February 27th, 2018 City of Mayville

Project Location and Schedule Construction work Detour Route Business Access During Construction Temporary Business Signs What WisDOT Can Do During Construction What Businesses Can Do During Construction 2

Project Location & Schedule MARCH-

Remain open with the exception of approx. two week long closures. Only one can be closed at a time. Only closed during Stage 2 (Mid July through end of August. ) Clark Street, John Street, and Ruedebusch must be open 4

WIS 28/67 project includes new: Concrete pavement Sidewalks (Adding new sidewalk on east side of STH 67 from Ruedebusch to Mayville Savings bank) Curb & gutter Storm sewer New signals at Clark Street and Horicon & Main Streets. Watermain and Sanitary Sewer. Salvage and re-paint light fixtures on STH 67 5

CONSTRUCTION ZONE 6

Construction Zone 7

Construction Zone 8

Vehicular access to businesses and residences provided on WIS 28/67 only as needed during construction. Constricted work area, deep trenches and rough pavement may damage vehicles not preferred. Businesses with alternate access will be encouraged to use that access throughout construction. Better for business to keep one consistent access point. Contractor will have to coordinate in advance for driveway closures. 9

THIS IS CONSTRUCTION 10

11

Sidewalk on at least one side of STH 28 will have to remain in place and open at most times. New sidewalk will be constructed on the east side of STH 67 prior to replacing existing sidewalk on west side of STH 67 Temporary crosswalks will be maintained at intersections outside the construction area along with pedestrian across STH 28 at Henninger, Oak, Walnut, John, School Streets & STH 67 at Ruedebusch Streets at most times. 12

13

Temporary Pedestrian Barrier 14

Approx. 72 hours notice prior to closure of driveway access. Approx. 10 days notice prior to intersection closures Approx. 48 hours prior to sidewalk / utility interruption. 15

Driveways off of Horicon/Clark Streets closed for approximately: 48 hours for utility installation 48 hours for roadway excavation 5 calendar days for concrete pavement 10 calendar days for curb and gutter, concrete driveway, and concrete sidewalk. 16

WisDOT Traffic Control signs near the start of the detour route to let drivers know they can still access local businesses. Identify Alternate Business access routes Closer to construction complete permit for temporary signs to identify size, material, and location of temporary business sign. Handout maps showing alternate access and location of business can help customers during construction. 17

18

Clark St. Dayton St. 19

20

Mtn. Dr. Dayton St. 21

Clark St. John St. Dayton St. 22

John St. Ruedebusch St. 23

24

Safe location, not creating an obstacle or an obstruction to visibility Must mount on crash-safe supports Clear, simple message Encourage use of joint signs for groups of businesses in the same area Black lettering on white background, minimum 4 height, simple block-style font Get permission of local authority for signs on local roads

26

27

Which is it?

Field staff will be on site during construction for response to questions/concerns affecting businesses. Send weekly updates via email describing project progress and upcoming activities. WisDOT In this Together website 30

http://www.dot.wisconsin.gov/business/engrserv/itt/index.htm Project Website: http://wisconsindot.gov/pages/projects/byregion/sw/wis28wis67/default.aspx We will email this link to everyone who signs up for our email update list, so please sign up today.

PLAN AHEAD Work together to devise a creative plan or City Theme used to advertise business areas. Work with City and other businesses to find alternate access alternatives if needed Advertise Designate one person to filter questions through

Jeremy Hall, P.E., WisDOT Project Manager 608-245-2655, jeremy.hall@dot.wi.gov Ryan Arndt, P.E., Consultant Project Leader 920-924-5720, r.arndt@gremmerassociates.com Nathan Kempke, City of Mayville Engineer 920-387-7906, nkempke@mayvillecity.com Don Neitzel, Kunkel Engineering Group City Planner 920-356-9447, dneitzel@kunkelengineering.com 36