E (S) Act, 1948. According to the provisions under the Act, the Board has to issue consent to establish a new generating station in case the generation cost of the generator is less than the Board s tariff, and, therefore, issue of conditional NOC is unjustified. C:\Users\pravin.ganvir\Desktop\SAC\Minutes-Third Meeting (17.6.2002).doc - 2 -

12. Shri Goenka further pointed out that with the introduction of Electricity Reform Bill 2000 in the Lok Sabha and Maharashtra Electricity Reform Bill, the present scenario of captive power generation, cogeneration, sale of power to third party will undergo a radical change and, the electricity generation & distribution shall become a purely commercial activity. The State Regulatory Commission will be empowered to issue such sanctions & consents for Captive Power Plants. All the above relevant points must be kept in mind while deciding the upcoming policy formulations / guidelines. Nimbkar Agricultural Research Institute (NARI) 13. Dr Rajvanshi of Nimbkar Agril Institute opined that there should be a common GoM policy for all NRSE projects though the tariff rate could be changed from one source to another such as bagasse, biomass, solar, wind, etc. He further suggested that the terminology should be changed from Bagasse to Biomass based Power Projects since Bagasse is also a biomass fuel. In the background of tremendous power shortages / power cuts of about 4-5 hours/daily in the rural areas, he felt that we should not create any stumbling block, and, therefore, with certain amount of reasonable justice the NOCs, with minimum conditions, should be cleared for all power generation projects and projects to come up in Maharashtra. The policy could be reviewed after the gestation period of say 8-10 years of the project. He commented that the aim should be self-sufficiency of Rural Areas in both the field of Electricity Generation and Distribution. 14. Shri Dua of BSES commented that idea of Distributed Generation must be persuaded to make rural area self sufficient in Distribution. 15. CII submitted that there is a dire need to establish a long term policy and industrial co-generation must be component of such policy due to Energy Efficiency enhancement. Mumbai Grahak Panchayat (MGP) 16 Dr Ashok Pendse of Mumbai Grahak Panchayat stated that we could have certain common parameters with respect to banking, wheeling, third party sale, payment terms, etc., for all NRSE projects, including waste heat recovery projects, though the tariff could be different depending upon the type of project. He requested that the MSEB must submit immediately a short term (3 year) demand projection and integrated resource plan and long term (upto 2012) at a later date. This will enable to define the quota of procurement and merit order scheme. Prayas: 17. Shri S. Dixit of Prayas, Pune stated that the main thrust could be how much renewable energy should come from different NRSE systems into the grid. If the renewable energy is costing more than the conventional energy, then certain ceiling on purchase should be imposed. He further stated that, if after C:\Users\pravin.ganvir\Desktop\SAC\Minutes-Third Meeting (17.6.2002).doc - 3 -

certain period, say 2-3 years, if there is no shortage, then what will be the impact of these purchases on the utility/consumers. The policy should clearly spelt out the issues of (i) captive purpose, (ii) third party sale, (iii) standby charges, (iv) wheeling charges, (v) transmission losses, (vi) banking, (vii) ceiling of rate, etc. There should be a common & comprehensive policy, which should be made applicable to all NRSE projects and all utilities / licensees in the State. He stressed the underlining importance of drawing a least cost plan based on Integrated Resource Planning (IRP) for the State failing which there is also the possibility of deemed purchase, which are not needed. Energy Forum, Pune 18. Shri D.S. Gandhe of Energy Forum stated that the evacuation charges based on distances, wheeling charges, etc., should be collected at the minimum level. There should only be one tariff rate for all NRSE projects and considering the urgency the Commission should announce the tariff structure as early as possible. He further suggested that with appropriate planning, the co-generator could collect and store its required quantity of raw material like bagasse, as they do in other field of operations. He suggested that purchase of bagasse, can be routed through a separate institutional body, which could effectively regulate the bagasse price / ton thereby controls the cost of project as well as generation cost. MSEB: 19. The Chairman stated that the Board is all along adopted the policy guidelines of the GoI / GoM in this regard. There is a wrong notion that NRSE projects will be in a position to manage the grid efficiently. In fact, the NRSE projects are of seasonal inature and, therefore, infirm. The Board cannot plan its distribution system with such an infirm / uncertain source. However, the MSEB is purchasing the power from these sources with a view to encourage them in line with the GoM / GoI policy guidelines. The Bagasse based power projects should plan their power generation on a continuous (yearly) basis and make purchases of the bagasse accordingly. Regarding the 15% supervision charges, it is even charged by other agencies like PWD, Irrigation, which is an accepted method. 20. The Chairman, MSEB further stated that the `Captive Power, which by definition is captive in nature, must be kept separate as the conditions for such captive power plants are totally different and it will be unreasonable to include them under the present scope of policy. He also opined that the `Power Evacuation Charges must be levied with reasonable cost, which can be discussed. Regarding Conventional Fuel Pass Through, he stated that as the projects are developed on the basic principles of using NRSE fuel, no conventional fuel pass through should be allowed. On the question of `Deemed Generation, he strongly felt that it has got a strong bearing on the supply of firm power by the generator. Therefore, for such infirm sources, considering `deemed generation is not appropriate. On the issue of `Reactive Power, he stated that the suggestion made by Shri Goenka of VIA, if found technically justified, can definitely be adopted. C:\Users\pravin.ganvir\Desktop\SAC\Minutes-Third Meeting (17.6.2002).doc - 4 -

21. Shri Kukde, Technical Member, MSEB stated that in such cases where the MSEB is a consumer, the conditions of purchase must be feasible to the consumer alone and not otherwise. He also stated that the clause related to the Demand Charges and the Standby must be kept as proposed which is quite reasonable. MERC 22. Member (Shri Deo) observed that in Germany there is a 30% spinning reserve, and, therefore, there is opportunity for them to deal with such NRSE projects to be accommodated into their system. He further felt that choosing optimum size of the power plant for such bagasse based co-generation units as well as various data such as ratio of bagasse burnt to that of power produced shall be useful to make an informed decision. 23. Member (Dr Deo) remarked that the issue is not only limitation of fossil fuel but one must take into consideration the environmental effect, and global warming, making it necessary to use the available NRSE for power generation, which is environmental friendly. Now as the technology is developed and constantly upgraded, we are in a better position to tap these sources. He further stated that the MNES, GoI policy guidelines is also based on these principles. MEDA: 24. Shri G.M. Pillai, Director General, MEDA stated that the PLF for such co-generation projects must be calculated based on total generation and not based on exportable power which tends to mis-representing the technical figure possible. He further stated that the process of such projects may reduce in future due to various options of soft loan being proposed by STF. Further, he felt that the bagasse being an item having varied optional use, may be manipulated depending on the demand-supply situation in the market. Therefore, the user profile of bagasse and consideration of regulated bagasse market may be kept in mind while defining the policy. He further stated for the information of the Members that corporate model for distributed power for un-electrified villages is under active consideration of the Power Ministry and may soon fruitify into a model project. 25. The Chairman, MERC summed up the discussion stating that the discussion was a lively and enlightening one, with the following observation. The Commission will shortly submitting its report to the Government for consideration. (a) Definition of `Co-generation (b) The policy guidelines proposed shall be positively for all biomass based generation projects and power purchase plan shall aim at 7-10 years time frame. (c) The Commission, in the matter of PPAs before it u/s 22(1) (c) of the ERC Act, 1998, shall decide the rate. (d) Evacuation Cost is questionable and needs to be supported by appropriate back up reasoning. (e) Conventional Fuel Pass Through not to be allowed. C:\Users\pravin.ganvir\Desktop\SAC\Minutes-Third Meeting (17.6.2002).doc - 5 -

(f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) Bagasse Price to be determined by the Commission. Co-operative Agreement O.K. Third Party Sale the Commission s philosophy should be adopted as proposed in the Reform Bill. With the introduction of better efficient technology the aim should be to achieve `efficient utilisation of resources under co-generation projects. Deemed Generation: In case of Deemed Generation be allowed, the promoter must commit itself to supply required firm power without which such deemed generation shall not be allowed. Payment mechanism as proposed by VIA. Penalty for Non-Supply: the same will be applicable only when the confirmed power delivery is there. Penalty for Reactive Power: The issue will be reviewed with technical justification by the MSEB to accept the VIA s recommendation. Wheeling & Transmission Charges: the Commission shall decide the same. Contract Demand: The same should be de-linked from that of Captive Policy and should be spelt out exclusively for such projects. Foreign Exchange Fluctuation: In view of adverse experience, no foreign exchange variation shall be permitted. Sanjay Kumar Secretary, MERC C:\Users\pravin.ganvir\Desktop\SAC\Minutes-Third Meeting (17.6.2002).doc - 6 -